Professional Documents
Culture Documents
Case Studies in Managing Geotechnical Risks During Procurement
Case Studies in Managing Geotechnical Risks During Procurement
net/publication/321292720
CITATIONS READS
0 445
2 authors:
Some of the authors of this publication are also working on these related projects:
Alternate Design / Alternate Bid Process for Pavement Type Selection View project
All content following this page was uploaded by Douglas D. Gransberg on 25 November 2017.
24 The risk associated with the subsurface conditions in a construction project can only be
26 has already started. In projects delivered using Design-Bid-Build (DBB) the design is completed
27 before awarding the contract, allowing the opportunity to mitigate the geotechnical risk by means
28 of geotechnical investigations tailored to the design. Projects delivered using Design-Build (DB)
29 present a challenge since the design is not completed at the time of contract award, changing the
30 way risks are allocated between owner and contractor. Previous studies have demonstrated that
31 despite owner attempts to contractually shift the geotechnical risk to the DB contractor, courts
32 often assign the risk of differing site conditions to the owner. This paper presents the results of
34 geotechnical risks during DB project procurement. The paper proposes 12 tools that can be used
35 to reduce the uncertainty associated with subsurface conditions and improve the way
37 INTRODUCTION
38 Geotechnical risk in the construction context refers to the uncertainty in subsurface ground
39 conditions which can cause adverse effects on project cost, time, quality, and environmental
40 objectives (1). Every construction project that relies on the characteristics of the soil for its
41 design and constructability will have a degree of uncertainty with regard to subsurface
42 characteristics inside the project footprint until work starts and the subsurface soil is uncovered.
43 This is especially important for projects in the transportation industry where large project
44 footprints are required, making the impact of having actual conditions differ from those assumed
45 during design very critical to achieving project cost and time objectives (2).
46 The analysis presented in this paper focuses on the unique risk profile that occurs when projects
47 are delivered using the Design-Build (DB) method. DB is a contracting scheme in which one
48 party performs both design and construction services in a single contract with the owner of the
49 project (3). It is considered an alternative project delivery method to the standard Design-Bid-
50 Build (DBB) low bid approach where the owner furnishes a complete design before a
52 The nature of DB contracting provides a unique opportunity for sharing the geotechnical risk
53 because the design-builder is able to perform its own subsurface investigation and accommodate
54 actual site conditions in the design while it progresses with construction. On the other hand, the
55 delivery method also presents some challenges when determining which party is responsible for
57 There are two opposite and mutually-exclusive positions regarding the allocation of the
59 1) Position 1: The Design-Builder is responsible for the design of the project as well as its
61 to account for potential variations in the subsurface conditions when pricing the project
62 (4).
63 2) Position 2: The project site belongs to the owner and the Design-Builder cannot be
65 price proposal, therefore, the impact of unexpected conditions should be borne by the
66 owner. Moreover, some contractors will not participate in projects if they face unlimited
67 risk for differing site conditions (5). The unintended result is less competition and higher
68 construction costs.
69 Public owners typically deliver projects using DB when there is a need to accelerate process by
70 streamlining the design and construction process (6). This time is of essence approach alongside
71 the fact that the geotechnical activities are amongst the first to be performed after contract award,
72 typically makes geotechnical task critical path activities in a construction schedule (7).
73 Therefore, the geotechnical risk must be addressed earlier in the DB project development process
74 than it is in DBB construction projects. (2). In most cases, that means during the development of
75 the DB RFP before the project advertised. The criticality of the geotechnical work exacerbates
76 the above cited conflicting positions on liability for differing site conditions, and contributes to
77 conclusions from existing literature in that geotechnical risk could be the most difficult aspect to
78 manage when using alternative project delivery methods (4; 8; 9; and 10).
79 Therefore, the purpose of this paper is to identify effective practices for managing the
80 geotechnical risk in DB projects from US public agencies and their DB contractors, synthesize
81 the findings and propose a set of tools for allocating the geotechnical risk in DB project
82 procurement.
83 BACKGROUND
85 transportation industry by allowing construction to start before the design is complete (11).
86 Taking advantage of that benefit, the use of DB has significantly increased in the recent decades
87 with 48 states currently implementing this delivery method in their infrastructure projects (3).
88 Despite its increasing popularity, many agencies are challenged by DB projects with high
89 subsurface condition uncertainty. The primary issue is the lack of information available from not
90 having a geotechnical design report during the procurement phase. Thus, the incomplete
91 geotechnical scope of work hinders the ability to characterize the actual subsurface site
93 Several past studies support the need to identify, quantify and mitigate the risk of differing site
94 conditions before the DB contract is awarded (4). McLain et al. (13) suggest expediting the
96 owner and contractor through a thoughtfully developed differing site conditions clause. The
97 subject has also been studied from the legal perspective and improvements have been proposed
98 to mitigate the risk by incentivizing early contractor design (ECDI) through contractual
99 provisions such as alternative technical concepts (ATC) (14). Gransberg and Loulakis (2) found
100 in that regardless of the specific contractual language, the Design-Builder is entitled to rely on
101 the information provided in the RFP and that differing site conditions (DSC) clauses constitute
102 the provision under which the Design-Builder can claim compensation for the time and cost
103 associated with encountering conditions differing from the information provided by the owner in
105 The wording and information included in the RFP plays a critical role in the successfully
106 allocating subsurface risk in a DB project with significant geotechnical issues. A well-written
107 RFP provides the proposers with either sufficient information to price the job accurately or with
108 fair mechanisms such as the DSC to claim compensation if the risk materializes (15). The study
109 presented in this paper seeks to identify and provide the effective practices to contractually
110 allocate, manage and mitigate the geotechnical risk in the procurement phase. By proposing a set
111 of tools rather than a utopian single solution allows owners to adapt their practices to incorporate
112 improvements while remaining within their policies and risk profile.
113 METHODOLOGY
114 The study presented in this paper relied on four different research instruments to assess the
115 current practices in managing the geotechnical risk in DB projects. The first step was to perform
116 a literature review of publications in the subject and a formal content analysis of 59 RFPs across
117 29 state departments of transportation (DOT) that procure projects using DB. While performing
118 the RFP content analysis, a survey was conducted to collect general information from agencies
119 and contractors across the US regarding practices for managing geotechnical risks in DB projects
120 (16).
121 This paper focuses on case studies that were selected based on the results of the content analysis
122 and the survey. Ten (10) DB projects with high geotechnical risks were identified to obtain
123 details of commonly observed practices and assess their effectiveness on a case-by-case basis.
124 The case study methodology has proven to be effective in collecting, categorizing and analyzing
125 emerging technologies and practices (17). This research instrument is appropriate since it allows
126 the in-depth analysis of a project with all of its details and provides understanding behind the
127 rationale followed by the agency when selecting a mechanism to manage the geotechnical risks.
128 The case study data collection is performed by means of structured interviews that follow a
129 standard protocol to ensure replicability and ability to compare the different cases. Following
130 Yin’s (18) protocol on the case study research instrument, the interviews are performed in face-
131 to-face meetings having sent the interview protocol ahead so the interviewees can prepare and
132 collect supporting information. This tool has been proven its robustness when emerging
133 technologies or practices are being analyzed (17). It allows the researcher to glean in-depth
134 information to facilitate the understanding of the rationale behind the distinctive characteristics
136 The completed case studies provide different practices regarding the management of the
137 geotechnical risks will be detailed and put in context so their effectiveness can be assessed and
138 conclusions can be drawn with respect to each tool’s efficacy in providing a contractual base for
139 managing the geotechnical risks in DB projects. Figure 1 shows the methodology process for this
140 paper.
141
Perform structured
interviews for selected
case studies
Evaluate effectiveness of
different strategies and
draw concusions
142
143 Figure 1 - DB Geotechnical Risk Management Practices Case Study Methodology
145 As described in the methodology, a content analysis of DB RFPs and a nation-wide survey were
146 conducted and based on those efforts and a comprehensive literature review, projects eligible for
147 case studies were identified. A case study protocol was developed with the objective of
148 identifying, analyzing and understanding the current models for successful geotechnical risk
149 management on projects delivered using DB. This protocol is then used to conduct structured
150 face-to-face interviews, producing results with established points of comparison and a high level
151 of reliability.
152 Interviews were performed on ten (10) case study projects across nine (9) states in the US:
153 California, Maryland, Missouri, North Carolina, Ohio, South Carolina, Texas and Utah. All of
154 these case studies are projects that involved significant geotechnical risks and several differences
155 and similarities were found in the way the DOTs managed them, which provided valuable insight
156 towards identifying different tools and methods that are currently being used to handle the
157 geotechnical risk. Table 1 provides summary information on each case study project as well as
158 key geotechnical risk mitigation practices that were identified during the structured interviews.
159 Table 1 - Case Study Projects and Summary of Mitigation Practices Used.
Case DOT Case Study Project Contract Contract Geotechnical Risk Mitigation Practice
No. Award Amount
Year
$million
5 UT SR-73 Pioneer 2009 $282 Exclude owner's studies from DSC clause.
Crossing, Lehi Mandatory specifications and extended
warranty for settlement.
6 TX Dallas, Horseshoe 2012 $818 DSC clause with caps. Two NTPs. Not limiting
Project contractor's geotechnical investigation.
Mandatory pavement designs.
11 NC I-40 Landslide 2004 $10.5 Provide as much raw data as possible in the
Project contract. Allow requests for more borings. No
DSC clause. Nested DB.
160
161 Detailed information from each of the case studies follows including the geotechnical risks
162 involved and the approach followed by the agency to manage the geotechnical risk in the
164 Case Study 1: I-64 Daniel Boone Bridge over the Missouri River – St. Louis, Missouri
167 Scope of work: The project consists of building a new bridge over the Missouri River to connect
168 St. Charles and St. Louis, replacing the existing 80-years old structure which is required to be
169 removed, and constructing a bicycle pedestrian facility to connect the Katy Trail State Park to the
171 Geotechnical Risks: MoDOT considers that every bridge project has a higher geotechnical risk
172 as compared to other projects. The risk analysis initially performed by MoDOT included the
173 identification of Differing Site Conditions, Scour and Settlement as geotechnical risks related to
174 this project. Table 2 shows MoDOT’s Risk Assessment Worksheet for this project where a
175 quantitative analysis was performed for each identified risk. This case study stands out for
176 analysis since a complex geotechnical risk such as the potential for liquefaction was identified by
178 Table 2 - MoDOT Risk Assessment Worksheet – Geotechnical / Daniel Boone Bridge Project
181 geotechnical risks in this project was to provide as much information as possible to the proposers
182 in the form of a geotechnical baseline report (GBR). This includes performing additional borings
183 -as requested by the proposers- before awarding. The agency considers that the main
184 geotechnical risk factor in DB contracts is the lack of a detailed design when the contract is
185 awarded. In this case, the agency had to estimate the location of the piers or the final alignment
190 Scope of work: The project consists of designing and building improvements to the I-15/I-215
191 interchange by eliminating existing lane reductions on I-15, reducing operational issues due to
192 weaving trucks, reducing interchange operational deficiencies such as non-standard design
194 Geotechnical Risks: The project site is located in the highly seismic Southern California region
195 within the influence of two fault system (San Jacinto and San Andreas) that are considered to be
196 potentially active. The owner anticipates that the project site will periodically experience ground
197 acceleration due to of small to moderate magnitude earthquakes. The geotechnical report
198 prepared by the owner during the preliminary engineering design identified the two potential
201 build project in their district, the agency knew that there was an inherent risk that needed to be
202 dealt with. In order to manage the geotechnical risk, the agency decided to do a fault trench study
203 to determine and confirm the presence of a fault and to estimate the degree of fault rupture. In
204 addition, adequate subsurface exploration was conducted at strategic locations to help to provide
206 Case Study 4: I-15 Corridor Reconstruction Project – Salt Lake City, Utah
209 Scope of work: The work consisted of reconstructing the I-15 Corridor extending approximately
210 26 km (16 miles) which included widening, a new high occupancy vehicle (HOV) lane and
212 Geotechnical Risks: This project was considered to have a high geotechnical risk because the
213 presence of soft compressive soil was identified in the preliminary studies, which creates the
214 potential for settlement. Despite the accuracy of the information provided in the RFP, a change
215 order had to be issued by the DOT after a claim was filed due to the occurrence of settlement in
216 the structures adjacent to the project due to the weight of the embankment. The solution to the
217 problem was to redesign the embankment so the dimensions are reduced and the load on the soil
218 lowered.
219 Agency approach to manage the geotechnical risk: Being their first large DB project, UDOT
220 approached the geotechnical risk by providing a GDR including nearly 100% AASHTO standard
221 borings which they consider uncommon for a project delivered under the DB scheme.
222 Additionally, having identified the risk of settlement in the preliminary studies, UDOT decided
223 to increase the settlement warranty requirement for this project to three years instead of their
228 Scope of work: The project included six miles of a new connector featuring a new Diverging
229 Diamond Interchange, a ne1 60-in. waterline for the Central Utah Water Conservancy District, a
230 5- to 7-lane urban arterial with PCCP pavement, new bridges over the Jordan River and Union
231 Pacific Railroad, new concrete box culverts at the Dry Creek and Lehi Trail crossing, noise
232 walls, retaining walls, aesthetics/landscaping, drainage, utility relocations, ATMS, and traffic
234 Geotechnical Risks: This project was not initially considered to have particularly high
235 geotechnical risks when estimated by UDOT. The presence of a wetland was identified but the
236 original alignment was not intended to use that area. During the procurement process, an ATC
237 was received to shift the alignment. The ATC was approved but the new alignment did cross
238 through the wetland area resulting in encountering soft soil conditions which led to a claim that
239 was settled in favor of the contractor by means of a contractual change order.
240 Agency approach to manage the geotechnical risk: UDOT provided a Geotechnical Data Report
241 (GDR) in the contract with an estimated cost of 0.5% of the total project amount and dedicate
242 around six (6) months to perform the preliminary studies. Additional studies were allowed to be
243 performed by the proposers if requested, which did not occur in this project. Along with the
244 GDR and the contractual provisions for ATCs and the DSC clause, UDOT provided
245 specifications that had to be followed to mitigate differential settlement and also required at least
250 Scope of work: The U-shaped $818 million bridge and roadway project near Dallas’ Central
251 Business District is referred to as The Horseshoe Project. TxDOT replaces bridges that cross the
252 Trinity River on Interstate 30 and I-35E, as well as upgrade the connecting roads just south of
253 downtown Dallas. The Horseshoe improves safety and increases capacity on these bridges and
254 roadways, which are central to the vitality of the Dallas economy.
255 Geotechnical Risks: This project is considered to have high geotechnical risks due to the high
256 uncertainty related to presence of around 30 to 40 feet of loose clay and soft soil (poor soil
257 conditions) in the site. These conditions present a challenge, especially for the foundations of the
259 Agency approach to manage the geotechnical risk: Given the inherent geotechnical risk,
260 TXDOT procured the project as a DB delivery in order to encourage innovation. In addition,
261 TxDOT managed the geotechnical risk by not limiting geotechnical investigations to be
262 performed by the contractor, promoting the proposal of ATCs, and letting the contractor decide
263 on geotechnical solutions like using a bridge instead of a retaining wall. However, some
264 mandatory design parameters are included as a mitigation action, such as standard pavement
265 designs and a full geotechnical manual that has to be followed except for approved ATCs as
266 occurred in this project (Allowable Skin Friction vs Texas Cone Penetrometer Chart).
267 TxDOT also included liability caps to the DSC clause to clearly establish the shared
268 responsibility of the geotechnical risks and incorporated two notices to proceed (NTP) in the
269 contract; the first NTP included preliminary work and studies, and the second NTP corresponds
271 Case Study 7: Innovative Congestion Management Project – Montgomery and Frederick
273 Location: Montgomery and Frederick Counties, Maryland Award Year: 2017 (Est.)
275 Scope of work: The project consists of a 32-mile corridor, being delivered using Progressive
276 Design-Build, there is no specified scope of work in the RFQ, but mobility, operation and safety
277 are the overall goals. The progressive DB contract consist of a two-phase, fixed value contract.
278 The first phase is for the Design-Builder to provide design and preconstruction services up to a
279 point where specific work packages can be priced. At which point the Design-Builder negotiates
280 a Construction Agreed Price (CAP) price and, if approved by the owner, then a NTP for the
281 second phase is issued and the Design-Builder is able to start construction. The owner reserves
282 the right to not proceed with the second phase is a CAP is not agreed upon.
283 Geotechnical Risks: Given that this projects is procured using Progressive-DB, the Design-
284 Builder and the owner have the flexibility to negotiate the geotechnical scope of the project. This
285 project is considered as a common project with regards of the geotechnical risk. Considering that
286 the contract has not been awarded at the moment of this study and the scope is very broad at this
288 Agency approach to manage the geotechnical risk: Progressive DB is considered a way to
289 manage the geotechnical risk since the uncertainty associated with the subsurface conditions is
290 resolved by the contractor early in the project. Additionally, a scope validation period is
291 incorporated in the contract to allow the contractor to incorporate any differing site conditions
292 early in the project. The agency also considers that there should be a balance in the amount of
293 information that is given to contractors, as too much information or interpretation can give
294 foundations for change orders during the project execution. Giving the DB additional
295 information could reduce the initial cost but cause a change order down the line. Additionally, a
296 scope validation period is incorporated in the contract to allow the contractor to incorporate any
297 differing site conditions early in the project, no DSC claims are allowed outside of this period.
301 Scope of work: The work involved realignment of l-670 EB so through traffic stays to the left
302 and traffic to I-71 exits to the right and work on I-71 from over Jack Gibbs to Long Street.
303 Includes 21 mainline, ramp and overhead bridges. Includes one bridge cap on Spring St and two
305 Geotechnical Risks: Given the overall size of the project, the geotechnical risk was considered
306 higher compared to other projects. In addition, other risks were the high water table on northern
307 section of project, the required dewatering to occur prior to construction, the micro tunnel
309 The location of the project was categorized as: Below the pavement and topsoil layers, the
310 borings encountered primarily Medium dense to very dense sand and gravel consisting of gravel
311 (a-1-a), Gravel with sand {a-1-b), fine sand (a-3) and coarse and fine sand {a-3a) With lesser
312 amounts of gravel with sand and silt (a-2-4) and gravel with Sand, silt, and clay (a-2-6). Hea vino
313 sands were also encountered generally below depths of 15.0 feet. Conditions of specific layers
314 were of quality and gradation that it met the requirements of MSE wall backfill. Contractor did
315 utilize onsite materials for MSE walls with synthetic reinforcement (Tensar).
316 Agency approach to manage the geotechnical risk: The first $250,000 of differing site
317 conditions was to be considered incidental. Micro Tunnel required with location of pre-
318 determined receiving pits defined. Requirement to provide a geotechnical baseline tunneling
320 Case Study 9: Cleveland Innerbelt CCG1 (I90WB Bridge) – Cleveland, Ohio
324 Cleveland. Includes associated roadway work to reconfigure the Interchanges adjacent to the
325 bridge work. First project includes new bridge which will initially carry bi-direction I90 traffic,
326 but in the future will carry only I90WB traffic. The project included approximately 2 miles of
327 mainline interstate reconstruction, including a 4,000’-long viaduct over the Cuyahoga River
328 Valley, system ramps, on/off ramps, local street grid modifications. The work includes
330 Geotechnical Risks: ODOT only identified the stabilization of landslides (west slope adjacent to
331 Cuyahoga River) as complex geotechnical activity. However, given the size of the contract, the
332 project was considered as a complex. In addition, geotechnical risks identified were: abandoned
333 foundations; 150' average depth of poor quality soils above bedrock, for main viaduct bridge;
334 vibration impact on existing structures; control over foundation and wall types; and mitigation of
336 Agency approach to manage the geotechnical risk: the agency conducted a robust subsurface
337 exploration program in advance of the procurement, prescribed the west bank slope stabilization
338 with sealed construction plans in the contract documents, and provided scope language requiring
339 deep foundations to bedrock for the main viaduct bridge, and drilled shaft foundations for main
340 viaduct substructures located within the Cuyahoga River west bank zone. A $500,000 differing
342 Case Study 10: Port Access Road – Charleston County, South Carolina
345 Scope of work: The Project consists of the construction of a new fully directional interchange on
346 I-26, a Bainbridge Connector Road, the extension of Stromboli Avenue and associated roadway
347 improvements to surface streets to serve the proposed Naval Base Terminal (NBT) in Charleston
349 Geotechnical Risks: The risk was perceived to be very significant, therefore, extensive
350 geotechnical and environmental testing was completed prior to advertising the project to assess
351 the potential risk. The project is located in a highly seismic area. Underground conditions consist
352 of soil potential for liquefaction, soft compressive clays, variable conditions and dipping stratum,
354 Agency approach to manage the geotechnical risk: A total of about $1.2 million and more than
355 7000 man-hours were used for performing the geotechnical and environmental investigations in
356 this project, around a third of the cost was due to deep boring for seismic consideration.
357 There is interpretation of the data, though it doesn’t specifically reference DSC clause and is
358 provided for information only. Interpretation of the data is used in part in developing the RFP to
361 - More information was made available to the proposers, including deep boring. As much
362 drilling as the agency could do was performed, up to approximately 70% of what would
363 have been done for a DBB. Regular projects are around 20-30% or enough to meet NEPA
364 test.
365 - The alignment was narrowed down for this project, so the contractor did not have too
367 - Seismic parameters where provided. Liquefaction or loss of shear capacity and slope
368 stability.
369 - An attempt to reduce overall risk was made by conducting relatively extensive
370 geotechnical and environmental testing prior to issuing an RFP. A specified dollar
371 allowance was included in the RFP Agreement for testing and handling of hazardous
373 - Differing Site Conditions rights due to geotechnical/geological issues were eliminated
375 Case Study 11: I-40 Landslide Project – Haywood, North Carolina
378 Scope of work: The 2004 hurricane season wreaked havoc in western North Carolina from four
379 different storm events with immense rainfall. These rains caused a massive amount of damage to
380 the communities and transportation facilities in western North Carolina. The Pigeon River,
381 swollen with runoff from Hurricanes Jeanne and Ivan and a flood release from the Walters Dam
382 scoured away the toe of several embankment slopes supporting Interstate 40 near the North
383 Carolina-Tennessee border. On September 17, 2004, several landslides occurred between Mile
384 Markers 1 and 4. Portions of eastbound I-40 fell into the river. I-40 was closed in both
385 directions and traffic was rerouted. The NCDOT was faced with the challenge of re-opening all
386 lanes of traffic on I-40 to the traveling public as soon as possible. Numerous units from the
387 Design Branch and the Division Construction staff of the NCDOT had to work together within a
389 Geotechnical Risks: NCDOT realized that the required tie-backs for the retaining wall were
390 going to have to be long, a risk was identified for the case that the required length ends up being
391 longer than expected due to the site conditions. In addition, the potential was identified for
392 finding underground boulders on the site, which would impact the project execution.
393 Agency approach to manage the geotechnical risk: NCDOT provides as much raw geotechnical
394 data (no interpretation) as possible in their contracts. In this project, due to the emergency nature,
395 four different geotechnical firms were contracted to perform borings and collect data at each
396 landslide location. A total of 35 borings were performed in a 3-week timeframe, which was the
397 time spent for letting and awarding the contract. The geotechnical studies in this project
398 represented around 5% of the project total amount, when the typical value for NCDOT’s DB
400 The proposers are typically able to request additional borings to be performed by NCDOT during
401 the letting process. The results of these additional borings are made available to all competitors,
402 but sometimes the agency performs more borings to avoid giving away the location requested by
405 Considering that there is no unified approach towards managing the geotechnical risk in DB
406 projects and every agency and project will have distinctive characteristics that may constrain
407 agencies from implementing all possible pre-award mitigation actions available, the main
408 contribution of this study is a set of tools that can be independently implemented to
409 accommodate the risk profile of a given project. Based on the findings of the case studies
410 intersected with the results of the content analysis of 59 RFPs across 29 DOTs, the proposed
412 The first group is comprised of tools that are commonly used in the transportation industry,
413 Table 3 shows a synthesized list including the state in which they were found in the case study
414 analysis and the relative frequency in which the same tools were found in the content analysis.
415 The relative frequency is presented as a ratio (%) of the frequency and the total number of
Source
Content Analysis
Tool
Case Studies (% relative
frequency)
Allow proposers to request/perform MO, CA, IN, UT, TX,
42%
additional studies during procurement. MD, OH, SC, NC
MO, CA, UT, TX,
Request of geotechnical ATCs 58%
MD, OH, SC, NC
Provide enough geotechnical
MO, CA, UT, TX,
investigation data to thoroughly 64%
OH, SC, NC
describe the site before advertising.
MO, CA, IN, UT, TX,
Include differing site conditions clause 59%
OH, SC
Incorporate prescriptive design
parameters on critical aspects (e.g. CA, TX, OH, SC 63%
seismic risk).
Include differing site conditions clause,
MO, CAL, OH 17%
allow claims based on owner's studies
Require additional performance
UT 7%
warranties
Include owner's interpretation of the
SC 8%
geotechnical data in the contract (GBR)
418
419 The second group is comprised of those considered emerging tools found in the case study
420 analysis, which are shown in Table 4. These tools are characterized by innovation and represent
421 the current direction in which agencies pursue an increase in effectiveness when managing the
Progressive DB: two (or more) phases DB contract, scope is developed and
prices are agreed upon as the design progresses and preliminary engineering
MD
is performed by the Design-Builder, the owner retains option to not proceed
with the project (or its components) if prices are not agreed.
424
425 Conclusions
426 The case study bottom-line is that geotechnical risk is best managed by getting project
427 excavations underway as soon as practical so that any differing site conditions can be identified
428 and resolved. The worst way to approach geotechnical risk is to attempt to shed it using
429 exculpatory contract clauses because the courts have repeatedly ruled against owners who
430 naively address this risk in an adversarial manner (19). Therefore, risk management and
431 mitigation tools that facilitate the sharing of geotechnical risk and those that seek to accelerate
432 the start of geotechnical design and project excavation appear to be potentially more efficient
433 than those that rely on additional subsurface investigations during preliminary engineering. Put
434 another way, increasing the boring and testing effort will reduce the differing conditions risk, but
435 it does not reduce the impact of a differing site condition established after award of the DB
436 contract. Means like the scope validation period found in the MSHA progressive DB project
437 delivery method provide a mechanism to jointly identify and address geotechnical risk early in
438 project execution and appear to be quite effective in mitigating the impact of difficult
440 It is important to note that even though some tools are found to be more widely used than others
441 and might be interpreted as the ‘tested and proven’ approaches, the more innovative tools like
442 Progressive DB, Scope Validation Period, Multiple NTPs, or Monetary Allowances are the ones
443 pushing forward towards finding a solution to effectively mitigate the geotechnical risk. This is
444 consistent with the overall perception collected from the case studies that the involvement of
445 potential contractors early on the process allows for better risk sharing and problem solving,
446 increasing the effectiveness of any mitigation action that the owner might implement on its own.
447 Each project will have its own context and no single tool will eliminate the geotechnical risk
448 entirely before the work starts and the subsurface conditions are uncovered. However, a
449 combination of the proposed tools, as shown in the case studies, does provide an effective way to
450 mitigate the effects of the risk by incorporating innovative approaches while complying with
454 request.
455 REFERENCES
456 1. Clayton, C.R.I., Managing Geotechnical Risk. The Institute of Civil Engineers, UK,
457 2003.
458 2. Gransberg D. D. and M.C. Loulakis, NCHRP Synthesis 429: Geotechnical Information
461 3. Design-Build Institute of America (DBIA). State Statute Report, 2015. [online] Available
464 4. Christensen M.R. and Meeker, L.E. “Design/Build Projects – Lessons Learned from the
467 5. Loulakis, M.C., B.P. Wagner, and H.C. Splan. Differing Site Conditions, Chapter 11,
468 Construction Claims Deskbook, Aspen Law and Business, New York, N.Y., 1995, 131–
469 166.
470 6. Songer, A. D., and K.R. Molenaar. "Selecting design-build: Public and private sector
474 Geosustainability And Geohazard Mitigation, New Orleans, Louisiana, March 9-12 2008,
478 9. Hatem, D.J., “Risk Allocation for Subsurface Conditions and Defective Design,” Design
479 Build Subsurface Projects. Edited by Brierley, G.S. Corkum D.H. and Hatem, D. J.
480 Society for Mining, Metallurgy and Exploration, Englewood, Colorado, 2011, 228pp.
481 10. Schaefer, V.R., Douglas, S.C. and Berg, R.R., “SHRP2 R02 Geotechnical Solutions for
482 Transportation Infrastructure: Guidance and Selection System,” TRB 2011 Annual
487 2006.
488 12. Beard, J. L., M. C. Loulakis, and E. C. Wundram. Design-build: planning through
490 13. McLain, K., D.D. Gransberg, and M.C. Loulakis. "Managing geotechnical risk on US
493 14. Papernik, B.G. and Farkas, D.J., “Using Alternative Technical Concepts to Improve
494 Design-Build and PPP Procurements,” Nossaman E-Alerts, (2005) [Online]. Available:
495 http://www.nossaman.com/using-alternative-technical-concepts-improve-designbuildppp,
497 15. U.S. Army Corps of Engineers (USACE), Army Reserve Design/Build RFP Instruction
501 Research Record: Journal of the Transportation Research Board, Vol. 2630, 2017, pp.
502 9–14.
503 17. Eisenhardt, K. M. Building Theories from Case Study Research. Academy of
505 18. Yin, R. K. Case Study Research: Design and Methods. Sage Publications, New York,
506 2011.
507 19. Loulakis, M.C. and Shean, O. J., “Risk Transference in Design-Build Contracting,”
508 Construction Briefings, 2nd series, Federal Publications, Washington, DC, 1996, 12pp
509