Professional Documents
Culture Documents
A business system refers to the total picture of men, machine, materials and paper
work in
in-volved
volved in the implementation of any phase of a project
project. The purchasing system
system,
for example, involves purchase officers, vendors, materials, specifications, general
purchase conditions and purchase order.
P
Procedure
d
A procedure, on the other hand, is a planned sequence of operations for carrying out a
recurring
ecu g worko involved
o ed in a syste
system uuniformly
o ya and
d co
consistently.
s ste t y In tthe
e pu
purchase
c ase syste
system,,
procedures need to be developed for shortlisting vendors, issuing enquiry to them,
evaluation of offer and finally placement of order.
SYSTEM CHARACTERISTICS
2. The elements are organized systematically = There is most of the time a pattern
in which the elements are arranged
3. The elements are interrelated = Each element has its own individual function to
perform, it in turn makes other elements perform. The absence of one element in a
system
y will disable another element if the latter depends
p for its input
p on the output
p
of the former.
2. natural system
3. self-regulating system
4. controlled system
1 Th
1. The system
t mustt be
b as natural
t l as possible.
ibl OOne cannott putt a tiger
ti and
d sheep
h
together and hope that they would work harmoniously for a common cause.
2. The system
y must be information bound. The elements in the system
y must
communicate with each other. They must continuously send information and also
receive feed-back information till the system outlives its purpose.
The design philosophy is to create a set of inter-related elements so that they can
regulate and control themselves without outside intervention e.g. When a contract is
awarded for a system, say water supply and distribution, not only the number of
coordination and intervention points get reduced but it also offers the system
contractor flexibility in decision making. On the other hand, if for the same system the
consultant does the design, the owner does the procurement, the various vendors
supply the equipment and the contractors of different trades are engaged for civil,
mechani-cal and electrical works, then the controllability of the system would not be as
assured
WORK BREAKDOWN STRUCTURE (WBS)
Work breakdown structure, WBS in short, is a technique which breaks down a work
p
into its components and at the same time establishes the connections between the
components on the lines of a family tree. Work breakdown structure, thus, enables
the integration of people, hardware and software into a total project work system
PROJECT EXECUTION PLAN (PEP)
1. Contracting plan
This is the first step in the preparation of a project execution plan. Owners
invariably need some agencies with whom they can share responsibilities.
Having decided the number of contracts and their scope, the owner is now in a
position to set his own house in order. Normally, the owner's intervention can be
in three ways:
a) Coordinate the various interfaces between the various agencies lined up for
execution.
b) Activate and motivate each agency so that they perform as they should.
Since project management calls for organization of disorganized work forces, a heavy
emphasis has to be placed on routine systems and procedure so that no intervention
is required in the day-to-day
day to day operation of a system. There are at least eight routine
sub-systems of project management for which appropriate procedures can be
conceived right at the start of the project implementation.
1. Contract management
2. Configuration management
3. Time management
4
4. C t managementt
Cost
5. Fund management
6. Materials management
7. Man management
g
8. Communications management
SUB-SYSTEMS OF PROJECT MANAGEMENT
1. Contracts Management
1. Prequalification procedure
2 General conditions of contract
2.
3. Tendering procedure
4. Procedure for tender evaluation and award of a contract
5. Procedure for signing an agreement
6 Measurement
6. M t procedure
d for
f completed
l t d workk
7. Billing and payment procedure
8. Free issue material reconciliation procedure
9. Change g order pprocedure
10. Work inspection and acceptance procedure
11. Completed work take-over procedure
2
2. C fi
Configuration
ti Management
M t
1. Project
1 P j t costt estimation
ti ti procedured
2. Cost coding and cost accumulation structure
3. Procedure for cost updatirg and revision
4. Procedure for manhour control
5. Procedure for value engineering and ongoing cost reduction
6. Procedure for price evaluation of bids
7. Procedure for commitment control
8 Procedure for change control
8.
9. Procedure for cost reporting
10. Procedure for project cost review
11. Procedure for expenditure control
12. Procedure for cost and productivity audits
8
8. Fund Management
A decision network, on the other hand, assumes that the activity itself may vary.
Accordingly, some probability is associated with each possible alternative activity;
the sum of the probabilities for the various alternatives
alternatives, of course
course, equals 1
1.0.
0 The
time duration on each alternative is, however, deterministic.
GERT network
The most complex network is perhaps the GERT network. In a GERT network both
activity and time are considered probabilistic. Further, a GERT network for the first
time provides for repetition of an earlier activity based on feedback
feedback. Though the
scenario it represents is quite realistic, the arithmetics involved are complex.