You are on page 1of 13

Legal Note

Claims for Extension of Time and Additional


Payment under Common Law FIDIC:
Civil Law Analysis
Salwa A. Fawzy 1; Islam H. El-adaway, F.ASCE 2; Louis Perreau-Saussine 3;
Mohamed S. Abdel Wahab 4; and Tarek H. Hamed 5
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

Abstract: Lately, Egypt has been at the forefront of multiple megaconstruction projects and the same trend is expected to continue in the
future. Since such projects are mainly carried out by international contractors, the associated construction contracts mainly use the stan-
dard conditions of contract for international projects published by the Fédération Internationale des Ingénieurs-Conseils (FIDIC). The
FIDIC is based on legal concepts rooted in the common law system, whereas the legal doctrine that Egypt follows is founded upon civil law
principles as mandated by the Egyptian civil law (ECL). Therefore, employers, contractors, international financing organizations, en-
gineers, and lawyers, who use FIDIC in Egypt, need to understand the interpretation of the FIDIC provisions against a civil law back-
ground. This paper uses a multistep interdependent desktop research methodology to investigate the application of the general provisions
of extension of time and additional payment of the FIDIC Conditions of Contract for Construction–Red Book 1999, i.e., FIDIC (CONS), in
the context of ECL. To do so, provisions of extension of time and additional payment were studied separately under the FIDIC (CONS),
and similarly under the ECL. Consequently, the authors conducted a comparative analysis to recognize similarities and differences be-
tween both FIDIC (CONS) and ECL. Finally, the authors identified gaps and requirements for successful application of FIDIC (CONS)
under ECL. The analysis reveals that the ECL does not provide clear procedures and mechanisms regulating the contractor’s entitlement to
extension of time and/or additional payment. Accordingly, it is recommended to add a new, three-part article to the ECL as well as to
amend the first two paragraphs of Subclause 20.1 in the FIDIC (CONS). It is envisaged that this research would help stakeholders in the
construction industry, entering into projects based on the FIDIC (CONS) in Egypt, to properly manage time provisions and the associated
delays and risks leading to additional payment in the construction contracts. This should help minimize, as much as possible, disputes
associated with and/or resulting from the delays and claims for extensions of time and/or additional payment. Since most of the Middle
East countries follow civil law jurisdictions, and are most heavily influenced by the ECL, it is also envisaged that this research would
support effective and efficient contract administration of construction projects in the ME region. DOI: 10.1061/(ASCE)LA.1943-
4170.0000276. © 2018 American Society of Civil Engineers.

Introduction in the heart of the Suez Gulf. This zone is expected to provide
Egyptian and foreign investors with top-class infrastructure, market
Egypt has an important role in the economic growth of the coun- access, and streamlined administrative procedures. However, de-
tries in the Middle East region (Ezeldin and Abdel-Ghany 2013). lays in the Egyptian construction market continue to be a repetitive
To this end, Egypt is planning to establish a special economic zone and concerning phenomenon (Ezeldin and Abdel-Ghany 2013). In
fact, a study revealed that the main causes of delay in construction
1 projects in Egypt are the following: financing by contractors during
Contracts Associate Director, Dar Al Mimar Group; Instructor, Engi-
neering and Sciences Services, American Univ. in Cairo, 1 Abu Bakr El construction, delays in payment by owners, design changes by or
Seddik St., Dokki, Giza, Egypt. Email: salwafawzy@gmail.com on behalf of owners during construction, partial payments during
2 construction, and nonutilization of professional construction/
Hurst-McCarthy Professor of Construction Engineering and Manage-
ment, Dept. of Civil, Architectural, and Environmental Engineering and contractual management (Abd El-Razek et al. 2008). Likewise,
Dept. of Engineering Management and Systems Engineering, Missouri the construction industry in the Middle East (ME) is at the center
Univ. of Science and Technology, 228 Butler-Carlton Hall, 1401 N. Pine for multiple megaconstruction projects and is impacted—more or
St., Rolla, MO 65401 (corresponding author). Email: eladaway@mst.edu
3 less—by the same problems in the Egyptian market (Grose and
Professor of Law, Paris-Dauphine Univ.; PSL Research Univ., Paris,
France. Email: louis.perreau-saussine@dauphine.fr Shlah 2015).
4
Chair of Private International Law and Professor of Dispute Resolu- Most of the contracts used for construction projects in Egypt,
tion, Cairo Univ.; Founding Partner and Head of International Arbitration, predominantly use the standard conditions of contract for
Zulficar & Partners Law Firm, Cairo, Egypt. Email: msw@zulficarpartners international projects published by the Fédération Internationale
.com des Ingénieurs-Conseils (FIDIC) (Skaik 2009). In fact, FIDIC is
5
Instructor for Construction Contracts and Claims, Faculty of Engineer- the established form of construction contract in the ME region
ing, Cairo Univ., Cairo, Egypt. Email: tarek3hs@yahoo.com (Rose 2009). It is used in public-works contracts of many of the
Note. This manuscript was submitted on December 20, 2017; approved on
March 29, 2018; published online on June 28, 2018. Discussion period open
most important construction and industrial projects in Egypt; for
until November 28, 2018; separate discussions must be submitted for indivi- example, the Greater Cairo Waste Water Project, the Cairo Metro
dual papers. This legal note is part of the Journal of Legal Affairs and Dispute Project, Demietta Port, and terminal two of Cairo International
Resolution in Engineering and Construction, © ASCE, ISSN 1943-4162. Airport. Moreover, the FIDIC conditions are adopted in all projects

© ASCE 06518002-1 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


financed by the World Bank and by the USAID (United States Aid under the ECL, this research will focus on contracts of the
for International Development), which, in turn, finance a significant same characteristics. Moreover, the construction contracts in the
number of major infrastructure projects in Egypt (Sarie-El Din Egyptian legal system are classified into civil contracts and admin-
1994). istrative contracts, which are governed by two different systems of
The legal concepts in the FIDIC are based on the common law law, depending on the nature of the employer. This research will be
system (Axel-Volkmar and Gotz-Sebastian 2010; Bunni 2005). In limited to the study of civil construction contracts. Further, the spe-
1999, FIDIC published the new suite of standard contracts. This cific provisions entitling the contractor to extension of time and/or
suite includes the conditions of contract for construction, which additional payment under the FIDIC (CONS)—for example, de-
is recommended for building and engineering works designed layed drawings and instructions, unforeseeable physical conditions,
by or on behalf of the employer, although some elements of design setting out errors, : : : , etc.—have different applications under the
may be given to the contractor, known as the new Red Book, which Egyptian Civil Code (ECC). These specific provisions will not be
is referred to hereinafter as FIDIC [Conditions of Contract for Con- dealt with in this paper. The analysis will cover the application of
struction (CONS)]. A survey of the users’ feelings about the FIDIC the general provisions of extension of time and/or additional pay-
contract policy in general, and the FIDIC (CONS) in particular, was ment of the FIDIC (CONS) under the ECL, being the applicable law
of the contract.
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

undertaken by Reading University in England at the combined re-


quest of the European International Contractors (EIC) and FIDIC. Accordingly, the associated research objectives include:
The final survey report was published in June 1996 and provided, (1) highlighting similarities and differences between the relevant
among other data, specific contractual issues relating to the Red provisions under the FIDIC (CONS) and the ECL; and (2) providing
Book, including applicability to civil law jurisdictions (EIC/FIDIC recommendations to amend the relevant provisions under the ECL
Questionnaire Survey 1996). and/or under the FIDIC (CONS).
Egypt bases its Egyptian Civil Law (ECL) on a mixture of
French civil law and Shari’a law. In turn, most laws used in coun-
tries of the ME region are heavily influenced by the ECL. It is rather Background Information
ironic that most of these countries base their construction contracts
on the FIDIC forms, which are based largely on common law prin-
ciples (Marke 2015). Unfortunately, contractors operating in Delays and Extension of Time
Egypt—and the ME region—often fail to appreciate the magnitude Delayed completion is one of the most common problems facing
of the impact of contract interpretation in view of the local laws in construction projects. However, delayed completion is not unique
the region. Local laws in the ME should be considered carefully by to the construction industry. It also happens in other industries, in-
both contractors and employers, as part of a proper risk evaluation cluding, for example, aerospace projects, ship building, IT, oil and
(Abu-Manneh 2008). gas, rail transport, and petrochemical and process plants. Delay is
Under the ECL, risks are allocated among the employer and the also not unique to a particular culture or jurisdiction; delay occurs
contractor via the conditions of the contract agreed upon between in the United Kingdom as it occurs in Russia, the United States,
the parties, the provisions of law, or both. Relevantly, under the Hong Kong, the ME, Pakistan, India, South Africa, Australia, and
ECL, building and construction contracts do not have separate the forests of Peru. Delayed completion happens in all industries,
rules; rather, there are certain rules that apply to all contracts for jurisdictions, and cultures in which a unique product, the character
works (muqawala contracts), including building and construction of which is expected to change, is created over a period of time by a
ones. However, building and construction contracts differ from combination of specialized resources (Pickavance 2010; El-adaway
other muqawala contracts in many aspects; for instance, under et al. 2014; Fawzy and El-adaway 2012).
building and construction contracts, the costs and expenses to Under the common law, extension-of-time provisions include
execute the works as well as the time for completion thereof are the agreement of the parties under a building contract on the
much greater than those under other muqawala contracts (Hamed apportioning of risk of delay between them [see Henry Boot Con-
et al. 2012). The provisions of muqawala contracts under the struction, Ltd., v. Central Lancashire New Town Development,
Egyptian Civil Law are affected by the following factors (Hamed Ltd.]. The causes of delay could be the responsibility of the em-
2010): ployer, the contractor, or neither of them, i.e., neutral events. Most
• The provisions are general, i.e., they have been set for all building contracts contain express provisions under which the time
muqawala contracts, not only for construction contracts. for completion allowed for the contractor to undertake and com-
• The provisions are brief, which is consistent with the civil-based plete the works can be adjusted. These provisions provide mostly
legal systems. for delays that are neither caused by the contractor nor within his
• The provisions are stable for long periods of time, notwithstand- responsibility. Such provisions obviously benefit the contractor,
ing that the construction industry is a continuously developing since they eliminate liability to pay delay damages for its failure
industry. to complete by the original completion date, during a valid ex-
tended period of time in accordance with the contract (Murdoch
and Hughes 2008; Fawzy et al. 2015). Extension-of-time provi-
Goal and Objectives sions also provide certainty in the event of a delay caused by or
attributable to the contractor under the contract (Furst and
The goal of this research was to study the provisions of extension Ramsey 2012).
of time and/or additional payment under the common law-based Extension-of-time clauses are also beneficial for the employer
FIDIC (CONS) within the context of the ECL. It is worth noting under the common law. Such clauses enable the original comple-
that the FIDIC (CONS) is recommended for building and engineer- tion date to be readjusted, in which delay to the completion of the
ing works designed by or on behalf of the employer, although some works has been the employer’s responsibility, thereby retaining
elements of design may be given to the contractor. Furthermore, the benefit of a clearly identified completion date and consequently
the FIDIC (CONS) is a remeasured contract. Accordingly, when any related entitlement on the employer’s part to liquidated dam-
examining the extension of time and additional payment provisions ages [see Holme v. Guppy and Peak Construction (Liverpool),

© ASCE 06518002-2 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


Ltd., v. McKinney Foundations, Ltd.,] (Furst and Ramsey 2012; Since the prevention principle was developed under the com-
MacRoberts Solicitors 2008; Knowles 2012; Fawzy et al. 2015). mon law, careful drafting of extension-of-time clauses has avoided
Because the FIDIC concepts are based on the common law many of the problems caused by its operation. Drafters of many
system, it is worthwhile to dwell upon the issues of delays and ex- standard forms of contract now do this by including extension-of-
tensions of time and their relation to liquidated damages, under the time clauses based expressly on acts of prevention or default on the
common law. In this context, the time for completion can only be part of the employer or his agents, thereby successfully defeating
extended where the contract permits, and strictly in accordance attempts to avoid the contractual liquidated damages.
with the contract provisions (Murdoch and Hughes 2008). Accord- Under the common law, if there is no express provision to
ingly, extension-of-time clauses should be drafted to account for all extend the time for completion for a delay caused by events over
delays that may be the responsibility of the employer (Gibson which the contractor may genuinely have no control, the contrac-
2008). Further, if the contract does not provide grounds for extend- tor takes the risk of such delay, unless these events are such as to
ing the completion date due to an employer’s delay event, and if frustrate the contract entirely, which will only rarely occur in a
completion is delayed due to such delay event by the employer, the construction context (see Percy Bilton, Ltd., v. Greater London
employer will lose his right to deduct liquidated damages in respect Council) (Bunni 2005; Wallace 2012). Examples of such events
of the contractor’s delay in completion. Effective contracts avoid
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

could be weather, strikes, labor or materials shortages, or damage


this by having a fully comprehensive extension-of-time clause that or obstruction by third parties for whom the employer is not
properly caters for all delays by the employer or the architect responsible. In common law jurisdictions, it is important to in-
(Knowles 2012; Fawzy and El-adaway 2014). clude in the contract a precise list of neutral events; otherwise,
It is also important to note that, under the common law, if the they cannot constitute a reason for the implementation of the
contractor is prevented from completing by the specified comple- extension-of-time clause, and in case of delay due to any of these
tion date, due to the employer’s responsibility, and there is no cor- events, the contractor will remain liable to pay damages to the
responding right to extend the time for completion or it is not employer (Rosher 2014).
properly extended, time becomes at large. If time becomes at large, Finally, where the ground of extension of time would otherwise
the employer would no longer be entitled to insist upon the com- be the contractor’s risk, the extension of time is purely a conces-
pletion date and there is no enforceable date for completion of the sion, i.e., the contractor shall be entitled to extension of time, but
works. However, the contractor is still under the obligation to com- not to additional payment, such as in the case of inclement weather.
plete the works within a so-called reasonable time (Pickavance However, when the extension of time is as a result of an act or de-
2006). fault of the employer such as issuing variations or giving late in-
Time is said to be at large as a result of what is known as the structions, the contractor may be entitled also to additional payment
prevention principle, i.e., a party cannot insist on the performance (Uff 2009).
of a contractual obligation by the other if it is itself the cause of the
nonperformance (Fawzy and El-adaway 2014 and see Barque
Quilpe, Ltd., v. Brown). The cause of delay attributable to the Contractor’s Claims for Additional Payment
employer is often referred to as an act of prevention. Such acts It has been said that “claims are a fact of life” and “claims are here
of prevention could be a breach of contract by the employer, such to stay.” It has also been said that “more than a quarter of the money
as a delay in giving the contractor essential instructions [see Dodd paid by employers to contractors is now based on negotiations that
v. Churton], failure by the employer to give possession of the site take place after the contract is signed.” If claims are unwelcomed
[see Holme v. Guppy], delay in providing plans [see Roberts v. yet unavoidable, then at least the construction project stakeholders
Bury Commissioners, or failing to deliver components it is bound should equip themselves to deal with them efficiently and expedi-
to provide under the contract [see Perini Pacific v. Greater Van- tiously and minimize the cost in terms of both money and staff re-
couver Sewerage and Drainage District and Furst and Ramsey
sources (Hughes 1985). In fact, few civil engineering contracts of
2012]. Contrarily, an act of prevention by the employer could
any size reach completion without claims being made by the con-
be a perfectly legitimate action that causes a delay beyond the time
tractors for extension of time or additional payment (Powell-
for completion, such as instructing additional work or other varia-
Smith 1989).
tions [see Dodd v. Churton]. These acts of prevention by the em-
Claim is a general term for the assertion of a right to money,
ployer would release the contractor from its obligation to complete
property, or remedy. However, in the construction context, the
the works within a fixed construction period or date, absent of an
word claim is commonly used to describe any application by
effective extension-of-time clause that provides otherwise [see
the contractor for additional payment that arises other than under
Holme v. Guppy and Dodd v. Churton] (Fawzy and El-adaway
the ordinary contract provisions for payment. In addition, the
2014).
word claim is also used to describe a contractor’s application
The importance of time becoming at large lies in the fact that the
for extension of time for completion (Powell-Smith 1989;
employer loses his entitlement to deduct liquidated damages for
Chappell et al. 2005). In this regard, Subclause 20.1 of the FIDIC
delay, and can claim only for unliquidated damages, which are
(CONS) states that
those losses resulting from the delay that can actually be proven
(Murdoch and Hughes 2008). Moreover, even when the delay If the Contractor considers himself to be entitled to any ex-
caused by the employer is a very small part of the overall delay, tension of the Time for Completion and/or any additional pay-
the employer cannot simply discount this delay and claim liqui- ment, under any Clause of these Conditions or otherwise in
dated damages for the remainder, because the provision for liqui- connection with the Contract, the Contractor shall give notice
dated damages fails altogether (Murdoch and Hughes 2008). to the Engineer, describing the event or circumstance giving
Therefore, for the employer to maintain entitlement to deduct liqui- rise to the claim.
dated damages for the contractor’s delays, it is of his own benefit to
include a provision in the contract that allows for extending the It is clear then that the FIDIC (CONS) seems to ignore claims
time for completion in case any of the occurring delays are the em- arising from anything other than the assertion for an entitlement to
ployer’s responsibility (Fawzy et al. 2015). extension of time or additional payment (Bunni 2005).

© ASCE 06518002-3 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


Fig. 1. Research methodology.

The construction contract is unique in that most construction 1. A Variation [unless an adjustment to the Time for Completion
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

contracts seek to provide for a specific remedy in the event of has been agreed under Subclause 13.3 (Variation Procedure)]
any breach of the terms and conditions within its framework or other substantial change in the quantity of an item of work
and/or for a contractual entitlement in respect of specified events. included in the Contract;
The genesis and development of the standard form of construction 2. A cause of delay giving an entitlement to extension of time un-
contract was based on the need to redefine and reapportion the risk der a Subclause of these Conditions;
ascribed to the respective parties by the applicable law. Most stan- 3. Exceptionally adverse climatic conditions;
dard forms of construction contracts include a mechanism to give 4. Unforeseeable shortages in the availability of Personnel or
one party a certain remedy if a specified event arises. The risk of Goods caused by epidemic or governmental actions; or
that event, which would otherwise remain with that party, is trans- 5. Any delay, impediment, or prevention caused by or attributable
ferred to the other party. Whether the remedy sought is in respect of to the Employer, the Employer’s Personnel, or the Employer’s
a breach of contract by the other party, or for the occurrence of a other contractors on the Site.
specified event, all construction contracts place an obligation on the Some of the aforementioned events are attributable to the em-
party seeking to avail itself of that remedy to follow a set proce- ployer and others are attributable to neither the employer nor the
dures, referred to as the claims procedure. The first step of the contractor.
claims procedure of any construction contract is the making of a Subclause 8.4 does not include a descriptive list of all events that
notice (Bunni 2005). This paper is concerned only with the general can give rise to an extension of time. Instead, in addition to giving a
provisions related to the contractor’s entitlement to additional pay- short list of such events, Subparagraph (b) refers to other sub-
ment and not to the analysis of the individual events that raise the clauses that entitle the contractor to the extension of time. These
contractor’s entitlement thereto. subclauses can be summarized as follows:
• Subclause 1.9: Delayed Drawings or Instructions
• Subclause 2.1: Right of Access to the Site
Methodology • Subclause 4.7: Setting Out
• Subclause 4.12: Unforeseeable Physical Conditions
As shown in Fig. 1, this paper uses a multistep interdependent desk- • Subclause 4.24: Fossils
top research methodology to analyze the issues of delays and ex- • Subclause 7.4: Testing
tension of time, as well as the contractor’s claims for additional • Subclause 8.5: Delays Caused by Authorities
payment. First, provisions related to delays and extension of time • Subclause 8.9: Consequences of Suspension
are investigated in terms of entitlement and procedural matters • Subclause 10.3: Interference with Tests on Completion
under the FIDIC (CONS). Second, the same provisions are exam- • Subclause 13.7: Adjustments for Changes in Legislation
ined under the ECL. Third, the authors critically analyze the appli- • Subclause 16.1: Contractor’s Entitlement to Suspend Work
cation of the relevant provisions under the FIDIC (CONS) in the • Subclause 17.4: Consequences of Employer’s Risks
context of the ECL as the applicable law of the contract. The same • Subclause 19.4: Consequences of Force Majeure
three-step analysis is undertaken for issues of claims for additional It is further noted that under Subclause 8.4(c), the contractor is
payment. Finally, the authors make recommendations as to the entitled to an extension of time for climatic conditions which are
amendments required to the relevant provision under the ECL exceptionally adverse. However, there is no equivalent entitlement
and to FIDIC (CONS). Case law is used in developing and support- to additional payment in respect of the delay resulting from such
ing all arguments provided in this research. event. However, if such an event is categorized as one of the em-
ployer’s risks and satisfies the criteria specified in Subclause 17.3(h)
as “any operation of the forces of nature which is Unforeseeable or
against which an experienced contractor could not reasonably have
Results and Analysis
been expected to have taken adequate preventative precautions,”
then Subclause 17.4 entitles the contractor to compensation for rec-
Delays and Extension of Time under the FIDIC (CONS) tifying the damage attributable to such climatic conditions (Booen
2000). It is noted that the entitlements to extension of time do not
Entitlement to Extension of Time themselves entitle the contractor to additional cost and in some
Subclause 8.4 (Extension of Time) of the FIDIC (CONS) details cases to profit. This depends on the event that gives rise to the claim
the delay events that could possibly raise entitlement to extension for an extension of time and the relevant subclause concerned
of time under the subject contract. Such events comprise the (Glover and Hughes 2006). Subclause 8.5 [Delays Caused by
following: Authorities] raises entitlement to extension of time only.

© ASCE 06518002-4 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


Fig. 2. Procedures for claims under the FIDIC (CONS).

Glover and Hughes (2006) provided samples for the subclauses precedent to such rights [see Bremer Handelsgesellschaft mbh
that raise entitlement to extension of time and cost and those raising v. Vanden Avenne-Izegem; Maidenhead Electrical Services,
entitlement to extension of time, cost, and reasonable profit. The Ltd., v. Johnson Control Systems, Ltd.; City Inn, Ltd., v. Shep-
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

following subclauses raise entitlement to extension of time and herd Construction, Ltd.; Steria, Ltd., v. Sigma Wireless Commu-
cost: nications, Ltd.] (Knowles 2012).
• Subclause 4.12: Unforeseeable Physical Conditions By applying the aforementioned to the wording in the FIDIC
• Subclause 4.24: Fossils (CONS), according to Subclause 20.1, “If the Contractor fails to
• Subclause 8.9: Consequences of Suspension give notice of a claim within such period of 28 days, the time
• Subclause 13.7: Adjustments for Changes in Legislation for completion shall not be extended : : : ”. Hence, it is contended
• Subclause 17.4: Consequences of Employer’s Risks that the service of a notice, in accordance with the provisions and
• Subclause 19.4: Consequences of Force Majeure time limits required by Subclause 20.1, is considered a condition
The following subclauses raise entitlement to extension of time, precedent to the contractor’s entitlement to extension of time.
cost, and reasonable profit: Failure by the contractor to comply with the notice requirements
• Subclause 1.9: Delayed Drawings or Instructions will result in loss of his right to an extension of time. The notices
• Subclause 2.1: Right of Access to the Site should comply with Subclause 1.3 (Communications) of the FIDIC
• Subclause 4.7: Setting Out (CONS). Furthermore, the progress reports submitted by the con-
• Subclause 7.4: Testing tractor, under Subclause 4.21 [Progress Reports] should include a
• Subclause 10.3: Interference with Tests on Completion list of notices given under Subclause 20.1 [Contractor’s Claims]
• Subclause 16.1: Contractor’s Entitlement to Suspend Work (Booen 2000).
As shown in Fig. 2, Subclause 20.1 goes on to state the
Procedures and Procedural Breaches
following:
The procedures for agreement or determination of extension of
time under the FIDIC (CONS) are the same procedures for addi- Within 42 days after the Contractor became aware (or should
tional payment and are provided for in Subclause 20.1 [Contrac- have become aware) of the event or circumstance giving rise
tor’s Claims] of the FIDIC (CONS), which provides, first, the to the claim, or within such other period as may be proposed
following: by the Contractor and approved by the Engineer, the Contrac-
tor shall send to the Engineer a fully detailed claim which
If the Contractor considers himself to be entitled to any ex-
includes full supporting particulars of the basis of the claim
tension of the Time for Completion and/or any additional pay-
ment, under any Clause of these Conditions or otherwise in and of the extension of time and/or additional payment
connection with the Contract, the Contractor shall give notice claimed : : :
to the Engineer, describing the event or circumstance giving As for the procedures for extension of time for events having a
rise to the claim. The notice shall be given as soon as prac- continuing effect, Subclause 20.1 states that:
ticable, and not later than 28 days after the Contractor became
aware, or should have become aware, of the event or If the event or circumstance giving rise to the claim has a
circumstance. continuing effect:
If the Contractor fails to give notice of a claim within such (a) this fully detailed claim shall be considered as interim;
period of 28 days, the Time for Completion shall not be ex- (b) the Contractor shall send further interim claims at
tended, the Contractor shall not be entitled to additional pay- monthly intervals, giving the accumulated delay and/or
ment, and the Employer shall be discharged from all liability amount claimed, and such further particulars as the Engineer
in connection with the claim. Otherwise, the following provi- may reasonably require; and
sions of this Sub-Clause shall apply : : : (c) the Contractor shall send a final claim within 28 days
after the end of the effects resulting from the event or circum-
Courts, in the common law legal system, are less likely to con-
stance, or within such other period as may be proposed by the
strue the requirements as to the form and content of the notice
Contractor and approved by the Engineer : : :
required under claim clauses too strictly [see Tersons, Ltd., v.
Stevenage Development Corp; and Rees & Kirby v. Swansea In the last paragraph of Subclause 20.1, it is stated that:
C.C.]. Furthermore, courts are reluctant to treat the notices as
conditions precedent to the contractor’s entitlement to extension If the Contractor fails to comply with this or another Sub-
of time, unless they are expressly stated as being so. In other Clause in relation to any claim, any extension of time and/
words, failure of a contractor to serve a proper delay notice will or additional payment shall take account of the extent (if
not result in the loss of rights to an extension of time, unless the any) to which the failure has prevented or prejudiced proper
contract expressly states that the service of a notice is a condition investigation of the claim : : :

© ASCE 06518002-5 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

Fig. 3. Procedures for claims events having continuing effects under the FIDIC (CONS).

The preceding provision could be interpreted to include the Delays and Extension of Time under the Egyptian
contractor’s failure to properly follow the procedures pertaining Civil Law
to providing the details of the claim for extension of time
(Fawzy and El-adaway 2012). Therefore, if a breach by the con- Entitlement to Extension of Time
tractor, in that regard, had caused a delay that would otherwise Under the ECL, the contractor is under obligation to complete the
have been avoidable, then the contractor would not be entitled works within a specific duration. If the employer and contractor do
to recover for that avoidable delay (Glover and Hughes 2006). not agree on the duration for completion, the contractor will be
The contractor shall be entitled to payment for any such part under obligation to complete the work within a reasonable period,
of the claim since he has been able to substantiate. This is ex- taking into consideration the nature of the works, the trade usage,
plained visually in Fig. 3. and the contractor’s capabilities and methods (Al-Sanhuri 1989;
Subclause 20.1 provides the time period for the engineer to Shanab 1963). Delayed work by the contractor or malfunctioning
respond to a claim for extension of time. This subclause states works is considered a nonperformance (see Egyptian Cassation)
the following: (Al-Sanhuri 1989; Axel-Volkmar and Gotz-Sebastian 2010). In this
Within 42 days after receiving a claim or any further partic- section, delays attributable to the employer and neutral events are
ulars supporting a previous claim, or within such other discussed in the context of the ECL.
period as may be proposed by the Engineer and approved There are no express provisions in the muqawala section in the
by the Contractor, the Engineer shall respond with approval, ECC specifically regulating the contractor’s exemption from pay-
or with disapproval and detailed comments. He may also re- ing damages for delay in performance, which was caused by em-
quest any necessary further particulars, but shall nevertheless ployer’s acts or other events that resulted in delay in completion.
give his response on the principles of the claim within Accordingly, the general principles of contract law shall apply in
such time. such case. In this relation, Article 215 of the ECC stipulates the
following:
In addition, Subclause 20.1 states that the engineer’s determi-
nation shall be made pursuant to Subclause 3.5 as follows: When specific performance by the debtor is impossible, he
will be ordered to pay damages for non-performance of his
Within the above defined period of 42 days, the Engineer shall obligation, unless he establishes that the impossibility of per-
proceed in accordance with Sub-Clause 3.5 [Determinations] formance arose from an external cause beyond his control.
to agree or determine (i) the extension (if any) of the Time for The same principle will apply, if the debtor is late in the per-
Completion (before or after its expiry) in accordance with formance of his obligation.
Sub-Clause 8.4 [Extension of Time for Completion], and/or
(ii) the additional payment (if any) to which the Contractor Translating this to a construction setting, if the contractor proves
is entitled under the Contract. that the delay in performance of his obligation (in this case, delays
to completion of the works) was due to an external cause beyond
It is interesting to note that, since the FIDIC concepts are his control, the contractor would be exempted from paying dam-
based on the common law system, Subclause 8.4 sets out as ages for failure to fulfill his commitments. The external cause
one of the events giving the contractor entitlement to extension exempting the contractor from his liability to pay delay damages
of time as the following: “(e) any delay, impediment or preven- can be applied to the case in which the contractor has been delayed
tion caused by or attributable to the Employer, the employer’s by an act of the employer, such as breach of contract or the instruc-
personnel, or the employer’s other contractors.” The foregoing tion of additional works (Al-Sanhuri 1989; Bellhouse and Cowan
provision is a catchall provision for any events that are the 2008). Therefore, if the employer is delayed in the delivery of
responsibility of the employer. The goal of such provision is to material he was obliged to provide, and such delay resulted in
avoid any possibility of time becoming at large due to an act of the delay to the construction works, the contractor shall not be held
prevention for a cause for which the employer is responsible. responsible for the delay. Moreover, the contractor is relieved from
This catchall provision is included in other standard forms of responsibility for a delay if the employer delays the payment of
contracts for the same purpose (Chappell et al. 2005; Fawzy amounts due to the contractor, and as a result, the contractor is de-
and El-adaway 2014). layed in completion. It is worth mentioning that such an act by the

© ASCE 06518002-6 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


employer resulting in delay to the works does not need to be a provisions does not imply absence of entitlement, it is recom-
breach of contract. I If the employer issues instructions for varia- mended, for unequivocal certainty, to include such specific provi-
tions leading to contractor’s delay in completion, the contractor sion in the ECC, to regulate the contractor’s entitlement to
shall not be held responsible for such delay, if he executes the var- extension of time and the procedures related thereto. However,
iations within a reasonable period [see French Court of Cassation it is advisable that such provision be included in the same provision
10.12.1913 Sirey 1914 (Bull. Som.) 1-19; French Court of Cassa- related to the contractor’s entitlement to additional payment as a
tion 27.02.1888 Dalloz 89-1-31; Cassation 01.06.1972 Cassation result of an event attributable to the employer or for which he is
Cases year 23 no 166 p 1062; Mixed Appeal 02.05.1906 no 18 p responsible (discussed in the “Contractor’s Claims for Additional
223] (Al-Sanhuri 1989; Shanab 1963; Fawzy et al. 2015). More- Payment” section in this paper).
over, it should be noted that, under the ECL, the external cause,
which exempts the contractor from paying damages for his delay
in performance, does not only apply to delays caused by the em- Application of the FIDIC (CONS) under the Egyptian
ployer, but also to delays caused by a neutral event. Civil Law
Furthermore Article 216 of the ECC states the following: It was mentioned that the FIDIC (CONS) provides for events that
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

could possibly entitle the contractor to extension of time under


The judge may reduce the amount of damages or may even
Subclause 8.4. Subparagraph (b) of Subclause 8.4 refers to other
refuse to allow damages if the creditor, by his own fault, has
subclauses that entitle the contractor to extension of time. Some
contributed to the cause of, or increased, the loss.
such events that entitle the contractor to extension of time are
According to the aforementioned Article, if the contractor was attributable to the employer and others are caused by neutral events.
delayed because of a reason caused by the employer or if the em- Subclause 8.4 contains a catchall provision for any delay events
ployer contributed to such delay, the judge may rule that the amount that are the responsibility of the employer; namely “(e) any delay,
of agreed damages may be reduced or not paid at all by the impediment or prevention caused by or attributable to the Em-
contractor. ployer, the employer’s personnel, or the employer’s other contrac-
Additionally, there are several judicial cases, under French law, tors.” The goal of the catchall provision is to avoid any possibility
which furnish numerous examples of delays for which the em- of time becoming at large from an act of prevention for a cause for
ployer was held responsible, amendment of the initial project which the employer is responsible. Time at large is a common law
(see 3rd Civil Chamber, May 10, 1994; 3rd Civil Chamber, concept and in most civil law countries, this concept remains un-
May 4, 1995), delay in payment of the agreed price (see 3rd Civil known as distinctive (Bellhouse and Cowan 2008).
Chamber, May 16, 1984), absence of endeavors to remove admin- This section will examine the situation where FIDIC (CONS)’s
istrative barriers (see Poitiers Appeal Court), interruption of the extension-of-time clause was omitted for some reason, and the
works at the request of the employer without setting an exact re- works were delayed for a reason for which the contractor is not
sumption date (see 3rd Civil Chamber, November 4, 1993), con- responsible, to determine if provisions would be imported from
clusion of many amendments and a delay of administrative plans the ECL. However, to avoid misunderstandings, it might be a good
and authorizations amounting to several months (see 3rd Civil idea to apply the case to the common law first, then to the ECL.
Chamber, January 15, 2003), etc. (Rosher 2014). It is thought that Under the common law, if the delay was the employer’s respon-
the same applies to the ECL. sibility, time would become at large. Consequently, the employer
In addition, French law does not provide any methods for delay will lose his right to deduct liquidated damages in respect of the
analysis and their calculation, and that remains a gray area in the contractor’s delays, and the contractor would be under obligation
execution of construction contracts. Accordingly, this can be a to complete within a reasonable period. On the other hand, if the
source of serious difficulties and conflicts for French construction works were delayed by a neutral event, such as weather or strikes,
companies. In this context, the insertion of clauses related to the contractor takes the risk of such delay, unless such events are
extension of time and methods for delay analysis could be very such as to frustrate the contract entirely [see Percy Bilton, Ltd., v.
helpful (Rosher 2014). The same applies to the ECL. Greater London Council] (Bunni 2005; Wallace 2012). On the
other hand, French law contains no express principle of prevention;
Procedures and Procedural Breaches however, notions that come very close to it exist (Rosher 2014).
As for procedural matters, generally under civil law jurisdictions, The same applies to the ECL. There are no express provisions
there is no clear system of claims for extension of time, which is in the muqawala section in the ECC covering contractor’s exemp-
typically not claim-based. Usually, at the end of the project, the tion from paying damages for delays caused by employer’s acts or
parties will discuss each event that prevented the contractor from other events leading to delay in completion. Accordingly, the gen-
completing within the contract duration, to reduce the total time eral principles of contractual liability shall apply. In such case, the
overrun (Axel-Volkmar and Gotz-Sebastian 2010). It is thought that contractor could resort to Article 216 of the ECC to be exempted
the same applies to the ECL. from the damages for the delay in performance of his obligation if
The general principles of contract law of the ECC provide that he establishes that such delay was due to a cause attributable to the
the debtor (in the case at hand, the contractor) would be exempted employer. In addition, the damages could be reduced if the em-
from paying damages for his delay in performance, if he proves that ployer has contributed to the delay. The contractor could also resort
the delay in performance was caused by an external cause beyond to Article 215 of the ECC to be exempted from the damages, if
his control. Yet, the ECC does not provide any express specific he establishes that the delays to the completion of the works were
provision for the contractor’s entitlement to extension of time caused by an external cause beyond his control, which could be an
and a mechanism for such extension. Although the contractor is act of the employer or delays caused by a neutral event.
relieved from the damages for delay by means of a judicial award, Based on the aforementioned, it is concluded that if the
yet, at the time of execution of the works the time for completion is extension-of-time clause was omitted in the FIDIC (CONS), in
unclear either to the employer or to the contractor, which could the context of the ECL, and there are solutions to be imported and
result in disputes between the parties (Hamed 2010). As a result, principles to be derived from the ECL. If the contractor was pre-
and while acknowledging that the absence of express legislative vented from completing the works by the time for completion due

© ASCE 06518002-7 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


to a cause for which the employer is responsible, then under both accordance with customary trade practice. If he discovers a
the common law and the ECL, the employer will not be entitled to defect which the vendor warrants against, he must notify
the delay damages agreed in the contract. On the other hand, it is him of it within a reasonable time. If he fails to do so, he
vital to note that the contractor’s delay due to neutral events, in the is considered to have accepted the object sold.
absence of the extension-of-time provision, is treated differently 2) If, however, the defect is such that it cannot be discovered
under the common law and the ECL. Under the common law, by ordinary examination, and the purchaser discovers it, he
the contractor shall be held responsible for the delay and will be must notify the vendor of the defect as soon as it appears,
liable for delay damages. In the case of the FIDIC (CONS), for or else he is considered to have accepted the object sold, with
the contractor to be exempted from delay damages for a delay its defects.
caused by a neutral event, then the neutral event must be listed
in Subclause 8.4 or referred to through Subparagraph (b). The Article 455 states the following:
ECL is more comprehensive in that it allows the contractor to In the absence of an agreement to the contrary, if the vendor
be exempted from damages if he establishes that the delayed com- warrants the good working condition of the object sold for a
pletion was caused by an external cause beyond his control, which specific period of time, and a defect in the object appears, the
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

would include neutral events. Therefore, the solution under the purchaser must notify the vendor of the defect within one
ECL is more favorable to the contractor. month from its appearance, and must bring an action within
Unlike the FIDIC (CONS), the ECC does not provide detailed six months from the notification. Otherwise, his right to the
legislative procedures, mechanisms, and sanctions in case the con- warranty is forfeited.
tractor fails to follow the procedures. Although the contractor is
relieved from the damages for delay by means of a judicial award However, it is argued that the notice requirements under Sub-
at the time of execution of the works, the time for completion is clause 20.1 of the FIDIC (CONS) may be considered strict pro-
unclear to the employer and contractor, which could result in dis- cedural requirements that could amount to a waiver of right
putes between the parties (Hamed 2010). depending on the factual matrix of the case. Such a waiver may
As for the procedural failure by the contractor, the FIDIC be substantively countered by some legal principles in the ECL,
(CONS) requires the contractor to serve a proper delay notice in including principles of good faith, abuse of right, unjust enrich-
accordance with Subclause 20.1, which states, “If the Contractor ment, and estoppel. The said legal principles in this context will
fails to give notice of a claim within such period of 28 days, be analyzed subsequently. Articles were written in relation to
the time for completion shall not be extended : : : ”. This indicates the notice requirements of the FIDIC and their application under
that the FIDIC drafter intends to make the service of the notice in the United Arab Emirates (UAE) law (Skaik 2009; Marke
compliance with the aforementioned subclause. A condition prec- 2015). Since the UAE’s legal system is highly influenced by the
edent to the contractor’s entitlement to extension of time and failure Egyptian legal system, an analogy is made herein for such legal
by the contractor to comply with the notice requirements will result principles under the ECL.
in loss of his right to an extension of time. Before rejecting a claim under the FIDIC due to noncompliance
As mentioned previously in this section, courts in the common with strict technicalities of the notification procedures, it is impor-
law legal system are less likely to construe the requirements, in tant to consider the provisions of the Civil Code, which might have
form and content, of the notice required under claim clauses too a bearing on the issue (Skaik 2009; Marke 2015). According to
strictly. They are also reluctant to treat the notices as conditions Article 148/1 of the ECC, the obligations resulting from contracts
precedent to the contractor’s entitlement to extension of time, un- must be performed in good faith. It is argued that this could apply to
less they are expressly stated as being so. Moreover, it should not be the case in which a contractor considers information given in
overlooked that in certain jurisdictions the employer would not be agreed minutes of a meeting or report, as written notice, as required
able to rely on a breach by the contractor of such condition prec- by the FIDIC (CONS). Consideration of good faith may be relevant
edent to claim for delay damages. This is because some local laws in such case and the contractor may argue that the engineer and the
disallow any contractual right to restrict the right to bring a claim employer have actually been notified of the existence of the claim
before a judge or arbitral tribunal, for example, in Taiwan pursuant within the time stipulated in the contract and in a written form.
to Article 58 of the Civil Procedural Code (Glover and Accordingly, the purpose of the notification provision would have
Hughes 2006). been fulfilled in such case, making it an act of bad faith not to ac-
By applying such procedural failure in the context of the ECL, cept this.
reference is made to Article 147/1 of the ECC, which states, “The Moreover, according to Article 5 of the ECC, the exercise of a
contract is the law of the contracting parties. It can be revoked or right is considered unlawful if the desired benefit is out of propor-
altered only by mutual consent of the parties or for reasons pro- tion to the harm caused thereby to others. Thus, if a valid claim is
vided for by law.” According to this Article, the agreement between rejected solely by reason of purely technical breach of notice re-
the employer and the contractor on an express provision to the ef- quirement, this may well be considered unlawful, especially if
fect that a proper notice is a condition precedent for the contractor’s the interest in upholding the employer’s contractual right to receive
entitlement to extension of time will be legally enforceable, subject the notice within the stipulated time is disproportionate to the likely
to any applicable general principles of good faith, abuse of right, financial harm to the contractor.
estoppel, etc. In addition, the ECL acknowledges and enforces the Furthermore, if a valid claim for extension of time due to a varia-
parties’ express agreement that a right is forfeited or waived if a tion for additional work is rejected by the engineer purely on the
party fails to provide a notice within an agreed or reasonable period, grounds of a contractor’s noncompliance with the requirements of
as the case may be. Attention is drawn to the provisions related to contractual notice provisions, then it is possible, under the ECL,
sales contracts, specifically to Articles 449 and 455 of the ECC. that the employer has been unjustly enriched by benefiting from
Article 449 states the following: the additional work. This could be considered the case if the em-
ployer is trying to avoid payment for such additional work by re-
1) When the purchaser has taken delivery of the object sold, lying on the contractor’s failure in a procedural matter. Unjust
he must ascertain its condition as soon as he is able to do so, in enrichment is deemed unlawful under the ECL, in which, according

© ASCE 06518002-8 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


to Article 179 of the ECC, each person, even one lacking discretion, Procedures and Procedural Breaches
who unjustly enriches himself to the detriment of another person, is The procedures for agreement or determination of additional pay-
liable, to the extent of his profit, to compensate such other person ment for the contractor under the FIDIC (CONS) are the same pro-
for the loss sustained by him. However, it is worth noting that, as a cedures as those for extension of time and are provided for in
matter of law, contractual liability and unjust enrichment cannot Subclause 20.1 (Contractor’s Claims) of the FIDIC (CONS).
be combined, and that unjust enrichment would not be invoked The procedures are discussed earlier in the “Delays and Extension
in the presence of a valid contract, since claims would have to of Time” section in this paper.
be pursued as contractual claims and not separate unjust enrichment
claims.
Last, based on the principle of estoppel, the engineer cannot, Contractor’s Claims for Additional Payment under the
upon accepting a claim referred to him by the contractor after Egyptian Civil Law
the lapse of the time frame required by Subclause 20.1 of the FIDIC
(CONS) and render a determination thereon, subsequently reject Entitlement to Additional Payment
the claim on the basis of the contractor’s failure to provide the Under the ECL, the contract price cannot be modified, except by
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

notice within such time frame. In this case, the employer could the agreement of the parties or as provided by law (Shanab 1963).
be estopped from arguing that this claim is inadmissible and that This provision stems from the general rule stipulated in Article
the contractor has waived his right by not giving notice in a 147/1 of the ECC, which states,“The contract is the law of the
timely manner. It is noted that the principle of estoppel was up- contracting parties. It can be revoked or altered only by mutual
held in court awards in Egypt (see Cassation 18.08.1951; Cairo consent of the parties or for reasons provided for by law.” The
Appeal Court). It is also possible to consider that certain acts or muqawalasection in the ECC does not include any express pro-
omissions by the employer or engineer could qualify as implying visions that provide for the contractor’s entitlement to increase
a waiver of right to insist on the notice requirement, but this has to in the contract price due to an event caused by or attributable to
be assessed on a case-by-case basis in light of the parties’ con- the employer. Exception is made in Article 658 of the ECC in the
tractual conduct. case of lump sum contracts. This article covers the case of mod-
Considering the aforementioned, the strict procedural require- ifications or additions made to the design due to the fault of the
ments under Subclause 20.1 of the FIDIC (CONS) may be substan- employer, or authorized by him, and the price thereof is agreed
tively countered, when regarded in the light of the legal principles with the contractor. Accordingly, the general principles of con-
of the applicable ECL. tract law shall apply in the other cases in which there is an increase
in the contract price due to an event caused by or attributable to
the employer.
Contractor’s Claims for Additional Payment under the Furthermore, as stated by scholars in their commentary on
FIDIC (CONS) Article 658/1 of the ECC, for the contractor to be entitled to addi-
tional payment, it is not necessary to prove that the employer had
Entitlement to Additional Payment bad intentions or was in breach. Contractor’s entitlement to addi-
The FIDIC (CONS) subclauses referring to the contractor’s entitle- tional payment could result from an increase in price from an act by
ment to additional payment are as follows: the employer or attributable to him. Such acts could go beyond
• Subclause 1.9: Delayed Drawings or Instructions modifications occurring in the design, to any additional costs
• Subclause 2.1: Right of Access to the Site caused by or are attributable to the employer. For example, if
• Subclause 4.7: Setting Out the employer was delayed in issuing the permits or giving the con-
• Subclause 4.12: Unforeseeable Physical Conditions tractor access to the site and such event resulted in additional costs,
• Subclause 4.24: Fossils the contractor shall be entitled to additional payment (Shanab 1963;
• Subclause 7.4: Testing Al-Sanhuri 1989). However, the ECC does not include any express
• Subclause 8.9: Consequences of Suspension provision to that effect. It also does not specify the events that could
• Subclause 10.2: Taking Over of Parts of the Works trigger the contractor’s entitlement to additional payment, as a re-
• Subclause 10.3: Interference with Tests on Completion sult of events caused by or attributable to the employer (Hamed
• Subclause 11.2: Cost of Remedying Defects 2010). As mentioned herein previously, this does not, in and of
• Subclause 11.8: Contractor to Search itself, imply nonentitlement, but it is recommended to introduce
• Subclause 12.4: Omissions a provision in the ECC to expressly regulate such entitlements,
• Subclause 13.2: Value Engineering which would boost predictability and certainty and would be con-
• Subclause 13.7: Adjustments for Changes in Legislation sistent with the general principles of the ECC and the provisions
• Subclause 15.5: Employer’s Entitlement to Termination governing contractual liability.
• Subclause 16.1: Contractor’s Entitlement to Suspend Work By reverting to the general principles of contract law, it is of
• Subclause 16.4: Payment on Termination paramount importance to draw the attention to the fact that the con-
• Subclause 17.4: Consequences of Employer’s Risks tracting party (the employer, in the case at hand) is required to per-
• Subclause 19.4: Consequences of Force Majeure form his obligations under the contract, according to the provisions
• Subclause 19.6: Optional Termination, Payment and Release of Article 148/1 of the ECC, which states, “A contract must be per-
• Subclause 19.7: Release from Performance under the Law formed in accordance with its provisions and in compliance with
For each of the aforementioned events, the FIDIC (CONS) spec- the requirements of good faith.” If the employer does not perform
ifies the basis for the extent of the contractor’s entitlements to addi- any of his obligations under the contract or is delayed in the per-
tional payment; specifically, it is clearly stipulated whether the formance of his obligations, then he is considered in breach of con-
contractor shall be entitled to cost only, or to cost and reasonable tract. In such case, the contractor shall be entitled to compensation
profit. Generally, the FIDIC (CONS) specifies that the contractor is for all damages he incurs as a result of the employer’s breach; such
entitled to reasonable profit, in the events attributable to the provision is enshrined in Article 215 of the ECC, which stipulates
employer. the following:

© ASCE 06518002-9 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


When specific performance by the debtor is impossible, he related to the notice; therefore, there is no need for the notice.
will be ordered to pay damages for non-performance of his A third group of scholars argue that if specific performance is pos-
obligation, unless he establishes that the impossibility of per- sible, then a notice is required for the entitlement to damages to be
formance arose from an external cause beyond his control. established, and the notice establishes the entitlement to damages in
The same principle will apply, if the debtor is late in the per- case the debtor does not perform his obligation. Consequently, the
formance of his obligation. notice would be meaningful. On the other hand, if specific perfor-
mance is not possible, then the notice would be useless and the
In relation to the extent of damages, attention is drawn to Article situation would be classified under one of the exceptions at law
221 of the ECC, which states the following: in which no notice is required (Al-Sanhuri 1989), according to
1) The judge shall assess the amount of damages, if it has not the stipulations of Article 220 of the ECC which states, “No no-
been fixed in the contract or by a provision of law. Damages tification of the debtor is necessary in the following cases: (a) if
include compensation for losses incurred by the creditor and the performance of the obligation becomes impossible or useless
profits foregone, provided that they are the natural result of the due to an act of the debtor : : : ”. Nevertheless, in any case, there
failure to perform the obligation or of delay in such perfor- is no requirement for the notification to be made within a specific
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

mance. The harm shall be considered a natural result if the period or otherwise the contractor’s entitlement is waived, except
creditor is unable to avoid it by exerting reasonable efforts. for the limitation periods provided by law. As for the required form
2) If, however, the source of the obligation is a contract, a of the notice, Article 219 of the ECC stipulates the following:
debtor who has not committed fraud or gross negligence shall A debtor is notified by a summons or its equivalent. The no-
not be held liable for damages except for harm which was
tice may be delivered by mail in the manner provided for in
generally foreseeable at the time of entering into the contract.
the Code of Civil Procedure, or may be the result of an agree-
Legal jurisprudence writings and scholars stipulate that it is the ment stipulating that the debtor shall have constructive notice
obligation of the employer, under the ECL, to perform what is nec- by the mere expiration of the term (granted for performance of
essary for the contractor to commence and proceed with the works the obligation), without the need for any other procedure.
until completion. Therefore, if the employer is required, under the
contract, to provide permits, drawings, specifications, or data, or to
supply material or equipment to the contractor, then according to Application of the FIDIC (CONS) under the Egyptian
the ECL, the employer is required to perform such obligations in Civil Law
the agreed time or, if there is no agreed time, within a reasonable
period. In addition, the employer is under the obligation not to im- The FIDIC (CONS) provides for several events that raise the con-
pede the contractor from performing his obligations under the con- tractor’s entitlement to additional payment. Some of the events en-
tract (Al-Sanhuri 1989; Shanab 1963), which is fully consistent titling the contractor to additional payment are attributable to
with the requirements of good faith. the employer, while others are caused by neutral events. However,
the ECC does not specify the events caused by or attributable to the
Procedures and Procedural Breaches employer, which could raise the contractor’s entitlement to addi-
As for the procedures for the contractor’s claim for additional pay- tional payment. With the exception of Article 658 of the ECC, there
ment, the muqawala section of the ECC does not provide any ex- are no express provisions in the muqawala section in the ECC that
press provision for a specific mechanism for the contractor’s provide for the contractor’s entitlement to increase in the contract
entitlement to additional payment due to an event caused by or price from an event caused by or attributable to the employer.
attributable to the employer. However, one very primitive sort of Accordingly, the general principles of contract law will apply in
procedure is provided in the general principles of contract law, such case.
where Article 218 of the ECC, states, “Subject to any provision Generally, if the employer is in breach of any of his obligations
to the contrary, damages are not due unless the debtor receives no- under the FIDIC (CONS) and the contractor’s relevant entitlement
tification requesting him to perform his obligation.” Translating this to additional payment was omitted from the contract, the general
to a construction setting, for the contractor to be entitled to com- principles of contract law under the ECC shall apply. In such case,
pensation for the damages he incurs as a result of the employer’s the contractor would still be entitled to compensation for the dam-
breach of contract, the contractor is expected to submit the required ages he incurs as a result of the employer’s breach, pursuant to
notice, according to the provisions of Article 218 of the ECC. Article 215 of the ECC. The contractor would have to notify
By notifying the employer, the contractor legally establishes that the employer of the breach to establish his entitlement to damages.
the employer is delayed in performing his obligation mise en de- However, the claim cannot be time-barred compared to the provi-
meure, mora, retard If the employer is delayed in performing his sion in Subclause 20.1 of the FIDIC (CONS). The claim would only
obligation and the contractor is delayed in notifying the employer, be subject to the limitation periods provided by law.
it may be assumed, subject to the facts of each case, that the con- As for the procedures and mechanism for additional payment,
tractor accepts the delay by the employer until the notice to that the FIDIC (CONS) provides detailed procedures and sanctions in
effect is given, unless the parties agree otherwise and save for case the contractor fails to follow the procedures. On the other
the exceptions provided by law in Articles 219 and 220 of the hand, the ECC does not provide any express provision for specific
ECC, which will be discussed subsequently in this section (see procedures or mechanism in relation thereto in the muqawala sec-
Civil Cassation 21.12.1933; Mixed Appeal 12.02.1919; Mixed Ap- tion. The very primitive procedures in the general principles of con-
peal 28.03.1935; Mixed Appeal 31.03.1898) (Al-Sanhuri 1989). tract law, under Article 218 of the ECC, can be referred to in such
If the breach is related to nonperformance of the obligation, case. These provide that for the creditor (the contractor in the cur-
some scholars argue that the notice is still a condition precedent, rent case) to be entitled to compensation for all damages he incurs
because of the generality of Article 218 of the ECC. Whereas, other as a result of the debtor’s (the employer in the current case) breach
scholars argue that the notice is not obligatory, because the dam- of contract, the contractor should submit the required notice, unless
ages caused by nonperformance are due to an event that is not exempted by law or contractually.

© ASCE 06518002-10 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


Regarding the procedural failure by the contractor, the FIDIC entitlement to extension of time and the procedures related thereto.
(CONS) requires the contractor to serve a proper notice in accor- However, it is recommended that such provision be included in the
dance with Subclause 20.1, which states, “If the Contractor fails to same provision related to the contractor’s entitlement to additional
give notice of a claim within such period of 28 days, the time for payment as a result of an event attributable to the employer or for
completion shall not be extended, the contractor shall not be enti- which he is responsible. Further, there are no express provisions in
tled to additional payment, and the employer shall be discharged the Muqawala section in the ECC that provide for the contractor’s
from all liability in connection with the claim.” Accordingly, and entitlement to additional payment due to an event caused by or
similar to the analysis provided in the “Delays and Extension of attributable to the employer and there is no provision regulating
Time” section in this paper, the provisions and time limits required the procedures and mechanism of such entitlement. Accordingly,
by Subclause 20.1 intend to ensure that the service of the notice is it is recommended to add such provisions in the ECC. As such,
requisite to the contractor’s entitlement to additional payment. it was previously suggested in the relevant parts of the previous
Therefore, failure by the contractor to comply with the notice re- section of this paper to introduce a provision to regulate the con-
quirements may result in loss of his right to additional payment, tractor’s entitlement to extension of time and the procedures related
unless there are valid legal or contractual grounds that safeguard thereto and to include such provision in the provision for the con-
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

the contractor’s entitlement. For this reason, the solutions in the tractor’s entitlement to additional payment as a result of an event
FIDIC (CONS) in relation to this particular provision may come attributable to the employer or for which he is responsible. Based
across as less favorable to the contractor than those under the on the aforementioned, it is recommended to introduce the follow-
ECL, as a result of the implied waiver of right associated with ing new Article to the ECL:
the lapse of time. 1. The contractor shall be entitled to extension of time, if comple-
On the other hand, in the context of the ECL, reference is made tion is delayed or will be delayed, as a result of an external cause
to Article 147/1 of the ECC, which states, “The contract is the law beyond the contractor’s control, whether attributable to the em-
of the contracting parties. It can be revoked or altered only by mu- ployer or a neutral event. The extension of time shall be to the
tual consent of the parties or for reasons provided for by law.” extent the works were delayed by such event, taking into con-
In light of this Article, if the parties expressly agree that the serving sideration any likely delays by the contractor.
by the contractor of a proper notice is a condition precedent for the 2. The contractor shall be entitled to additional payment if he in-
contractor’s entitlement to additional payment, then such agree- curs additional costs, as a result of an event caused by or attri-
ment will be enforced by law. That is because such agreement butable to the employer, taking into consideration any likely
is not contradictory to a mandatory provision at law. In addition, delays by the contractor. The extent of the additional payment
and as mentioned in the “Delays and Extension of Time” section in shall be the additional costs incurred by the contractor, in addi-
this paper, the ECL acknowledges and enforces the parties’ agree- tion to a reasonable profit.
ment that a right may be waived or forfeited if a party fails to pro- 3. If the contractor considers himself entitled to extension of time
vide a notice within an agreed period. Examples of such provision and/or any additional payment, under the previous subpara-
under the ECL are provided in Articles 449 and 455 of the ECC, as graphs, the contractor shall give notice to the employer, describ-
clarified previously. However, and as mentioned previously, it is ing the event giving rise to the claim. The notice shall be given
argued that the notice requirements under Subclause 20.1 of the as soon as practicable after the contractor became aware, or
FIDIC (CONS) are considered strict procedural requirements that should have become aware, of the event. By giving notice,
amount to a waiver of right and depending on the factual matrix. the contractor is deemed to have established his entitlement
Such waiver may be substantively countered by some legal prin- to extension of time and/or additional payment from a date start-
ciples in the ECL, including principles of good faith, abuse of right, ing up to 28 days before the date of the notice, but not before the
unjust enrichment, and estoppel. date of the event. The contractor is deemed to have waived his
Based on the foregoing, it is concluded that the solutions related right for extension of time and/or additional payment for the
to the contractor’s claims for additional payment under the FIDIC impact of the event that has occurred before such date.
(CONS) are similar in some instances to those under the ECL. As for recommendations for amendments to the FIDIC (CONS),
However, still, there are some notable differences between both it is thought that the provisions related to the effect of notices under
of them. the ECL, as amended previously, are more appropriate to construc-
tion contracts, than the time-barring provision provided in Sub-
clause 20.1 of the FIDIC (CONS). Therefore, it is recommended
Recommendations and Additions to the Body of to amend Subclause 20.1 to make the effect of the notice to estab-
Knowledge lish the contractor’s entitlement to extension of time and/or addi-
tional payment and that failure to provide such notice would not
When examining the provision of the delays and extension of time result in the contractor losing his entitlement to extension of time
of the FIDIC (CONS) and of the ECL, it is concluded that the so- and/or additional payment. The contractor, in such case, is deemed
lutions related to the delays and extension of time under the FIDIC to have waived his right for extension of time and/or additional pay-
(CONS) are similar in some instances to those under the ECL. That ment for the period preceding the date up to 28 days prior the no-
is despite the legal concepts under the FIDIC (CONS) are derived tice, but not before the date of the event. The reason for such
from the common law system and are different from the legal rul- 28 days is to give the contractor some time to assess that an event
ings in the ECL. However, still, there are some notable differences could have a time/cost impact, so the notice should establish the
between the solutions in the FIDIC (CONS) and under the ECL. In right of extension of time and/or additional payment, not from
this paper, similarities and differences have been pointed out. the date of the notice, but starting from up to 28 days before
As mentioned previously in this paper, the ECC does not the date of the notice (but not before the date of the event), as pro-
provide any express legislative provision for the contractor’s enti- vided by the contractor in the notice.
tlement to extension of time or for a mechanism for such extension. Based on the aforementioned, it is recommended to make the
Accordingly, it is recommended to add such provision in the ECC, following amendment to the first and second paragraphs of Sub-
to regulate, with more certainty and predictability, the contractor’s clause 20.1 (Contractor’s Claims) of the FIDIC (CONS):

© ASCE 06518002-11 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


If the Contractor considers himself to be entitled to any ex- Peak Construction (Liverpool), Ltd., v. McKinney Foundations,
tension to the Time for Completion and/or any additional pay- Ltd., 1 BLR 111 at 121 (Salmon LJ) (1970).
ment, under any Clause of these Conditions or otherwise in Percy Bilton, Ltd., v. Greater London Council, 20 BLR 1
connection with the Contract, the Contractor shall give notice (1982).
to the Engineer, describing the event or circumstance giving Perini Pacific v. Greater Vancouver Sewerage and Drainage
rise to the claim. The notice shall be given as soon as prac- District, 57 DLR (2d) 307 (1966).
ticable after the Contractor became aware, or should have be- Rees & Kirby v. Swansea C.C., 30 BLR 1, CA (1985).
come aware, of the event or circumstance. Roberts v. Bury Commissioners, LR 5 CP 310 (1870).
Steria, Ltd., v. Sigma Wireless Communications, Ltd., BLR 79
By giving the notice, the Contractor is deemed to have established (2008).
his entitlement to extension of time and/or additional payment from Tersons, Ltd., v. Stevenage Development Corp., 2 Lloyd’s
a date starting up to 28 days before the date of the notice, but not Rep. 333 (1963).
before the date of the event. The Contractor is deemed to have
waived his right for extension of time and/or additional payment Egyptian Case Law
for the impact of the event or circumstance that has occurred before
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

Cassation Cassation Cases year 5 No. 1380, August 18, 1951,


such date. p. 1325.
Civil Cassation Group Omar 1 No. 156, December 21, 1933,
p. 292.
Conclusion Cairo Appeal Court No. 35, 41, 44, and 45 Year 129,
February 5, 2013.
Egypt bases its civil law on a mixture of French civil law and Mixed Appeal No. 31, February 12, 1919, p. 165.
Shari’a law, yet FIDIC, which is based on legal concepts rooted 3rd Civil Chamber, No. 01-13.871, January 15, 2003.
in the common law system, is the established form of construc- Cassation Cases year 23 No. 166, June 1, 1972, p. 1062.
tion contract in the Egyptian construction projects. Awareness of Mixed Appeal No. 47, March 28, 1935, p. 223.
the local laws and the mandatory provisions thereof is a must Egyptian Cassation Cases Year 26, March 23, 1975, p. 457.
for the stakeholders operating with FIDIC contracts and/or indi- Mixed Appeal No. 23, March 31, 1898, p. 223.
viduals entrusted with determining disputes in a civil law juris- Mixed Appeal No. 18, May 2, 1906, p. 223.
diction. This paper used a multistep interdependent desktop 3rd Civil Chamber, No. 93-14.050, May 4, 1995.
research methodology to study the general provisions of exten- 3rd Civil Chamber, No. 92-19.704, May 10, 1994.
sion of time and/or additional payment of the FIDIC (CONS) 3rd Civil Chamber, RDI 1984.413, May 16, 1984.
within the context of the ECL. Through highlighting similarities 3rd Civil Chamber, No. 91-22.289, November 4, 1993.
and differences between the relevant provisions under the FIDIC Poitiers Appeal Court, November 16, 1986.
(CONS) and the ECL, this research adds to the body of knowl-
edge by providing recommendations to amend the relevant pro- French Case Law
visions under the Egyptian Civil Code (ECC) and/or FIDIC French Court of Cassation February 27, 1888 Dalloz 89-1-31.
(CONS). Accordingly, it is recommended to add a new three-part French Court of Cassation December 10, 1913 Sirey 1914 (Bull.
article to the ECL as well as to amend the first two paragraphs of Som.) 1-19.
Subclause 20.1 in FIDIC (CONS). As such, this study would
help employers, engineers, and contractors who are associated
with projects in the Egyptian market to be better positioned
to properly manage time provisions, delays, and risks leading Works Cited
to additional payment in the construction contracts. This should
Abd El-Razek, M., H. Bassioni, and A. Mobarak. 2008. “Causes of delay in
also enable more effective and efficient contract administration
building construction projects in Egypt.” J. Constr. Eng. Manage.
of construction projects in the Egyptian construction sector.
134 (11): 831–841. https://doi.org/10.1061/(ASCE)0733-9364(2008)
Since most legal systems in the ME countries are heavily im- 134:11(831).
pacted by the ECL, the benefits of this research will extend Abu-Manneh, R. 2008. Contracting in the Middle East, construction and
to the ME region. engineering legal update. Washington, DC: Mayer Brown.
Al-Sanhuri, A. 1989. A treatise on civil law. 2nd ed. Cairo, Egypt: Dar El
Nahda El Arabiya Publisher.
References Axel-Volkmar, J., and H. Gotz-Sebastian. 2010. FIDIC: A guide for practi-
tioners. Berlin: Springer.
List of Cases Bellhouse, J., and P. Cowan. 2008. Common law “time at large” arguments
in a civil law context. London: White & Case LLP.
Common Law Cases Booen, P. L. 2000. The FIDIC contracts guide. Geneva: FIDIC.
Barque Quilpe, Ltd., v. Brown, 2 K.B.264 (1904). Bunni, N. G. 2005. The FIDIC forms of contract. Chichester, UK: Wiley-
Bremer Handelsgesellschaft mbh v. Vanden Avenne-Izegem, Blackwell.
Chappell, D., V. Powell-Smith, and J. Sims. 2005. Building contract
2 Lloyd’s Reports 109 (1978).
claims. 4th ed. Oxford, UK: Blackwell Publishing.
City Inn, Ltd., v. Shepherd Construction, Ltd., SLT 781 (2002).
EIC/FIDIC Questionnaire Survey. 1996. EIC/FIDIC questionnaire survey:
Dodd v. Churton, 1 QB 562 (1897). The use of the FIDIC Red Book. Final Rep. Reading, UK: Dept. of
Henry Boot Construction, Ltd., v. Central Lancashire New Construction Management and Engineering, Reading Univ.
Town Development, Ltd., 15 BLR 1 at 12 (1980). El-adaway, I., S. Fawzy, R. Bingham, P. Clark, and T. Tidwell. 2014.
Holme v. Guppy, 3 M & W 387 (1838). “Different delay analysis techniques applied to AIA A201-2007 stan-
Maidenhead Electrical Services, Ltd., v. Johnson Control dard form of contract.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 6 (3):
Systems, Ltd., 7 BLISS 7 (1996). 0514001. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000145.

© ASCE 06518002-12 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002


Ezeldin, S., and M. Abdel-Ghany. 2013. Causes of construction delays for Knowles, R. 2012. 200 contractual problems and their solutions. 3rd ed.
engineering projects: An Egyptian perspective. 54–63. State College, Chichester, UK: Wiley-Blackwell.
PA: ASCE. MacRoberts Solicitors. 2008. MacRoberts on Scottish building contracts.
Fawzy, S., and I. El-adaway. 2012. “Contract administration guidelines for 2nd ed. Oxford, UK: Blackwell Publishing Limited.
U.S. contractors working under world bank funded projects.” J. Leg. Marke, T. 2015. “FIDIC contracts in a civil law setting: Guarding against
Aff. Dispute Resolut. Eng. Constr. 4 (2): 40–50. https://doi.org/10 inoperability.” Accessed April 19, 2016. http://www.lexology.com
.1061/(ASCE)LA.1943-4170.0000088. /library/detail.aspx?g=2d610b74-9b15-4731-b939-4b666a382a6c.
Fawzy, S., and I. El-adaway. 2014. “Time ‘at large’ within the common law Murdoch, J., and W. Hughes. 2008. Construction contracts law and man-
legal system: Application to standard forms of contract.” J. Leg. Aff. agement. 4th ed. London: Taylor & Francis.
Dispute Resolut. Eng. Constr. 6 (1): 04513002. https://doi.org/10 Pickavance, K. 2006. “Calculation of a reasonable time to complete when
.1061/(ASCE)LA.1943-4170.0000124. time is at large.” Int. Constr. Law Rev. 23 (2): 167.
Fawzy, S., I. El-adaway, and T. Hamed. 2015. “Contracting in a global Pickavance, K. 2010. Delay and disruption in construction contracts.
world: Application of the ‘Time at Large’ principle.” J. Leg. Aff. 4th ed. London: Sweet & Maxwell.
Dispute Resolut. Eng. Constr. 7 (3): 04515001. https://doi.org/10.1061 Powell-Smith, V. 1989. Civil engineering claims. Great Britain, UK: BSP
Professional Books.
/(ASCE)LA.1943-4170.0000170.
Rose, N. 2009. “Boom and recovery: Understanding the Middle
Furst, S., and V. Ramsey. 2012. Keating on construction contracts. 9th ed.
Downloaded from ascelibrary.org by Tufts University on 07/01/18. Copyright ASCE. For personal use only; all rights reserved.

East construction market.” Accessed April 23, 2016. http://www


London: Sweet & Maxwell.
.nortonrosefulbright.com/knowledge/publications/21430/boom-and
Gibson, R. 2008. Construction delays extensions of time and prolongation
-recovery-understanding-the-middle-east-construction-market.
claims. Abingdon, UK: Taylor & Francis.
Rosher, P. 2014. Delay analysis in international construction projects:
Glover, J., and S. Hughes. 2006. Understanding the new FIDIC Red A comparative study in English and French Law. Toronto: Thomson
Book—A clause-by-clause commentary. London: Sweet & Maxwell. Reuters.
Grose, M., and R. Shlah. 2015. “Construction law in Qatar and the United Sarie-El Din, H. 1994. “Operation of FIDIC civil engineering conditions
Arab Emirates: Key differences.” Turkish Commer. Law Rev. 1 (3): 189. in Egypt and other Arab Middle Eastern Countries.” Int. Lawyer
Hamed, T. 2010. “Risk provisions in building and construction contracts, a 28 (4): 951.
comparative study between the Egyptian civil code and the FIDIC con- Shanab, M. 1963. Commentary on Muqawala contract. Cairo, Egypt: Dar
ditions of contract.” Ph.D. thesis, Faculty of Engineering, Cairo Univ. El Nahda El Arabiya Publisher.
Hamed, T., S. El Haggan, and N. Yehia. 2012. “Employer’s failure to make Skaik, S. 2009. “GCC in Catch-22 over FIDIC forms.” Accessed April 19,
payment to contractor—A study of construction contracts under the 2016. http://www.cmguide.org/archives/2031.
Egyptian civil law.” Int. Constr. Law Rev. 29 (4): 369. Uff, J. 2009. Construction law. 10th ed. London: Sweet & Maxwell.
Hughes, G. 1985. Building and civil engineering—Claims in perspective. Wallace, D. 2012. Hudson’s building and engineering contracts. 12th ed.
2nd ed. New York: Longman. London: Sweet & Maxwell.

© ASCE 06518002-13 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2018, 10(4): 06518002

You might also like