Table 5.1 - CONVENTIONAL CONCRETE PROPORTIONS
MINIMUM
APPROXIMATE COMPRESSIVE
MATERIALS REQUIRED PER CU.M. CONCRETE
CONCRETE MIX STRENGTH AT 28
CLASS DAYS
RATIO
PROPORTION CEMENT (40 SAND GRAVEL WATER MAX
Mpa Psi
kg/bag) cu.m. cu.m. (gallons-US)
AAA 1 : 1 : 2 27.6 4000 12.5 0.35 0.7 46 - 57
AA 1 : 1.5 : 3 24.1 3500 10.5 0.4 0.8 42 - 55
A 1 : 2 : 3 20.7 3000 9 0.41 0.82 43 - 53
B 1 : 2 : 4 17.2 2500 8.5 0.42 0.84 40 - 50
C 1 : 2.5 : 5 13.8 2000 6.5 0.46 0.88 38 - 47
D 1 : 3 : 6 10.3 1500 5.6 0.5 0.9 38 - 45
Where
Cr = compaction rate change
Basic Pay = Rw x Minimum Wage Rate
WASTE AND
WORK DESCRIPTION
SPILLAGE (%)
a. Slab on grade 1
b. Wall footings 1 - 2
c. Small spread footings (less than 2.5 sq.m.) 2 - 3
d. Large spread footings (over 2.5 sq.m.) 1 - 2
e. Foundation shear walls 1 - 2
f. Columns and beams (no slab) 2 - 3
g. Suspended slabs and beams 2
h. Deep bored piles 4 - 5
i Pile cap 3 - 4
MANUAL LABOR
LO, (cu.meter/man-hour) LP, m-h/cu.m.
PARTICULARS
100% 45 min-hr. 45 min-hr.
efficiency efficiency efficiency
1 For isolated and Wall Footings 0.48 0.36 2.78
2 For Grade & Tie Beams and Ground Slab 0.48 0.36 2.78
3 For Ground Columns 0.4 0.3 3.33
4 For Suspended Slabs 0.385 0.288 3.47
5 For Floor Beams, Girders and Storey Column 0.355 0.266 3.76
6 For Stairs 0.385 0.288 3.47
7 For Roof Slab and Gutter 0.343 0.257 3.89