Professional Documents
Culture Documents
ELECTRIC POWER
APPLICATIONS, ENGINE &
GENERATOR SIZING
Contents
©2005 Caterpillar®
All rights reserved.
SECTION CONTENTS
©2006 Caterpillar®
All rights reserved. Page 1
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 2 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
runs it two hours a week. During extra cost) of the published Prime
those two hours, it runs at 400 kW power over each 24 hour period.
for 1.5 hours. Find the load factor. 10% overload limited to 1 in 12
The formulas reveal the following: hours but not to exceed 25 hours
per year. The 10% overload is
400 kW
% of load = = 0.73 available in accordance with ISO
550 kW
3046-1 (2002). Life to overhaul of
the engine is dependent on
90 min. operation as outlined in ISO8528
% of time = = 0.75
120 min. (2005) and time spent during
operation above 100% load may
Load Factor = 0.73 x 0.75 = 54.75% affect the life to overhaul.
Continuous Power
This load factor would indicate Unlimited hours of usage. Load
that the generator set could be used factor 100% of the published
as a standby rated generator set Continuous Power. Generally, as ISO
because it meets the load factor and 8528 (2005) Continuous power.
other criteria of standby. Note: Operating above these rating
Power rating definitions for definitions will result in shorter life
Caterpillar generator sets are based and higher generator and engine
on typical load factor, hours of use costs per year.
per year, peak demand and
The International Standards
application use. Caterpillar generator
Organization (ISO)
set ratings for emergency standby,
ISO 8528-1 (2005) defines three
standby, prime and continuous
types of duty:
power are listed.
• Continuous Operating Power
Emergency Standby Power (COP)
Typical usage of 50 hours per year
with a maximum of 200 hours per • Prime Running Power (PRP)
year. Typical variable load factor of • Limited-Time running Power
70%. (LTP)
Standby Power Continuous Operating Power (COP)
Maximum usage 500 hours per Continuous operating power is the
year, up to 300 hours of which may power a generator set can operate
be continuous running with varying at a continuous load for an unlimited
loads. No overload is available. number of hours under stated
Rating is equivalent to Prime +10%. ambient conditions. Maintenance
Load factor maximum is 70% of according to the manufacturer must
Standby rating. be followed to reach these
standards.
Prime Power
Unlimited hours of usage. Load
factor (70% maximum /80% if no
©2006 Caterpillar®
All rights reserved. Page 3
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 4 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 5
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 6 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 7
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 8 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 2
©2006 Caterpillar®
All rights reserved. Page 9
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 10 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 4
Typical voltage dip limitations are Greater voltage fluctuations permitted with emergency power
systems.
found in Table 3 for various
Table 3
facilities.
Motor Starting
Typical Voltage Dip Limitations The generator set’s ability to start
Permissible large motors without large frequency
Facility Application
Voltage or voltage dips depends on the
Dip entire system. System factors
Hospital, hotel Lighting load, 2% include:
motel, large Power Infrequent
apartments, load, large • Available engine power
libraries, Flickering highly
schools, and objectionable. • Capacity of the generator
stores.
Movie Theaters Lighting load, 3% • Energy stored in the rotating
(sound tone large Flickering Infrequent
requires objectionable.
inertia of the generator set
constant • Acceleration of the motor and
frequency. Neon
flashers erratic) its load (motor characteristics)
Bars and Power load, 5% - 10%
resorts. large Some Infrequent • Electrical components
flicker between the generator set
acceptable
Shops, Power load, 3% - 5% and motor.
factories, mills, large Some Frequent
laundries. flicker
A properly sized generator will
acceptable support the high starting kVA
Mines, oil field, Power load, 25% - 30%
quarries, large Flicker Frequent
(skVA) required and sustain
asphalt, plants. acceptable. adequate output voltage for the
©2006 Caterpillar®
All rights reserved. Page 11
EP Applications, Engine & Generator Sizing Application and Installation Guide
motor so it can produce the needed Refer to the Motor Loads and
torque to accelerate its load to rated Motor Performance Sections on
speed. Pages 43 & 48 for more
After the initial voltage dip, it is information.
important that the generator restore Block Load
voltage to at least 90% to develop A block load refers to the
adequate torque to accelerate its percentage of rated power at rated
load to rated speed. Full voltage power factor instantaneously added
starting causes the largest voltage to the generator set. When block
dip. For this reason, public utilities loads are large, sometimes they
will not always allow full voltage should be accepted in smaller
starting of large motors. Details on portions in various steps. Step
motor starting are later discussed in loading is very common when load
the “load analysis” section of this acceptance performance criteria are
guide. required. For example, if a generator
Transient response of a generator set is rated 1000 ekW at 0.8 pf and
set is a description of the maximum a 250 ekW load at 0.8 pf is applied
voltage and frequency change on to the generator set, a block load of
application of a load and the time to 25% [(power applied/rated power) x
recover to nominal voltage and 100%] is applied.
frequency conditions. Typically, the
maximum allowable voltage dip is
Transient Response Standards
30%. The maximum frequency dip There are standards in various
is about 25% but modern equipment countries; and industries that require
is restricting this to tighter margins. generator sets to be capable of
accepting and recovering a full load
It is not always necessary to have step. However, many do not specify
the quickest transient response frequency and volt deviations. ISO
possible; only the best response for 8528 has set transient response
the application’s need. Generator standards. Four performance classes
sets all perform differently by the are designated in ISO 8528-1-7 to
design of the engine, governing, and describe a generator set in terms of
voltage regulation systems. voltage and frequency. The chart
Transient response characterizations below lists the performance class
must be compared to the equipment and their criteria and application
that will be used at the facility; this examples. The performance class
will ensure the generator set is sized relevant for the application must be
to the loads that will be applied. followed to be within the standard
and achieve maximum performance.
©2006 Caterpillar®
Page 12 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 13
EP Applications, Engine & Generator Sizing Application and Installation Guide
Table 4 shows the acceptance but are not helpful when comparing
(dip) and rejection (overshoot) engines of different sizes and
parameters identified by ISO 8528- designs. Instead, engines can be
5. Class G4 is reserved for limits compared by referring to their brake
that are unique and must be agreed mean effective pressure (BMEP).
upon by the manufacturer and The “mean effective pressure” is
customer. ISO 8528-5 also sets an average of the pressure that
limits on recovery times for each would need to be present in the
class and identifies how recovery engine’s cylinder for the power and
time is measured. torque to be produced. BMEP refers
to the brake MEP or the useful work
Agreed between Manufacturer done at the engine flywheel.
and Customer (AMC)
Class Class Class Class BMEP is an indicator of how much
G1 G2 G3 G4 engine torque is available. The BMEP
Frequency %
–15 –10 –7 AMC can indicate if the pressure within
Acceptance
the cylinder is within the optimal
Frequency %
18 12 10 AMC performance parameter. BMEP is a
Rejection
Voltage % relative number that is only used as
–25 –20 –15 AMC
Acceptance a standard to compare engines of
Voltage %
35 25 20 AMC different designs or sizes. It can be
Rejection
expressed in psi, kPa or bar.
Time Seconds 5 5 3 AMC
BMEP Load Step
Table 4 Two engines of different sizes are
working similarly if they operate at
the same BMEP.
SAE Standard J1349 specifies
A BMEP load is described in the
inlet air and fuel supply test
following figures and text.
conditions. It also gives a method
for correcting observed power to Step-by-Step Events — Load Applied
reference conditions and a method Figure 5 and Figure 6 illustrate full
for determining net full load engine load addition to a generator set with
power with a dynamometer to a turbocharged-aftercooled (TA)
engines. engine, and a 1:1 Volt/Hz voltage
regulator. Figure 5 shows how the
Engine Considerations
parameters vary as a function of
Brake Mean Effective Pressure engine speed; Figure 6 presents the
(BMEP) same events versus time.
When sizing a generator set, Note: Reading through this topic,
comparing engines may be prior to reviewing the figures, will
necessary to determine optimal aid in understanding the content.
performance, especially when motor
starting. Both torque and
horsepower are necessary measures
©2006 Caterpillar®
Page 14 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 5
©2006 Caterpillar®
All rights reserved. Page 15
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 6
©2006 Caterpillar®
Page 16 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 17
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 18 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 19
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 20 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 21
EP Applications, Engine & Generator Sizing Application and Installation Guide
Customer Requirements
graph a complete year and
Power Demand determine any seasonal variations.
On Site Power Requirement A daily chronological load curve,
Before selecting an engine model illustrated in Figure 8, shows load
and rating, a load analysis needs to demand throughout the day. A
be performed. This section will chronological curve establishes the
consider the factors which affect peak daily demand and an energy
generator sizing including load usage profile which can aid in the
management needs, voltage and selection of an appropriately sized
frequency dip limitations, motor engine. This load curve is also useful
starting considerations, start-up in programming units for economical
needs and all required standards. operation.
Load Management
Load management is the deliberate
control of loads on a generator set
and/or utility to have the lowest
possible electrical costs.
Assessing the customer’s load
profiles is a key component to
establishing their load management
profile and ultimately the size of
generator set needed to operate
within that profile.
Loads Profiles
The duration and nature of a load
must be established to select and Figure 8
operate a generator set system at
Daily typical peaks for various
maximum efficiency. To analyze a
industries can be graphed based on
load, a family of load profile charts
typical loads as shown in Figure 9.
is necessary. Chronological and
duration load profiles best serve this
purpose.
Note: Unless the load is known to
be steady, this average cannot be
used to establish the engine and
generator requirements because the
Figure 9
average will always be lower than
the maximum kW demand. Duration curves, as shown in
The purpose of the monthly Figure 10, rearrange chronological
average number is to be able to curves and summarize daily load.
©2006 Caterpillar®
Page 22 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Such curves are developed for a For existing loads that are served
week, month, season or year. The by a utility, power bills or power
daily chart represents the average consumption records will provide the
kilowatt load for each day, while the needed data for a twelve-month
twelve-month chart, shown in Figure period. The average kW load can be
11, represents the average kilowatt determined by the following
load for each month. equation:
Average kW Total kW used in Month
=
Load for Month Total Monthly Hours of Operation
Figure 10
Figure 11
©2006 Caterpillar®
All rights reserved. Page 23
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 24 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Load Example
VA/FT2 Load Estimating Calculate the load for a 10,000
For estimating purposes, power square foot office with electric air
loads and lighting loads can be conditioning.
measured in VA/FT2. However, a Solution
detailed analysis requires individual The left-hand column of Table 6
measurement of power loads to indicates the maximum lighting load
ensure accuracy. in an office building is 4.0 VA/FT2.
A simple table, based on VA/FT2, Therefore, the lighting load equates
is used to obtain a rough estimate of to:
a load as expressed in total kVA 4.0 VA/FT2 x 10,000 (square feet) = 40,000 VA
generated; Table 6 shows such a
table.
©2006 Caterpillar®
All rights reserved. Page 25
EP Applications, Engine & Generator Sizing Application and Installation Guide
Reading the table from left to BMEP load step analysis, described
right: earlier in this guide, is one system
2.0 VA/FT2 is required for for developing a starting method.
miscellaneous power loads: Most loads do not draw power in a
2.0 VA/FT2 x 10,000 (square feet) = 20,000 VA steady-state fashion; therefore, it is
important to know the operating
sequence and what else is running
7.0 A/FT2 is required for electrical when loads are connected.
air conditioning loads:
7.0 VA/FT2 x 10,000 (square feet) = 70,000 VA Prioritization
Prioritization is the process by
which the customer identifies what
Add the individual loads to electrical loads are needed and in
determine the combined load: what priority. The highest priority
40,000 + 20,000 + 70,000 = 130,000 VA loads would be in the first step;
even if all the generator sets are not
When using the table, it is ready for load. The first generator
important to remember that the set ready to accept the load would
table does not account for power take the first priority loads. The next
losses caused by the resistance step would go to the next highest
found in wires and cables. A power prioritized load. This process will
loss of up to 6% would be factored repeat until all loads are applied.
into the VA total when estimating a Smaller load steps equate to
facility with extensive wiring. smaller transients, which result in a
smoother transition. For example, a
Load Steps medical center might prioritize
Load steps refer to the amount of lifesaving equipment as their number
load that will be placed on a one need. That equipment (or
generator set at one time. A special outlets for that equipment)
generator set may accept load in would be the first supplied with
one load step, or may spread it out electricity from the first available
over several load steps. The generator set. Lights may be
customer can identify the needs of identified as the second most
the environment and then a proper important need and handled by the
method of starting can be applied. second load step.
©2006 Caterpillar®
Page 26 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 27
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 14
Figure 13
©2006 Caterpillar®
Page 28 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 15
©2006 Caterpillar®
All rights reserved. Page 29
EP Applications, Engine & Generator Sizing Application and Installation Guide
Table 7
©2006 Caterpillar®
Page 30 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 31
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 32 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
the loads are not interlocked, the diversity factor is 1.4, for example,
generator set rating could be 690 kVA divided by 1.4 equals 492
exceeded. Despite this precaution, kVA. Hence, a generator set rated at
you must always assume that total 500 kVA would satisfy the load.
time-current characteristics of all In summary, all loads need to be
motors and other loads starting at analyzed so that the correct size
the same time will not exceed the generator can be matched to the
short-term generator set rating. load. When sizing a generator for an
Figure 19 illustrates how demand application, the steady state load
and diversity factors are used in and maximum transient load need to
generator set sizing. be considered.
Frequency Dips
Frequency dips are related to the
size of load being connected.
Twenty to 25% maximum frequency
dip is the standard limit. A
frequency dip above 35% may
cause the engine difficulty in
recovering. Frequency dips are
normally more tightly controlled than
voltage dips because they are
typically connected to more
sensitive electrical equipment.
Figure 19 Block Load & Standards
The NFPA (National Fire Protection
Association) standard 110 requires
In Figure 19, connected loads of that a generator set must be capable
300 kVA, 100 kVA and 500 kVA of picking up a 100% block load. It
are shown. After calculating demand does not specify frequency and volt
factors for each of the same loads, deviations.
the corresponding demand loads are ISO 8528 (2005) also has
240, 100 and 350, respectively. transient response standards that
When combined, the total demand are discussed in the Engine Ratings
load on the system is 690 kVA. section of this guide. The
When the diversity factor is 1.0, the performance class relevant for the
total 690 kVA is divided by 1.0 to application must be followed to be
get 690 kVA. To meet this load, a within the standard and achieve
generator set rated at a standard maximum performance.
size of 750 kVA is needed.
Starting Requirements
However, a different diversity
The time it takes to initiate a
factor on the same system will
generator set startup and when it is
change the total kVA needed. If the
©2006 Caterpillar®
All rights reserved. Page 33
EP Applications, Engine & Generator Sizing Application and Installation Guide
ready to accept load is defined as its Also, in cases where air starting
starting requirement. Starting is used, the air system must
requirements will vary depending on supply the required air volume
the application. A typical starting and maintain a 100 psi (689.5
requirement is 10 to 30 seconds. kPa) minimum pressure.
Load Acceptance 2. Combustion air must be a
Load Acceptance is the point at minimum of 21°C (70°F).
which breaker closure is initiated. 3. A jacket water heater to
This is considered to be 90% of maintain a minimum of 32°C
rated frequency. Figure 20 (90°F) jacket water
graphically shows a packaged temperature.
generator set’s typical starting
4. A readily available supply of
performance.
clean fuel.
5. The generator rotating inertia
must not exceed that of the
standard Caterpillar generator.
Any variation in these conditions
will affect the start time.
Natural Gas Engines
Special engine conditioning is
required for a natural gas engine to
start in 10 seconds. Ten-second
starting is only possible on specific
Figure 20 gas engines. Consult the factory for
specific engine model starting
requirements.
Ten-Second Start Starting condition requirements for
Ten-second start refers to the natural gas engines are the same as
ability of a non-paralleled generator diesel engine starting requirements,
set to start, accelerate to rated except for one detail: The solenoid
speed and be ready to accept load gas valve must be located as closely
within 10 seconds after receiving a as possible to the carburetor or “A”
signal to start. regulator, depending on the fuel
For 10-second starting, the train consists. A maximum distance
following conditions must exist: of 0.61 m (2 ft) is desired.
1. Cranking batteries must be A customer’s starting time
adequately sized and fully requirements should be determined
charged. before sizing the generator set. A
Note: there is a difference for quick starting application requires
battery versus ambient consideration of altitude,
temperature sizing. temperature and other factors that
©2006 Caterpillar®
Page 34 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
affect the engine starting to find the available in respective Application &
best solution. Installation Guides.
Refer to Emergency & Fast Natural Gas
Starting in the Starting Systems Natural gas engines are appropriate
Application and Installation Guide for for base loading, continuous
more information. operations. Natural gas does not
Health Care Facilities & NFPA 99 respond well to transients so it
The standard NFPA 99 is written would not be a good choice for
specifically for health care facilities. loads with fluctuations. Natural gas
can be less expensive, depending on
3-4.1.1.8 states the following:
availability, and it has superior
“The generator set(s) shall have
emissions.
sufficient capacity to pick up the
load and meet the minimum Diesel
frequency and voltage stability Diesel fuel is suited for large load
requirements of the emergency fluctuations. Fuel normally
system within 10 seconds after loss recommended for diesel generator
of normal power.” sets is No. 2 furnace oil or No. 2D
diesel fuel. When this fuel is used
Customers requiring this capability
for heating, common storage tanks
can achieve it by using the correct
for boilers and generator sets are
generator system. Select an
practical. In addition to reducing
appropriate generator set according
installation costs, this arrangement
to this standard for all health care
reduces fuel costs by quantity
facilities in the United States.
purchases and minimizes fuel
Sizing a generator set requires deterioration. Diesel is an excellent
knowledge of the customer’s loads choice for base loading and standby
and load management strategies as applications.
well as their requirements for
transient response, emissions and Heavy Fuels
starting. All these requirements need Heavy fuels are the by-products
to be determined before the from the refining process of oil. It is
generator set size and rating are extremely viscous and the fuel
established. quality is low. However, this fuel is
very inexpensive. For industries
Fuel Selection which burn large amounts of fuel,
Fuel selection can impact the heavy fuels are a choice to consider
performance of a generator set and, because of their economic
depending on availability, reduce advantages. Heavy fuels are not a
electricity costs for a generator set good choice for standby
user. Natural gas, diesel and heavy applications.
fuels are common choices.
Note: Detailed information on
gaseous fuels and diesel fuels is
©2006 Caterpillar®
All rights reserved. Page 35
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 36 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 37
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 38 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 39
EP Applications, Engine & Generator Sizing Application and Installation Guide
Load Analysis
Load analysis is the process of work. It is the product of power and
considering size, starting time.
characteristics and intended usage Energy = Power x Time
of electrical loads and their
collective impact on a generator set
power source. In electric power generation,
electrical energy produced or
At times, it may be necessary to
consumed is expressed in kilowatt-
conduct a detailed analysis, through
hours (kW-Hrs). A single kW-Hr of
discussion and observation, with the
energy is one kW of electrical power
user, customer, or
used for one hour.
consulting/specifying engineer to
determine the exact nature of the kW-Hrs = kW x Hrs
loads.
Determining the electrical load of a Loads have different electrical
facility is the first and most characteristics. When developing a
important step in supplying a load analysis, it is helpful to
generator set. The generator set categorize loads into groups with
supplier is looked upon as the expert common characteristics. There are
when it comes to choosing the right no rigid standards for categorizing
generator set to power the load. As loads. Architects, consultants,
a supplier of high-quality Caterpillar customers and generator set
generator sets, it is important to suppliers will determine or speak of
understand electrical loads and categories for loads based on the
possess a working knowledge of needs of the project involved.
basic load analysis. For example, loads may be
An electrical load is a device that categorized as normal loads and
uses electricity; lights, motors, emergency loads or perhaps critical
heaters, welders and loads and non-critical loads. There
communications equipment are just may be further division of the
a few examples of electrical loads. emergency or critical loads into
It is important to understand the additional categories of life-support
relationship between energy and or uninterruptible loads. On a
power when discussing electrical different project, the loads may be
loads. Power is a rate of doing work. labeled as base, intermediate and
It is a product of force and motion. peak shaving loads.
Electrical power is the product of Load analysis should define those
electromotive force (volts) and loads that are considered linear
current flow (amps). It is expressed (draw current in a sine waveform)
in watts or kilowatts. Energy is and non-linear (draw current in
pulses or non-sine waveform).
©2006 Caterpillar®
Page 40 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 41
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 42 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 43
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 44 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Table 12 lists the specifications for current. Because these motors have
each class of motor. no code letter, exact operating
performance must be obtained from
the motor nameplate or the
Squirrel Cage Motor Torques in Per Unit
of Full-Load Torque manufacturer. Typical applications
Locked-
are large pumps, long conveyers,
Class Breakdown Pull-Up large diameter fans and large
Rotor
rotating drum devices.
A 1.40 Over 2.00 1.00
B 1.40 2.00 1.00
The characteristics of current are
shown in Figure 24, as they
Over
C 2.00 1.90 correspond to steps in resistance.
1.40
Also shown are percentages of total
Not Not
D 2.75
specified specified
rated resistance in the rotor circuit.
With 100% or maximum resistance
Table 12 when the motor is started at zero
speed, the initial inrush line current
Wound Rotor (Slip Ring) is in the range of 100% full load
A wound rotor motor is a special current. If all rings were shorted at
induction motor which features a start up, as in a squirrel cage motor,
rotor that is wound with coils. there is zero resistance and starting
Windings are placed in slots around current would be approximately
the rotor periphery and connected to 460% of full load current. This
slip rings. The slip ring brushes are would present a much more severe
then connected to external resistors. starting condition. Normal operation
Changing the rotor circuit resistance of this motor is with all resistance
will change the induced rotor circuit shorted.
current and vary the motor’s
speed/torque characteristics. High
rotor resistance provides a high
starting torque with low starting
current. A wound rotor induction
motor normally has five to seven
steps of resistance in the rotor
circuit.
Wound rotor motors are used for
starting large rotating mass or high
inertia loads with a long acceleration
time. They provide a smooth start
with minimized motor heating during
the acceleration period. Usually the
motors are started near unity (1.0)
Figure 24
power factor. Starting current is
limited to 130% of rated operating
©2006 Caterpillar®
All rights reserved. Page 45
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 46 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 47
EP Applications, Engine & Generator Sizing Application and Installation Guide
applications will usually involve the total kW load may also be slightly
use of packaged static component higher because small motors are
drive controls, commonly called SCR frequently less efficient than large
drives. SCR drives are discussed in motors.
detail later in this section. If the single-phase motor load
A major consideration when sizing cannot be distributed, it may be
a generator is to look at the necessary to verify the ability of the
provision or inclusion of a suitable generator to provide the skVA.
DC supply. There must be enough Generally, with large blocks of
kVA to power both the DC supply single-phase motors started from
and the load. one phase, the available skVA of the
Single-phase Motors generator will be 56% of the normal
Single-phase motors are common three-phase skVA.
in fractional horsepower sizes. They Three-Phase Motors
may occasionally be used in sizes as Three-phase motors are very
high as ten horsepower. Single- common in industry. They provide
phase motors do not have the more output for physical size than
benefit of rotating magnetic fields single-phase motors and have the
produced by spaced voltage cycles advantage of having a simple
of a three-phase circuit. Therefore, a designed rotating magnetic field that
separate starter winding is included turns the rotor for starting. In a
in the stator with provisions to three-phase motor, there are three
supply a magnetic field that is out of equally spaced voltage cycles
phase with the main stator winding feeding respective windings in the
field. This results in a rotating field stator. A rotating magnetic field is
to start things moving. A centrifugal produced which the rotor
switch disconnects the starter immediately begins to follow.
winding as it achieves rated speed. Therefore, no special starter winding
Single-phase motors are not is required to begin rotation.
generally of great concern when
Motor Performance
started by a generator which is
Most three-phase motors are
relatively larger in size. It is good
squirrel cage type as mentioned
practice to divide multiple single-
earlier. When rotor slot cross
phase motor loads into equal blocks
sections are changed, different
per phase. If blocks of single-phase
torque and speed characteristics
motors are spread equally over the
result. How a motor and its load
three-phases and started as a group,
impact a generator is highly
this motor load can be considered as
dependent on the characteristics of
a single three-phase motor of equal
the motor.
hp. The skVA may be higher
because the skVA per hp is typically Design Class
higher for single-phase motors. The Motors with various rotor designs
are classified in the U.S. by the
©2006 Caterpillar®
Page 48 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 49
EP Applications, Engine & Generator Sizing Application and Installation Guide
Table 13
©2006 Caterpillar®
Page 50 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 51
EP Applications, Engine & Generator Sizing Application and Installation Guide
NEMA Code Letter Starting skVA/hp Table 15 lists standard sizes for 50
A 0.00 - 3.14 Hz motors. The starting kVA
B 3.15 - 3.54 numbers should be used as a
C 3.55 - 3.99 guideline only. For the exact skVA
D 4.00 - 4.49 of a motor, consult the motor
E 4.50 - 4.99 manufacturer.
F 5.00 - 5.59
G 5.60 - 6.29
Motor Size kW Starting kVA
H 6.30 - 7.09
.37 N/A
J 7.10 - 7.99
.55 4.9
K 8.00 - 8.99
.75 6.9
L 9.00 - 9.99
1.1 9.5
M 10.00 - 11.19
1.5 13.4
N 11.20 - 12.49
2.2 19.8
P 12.50 - 13.99
3 29.7
R 14.00 - 15.99
4 41.4
S 16.00 - 17.99
5.5 53.8
T 18.00 - 19.99
7.5 73.1
U 20.00 - 22.39
11 103
V 22.40 -
15 143
Table 14 18.5 171
22 204
30 254
37 322
45 378
55 502
75 721
90 906
110 1049
132 1255
160 1557
200 1940
250 2476
315 3113
356 3421
Table 15
©2006 Caterpillar®
Page 52 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 53
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 54 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Sample
Motor Torque & Current vs. Speed Figure 30
©2006 Caterpillar®
All rights reserved. Page 55
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 56 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 33
©2006 Caterpillar®
All rights reserved. Page 57
EP Applications, Engine & Generator Sizing Application and Installation Guide
Table 16
©2006 Caterpillar®
Page 58 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 59
EP Applications, Engine & Generator Sizing Application and Installation Guide
Table 17
©2006 Caterpillar®
Page 60 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
button is opened. The on-off control The generator set must have
commonly features integral overload sufficient motor starting kVA
protection. capacity to limit voltage drop. If
Full line voltage is supplied to the actual values of the motor starting
motor instantly when the motor current cannot be determined, an
switch is actuated; refer to Table approximate value of 600% of full-
18. Maximum starting torque is load rated current is a good
available; therefore, the motor will approximation for Design B motors;
have minimum acceleration time. approximate 1500% of full-load
Reduction of acceleration time is rated current for Design E motors.
advantageous for motors that cycle Refer to Figure 36.
off and on frequently. The shorter Full voltage starting is used unless
the time it takes the motor to get to there are limitations on inrush
full speed, the less heating will currents. Most public utilities do not
occur on the motor windings. This allow full voltage starting of large
will allow for increased service life motors. When large motors are
of the motor. started, a relief must be provided.
Figure 35
©2006 Caterpillar®
All rights reserved. Page 61
EP Applications, Engine & Generator Sizing Application and Installation Guide
Advantages Disadvantages
Autotransformer
1. Provides highest torque per amp of line current. 1. In lower hp ratings, it is most expensive design
2. Taps on autotransformer permit adjustment of
starting voltage.
3. Closed transition starting.
4. While starting, motor current is greater than line
current.
5. Low power factor.
Resistor
1. Smooth acceleration — motor voltage increases with 1. Low torque efficiency
speed. 2. Resistor heat
2. Closed transition starting. 3. High power factor during start.
3. Less expensive than autotransformer starter in lower
hp ratings.
4. Available with several accelerating points.
Part Winding
1. Least expensive reduced voltage starter. 1. Requires special motor design for voltages higher
2. Closed transition starting. than 230 v.
3. Most dual voltage motors can be started part winding
on lower of two voltages.
4. Small size.
Start Delta
1. Moderate cost — less than resistor or 1. Requires special motor design.
autotransformer. 2. Starting torque is low.
2. Suitable for high inertia, long acceleration loads.
3. High torque efficiency.
Table 18
©2006 Caterpillar®
Page 62 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 63
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 64 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 65
EP Applications, Engine & Generator Sizing Application and Installation Guide
Autotransformer – Closed
Figure 39
Autotransformer — Closed
Transition
An alternative to open transition
switching, is closed transition.
This technique minimizes shock by
providing continuous flow of current
while switching from
autotransformer tap to full voltage.
Closed transition switching, though
involving slightly more complex
switching, is preferred for
autotransformer starting.
Autotransformer starters are
magnetically controlled. Three taps
on the transformer secondary are
set for 50%, 65%, and 80% of full
line voltage. These three contactors, Figure 40
a timer, and a transformer make up
the starting device. This starter is
very smooth in acceleration and
allowance starting time is 30
©2006 Caterpillar®
Page 66 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 67
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 68 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Solid State
Figure 44
Solid-State Starter
Solid-state starters offer many
options in achieving desired starting
characteristics. Solid-state starters
adjust torque, acceleration ramp
time and current limit to cause a
motor start which has a controlled
acceleration. Solid-state starters
offer smooth, step-less motor
starting by varying the conduction
©2006 Caterpillar®
All rights reserved. Page 69
EP Applications, Engine & Generator Sizing Application and Installation Guide
Current Ramp
Use of the current limit ramp is
very common. Current is ramped up
within a prescribed time to reach a
programmed limit; refer to Figure
47. Current limit settings from
150% to 600% of full load current
are typically available. A 300% limit
Figure 45 reduces the starting kVA by 50%
from the normal 600% current with
The user adjusts the control to full voltage across-the-line starting.
deliver the best starting Use of the current limit setting
characteristic for the application. reduces motor torque available to
Variations of current and voltage the load as shown in Figure 45.
limit are sometimes used to achieve
linear speed ramp, however the
operating principle of the controlled
parameter is always based on
voltage control.
Voltage Ramp
Voltage/time ramp increases
voltage until full voltage is applied to
the motor terminals. Constant kVA
is maintained, and sudden torque
changes are eliminated, as illustrated
in Figure 46. Initial voltage step,
acceleration ramp, and current limit
are usually adjustable. An extended
acceleration ramp time and low
current limit setting results in the
least voltage and frequency dips.
Voltage Ramp
Figure 46
©2006 Caterpillar®
Page 70 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Current Ramp
Table of Methods and Types of Motor Starting
PU PU
Rated Rated
Method and PU Line
Start Start
Type of Voltage
Torque kVA
Starting Applied
Availabl Require
e d
Full Voltage
Across-the-Line 1.0 1.0 1.0
Full Voltage
Part Winding
Figure 47 (See Notes 1 & 1.0 0.70 0.70
3)
Reduced
Voltage 0.80, 0.64, 0.67,
Table 18 lists the various methods Autotransformer 0.65, 0.42, 0.45,
and types of starting, and their (See Note 2) 0.50 0.25 0.28
principle effects on motor starting. Reduced
Voltage
Extreme care should be given Reactor/Resisto 0.80, 0.64, 0.80,
when applying reduced voltage r (See Notes 1 0.65 0.42 0.65
starting to engine generator sets. & 3)
The amount of available starting Reduced
torque is reduced. Any transient Voltage Star- 0.58 0.33 0.33
Delta
voltage dip during start will further
NOTES:
reduce the starting torque. For
1. Values are typical. Various values of skVA and
example, if a motor is being started torque are available depending upon motor/starter
with an autotransformer starter on design. Consult the motor/starter manufacturer for
the 65% tap, the motor will have specific data.
only 42.25% of its full voltage 2. The calculated percentage values of Start kVA
have been increased by three percentage points to
starting torque available upon start. allow for the magnetizing kVA required for the
If the system voltage dips 20% autotransformer.
during transient, the voltage at the 3. Values listed are typical. Consult with the customer
motor terminals will be only 80% of or the manufacturer of the motor/starter for specific
65% of rated voltage (52% of full data.
voltage). Squaring 52% gives a net 4. In the absence of specific data, indicated typical
data may be used for estimating purposes, but should
value of 27% of full voltage starting be shown as “assumed values in lieu of specific data”.
torque, not the anticipated 42.25%. Performance of actual equipment may vary from
calculated performance on all calculations and
quotations.
Table 19
©2006 Caterpillar®
All rights reserved. Page 71
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 72 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 73
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 74 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 75
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 76 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 50
©2006 Caterpillar®
All rights reserved. Page 77
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 51
Figure 52
©2006 Caterpillar®
Page 78 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 79
EP Applications, Engine & Generator Sizing Application and Installation Guide
crossings” for timing may perform UPS output for computer loads is
erratically. If these devices are of frequently stated in terms of kVA.
low power, a simple and low cost For approximating, if UPS output
filter will usually eliminate any kVA is given and kW is unknown,
problem. use 0.9 pf (typical for computer
Power factor correction capacitors systems).
are used primarily for economic Battery recharge kW generally
reasons. They can also be effective ranges from 0 to 25% of input kW
in reducing waveform distortion. (15% is typical). If unknown, use
Caution must be exercised where 25% of output kW for an
power factor correction capacitors approximation.
are used. A resonant condition at If UPS efficiency is unknown, the
one of the harmonic frequencies following guidelines are
with some part of the line recommended:
inductance such as a transformer,
• Use 0.85 if UPS < 100 kW.
on-line motor or the generator is
possible. Excessive and possibly • Use 0.875 if UPS > 100 kW,
damaging currents at the harmonic but < 500 kW.
frequency can flow through the • Use 0.90 if UPS > 500 kW.
equipment. It may be advisable to
Note: Maximum input with
keep them off line until effects of
redundant systems is less than total
operating on an emergency rating of individual systems.
generator set with non-linear loads
can be observed. Part B
Establish the minimum size
UPS Sizing Example
generator to contain waveform
The following is a procedure to use
distortion (quality of electric power).
in sizing Caterpillar generator sets
that have static UPS systems as • 6-pulse rectifier/charger:
part or all of their load. This Minimum standby rated
procedure has four parts: generator set =
UPS input kW x 1.6.
Part A
Establish UPS input kW. Use UPS • 12-pulse rectifier/charger:
Minimum standby rated
input kW from supplier data. (In this
example use 255 kW.) If not generator set =
UPS input kW x 1.4.
available from supplier, the following
procedure and guidelines are
recommended to approximate or
estimate UPS input kW.
UPS Output kW + Battery Recharge
UPS Input kW = kW
UPS Efficiency
©2006 Caterpillar®
Page 80 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 81
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 82 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 54
Figure 55
©2006 Caterpillar®
All rights reserved. Page 83
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 84 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
and then smaller motors load. Line voltage drop change with
sequentially after that. load change also affects voltage
• When motors with electronic regulation at the load, if the load
drives are started, the “largest varies.
motor first” rule does not Power losses are calculated as I2R
necessarily apply. Electronic loss in watts or kilowatts. Voltage
drives allow better control of drop is calculated as I2R loss. The
the load by controlling the amount of resistance is based on
maximum current load and length, cross-sectional area,
rate of load application. These temperature, and substance of the
loads are more sensitive to conductors. Standard electrical
voltage variation than the handbooks contain tables of
motors started “across-the- resistivity of wire and cable for
line”. making calculations. Line losses are
• When UPS loads are present, not typically a factor with short
load them last. Generators are cable lengths of proper size.
more stable and less affected Power Factor Loads
by non-linear loads when Self-excited, synchronous
linear loads have been running generators are not designed to
before non-linear loads are operate with leading power factor
applied. load. The AC voltage generated is
• Loads that have filters or use controlled by DC excitation. The
power factor correction for amount of excitation required is a
power quality improvement function of generator load.
should not be applied to a Excitation required to maintain
light load level. The capacitive constant voltage increases with
elements of these loads make load. Reactive lagging power factor
the generator susceptible to load requires more excitation than a
huge voltage increases. unity power factor load. Leading
Line Losses power factor loads require less
Wires and cables in circuits always excitation than unity power factor
have some resistance to current loads. When a generator has a
flow. This presents a power loss and leading power factor, the armature
a voltage drop. The losses are a flux reacts additively with the field
function of line length and line pole flux to increase saturation and
current carrying capability. These produce a higher terminal voltage for
losses must be considered. a given amount of excitation. The
automatic voltage regulator
Line voltage drop may be a more responds to control voltage by
important consideration. Voltage reducing excitation. At light load,
drop can represent a significant the regulator will go to its minimum
difference between generated excitation capability. However, the
voltage and voltage delivered at the
©2006 Caterpillar®
All rights reserved. Page 85
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 56
©2006 Caterpillar®
Page 86 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Where: Where:
P= Power Loss in Watts P= Power Loss in Watts
L= One-way Length of a Circuit L= One-way Length of a Circuit
in feet in feet
CM = The Cross Section of a CM = The Cross Section of a
Conductor in Circular Mils Conductor in Circular Mils
I= Represents Current I= Represents Current
Example Example
Assume a single-phase motor rated Assume a three-phase motor rated
to deliver 7.5 hp at 115 V is to deliver 100 hp at 230 V
connected to a power source via a connected to the power source via a
200 foot, No. 1 AWG copper wire 400 foot cable sized at 250 MCM.
sized at 83,690 CM. Also, assume Also, assume the motor draws 248
the motor draws 80 amperes at full amperes at full load. What is the
load. What is the power loss? power loss?
Solution Solution
Use the formula for a single-phase Use the formula for a single-phase
motor: motor:
24 x 200 x 802 36 x 400 x 2482
=P =P
83,690 250,000
The result is a 367 watt power The result is a 3,543 watt power
loss. loss.
©2006 Caterpillar®
All rights reserved. Page 87
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 88 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Solution 1
1. First, find the current drawn
from each of the lines by the
three-phase load.
1.732 x I x pf x V P x 1000
P= I=
1000 1.732 x V x pf
Figure 58
50 x 1000
= 151 Amperes
1.732 x 240 x 0.8 Solution 2
1. First, find the current drawn
2. Find the coil current capacity from each of the lines by the
remaining for the single-phase three-phase load.
load: 1.732 x I x pf x V P x 1000
P= I=
334 – 151 = 183 amperes 1000 1.732 x V x pf
©2006 Caterpillar®
All rights reserved. Page 89
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 60
©2006 Caterpillar®
Page 90 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 61
©2006 Caterpillar®
All rights reserved. Page 91
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 62
©2006 Caterpillar®
Page 92 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 63
©2006 Caterpillar®
All rights reserved. Page 93
EP Applications, Engine & Generator Sizing Application and Installation Guide
kVA of AC Circuits
Table 23
©2006 Caterpillar®
Page 94 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 95
EP Applications, Engine & Generator Sizing Application and Installation Guide
Voltage and
Current Drawn Current Examples
Waveforms
Linear Proportional to Sine wave Incandescent light bulbs
voltage Induction and synchronous
motors
Electromagnetic devices
Resistance heaters
Non-Linear Non-proportional Pulses Silicon controlled rectifiers
to voltage Variable speed drives
Uninterruptible power
supplies
Battery chargers
Fluorescent lighting
Table 24
©2006 Caterpillar®
Page 96 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Table 25
©2006 Caterpillar®
All rights reserved. Page 97
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 64
Figure 65
©2006 Caterpillar®
Page 98 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 66
©2006 Caterpillar®
All rights reserved. Page 99
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 100 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 101
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 102 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 103
EP Applications, Engine & Generator Sizing Application and Installation Guide
Non-Linear Loads and 2/3 Pitch difference. In some cases, there may
Non-linear loads generate harmonic be no advantage to 2/3 pitch
currents which cause waveform winding when paralleling.
distortion of the generator. For When paralleling with a utility the
balanced three-phase loads, 2/3 pitch winding may be a
distortion is caused by voltage drop disadvantage due to low zero
due to the harmonic currents in the sequence reactance. Typically, 3rd
subtransient reactance of the harmonic current flow in the neutral
generator. The subtransient is of the most significance.
reactance of a generator is not a Reactors, resistors, or switches can
function of coil pitch. Therefore, the be installed to limit these currents.
coil pitch does not affect waveform
distortion. Applications Requiring 2/3 Pitch
When paralleling, it is desirable to
The zero sequence reactance of a match the pitch of the existing
generator is effective only to generators. If the existing generators
currents which flow in the neutral have 2/3 pitch another generator of
line. Single-phase non-linear loads matching 2/3 pitch is preferable.
usually generate high 3rd harmonic Single-phase non-linear loads that
currents. When these loads are are connected in a balanced manner
connected in a balanced manner to a with a neutral connector directly to
three-phase generator, the 3rd the generator is also an acceptable
harmonic currents add in the neutral application of a 2/3 pitch. An
to produce very high neutral example of this is a 277 V lighting
currents. L-N.
Only where the load is connected
Other Generator Set Selection
directly to the generator does the
Considerations
low zero sequence reactance of a
There are times that a facility will
2/3 pitch generator reduce the
have reconnection issues. For
voltage waveform distortion. If the
example, if a generator set is being
load is supplied through a Delta-Wye
placed at a site and then moved to
transformer, the 3rd harmonic
another site (with perhaps different
currents do not appear in the
applications) the generator set will
generator and the 2/3 pitch winding
have to be sized to meet the
does not help reduce distortion.
different requirements of both sites.
Paralleling and 2/3 Pitch It is also possible that a customer
Paralleling generators of different will know that the facility will be
pitch can cause harmonic distortion. rewired from 480 V to 240 V. Such
A circulating current will flow a situation will require additional
between paralleled generators if consideration when sizing the
they do not have equal generated generator set.
voltage waveforms. The flow is
dependent upon the voltage
©2006 Caterpillar®
Page 104 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 67
Figure 69
Delta Connection
Six Lead Delta Connection
Figure 68
©2006 Caterpillar®
All rights reserved. Page 105
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 106 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Cases where multiple generator set can the units be connected together
installations may prove more by a breaker.
economical are those where there is Synchronizing lights or meters are
a large variation in load during the used in a manual paralleling
course of a day, week, month, or operation to confirm both rotational
year. Such variation is typical in requirements and phase voltage
plants in which operations are requirements have been met.
carried on primarily during the day, Automatic, electronically controlled
while only small loads exist at night. measuring devices are used in
The more closely a generator set automatic paralleling.
comes to being fully loaded, the
The synchronized lights have
greater the fuel economy per
lamps, shown in Figure 72, that dim
kilowatt produced. Therefore, the
and brighten. When the units are in
use of a small generator set to
phase, the lights are at their
power light, off-hour loads, will
dimmest and the breaker can be
often result in long-term fuel
tripped to complete the paralleling. If
economy.
phase sequence is not matched, the
In installations where the load lamps will never be light or dark at
does not vary to the extremes the same time.
encountered between day and night
A synchronizing meter such as a
conditions, it is sometimes profitable
synchroscope, shown in Figure 73
to share the load between several
and Figure 74, can be used instead
small units operating in parallel.
of the synchronizing lights for
When the load is lighter, one or
synchronizing two or more generator
more of the units may be shut
sets. The direction the pointer
down; thereby loading the other
rotates indicates whether the
units closer to capacity. For
frequency of the incoming generator
example, this type of system is
is slower or faster than the
advantageous where load demand is
frequency of the on-line generator.
seasonal or when maintenance is
necessary and power interruption Similarly, the frequency at which
must be avoided. the pointer rotates indicates the
magnitude of difference in speed
Paralleling
between the generator sets. For
Generator sets can be paralleled to
paralleling, engine speed is changed
other generator sets or the utility.
until the synchroscope pointer
To operate in parallel, both units
rotates very slowly (less than 10
must match phase sequence,
rpm), again keeping the incoming
voltage frequency, manage neutral
generator set faster than the on-line
currents, operate with the same
generator set. When the pointer is at
frequency directional rotation and
the zero position, the circuit breaker
produce almost exact sine waves.
can be closed, thereby synchronizing
Only after these conditions are met
the units.
©2006 Caterpillar®
All rights reserved. Page 107
EP Applications, Engine & Generator Sizing Application and Installation Guide
Figure 72
©2006 Caterpillar®
Page 108 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 73
©2006 Caterpillar®
All rights reserved. Page 109
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 110 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
©2006 Caterpillar®
All rights reserved. Page 111
EP Applications, Engine & Generator Sizing Application and Installation Guide
©2006 Caterpillar®
Page 112 All rights reserved.
Application and Installation Guide EP Applications, Engine & Generator Sizing
Figure 75
©2006 Caterpillar®
All rights reserved. Page 113
LEBE5294-01 ©2006 Caterpillar® Printed in U.S.A.
All rights reserved.