CONTENTS
Page No.
CHAPTER-1
INTRODUCTION ether Orr
1.1 Sources of energy 1
1.1.1 Electrical energy 3
1.1.2 Power 4
1.1.2.1 Power available 4
1.2 Historical background of hydropower development 5
1.2.1 Importance of hydropower 1
1.2.2. Hydropower potential 8
1.2.2.1 Gross, technical and economical power potential 8
1.2.2.2 Hydropower potential of the world 8
1.2.2.3 Hydropower potential of Nepal 9
1.2.3 Energy /power consumption or situation in Nepal 10
1.2.4. Challenges and opportunities of hydropower development in Nepal u
1.3. Types and classification of hydropower plant 13
CHAPTER-2 ne le
POWER REGULATION ~ Prewrat mum
2.1. Firm power and secondary power 18
2.2 Terms related to power regulation 19
2.2.1. Significance of load factor and diversity factor 22
2.3 Power variation: daily, weekly and seasonal 2
24 Load curve 2B
2.4.1. Daily load curve 23
2.4.2 Weekly load curve 24
2.4.3. Seasonal load curve 24
2.5 Power grid 25
2.5.1. Advantages of integrated grid over the isolated grid 25
2.5.2. Components of power system 25
2.5.3 Power (electricity) system in Nepal 27
2.5.3.1 Production/generation 27
2.5.3.2 Transmission/evacuation system 28
2.5.3.3 Distribution system 28
SOLVED PROBLEMS 29-32
UNSOLVED PROBLEMS 33-353.1
ey
oe
3.4
EE)
. qe
cHaprers Weed”
PLANNING OF HYDROPOWER PROJECT
Site Selection for hydropower projects
3.1.1 Hydropower project planning studies
3.1.1.1 Reconnaissance study
3.1.1.2 Prefeasibility study
3.1.1.3 Feasibility study
Requirements for hydropower planning
3.2.1 Flow duration curve (PDC)
3.2.1.1 Uses of flow duration curve
3.2.2 Mass curve
3.2.2.1 Use of mass curve
3.2.2.2 Characteristics of the mass curve and its use for reservoir sizing
3.2.3 Energy flow diagram
3.2.4 Gross head and net head
3.2.5 Estimation of power potential
3.2.6 Demand or load prediction
3.2.6.1 Method of load or demand prediction
Reservoir regulation
. 33.1. Reservoir
3.3.1.1 Storage characteristics curves of reservoir
3.3.1.2 Storage zones of reservoir
3.3.2, Peak and normal flow
3.3.3 Reservoir sedimentation
3.3.3.1 Measures to control reservoir sedimentation
3.3.3.2 Density current
3.3.3.3 Trap efficiency
3.3.4 Reservoir losses
3.3.4.1 Evaporation losses
3.3.4.2 Absorption losses
3.3.4.3 Percolation losses
3.3.5 Life of reservoir
Layout of hydropower projects
3.4.1 Component parts of hydropower project
3.4.2 Layout of hydropower plant based on construction features
3.4.2.1 Run off River plants
3.4.2.2 Valley dam plant
3.4.2.3 Diversion canal type 1
3.4.2.4 High lead diversion plant
Classification based on storage
u —
36
37
37
38
39
41
41
44
44
44
45
46
SI
52
54
54
56
56
37
58
59
59
59
60
60
60
61
61
61
61
ALESa
66
67
67SOLVED PROBLEMS ‘ 70-81
UNSOLVED PROBLEMS 82-85
. CHAPTER-4 :
WATER RETAINING STRUCTURE. 16
>
>
>
It is economical to use for domestic, commercial, industrial and agricultural purpose.
in can be transmitted conveniently and efficiently from generating station to load centers
through conductor
It can be conveniently controlled over a wider range with simple arrangements.
It does not produce pollution
Tt can be easily converted into other forms of energy like heat, light, mechanical, sound
ete,
Table1.1: Common Energy Conversion Factors
Ton of oll | Standard | Raw Oil| Fuel
Unit MJ | kWh [Equivalent] m gas | Barel | wood
(TOE) (1 bhary)
TM - T | 0278 [0.000236 |" 0.025 | 0.000176] 7.8B-05
T kWh - 3.6 7 | 0.000085 | 0.09 [0.000635 0.00028 |
1 Ton of oil Equivalent (TOE) | 42300 | 11750 T 1190 7.49 3.31
TT Standard m gas 40 | ii.t1 | 0.00084 [1 0.00629 | 0.00279
i Raw Oil Barel 5650 | 1569 | 0.134 159 1 0.44
7 Fuel wood (I bhary=2.4 m)[ 12800 | 3556 | 0.302 359 225 | 1
Table1.2: Common units of ene!
srgy and power measurements used in hydropower engineering
‘Energy Power
Value ‘ame Symbol Value ‘Name
10°] Deca joule Daj 10° w Deca watt.
10} Hecta joule _| Ay 107 w “Hecia watt
10) Killojoule [Kj 10° w Killo watt
10%} Mega joule | MI 10 w Mega watt
10%} Giga joule | GI 10° w Giga watt
10" Tera joule TL 10" w Tera, watt
10) Pentajoule | PY low Petita watt
105} Exa joule ED iow Exa watt
1 Zettajoule [ZI 107 Ww Zetta watt,
| INTRODUCTION1.1.2 Power
It is the rate of energy supply/consumption/demand. It is represenited by ‘P” and standard unit of
measurement is Watt in SI unit.
Energy (J) _Work done _ Force (N)x Displacement (m)
Time (s) Time Time (s)
ie watt =1 [Jor 1y/s
Power (Watt) =
1.1.2.1 Power available
a) _ By converting potential energy into kinetic energy
Consider unit mass of water ‘m’ is flowing in the river from higher elevation to lower
Let ‘h’ be the difference in elevation between two points. Then, potential energy possessed by
the water by virtual of its position is ‘mgh’
If the flow is transported by some pipe conduits, the potential energy could be converted into
kinetic energy.
Kinetic energy = 5 mv $e Vv
Where, v = velocity at the exit of the conduit (v =/2gh )
mass density of water
volume of water
Love?
Hydropower available = “™#tcenergy _ ZPV¥" _1YY 9h = yon [Wattlor [
Ps time t 2gt g s
Where, y = specific weight of liquid in N/m?
Q= rate of flow in m’/s
f= available head in m
b) __ By converting potential energy into pressure energy :
Similarly in some cases, potential energy is converted in to the useful positive pressure energy
and remaining kinetic energy could also be utilized by converting into the negative pressure
energy below the turbine.(please refer Bernoulli's Equation at draft tube mouth and its outlet.)
Hydropower available = Pressure energyitime =""¥ = yQh (Watelor (£7
It shows that hydropower generation depends upon the rate of flow (Q) of the river and the head
(h) available. In nature, variations of ‘Q’ and ‘h’ are different at different locations, In some
cases, such as in lowland areas, ‘Q’ is abundant but the ‘h” available is minimum where as in
mountainous area, ‘h’ is sufficient but the ‘Q" is minimum. There may be cases when both ‘Q”
and ‘h’ are sufficient or insufficient. So the hydropower potential varies from place to place.
ie INTRODUCTION |1.2 Historical background of hydropower development
The first hydropower development or installation in the world was in 1882 and it is in Fox
River in Appleton, Wisconsin of USA. The capacity of the first hydropower plant was only
12.5 kW. Similarly the first hydropower development or installation in India was in 1987 in
Darjeling. The capacity of the Indian hydropower project was of 130 kW.
Pharping Hydel Powerhouse of 500 kW capacities is the first powerhouse installed in Nepal in
1911. The Pharping hydropower station was developed with the technical and financial aid of
British Government in 1911 (BS 1968 Jestha 9 completed date).The power house with the
installed capacity of 500 kW was running successfillly till 1981 but after then, the water used
for the plant was diverted for drinking purpose and the plant was shut down. Even now, the
plant can be restarted if the supply of water is made possible (NEA, 2003).
Nepal’s first hydropower plant was installed not so long time after the first hydropower plants
was installed in USA or in India.
Demand of electricity is increasing day by day in Nepal. In order to fulfill the growing demand
of electricity, The Government of Nepal decided to open its doors to the private sector involving
both local and foreign investors to promote Public Private Partnership in 1992.
Table1.3: Project under construction
| Installed
SN. Name of Project | Capacity | Investor | Status
[ (Mw)
[Lower Indrawati Khola SHP 4.50 TPP-Nepal
2 Mardi Khola SHP 3.10 | IPP-Nepal |Completed|
8 [Ridhi Khola - 2.40 IPP-Nepal |Compieted]
a |Upper Hadikhola — 0.991 IPP-Nepal |Completed!
5 \Lower Pilluwa 0.990 IPP-Nepal | Testing
6 (Kulekhanilll 14 Japan|
7 |Chamelia 30 Nepal/Korea;
8 [Mai khola (Himal Dolakha Hydro) | 4.455 IPP-Nepal |Completed|
[Lower Modi (United Hydro) 9.9 TPP-Nepal
0 _Siprin khola (Synergy HPP) 9.658 IPP Nepal
11 [Ankhu-I HPP (Ankhukhola Jalbidhut Company)| 6.930 IPP Nepal |.
2 [Phawa khola HPP (Shivani HPP Pvt. Ltd.) ~~ 4.950 IPP Nepal
(Source: NEA annual report 2010/11)
| INTRODUCTION |Table1.4: Commissioning dates of power projects in Nepal
Installed | Average [Commission
S. | Name of power |Capacity } annual and Investor | Cost per KW
N. project (Mw) | Energy | operation
(GWh) Year =
|A |Hydro Electricity e
|__Pharpinj 05 ts mem one1912 Nepal/British | RS 1426.75
2 [Sundarijal_ Oromia [aarti 1936 Nepal
B__[Panauti 2.4 7.0 1965 _ Russia _
4 [Pokhara Phewa 1.0 8.5 1967 India
[5__[Trishuli 21.0 4.5 1968 India US$1296.30-
l6_Sunkosi 10.0 70.0 {| __1973 China US$1093.70
{7_[Tinaw 1.0 10.2 _ 1974 BPC
8__|Gandak 15.0 48.0 1979 India US$1300.00
9 [Kulekhani-1 60.0 201.0 1982 | WB and others | US$1950.00
Devighat 14.1 114.0 1983 India US$2781.69
[Seti 2 15 18 1985 China _
IKulekhani-IT 32.0 95.0 1986 Japan USS1937.50
Marshyangdi 69.0 462.0 | __1989 German/WB_| US$3333.33
|Andhikhola 3.1, 38.0 “1991 BPC
himruk 12.3 81.0 1994 BPC __
(Chatara a2 38 1996 ‘Nepal/WB _
[Puwa khola 62 48.0 1999 Nepal U8$2887.10
iKhimti 60.0 353.0 2000 HPC/IPP- | US$2250.00
Ee Norway |
19. [Modi (140 87.0 2000 | Nepal/Korea_| US$1864.86
20_[Bhotekoshi 36.0 | 250.0 2000 IPP (USA) _| US$2666.67
bi [Kaligandaki 144.0 | 625.0 2001 Nepal/ADB_ | US$2638.89
22 lindrawati 75 49.7 2002 IPP-Nepal _ | US$2666.67
b3 |Chilime 22.1 137.0 2003 IPP-Nepal
24 [Tatopani (Myagdi) | 2.0 10.2 2004 Nepal
25 _|Sunkosi 2.6 14.4 2005 Nepal
26 |Piluwa khola 3.0) 19.4 [2006 IPP-Nepal
27_[Khudi 40 | 24.3 2006 IPP-Nepal _
28 [Middle Mrshyangdi| 70.0 398.0 2009 |Nepal/Germany| NRs 312000
29 [Small hydropwer-| 8.1 37.0 |different time! Nepal
B2nos
80 |Small hydropwer-| 7.64 40.0 different time] Nepal-IPP
|__|12 nos (UPP-Nepal) _
Total Hydro 635.84 | 3355.9 a
[Electricity
HERE wronucnon[B [Thermal
1 |Hetauda- Diesel 14.4 2B0 | 1963 Nepal
2 Duhabi multifuel_ | 39.0 165.0 1991 jepal-Finland
(Total Thermal 53.4 208.0
Electricity
|Grand Total 689.24 | 3563.9
t
(Source: NEA annual report 2009, 10 yr 10000 MW task force report 2009)
1.2.1 Importance of hydropower
Electrical energy can be produced using energy produced from coal, petroleum products, solar,
nuclear, flowing water, wind etc. The fuels used in power generation can be divided into fossil
fuels and non fossil fuels
The sources of fossils like coal, petroleum products, fire woods ete are plants and living things.
Use of these sources generally produced considerable amount of carbon and ultimately dispose
to the atmosphere ultimately causing green house effects resulting global warming and climate
change. The power produced from fossil fucls are also termed as thermal power as the fossil
fuels produced heat or thermal energy and converted into mechanical energy and then into
electrical energy. Thermal power is generally expensive ‘and produicing pollutions liké carbon
dioxide, ashes and others. The fossils fuels are non renewable and thus goes on depleting the
sources as it goes on continuous use. The price of fuels are increasing each year due to high
demand and depleting the sources.
The non fossil fuels like solar, nuclear, wind and water do not produce emissions like carbon
dioxide and ashes as from fossil fuels. The non fossil fuels are relatively clean and need
intensive capital investment for its development. The nuclear power development requires
complex technology for its operation and maintenance to control leakage of nuclear radiations
into environment which causes diseases like cancer and damage to the heredity characteristic of
the living things. The wind power, solar power and hydropower all are clean energy as well as
renewable energy. Although, Nepal has lot of potential wind power, it has not been materialized
yet due to unreliability and intermittent power production through wind mills. Solar power has
been widely used in rural areas for lighting purpose. The solar power has also been used as
backup system in telecommunication, traffic lighiting, and residential lighting purpose in urban
areas. Solar power is also taken as ornamental power because of high cost, intermittent
production, less efficiency and need battery backup for storage and re-utilization of the power.
Hydropower is renewable and the technology has been well developed and kept in practice in
all over the world. Although the development of hydropower projects are capital intensive, the
hydropower are cheap in operation and maintenance is available at free of cost and renewed
| iwrroouction [gaianaturally-in each year. There is not any pollution on production of hydropower although some
sort of environmental impacts are unavoidable. The environmental impacts are generally
negligible for micro hydro, small for run of river (ROR) to medium for run of river with
poundage (PROR) to high impacts for storage plant.
1.2.2. Hydropower potential
Economy of the nation depends on natural resources and its exploitation. Water resources are
one of the natural resources which may be the tool for the development of the nation. It can be
utilized in different sectors, such as in power generation, water supply, irrigation ete.
1.2.2.1 Gross, technical and economical power potential
The power which can theoretically possible to generate is known as gross power potential. A +
river basin is divided into number of stretch to measure available head and discharge of the
particular stretch, And based on available data gross power potential is calculated using relation,
P=ZyvQH
All the theoretically possible power in nature cannot be produced due to unfavorable geology,
topography, climatic condition ete. So, the power which is technically feasible to produce is
known as technical power potential.
Alll technically feasible projects cannot be implemented. The project is considered to be
economically sound if the internal rate of return is higher than prevailing interest rate and
benefie cost ratio is more than unity. So, the power which is technically as well as economically
feasible is known as economical power potential
1.2.2.2 Hydropower potential of the world
The world’s total technical feasible hydro potential is estimated at 14370 TWhiyear, of which
about 8082 TWh/year is currently considered economically feasible for development. About
700 GW (or about 2600 TWh/year) is already in operation, with a further 108 GW under
construction [Hydropower & Dams, World Atlas and Industry Guide, 2000]. Most of the
remaining potential is in Africa, Asia and Latin America,
Table1.5: Hydropower potential in the world
Region Technically feasible Economically feasible
potential, TWh/year potential, TWh/year
Africa 1750 1000
Asia . 6800 | - 3600 _
‘North+Central America 1660 _ 1000_
| South America 2665 _ 1600
Total: __12835 7200
gl INTRODUCTION |At present hydropower supplies about 20% of the world’s electricity. Hydro supplies more than
50% of national electricity in about 65 countries, more than 80% in 32 countries and almost all
of the electricity in 13 countries.
(Source: IAEA Report on Hydropower and the World's Energy Future)
1.2.2.3 Hydropower potential of Nepal
Nepal’s theoretical hydropower potential of 83 GW is about 1.5% of world’s total hydropower
potential of 5610 GW in comparison with the Nepal’s land (147181 km?) of only 0.11% of the
world total (Shrestha H.M., 1985).It shows that hydropower potential per unit larid area in Nepal
is about 13 times higher than that of the world average. As the above mentioned value of hydro
potential does not include that from the small river basins (i.e. catchment areas < 300 sq. km,
river length < 10 km.) and there are significant numbers of such rivers in Nepal, the real
hydropower potential of Nepal might be much higher than this. To date, there are no
comprehensive and detailed studies defining the total micro hydro potential of Nepal from such
small rivers.
Tablel.6: Theoretical hydropower potential of rivers of Nepal
[5.N. [Main River Basins [Hydropower potential, GW
Small Major [Total
IRivers* __|Rivers**
t oshi B.6 i8
b _(Gandaki ee ee ce
B [Karnali & Mahakali 3.5 2.68 [36.18
4 Southern Rivers 1.04 3.07 4.11
[Total 7 10.84 “72.45 ‘(83.29
* Rivers with catchment areas 300-1000 of sq km
** Rivers with catchment areas >1000 sq km (Source: Shrestha H.M. 1985)
Theoretical potential = 83000 MW
Technically viable = 44000 MW
Econoniiiéally viable = 42000 MW
Table!.7: Identified potential hydropower projects
SN. Project Capacity | Type J Remarks
(Mw) |
i West Seti_ 750) Storage _|
2__| An it 402, PROR
3 Budhi Gandaki 600 Storage
4___|KaliGandaki 660 Storage
3 Lower Arun 308 PROR__|
| INTRODUCTION ag6 Upper Arun 335 PROR,
7 | Karnali Chisapani 10800 Storage:
8 Upper Karnali 300 PROR
9 Chamelia 30 ROR
10 | Pancheswor 6480 Storage z
11__[ Thulodhunga 25 ROR
12 | Tamor/ Mewa _ 100) PROR.
13 | Dudh Koshi 300 Storage
14 Budhi Ganga an20! ROR i
15 | Rahughat Khola__ [27 ROR | caeeied
16 —_| Likhu 451 PROR
17 | Kabeli A 30 ROR
18 | Upper Marshyangdi A D1 PROR, |
19 | Kulekhani it 45 Storage | Cascade of Kulekhani-l and I
20___| Andhikhola (Storage) 180 Storage
21 Khimti I. - 27 ROR
22 | Upper Modi A 42 ROR
23 | Langtang Khola (Storage) 218 Storage
24 | Madi Ishaneswor (Storage) 86 Storage
25 | Upper Seti (Storage) 122 Storage
26 | Kankai (Storage) 60. Storage
[27 [Upper Tamakoshi 250 PROR
j 1.2.3. Energy /power consumption or situation in Nepal
Sectorial Energy Consumption in 2008/09
Transport
S233
Angus Enerpy Supply/eonsumption by Source in 2008/09
334%
Commercial
428% petralo
aeicumurat “Stas
‘oon
owner rset
ost 5798
ar edu,
36%
Fig.1.2: Sectorial energy consumption in 2008/09
In Nepal, most of the energy is used for residential purpose. The industrial use is comparatively
low and will be very high in development of economic activities under the process of making
new industrialized Nepal. The amount of per capita electricity consumption reflects the living
standard of people and their economic conditions. The per capita electricity consumption in
Nepal is only 69 kWh and aimed to reach up to 100 kWh by 2012 (II™ Interim Plan 2010-2012).
The per capita electricity consumption of Nepalese people is about 37 times less than the world
Ea INTRODUCTION |average and 27 times less than the average Asian people, 48% of the total population in Nepal
has access to the Electricity. Only 8% of people of rural areas enjoy it (Source: MOF 2007,
Energy Synopsis of Nepal WECS-2010)
Table1.8: Hydropower situation in Nepal and World
Country Energy Generated, GWh per annum Installed Power, MW
Canada ~341312 : 66954 7
[USA ___319484 ost ieeeeeneees
Brazil 285603 57517
China 204300 65000
Russia 160500 __ 44000_
Norway 121824 27528
[Japan 84500 e 27229
India 82237 : 22083 |
France 71500 25335,
Nepal 1700 610
1.2.4 Challenges and opportunities of hydropower development in Nepal
‘Although Nepal has developed its first hydropower project about a century ago, the development
pace of its hydropower development is not as it was expected and needed. Because of that,
severe load shedding is unavoidable and becomes a part of Nepalese people. Only about 1.5% of
the economically feasible potential or 1% of theoretical potential has been installed. Only about
48% of the total population has access to the electricity.
a) Challenges
Lack of political stability
Political situation in Nepal is not favorable and stable since from 1990. Any one of elected
government has completed its full phase tenure since from the great people's movement in 1990
(Jana Andolan 2046) and there is no clear vision for development of hydropower. During
Panchyat period also, the development pace in hydropower is not encouraging as the
development activities were based on grant and aid of developed countries and developing
partners. There was no vision of technology transfer and independency. During Rana’s regimes,
the hydropower development was’carried out only for limited use of their own benefits. Present
situation is also not favorable due to results retardation of investment and development activities
in hydropower.
Lack of technology and skilled man power
‘Although Nepal has large potential of hydropower development, it does not have its own
technology and sufficient skilled man power. The technology and technical equipments for
quality monitoring and standard specifications and norms has not been developed in Nepal. The
| INTRODUCTION fa]machines and hydro-mechanical equipments production and maintenance facilities has not yet
developed fally.
Lack of investment .
‘The development of hydropower project needs considerable investment it’s about Rs 120~140
millions to produce 1 MW hydropower development. The gestation period (i.e. the time period
between the start of investment to the start of return fromthe project) of the hydropower projects
are higher than 4~5 years, and the payback period (complete recovery of investment) of the
hydropower projects are 8~10 years, Although the investment in hydropower is relatively high
but not more beneficial compared to the investments in other sectors like trade and commerce,
industries etc, the investment in hydropower is not growing up in the scale as it is required.
Without foreign investment, the hydropower development could not be accelerated to its desired
level. For that, stable political system, safety and security, clear policies and priority of
hydropower developments, assured markets and return of their investment mechanism are
essentials for creating conducive environment of investment in hydropower.
Lack of infrastructures
The feasible and attractive hydropower projects are located in remote areas where physical
infrastructures like access road, transmission lines, basic health facilities, other essential skilled
manpower and construction materials with equipments availability is very poor or not available
at the site, Development of these infrastructures needs heavy investments. The lack of integrated
infrastructure developments policies made haphazard developments resulting the minimum
benefits of the infrastructures that could be achieved. The poor maintenance and rehabilitation of
the infrastructures reduces the service quality and reliability of the services,
Risk imposed by global warming and climate change
The water is the basic raw material for the power production through hydropower plant, The
global warming (0.06 °C ~ 0.08 °C in Nepal Himalayas) has resulted increase of atmospheric
temperature resulting the fast rate of snowmelt. The snow in the Himalayas acts as the overhead
tank and gives flow in the rivers continuously throughout the years. Fast melting of snow due to
global warming results the depletion of snow storage and can cause depletion of low flow in
long term posing threats to the hydropower production. The disturbances in monsoon rainfall
pattern and amount are also attributed to the climate change. The extreme drought and flood
events with high sediment and debris flow seems to be more frequent in recent years posing
Serious uncertainties and threads to the hydropower projects. The glacial lake outburst (GLOF)
events has been increased and caused serious floods with debris flow which may damage the
Structures of hydropower projects, The natural risks and threads have been taken as the one of
the most difficult challenges in hydropower development
ae INTRODUCTION |b) —_ Opportunities
Nepal is in between the two giant countries China and India, Both of the countries are
developing very rapidly in recent years. They need lot of power/energy for their development
activities. Nepal has more than six thousands of rivers and rivulets and has favorable
topographical and geological conditions for hydropower developments. The following points can
be taken as opportunities for hydropower development in Nepal.
Clean energy
Hydropower is taken as clean energy as it does not produce any pollution during its use and
production. It is renewable and hence more attractive sources of energy. The technology of its
production and uses has been already developed and affordable. The hydropower is easy to
handle and transport from the generating stations to the load center. The water of Nepalese rivers
can be taken as white coal and policies has been introduced to exploit the white coal in
worldwide for supply of necessary energy
Market available
The market for Hydropower is easily available for Nepal since its neighbors are being in
developing phase and the economic activities are being taken at rapidly. The electricity produced
in Nepal can be exported to India and China thus helps to reduce trade gap of the nations with
these country. Electricity produced can also be used for domestic use in promotion of industrial
activities and replacement of the petroleum fuels that has to be imported paying hard currency.
‘Thus market for hydropower development is abundant and can be taken as opportunities.
Favorable geological and topographical conditions
‘The steep topography (high river gradient) with good geological conditions (hard rock in river
bed) are the favorable and essentials for development of hydropower projects at low cost of
investment. The perennial rivers with considerable low flow are good for hydropower
productions. Although sediment flow rate in the middle mountains and Chure range are high, the
sediment flow and production rate in high Himalayas are less and can be taken as the
opportunity.
Availability of cheap labor force
Nepal has developed lot of engineering institutes and technical centers after the restoration of
Democracy in 1989°(BS 2046). The institutions have produced lot of skilled and semi skilled
man powers. Although the human resources do not have experience of the mega projects, they
have equipped with theoretical and practical knowledge at the institutions. These human
resources are available at cheap rate compared to that of the man power from developed
countries. The availability of the man powers both skilled and unskilled labors can be taken as
g00d opportunities to develop hydropower schemes for harnessing nation’s water resources.
| ivrooucion [Ream13 Types and classification of hydropower plant
Hydropower plant can be classified based on installed capacity, storage capacity, head,
constructional features etc.
I. _ Classification based on installed capacity
Based on capacity by E. Mosonyi
Midget hydropower plant < 100 kW
Low capacity hydropower plant 101 — 1000 kW
Medium capacity hydropower plant 1001 - 10000 kW
High capacity hydropower plant 10001 ~ $0000 kW
vvvv
Based on capacity by Dandekar and Sharma
> — Micro hydropower plant < 5 MW
> Medium capacity hydropower plant 5 — 100 MW
> High capacity hydropower plant 101 ~ 1000 MW
> Super capacity hydropower plant > 1000 MW
Based on Capacity in Nepal
» Micro hydropower plant < 100 kW
> Mini hydropower plant 101 - 1000 kW
> Small hydropower plant 1001 — 10000 kW
> — Medium capacity hydropower plant 10001 - 50000 kW
> Large capacity hydropower plant >50000 kW
Table!.9: Largest hydropower stations of world and Nepal
Power Station Country Completion Year | Installed Capacity, MW
Three Gorges Dam __| China 2012 22500
Ttaipu Brazil/Praguay 1984/1991/2003 14600
Guri Venezuela 1986 10200
Grand Coulee USA 1942/1980 6809
Sayano-Shyshenskaya | Russia __1985 6400
Krasnoyarskaya Russia 1972 BEmET6000
Robert-Bourassa [Canada : 1981 : 5616 |
Churchill Falls Canada 1971 5428
La Grande- 2 Canada 1979 5328
Bratsk Russia 1967 4500
Tucurui Brazil 1984 8370 |
[Kali gandaki ‘Nepal 2002, 144
Karnali Chisapani ‘Nepal Proposed 10800
waTmODUCTONIl. Classification based on head
Based on head by E. Mosonyi
> Low head plant H <15 m
> Medium head plant H = 15—50 m
> High head plant H > 50m
Based on head by Dandekar and Sharma
Low head plant H <15 m
Medium head plant H = 15-70 m
High head plant H = 71 — 250 m
Very high head plant H > 250 m
vvvv
Classification based on storage
Run of river plant
Peaking run of river plant
Storage plant
Pump storage plant
vvvws
Run of river plant (ROR)
A mun-of-river project is built to use some or most of the flow in a stream depending upon the
flow throughout the year. No attempt is made to store water for the dry periods. A run-of-river
project would not normally have a dam, other than an intake weir, which is a very low head
structure at the intake. The intake weir keeps the water in the stream high enough to fill the pipe
at all times.
Fig. 1.3: Sketch of run of river plant
Suitable where the fluctuation of flow in dry season and wet season flow are small like in rivers
coming from Tibet at border such schemes do not alter the flow regime at the downstream.
Khimti, Khudi, Trishuli, Bhotekoshi ete
| INTRODUCTIONPeaking run off river plant (PROR)
Run off river plants are provided with poundage to regulate flow to the plant which enables
them to take care of our to hour fluctuation in load on the plant throughout the day or week. The
water in river are stored at the head pond during non peak load or off peak load hours of a day
to with draw or use the stoted water for power production during the peak hours of load. The
PROR power plants may operates at full capacity for all hours during high flow or rainy season
but it produces power at full capacity at peak load hours. The power plant may shut down or
operate at lower capacity during the off peak hours in dry season. At the same location, the
installed capacity of the PROR plants are higher than the ROR type plants and operate at full
capacity only at peak load hours. Marshyangdi 69 MW, Middle Marshyangdi 70 MW and
Kaligandaki A 144 MW are PROR project in-Nepal.
Reservoir storage plant
Hydropower plants which draw water from large storage reservoirs developed by constructing
dam across the river are called reservoir or storage project. Depending upon the storage volume,
these plants can hold surplus water from periods when the stream flow exceeds demands for
utilization during the period when demand exceeds the stream flow. Better utilization of
hydropower potential is thus achieved with such plants, The water flow stores in wet season to
supply in dry season, Kulekhani reservoir project is only one storage project in Nepal
Kulekhani-I 60 MW and Kulekhani-II 32 MW.
Pump storage plant
Plants in which all or portion of the water used by these plants is pumped back to the head water
pond to be made available again for the power generation during peak hours of demand. This
type of the power plant essentially consists of a tail-water pond and head water pond, During
peak load water is drawn. from the head water ponds through the penstock to operate hydro
clectric generating units. The water is collected in to tail water pond and during the off peak
hours, pumps are operated to pump the water back from the tail water pond to the head water
pond. Power for operating the pumps is provided by some of peak thermal or hydropower plant.
Fig. 1.4: Sketch of pump storage
INTRODUCTION |For head up to 120 m’special Francis turbine has been developed for the pump storage plants.
‘The runners of the turbines are so shaped that they can be used both as turbine as well as pumps.
Such turbines are known as reversible turbines.
For high head, multistage centrifugal pumps are used for pumping water and high head Francis
Turbines are installed in power production.
IV. _ Classification based on function
> Base load plant
> Peak load plant
Base load plant
‘As the name indicates base load plants are those which are capable of substantially continuous
operation in the base of the load curve throughout the year. Both ROR and reservoir plants can
be used as base load hydro plants. When ROR plants without poundage are used as base load
plants, their full plant discharge is seldom more than the minimum flow of the river and cannot
support the power system during dry season. Hence the reservoir hydro power plants are used as
base load plants during the low. flow season.
Peak load plant
Peak load plants are those designed and constructed primarily for taking care of peak load of a
power system. Pumped storage plants are peak load plants. PROR plants can operate both as
peak load and base load plants depending upon the river flow and load on the power system.
| INTRODUCTION EaCHAPTER - 2
POWER REGULATION
Power regulation is the study of the power or energy consumption/demand variations and their
relationships in a particular power supply system for a community, society, cities, and region or
in country or countries. The demand of power is termed as load and supply of energy is termed
as power in power regulation study. As the individual consumer level, the electrical demand is
quite unpredictable, however as the demands of the various users-are accumulated and added at a
feeder or substation, they begin to exhibit definite pattern.
2.1. Firm power and secondary power
Firm power
The minimum power which can be generated throughout the year from the hydroelectric plant
under the most adverse hydraulic conditions and consumer can always be sure’ of getting this
power.
The firm power would correspond to the minimum stream flow and is available for all times. The
firm power could be increased by the use of poundage. The firm power does not necessarily
correspond to the continuous 24 hrs flow available (100% of time) thus the firm capacity
depends on the minimum stream discharge at the time of peak load, poundage available, shape
and size of connected load curve and the interconnection of other existing plants, It is also
known as primary power and the energy generated from the firm power is known as base energy. «
For a Run-off-River plant without any storage, the firm power would correspond to the
minimum flow of the river which would be available throughout the year. By providing the
storage (poundage), the firm power can be considerably increased.
The primary energy is reliable and available throughout the year and hence has high value for
reliable supply of energy.
Secondary power
The power in addition to the firm power would be generated for only a part of the year is known
as secondary or non firm power. The power is also known as surplus power and the energy is
known as surplus energy. The secondary power is available intermittently at unpredictable time
and hence has less value compared to that of primary power. There is no guarantee for secondary
power and it is supplied to the consumers on ‘as and when available’ basis.
The secondary power is usefull in an interconnected system of power plants. At off peak hours,
the secondary power station (captive plant or thermal plants acting as stand by station) may call
upon to relieve inter connected station thus affecting e¢onomy. The secondary power may also
POWER REGULATION |be used to take care of reducing load shedding hours by sharing the load as per power supply
from peaking power plant.
Pw IP
——:
= Primary Edeay
3 :
i ~
& | Fol entree ngfopeak ond
Peak load
Load factor of a power plant that hasbeen used to supply the power in a system would vary
greatly with the character of the load. High load factor in Industrial area is nearly 1 while it is
low in residential area as low as 0.25 to 0.30.
The installed capacity of a power plant/s has to be equal to the peak load but the total number of
units KWh generated or used will be governed by the average load. If load factor of a power
plant is low, large proportion of the generating capacity remain ideal for most of the time and the
cost of generation per unit energy (kWh) or power is high,
| POWER REGULATION |Load factor value of 0.80 is generally taken during the feasibility study of hydropower project in
Nepal.
Utilization factor or plant use factor
It is the ratio of peak load developed during a certain period to the installed capacity of the plant
Peak load developed during certain period
Utilization factor (UF) = ‘Imstalled capacity
It represents the maximum proportion of the installed capacity utilized during that period of
consideration, With constant head commonly in hydropower plant, utilization factor would
represent the ratio of the water actually utilized for peak load power supply corresponding to the
‘maximum water that can be withdraw from the river to produce installed capacity.
The values of utilization factor commonly vary from 0.4 to 0.9 depending upon the plant
capacity, load factor and available poundage or storage.
Capacity factor or plant factor
It is defined as the ratio of the energy that the plant actually produced during any period to the
energy that it might have produced if operated at full capacity throughout the period.
Actually produced energy Average load x7
Potential capacity of energey produced — Installed capacity xT
Capacity factor (CF) =
The capacity factor will be equal to the load factor if the maximum peak load of
the duration is equal to the installed capacity of the power plant. For hydropower plants, the
capacity, factors varies from about 0.25 to 0.75
depending upon the plant capacity, available poundage or storage and the load
characteristics curve.
Diversity factor
It is the ratio of sum of all individual maximum demands by the customer to the actual peak
load of a system.
Diversity factor (DF) =
Sum of individual max demand by the customer
‘Actual peak load of the system
It gives the time diversification of the load and used to decide the sufficient generating plants
and transmission utilities. If all demands came at the same time, the diversity factor will be
unity or one. The installed capacity that needed to be installed in the power system would be
much more. But the diversity factor is generally much higher than unity
Reserve factor
It is the reciprocal of utilization factor. It is the ratio of installed capacity to the peak load.
| POWER REGULATION Ewinstalled capacity
Reserve factor = %atletcapa
Relationship between capacity factor, load factor and utilization factor
Capacity factor = Load factor x Utilization factor and
Reserve factor = Load factor / Capacity Factor
Proof:
CF =LF x UF
FromRHS, LF x UF = average load/peak load x peak load / installed capacity
werage load/installed capacity = CF
So, CF =LF x UF and 1/UF = LF/CF = RF
2.2.1 Significance of load factor and diversity factor
Load factor and diversity factor play an important part in the cost of the supply of electrical
energy. Higher the value of load and diversity factor, lower will be the overall cost per unit
generated. Higher load factor means greater average load, resulting in greater number of unit
generated for a given maximum demand, Thus, the standing charges, which are proportional to
maximum demand and independent of number of units generated, can be distributed over a
larger number of units supplied and therefore overall cost per unit of electrical energy generated
will be reduced.
‘The capital cost of the power station depends upon the capacity of tlie power station. Lower the
maximum demand of the power station, the lower is the capacity required and therefore lower is
the capital cost of the plant. With given number of consumers the diversity factor of their loads,
the smaller will be the capacity of the plant required and consequently the fixed charges due to
capital investment will be much reduced.
2.3 Power variation: daily, weekly and seasonal
Power consumption in a community or society is not constant forever. It fluctuates hour to hours
in a day and day to day in week and month to months in different seasons. The power
consumption in a society or community depends on the following factors
Population
The population number/size that has to be served by the power system directly governs the
power consumption/demand in the system. Higher the number of people larger the power/energy
demand. During tourist season the power demand in Pokhara is higher than that in off season due
to increase of the people in the city that has to be served. The power demand in small city is
smaller than that of the demand in big cities. Balaju substation needs high power/energy than
that in Bhaktapur substation.
BE cower REGULATION |Climate
‘The climate is another important factor that influences rate of energy consumption per unit time.
In Nepal, the power demand is higher in winter season for heating purpose compared to that in
summer season while in India; the power demand in winter is less than that compared in summer
season mainly due to high temperature and high power demand for cooling.
Living standard
‘The living standard and life style of the people also directly affects the energy/power demand.
The use of electrical appliances for cooking (rice cooker, hot plate, oven etc), heating and
cooling consumes considerable amount of electric energy. The industrial area needs a lot of
energy and power compared to that in residential areas. The energy consumptions in city areas
are higher than that of remote areas mainly due to life style and living standard of the people
2.4 Load curve
It is a graphical representation of load consumption with respect to time. It may be daily,
weekly, monthly, yearly etc. it shows the variation of load during any time. It also gave
information whether the installation is working efficiently or not. The area under the curve
represents the total number of units generated at that duration
2.4.1 Daily load curve
Daily Variation of power supply or demand in a power system is known as daily load curve. The
power demand is not constant in different hours of a day and it varies from hours to hours
depending on the types of areas that have to be served. For domestic area, the peak demand
generally occurs at 18:00 to 20:00 for cooking and lighting purpose at evening. The peak
demand times slightly shifted earlier during winter season and the peak demand is also higher
than that in summer season. The daily load curve for industrial area is quite different than that of
the residential as the peak load generally occurs in day time as the industries runs at full phase
during the office working hours. The peak load may not alter too much even in night time if
there are large numbers of industries that runs continuously 24 hours.
Poser (MW)
oon @ ow nN
Time of Dap
Fig.: 2.2: Typical daily load curve for residential area
| POWER REGULATION—
Power (118)
6 e @ «8 ees
Time ofa Day.
Fig.2.3: Typical daily load curve for industrial / commercial area
2.4.2. Weekly load curve
The power demand or consumption in a community or society is not same in all days of a
week, The variations of the load in different days of a week are known as weekly load curve.
Iugusiriat
Power (3110)
Days ofa weit
Fig. 2.4: Typical weekly load curve for industrial/commercial and doméstic area
2.4.3 Seasonal load curve
The curve showing the variation of power consumption or demand in a power system feeding to
2 community/society or cities in different seasons is known as seasonal load curve. The seasonal
load of a particular place is mainly governed by the climate and culture besides the living
standard & style of the society. For example, the power demand in the winter in Himalayan and
high mountain areas are higher than that in the Terai/ plain terrain region of Nepal mainly due to
cold and arid climate in the winter season. The power demand in the September and October is
high in Nepalese society mainly due to main festival (Dashain and Tihar). ‘The industries and
commercial sectors are also run at full phase targeting the supply and service for the main
festival.
The study of the power/load variation is important for planning of power production/generation
and transmission and distribution utilities, It also helps to impose systematic tariff of electricity
based on the consumption amount and the sector of services. It also helps to prepare guide lines
for operation and maintenance of power projects to achieve the targeted service at optimum cost
BE] POWER REGULATION |for generation, transmission and distribution system. Hence it ultimately helps to formulate
policies in energy sectors to support sustainable economic development of country.
2.5 Power grid
Generating stations, transmission lines and the distribution systems are the main components of
power system. Since most of the hydropower stations are situated far away from the load centers,
it becomes necessary to transmit bulk power from such remote areas economically. The
efficiency of transmission is quite high when the power is transmitted at a high voltage.
Power grid is an essential component of the power system and it is dedicated to evacuate power
from the generation point to the nearby load centre and then distribute to the end customer. Grid
line generally transmit high voltage of 33 to 400 kV or higher. The power grid can be separated
in to two parts i) transmission lines and ii) distribution system.
Based on the number of production units connected to the grid, it can be classified in to isolated
and integrated grid. In isolated grid, the power to the grid is supplied from only one power
station while in integrated grid the power is supplied from two or more than two power stations.
In grid system, the general planning is such that some station may be run as’ base load station
while some other may be run as peak load stations. Power production is designed for optimizing
the cost and comprising mixture of thermal, hydro and nuclear sources.
2.5.1 Advantages of integrated grid over the isolated grid
Increase Reliability: in the event of a forced or planned outage of a power station, the affected
system can be fed from other stations. River flow, storage facilities, floods and draughts are the
factors that may affect the hydropower generation.
Reduction in the total capacity: in an isolated system, reserve units must be maintained
separately in power station but the reduction in total installed capacity depends on the
characteristics of inter connected system and desired degree of service reliability.
Economie operation: power station might be far from the load centre depending upon the
natural resources available e.g. thermal station can be built close to the source firels (coal, mines,
and petroleum refineries) 7
2.5.2 Components of power system
Generators: Generators are machines which generate electrical power when rotated about by
external sources of power such as water; steam etc, generators of hydro power stations have a
speed range of 70 — 1000rpm. The generators can have either a vertical shaft alignment or a
horizontal shaft alignment. The main components of the generators are
| POWER REGULATION> Stator ~ stationary part of generator it consists of frame, core, winding
> Rotor ~ rotating element of generators it consists of hub, rim, poles, excitation
> Bearings — it minimized frictional losses while operating the generator and improves the
efficiency
Transformers
These are devices which increase or decrease the voltages. It consists of a core made from
laminated silicon alloy steel having 0.35mm to 0.50mm thick each layer being insulated by thin
paper or varnish. Two coils of insulated copper wire known as the primary and secondary coils
are wound around the core. A yoltage in the primary coil produces a magnetic field in the core
and induces voltage in the secondary coils. The generation voltage of a hydro-generators may
vary from 6KV to about 20kV, whereas the transmission voltage in case of long transmission line
losses can be minimized and a transformer has to be provided for stepping up the generator
voltage to transmission voltage.
Switchgear
The power houses are designed to give continuous service without interruption of power. But
sometimes faults may develop in the system due to manmade or natural causes. In such cases
suitable protective devices have to be provided to locate the faults, isolate the faulty circuits from
the system and fo clear the faults as quickly as possible. The switching and protective equipment
used for this purpose is known as switchgear. It consists of circuit breakers, relays and
equipments for controlling and measuring such as current and potential transformers, isolators,
lightening arresters, control panels, switches and fuses etc.
Substations
It is generally located just outside the power station building on the ground or sometimes on the
RCC roof of the power house. It consists of incoming line, outgoing line, busbars, transformer,
high and low voltage switchgear like circuit breakers, isolators and lightening arresters, metering
panels, dropout fuses, station earthing system etc.
Control room equipment
It consists of
> Switches to control the operation of units
> Recording and signaling equipments
> Instruments measuring or controlling voltages, currents and frequencies of generation,
outgoing feeders, auxiliary power consumption and battery charging equipments
> Telemetering and telephone equipment
be Reservoir and tail race water level indicators
CeSunkoshi g, Khimil HP
Bhotekoshi
@.
12 KY (Si
‘Santina. ingle circuit
Distribution
a Lamosangha y
| Disuibution ‘Gubstadon)
| to consumers: 132 &
a Donble cireiitg,
Diswibution. <——————}
' to consumers
t
peso
Sawstith
Balaju
(Substation)
(toconsuinels | Bhaktapur
(GSabstation)- 3:
Panauti
Fig. 2.5: Power grid system of Nepal
2.5.3. Power (electricity) system in Nepal
Power System comprised of three components; a) Production/Generation b) Transmission’
; Evacuation and c) Distribution.
2.5.3.1 Production/generation
Power production in the form of electricity needs rotation of the electric coil inside strong
magnetic fields. Generator is the electromechanical parts which converts the mechanical energy
in to the electrical energy based on Faraday’s principle. The coil is rotated in strong magnetic
field at high velocity to induce electricity in the coil. Electric power is generated at low voltage
6.6 KV to 11 KV. The shaft of the generator can be rotated providing energy from various
sources like from coal, Diesel and water. Based on the use of energy to drive the shaft of
generator, power system can be grouped into two systems.
Thermal power system
Electricity is produced from running of generator directly obtained from diesel engines. Steam
engines can also be used to drive the shaft of generator. Coals/Gasoline is used as main fuel for
steam engines. The efficiency of the thermal power system is relatively lower than the
| hydropower generation and it is expensive than hydropower regarding the operation and
maintenance cost.
Hydropower system
In this system, Electricity power is generated by the use of potential or kinetic energy of water.
| As, water is being renewable in nature, high importance has been provided for this system.
Besides that, hydropower is environmental friendly system for power production. Although the
initial cost is high, the operation and maintenance cost is low and it is attractive being the clean
energy having no pollution during production and consumption.
| POWER REGULATION Ea2.5.3.2 Transmission/evacuation system.
Generally the load centre is far from the generation or production system and the power
produced from the plants are evacuated or transmitted to the distribution centre through
transmission line. As generation voltage of a hydro-generators are very low, it is stepped up to
the transmission voltage 33/66/132/230 kV, to minimize transmission losses, transmission line
may be single circuit or double circuit depending upon the numbers of wires in the transmission
line. In developed country high transmission voltage 765 kV and 1200 kV as power
capacity is directly proportional to the square of transmission voltage. For transmission line
greater than 600 km, DC transmission is economical at 400 kV and the line is connected to AC
system at the two ends through a transformer connecting through converter and inverter (silicon
control rectifier).
2.5.3.3 Distribution system
Based on supply system, power system can be divided into isolated and grid system. In isolated
system the power is supplied from a definite power plant while in grid system the supply of
power is made available from multi power plants. Failure of a particular power plant will not
disturb the power supply in grid system. The grid system might be regional, national or
international also.
Advantage
% Use of remote energy source
> Improve reliability
> Utilization of the time difference between various time zones where peak demand are not
coincident, require low installed capacity
> —— Maintenance of power plant possible without disturbing the supply
Disadvantage
> — High power loss in transmission lines in the grid connected system due to long
transmission lines
HEE Power sccutanonIt
SOLVED PROBLEMS
Example #1
The load on a hydel plant varies from a minimum of 10 MW to a maximum of 35 MW. Two
turbo generators of capacities 22MW each have been installed. Calculate a) Total installed
capacity of the plant b) Plant factor c) Maximum demand d) Load factor and e) utilization factor
Solution:
a) Installed capacity of the plant =2* 22 MW = 44MW.
"_ Average output of the plant
b) Plant factor = ee ei
= 20+35)/2 #199 = 51.13%
”
c) Maximum demand = 35 MW
verage output
4) Load factor = —Average output
Maximum demand
100 = 64.29%
Maximum demand on the power station
Rated capacity of the power station
eae =
= 4 *100 = 79. 55%
e) Utilization factor
Example #2
When a run of river plant operates as a peak load station with a weekly load factor of 20% all its
capacity is firm capacity. What will be the minimum flow in the river so that the station may
serve as the base load station? It is given that,
Rated installed capacity of generator = 10,000 kW
Operating hea
Plant efficiency = 80%
Estimate the daily load factor of the plant, if the stream flow is 15 cumecs.
Sm
Solution:
Rated installed capacity of generator = 10,000 kW
Operating head = 15m
Plant efficiency = 80%
When the plant operates as a peak load plant with 20% load factor, the total energy generated for
one week = 10000*0.20*(7*24) = 33.6*10* kWh. i)
If Q is the minimum flow necessary for the plant to run as a base load plant, the power
developed, P = ny QH
= 9.8 *0.8* 15*O
=117.6Q kW
Hence, total units generated for a week =117.60*(7*24)
=1.98*104 OkWh ii)
| POWER REGULATION [ESEEquating i) and ii).we obtain
33.6*10* kWh = 1.98*10° QkWh
6.96 cumecs
Q
Hence the minimum flow in the river = 16 96 cumee.
If the stream flow is 15 cumecs, then power developed per day
P=117.6 Q=117.6*15 = 1764 kW
Total units generator in 24 hours = 1764*24 = 42336 kWh
, 52336
Hence, daily load factor =
Tooo0-24
Daily load factor = 17.64%
= 0.1764
Example #3
Determine the power of a pump lifting liquid with density of 1200 kg/m’, discharge of 1100 Ips,
head of 60 m and efficiency of 70 %.
Solution:
Density of liquid (0) =1200 kg/m?
Discharge (Q) = 1100 Ips = 1.1 m’/sec
Head (H) = 60 m
Efficiency (7) = 70% = 0.7
We know, Power of the pump lifting = 1) y QH
= 0.7 *1200*9.81*1.1*60
Example # 4
Long term average monthly flow ofa large tropical river is given below:
Month Jan_[Feb | Mar | Apr [May [Jun | Jul [Aug | Sept | Oct [Nov | Dec
Discharge,m’/s | 280 | 250 | 210 | 84 [84 | 210 | 868 | 1064 | 2380 | 2492 | 2156 | 659
A hydropower plant is proposed on the river to meet the peak demand of 18 MW in the month of
May of an isolated town, where average annual load is 7 MW. Topography permits a natural net
head of 28 mand plant efficiency is 0.78.
i, If installed capacity is to be fixed to meet the peak demand, determine the percentage
utilization of runoff.
ii, If peak load increase to 37 MW and average load to 23 MW in the month of May , the
installed capacity is increased accordingly; and the power plant is to be operated for only
five days calculate the poundage requirement to regulate the flow over that period.
Solution:
Discharge on May Q = 84m*/s
Net head H= 28 m
ey POWER REGULATION |