Short-term capacity planning deals with which of the following factors?
Complete

Marked out of 1.00

Select one:
a. Overtime budgets

b. Inventories

c. All of the above


d. Workforce size

Question 2
ABC analysis in materials management is a method of classifying the inventories based on
Complete

Marked out of 1.00

Select one:
a. Economic order quantity

b. The value of annual usage of the items

c. Volume of material consumption


d. Quantity of materials used

Question 3
The maximum output that a process or facility could achieve under normal conditions is
Complete called
Marked out of 1.00

Select one:
a. Peak capacity
b. Capacity utilization

c. Effective capacity

d. None of the above


Question 4
The bill of materials shows all the parts required to make __________.
Complete

Marked out of 1.00

Select one:
a. work-in-process inventory

b. raw materials inventory

c. one item
d. the MPR

Question 5
Gantt charts are used for
Complete

Marked out of 1.00

Select one:
a. Linear programming

b. Forecasting sales

c. Production schedule
d. Scheduling and routing

Question 6
According to Johnson rule Define the schedule of the Job
Complete
Jobs Machine 1 Machine 2
Marked out of 1.00
A 4 8
B 3 5
C 6 9

D 7 1

Select one:
a. B-A-C-D
b. A-C-B-D

c. B-C-A-D
d. A-D-C-B
Question 7
Operation at peak capacity involves:
Complete

Marked out of 1.00

Select one:
a. Marginal methods of production

b. None of the above


c. Sustained low utilization rates
d. Maximum output under normal conditions

Question 8
All major inputs to the MRP system include:
Complete

Marked out of 1.00

Select one:
a. Master production schedule and bill of material
b. Bill of material and inventory records

c. Master production schedule, inventory records, and bills of material

d. Inventory records and master production schedule

Question 9
The objectives in developing an MRP include
Complete

Marked out of 1.00

Select one:
a. To maintain the desired level of customer service by maintaining finished goods
inventory levels or by scheduling to meet customer delivery requirements
b. To maintain inventory investment at the required levels

c. To make the best use of material, labour, and equipment

d. All of these
Question 10
Which of the following is not an advantage of using product layout?
Complete

Marked out of 1.00

Select one:
a.
Specialised supervision requirement

b. Minimum inspection requirement


c. Minimum material handling cost

d. None of these

Question 11
Which of the following technique emphasises transportation cost in the determination of
Complete facility location?
Marked out of 1.00

Select one:
a. Both (b) and (c)

b. Location rating factor technique

c. Centre-of-gravity technique
d. Transportation technique
(a) Transportation technique

Question 12
The Match List-I (Production control function) with List-II(Explanation) and select the Match
Complete List-I (Files in MRP) with List-II (Inputs required) and select the correct answer:
Marked out of 1.00 List-I List-II
A. Master production schedule 1. Scheduled receipts
B. Bills of materials 2. Units costs and discounts
C. Inventory records 3. Production capacity
4. Product structure

Select one:
a. A-4 B-1 C-3
b. A- 4 B-3 C-1

c. A-3 B-4 C-1

d. A-3 B-4 C-2


Question 13
Which of the following tools are of least use in capacity planning in the presence of
Complete uncertainty and variability?
Marked out of 1.00

Select one:
a. Process flowchart

b. Simulation models
c. Decision trees

d. Waiting-line mode

Question 14
___________ is the process of multiplying the requirements by the usage quantity and
Complete recording the appropriate requirements throughout the product tree.
Marked out of 1.00

Select one:
a. Planning orders

b. Lead time

c. Exploding

d. Offsetting

Question 15
In which of the following site selection techniques, a weightage between ‘0’ to ‘1’ is
Complete provided to factors that influence its location decision?
Marked out of 1.00

Select one:
a. Transportation technique
b. Location rating factor technique

c. None of these

d. Centre-of-gravity technique
Question 16
A _________ is used when companies usually make more than one product and the same
Complete components are often used in several products.
Marked out of 1.00

Select one:
a. product tree

b. single-level bill

c. multiple bill
d. multilevel bill

Question 17
Which of the following explain the need for facility location selection?
Complete

Marked out of 1.00

Select one:
a. All of these
b. When the lease expires and the landlord does not renew the lease

c. When a business is newly started


d. When the existing business unit has outgrown its original facilities and expansion is
not possible

Question 18
In a machine shop, Steel Strips of 15 mm diameter are produced at a rate of 1000 per
Complete month and the same is consumed at a rate of 600 per month. The production and
Marked out of 1.00 consumption continue simultaneously till the maximum inventory is reached. Then inventory
is allowed to reduce to zero due to consumption. The lot size of production is 1000. If
backlog is not allowed, the maximum inventory level is:

Select one:
a. 400
b. 700

c. 600
d. 500
Question 19
According to Critical Ratio Rule in the table given below __________________(if its already
Complete th
20 day)
Marked out of 1.00 Jobs Due Date(days) Processing Time
(days)

A 24 5
B 23 4
C 36 11

D 31 7

Select one:
a. As C.R. < 1 for Job B it’s on time

b. As C.R. < 1 for Job B its Late.


c. As C.R. >1 for Job B it’s on time
d. As C.R. >1 for Job B its Late

Question 20
There are two products P and Q with the following characteristics
Complete
The economic order quantity (EOQ) of products P and Q will be in the ratio
Marked out of 1.00
Product Name Demand (Units) Order Cost (Rs/Order) Holding Cost (Rs.
/unit/year)
SS Bearing A 2500 200 4
SS Bearing B 5000 400 1

Select one:
a. 1:4
b. 1:8

c. 1:2
d. 1:1
Question 21
The proper sequence of activities for material requirement planning is:
Complete

Marked out of 1.00

Select one:
a. Capacity planning, master production schedule, MRP and order release

b. Master production schedule, order release, capacity planning and MRP

c. Order release, master production schedule, MRP and capacity planning


d. Master production schedule, capacity planning, MRP and order release

Question 22
For planning the procurement or production of dependent demand items, the technique
Complete most suitable is……………...
Marked out of 1.00

Select one:
a. EOQ
b. MRP

c. Both
d. None of these

Question 23 Finite Capacity Scheduling allows the balancing of delivery needs and efficiency
Complete
Select one:
Marked out of 1.00
True
False
Question 24
Average Completion Time & Average job Lateness
Complete
Jobs Processing Time Due Date(days) Flow Lateness
Marked out of 1.00 (days)
Time
A 9 9 9 0

B 7 10 16 6
C 4 12 20 8
D 6 18 26 8

Select one:
a. 17.5 ,5.5

b. 12.25,5.5

c. 12.25,1.88
d. 17.5,1.88

Question 25
Assignment Min Cost (all values in $)
Complete
TYPE & JOB J1 J2 J3 J4
Marked out of 1.00
A 20 36 31 27

B 24 34 45 22
C 22 45 38 18
D 37 40 35 28

Minimum Cost is __________

Select one:
a. 107
b. 103

c. 108
d. 120