Table 5.1 - CONVENTIONAL CONCRETE PROPORTIONS
MINIMUM
APPROXIMATE COMPRESSIVE
MATERIALS REQUIRED PER CU.M. CONCRETE
CONCRETE MIX STRENGTH AT 28
CLASS DAYS
RATIO
PROPORTION CEMENT (40 SAND GRAVEL WATER MAX
Mpa Psi
kg/bag) cu.m. cu.m. (gallons-US)
AAA 1 : 1 : 2 27.6 4000 12.5 0.35 0.7 46 - 57
AA 1 : 1.5 : 3 24.1 3500 10.5 0.4 0.8 42 - 55
A 1 : 2 : 3 20.7 3000 9 0.41 0.82 43 - 53
B 1 : 2 : 4 17.2 2500 8.5 0.42 0.84 40 - 50
C 1 : 2.5 : 5 13.8 2000 6.5 0.46 0.88 38 - 47
D 1 : 3 : 6 10.3 1500 5.6 0.5 0.9 38 - 45

COMPACTING, FINISHING CONCRETE

For Concrete Vibrator,


Cr = 3.75 cu.m. to 4 cu.m.
LOn = 3.875 cu.m./m-hr (Average value)
LPn = 1/LOn
= 0.258 m-hr/cu.m.

For Hand Tools,


Cr = 0.35 cu.m. to 0.5 cu.m.
LOn = 0.425 cu.m./m-hr (Average value)
LPn = 1/LOn
= 2.353 m-hr/cu.m.

Where
Cr = compaction rate change
Basic Pay = Rw x Minimum Wage Rate

Wage Rate Factor


Rural Areas Urban Areas
Un-Skilled 1.00 1.00
Semi-Skilled 1.15 1.20
Skilled 1.25 1.30
Specialty 1.50 1.60
Foreman 1.40 1.50
Lead man:
For Laborers 1.10 1.15
For Semi-Skilled 1.25 1.30
For Skilled 1.35 1.40
For Skilled 1.60 1.70

Table 5.1 - CONVENTIONAL CONCRETE PROPORTIONS

WITH ADMIXTURE SPECIFIED STRENGTH AT 28 DAYS


APPROXIMATE RATIO PROPORTION
CLASS CONCRETE MIX Psi Mpa
RATIO PROPORTION 1 : 1.5 : 2 6000 41.4
1 : 2 : 3 5000 34.5
AAA 1 : 1 : 2 1 : 2 : 4 4000 27.6
AA 1 : 1.5 : 3 1 : 2.5 : 5 3500 24.1
A 1 : 2 : 3 1 : 3 : 5 3000 20.7
B 1 : 2 : 4 1 : 3 : 6 2500 17.2
C 1 : 2.5 : 5 1 : 3.5 : 7 2000 13.8
D 1 : 3 : 6
Table 5.3 - CONCRETE FACTOR FOR WASTE AND SPILLAGE

WASTE AND
WORK DESCRIPTION
SPILLAGE (%)

a. Slab on grade 1
b. Wall footings 1 - 2
c. Small spread footings (less than 2.5 sq.m.) 2 - 3
d. Large spread footings (over 2.5 sq.m.) 1 - 2
e. Foundation shear walls 1 - 2
f. Columns and beams (no slab) 2 - 3
g. Suspended slabs and beams 2
h. Deep bored piles 4 - 5
i Pile cap 3 - 4

Table 5.1 - LABOR RATE FOR MIXING CONCRETE (HAND MIX)

LABOR OUTPUT , CU.M./MAN-HOUR


CLASS CONCRETE PROPORTIONS HAULING DISTANCE
5m 10m 15m
AAA 1 : 1 : 2 (4 gals) 12.5 0.35 0.7
AA 1 : 1.5 : 3 (4.5 gals) 10.5 0.4 0.8
A 1 : 2 : 4 (5.25 gals) 9 0.41 0.82
B 1 : 2.5 : 5 (6.25 gals) 8.5 0.42 0.84
C 1 : 3 : 6 (7.25 gals) 6.5 0.46 0.88

Walking Condition Meters/hour Remarks


Excellent 1500 Open, wide space; flat ground
Above average 1400 Uphill slope < 5%
Average 1300 Uphill slope > 5%
Below average 1200 Restricted Uphill slope > 5%
Table 5.3 - CONCRETE FACTOR FOR WASTE AND SPILLAGE

MANUAL LABOR
LO, (cu.meter/man-hour) LP, m-h/cu.m.
PARTICULARS
100% 45 min-hr. 45 min-hr.
efficiency efficiency efficiency
1 For isolated and Wall Footings 0.48 0.36 2.78
2 For Grade & Tie Beams and Ground Slab 0.48 0.36 2.78
3 For Ground Columns 0.4 0.3 3.33
4 For Suspended Slabs 0.385 0.288 3.47
5 For Floor Beams, Girders and Storey Column 0.355 0.266 3.76
6 For Stairs 0.385 0.288 3.47
7 For Roof Slab and Gutter 0.343 0.257 3.89