PROJECT: PROPOSED PERIMETER FENCE SUMMARY

LOCATION: LUN MASLA, SARANGANI PROVINCE


SUBJECT: ESTIMATED COST PERIMETER FENCE
DATE: 28-Mar-21

ITEM NO. DESCRIPTION AMOUNT


1.0 EARTHWORKS 358,000.00
2.0 CONCRETE WORKS 113,400.00
3.0 MASONRY 540,750.00
4.0 STEEL REINFORSEMENT 513,100.00
5.0 BARBWIRES 94,500.00

SUB TOTAL (TOTAL COST OF MATERIALS) 1,619,750.00


LABOR 485,925.00
TOTAL COST OF PROJECT 2,105,675.00

ENGR. FERNANDO GUINTO


CIVIL ENGINEER
CONFORMED BY
EDMUND JALIM ONG

1
Item
No. DESCRIPTION QTY. UNIT UNIT COST AMOUNT
1.0 EARTH WORKS 358,000.00
1.1 Excavation
1.1.1 Column Footing 560 m³ 300.00 168,000.00
1.2 Back Filling and compaction
1.2.1 Back filling 400 m³ 250.00 100,000.00
1.2.2 Gravel Base 200.0 m³ 450.00 90,000.00

2.0 CONCRETE WORKS 113,400.00


2.1 Foundation
2.1.1 Column Footing 42 m³
Cement 378 bags 250.00 94,500.00
Sand 21.0 m³ 650.00 13,650.00
Gravel 21 m³ 250.00 5,250.00
3.0 MASONRY 540,750.00
3.1 Masonry
3.1.1 SLAB 210 m³
Cement 1,890 bags 250.00 472,500.00
Sand 105.0 m³ 650.00 68,250.00
Gravel 105 m³ 250.00 26,250.00
4.0 STEEL REINFORSEMENT 513,100.00
4.1 Foundation
4.1.1 COULUMN
10mm X6.0m Rebar 1,050 pcs 220.00 231,000.00
4.1.2 COULOMN
10mm X6.0m Rebar 900 pcs 126.00 113,400.00
4.1.3 SLAB
8mm X6.0m Rebar 2,800 pcs 100.00 280,000.00
4.1.3 SLAB
4mm X6.0m Rebar 1,260 pcs 95.00 119,700.00
5.0 BARBWIRE 94,500.00
5.1
BARB WIRE 35 ROLLS 2,700.00 94,500.00
150 MTRS/ROLL

``