Professional Documents
Culture Documents
The following are the major differences between Cost Control and Cost Reduction:
1. The activity of maintaining cost as per the established norms is known as cost control.
The activity of decreasing per unit cost by applying new methods of production in such a
way that it does not affect the quality of the product is known as cost reduction.
2. Cost Control focuses on decreasing the total cost while cost reduction focuses on
decreasing per unit cost of a product.
3. Cost Control is temporary in nature. Unlike Cost Reduction which is permanent.
4. The process of cost control is completed when the specified target is achieved.
Conversely, the process of cost reduction has no visible end as it is a continuous process
that targets for eliminating wasteful expenses.
5. Cost Control does not guarantee quality maintenance. However, 100% quality
maintenance is assured in case of cost reduction.
6. Cost Control is a preventive function as it ascertains the cost before its occurrence. Cost
Reduction is a corrective action.
What is responsibility centre? Briefly differentiate cost, profit and investment
centers identifying the basic characteristic of each.
Revenue Centers
managers are held responsible for revenues (sales) only.
managers of such centers also responsible for controlling expenses of unit as well.
Profit Centers.
a responsibility center having both revenues and expenses.
the manager must be able to control both of these categories.
controllable profits of a segment are shown when expenses under a manager's control
are deducted from revenues under that manager's control.
Investment Centers.
a responsibility center having revenues, expenses, and an appropriate investment base.
the manager in charge of an investment center is responsible for and has sizable control
over revenues, expenses, and the investment base.
Equivalent units is a cost accounting concept that is used in process costing for cost calculations. If
100 units are in process but you have only expended 40% of the processing costs on them, then you are
considered to have 40 equivalent units of production.
The loss expected or anticipated prior to production is a normal process loss. It is
thus called a standard loss. A provision for such a loss is made before starting production. Weight losses,
shrinkage, evaporation, rusting etc. are the examples of normal loss. Normal loss increases the cost of
production of the usable goods realized.
The loss realized over the normal loss is called an abnormal loss. Abnormal loss
arises because of abnormal working conditions, bad working condition, carelessness, rough handling, lack
of proper knowledge, low quality raw material, machine breakdown, accident etc .Therefore an abnormal
loss is an unanticipated loss. Abnormal loss is a controllable loss and thus can be avoided if corrective
measures are taken. Therefore, abnormal loss is also called an avoidable loss.
An opportunity cost is the benefit that is lost or sacrificed when rejecting some course of action.
Limiting Factors refer to the constraints in availability of production resources (e.g. shortages in labor,
machine hours or materials) that prevent a business from maximizing its sales.
Opportunity cost: Opportunity cost is the value of next best alternative that is sacrificed
while making a decision. Opportunity costs are implicit costs because they do not appear in
the accounting records.
For example: suppose, a certain piece of land is capable to produce 10 tons of rice or 5 tons
of jute. If a farmer produces rice, he needs to sacrifice to produce jute.
Relevant cost: A relevant cost is a future cash cost that is relevant to a particular decision.
This is used to exclude sunk costs, committed costs and non-cash costs from decision
making as considering these costs is typically illogical.
Replacement cost: Replacement cost is the price that an entity would pay to replace an
existing asset at current market prices with a similar asset. If the asset in question has been
damaged, then the replacement cost relates to the pre-damaged condition of the asset.
a) Selling price is constant. The price of a product or service will not change as volume
changes.
b) Costs are linear and can be accurately divided into variable and fixed elements. The variable
element is constant per unit, and the fixed element is constant in total over the relevant range.
c) In multi-product companies, the sales mix is constant.
d) In manufacturing companies, inventories do not change. The number of units produced
equals the number of units sold.
1. Segregation of total costs into its fixed and variable components is difficult to do.
2. Fixed costs are unlikely to stay constant as output increases beyond a certain range of activity.
3. The analysis is restricted to the relevant range specified and beyond that the results can be
unreliable
4. Besides volume, other elements like inflation, efficiency, capacity and technology can affect
costs
5. Impractical to assume sales mix remain constant since this depend on the changing demand
levels.
6. The assumption of linear property of total cost and total revenue relies on the assumption that
unit variable cost and selling price are constant. However, this is likely to be valid within
relevant range only.
Outline TWO advantages and TWO disadvantages of activity based costing
compared to a traditional absorption costing system.
Explain how the information obtained from the activity based costing might be used by
the management of the company.
Using an activity based costing (ABC) system the cost drivers that cause a change to the cost
of activities are identified. These cost drivers provide information to management to enable
them to take actions to improve the overall profitability of the company. Cost driver analysis
will provide information to management about how costs can be controlled and managed.
Variance analysis will also be more useful as it is based on more accurate costs. The
establishment of more accurate product costs should also help managers to assess product
profitability and make better decisions concerning pricing and product mix.
ABC gives more detailed information about how costs are incurred and the potential for cost
reduction by reducing activity levels. The company may also consider the possibility of
discontinuing the clothing product group as it is loss-making or allocating less store space to
that product group.
An activity based costing system can be extended beyond product costing to a range of cost
management applications known as activity based management. These include the
identification of value added and non value added activities and performance management in
terms of measuring efficiency through cost driver rates.
Explain why a back flush cost accounting system may be considered more
appropriate than a traditional cost accounting system, in a company that a just-in time
production and purchasing system.
Traditional cost accounting systems track the sequence of raw materials and components
moving through production. Such systems are time consuming and expensive to operate as
they require considerable documentation, such as material requisitions and time sheets, and
detailed accounting in order to maintain the job cards and inventory records.
Back flush costing delays the recording of costs until after production has been completed or
even sold. Standard costs can then be used to work backwards to 'flush' out the
manufacturing costs.
The absence of inventory in a just-in-time purchasing and production system makes choices
about inventory valuation methods unnecessary and the rapid conversion of direct materials
costs into cost of goods sold simplifies the cost accounting system.
The working capital cycle (WCC) is the amount of time it takes to turn the net current assets
and current liabilities into cash. The longer the cycle is, the longer a business is tying
up capital in its working capital without earning a return on it.
With an aggressive working capital investment policy, a company would hold minimal safety
inventories. Such a policy would minimise costs but it could reduce sales as the company
could not respond rapidly to changes in demand. Generally, the expected return is higher
under an aggressive policy but the risks are also greater. In cash management, an aggressive
policy involves holding low levels of cash which would expose the company to the risk that
they could not meet payments when they become due. In the case of accounts receivable
and account payable, an aggressive policy would mean low levels of receivables in relation
to sales and high levels of accounts payable.
With an aggressive working capital financing policy, the company finances part of its
permanent asset base with short term debt. This policy generally provides the highest
expected return but it is very risky due to the frequent need to refinance or if the company
relied on an overdraft, the risk of withdrawal of that facility at short notice.
What is working capital? Identify some working capital ratios and explain them. What
is the specialty in managing working capital needs for a supermarket?
Working capital is the amount of a company's current assets minus the amount of its current
liabilities. For example, if a company's balance sheet dated June 30 reports total current
assets of $323,000 and total current liabilities of $310,000 the company's working capital on
June 30 was $13,000. If another company has total current assets of $210,000 and total
current liabilities of $60,000 its working capital is $150,000.
See your study text.
Discuss the advantages to a company of taking steps to improve its working capital
management, giving examples of steps that might be taken.
Working capital is a vital part of a business and can provide the following advantages to a
business:
Firms with an efficient supply chain will often be able to sell their
products at a discount versus similar firms with inefficient sourcing.
The economic order quantity (EOQ) is based on the assumption that demand for the period is
known and constant. Therefore the optimum order quantity will be determined by the costs
that are affected by either the quantity of inventory held or the numbers of orders placed. A
higher quantity ordered each time will mean fewer orders each year and therefore a reduction
in ordering costs. However, this will also result in higher average inventory levels which
results in an increase in holding costs.
The EOQ therefore is a trade-off between the costs of carrying high inventory against the
costs of placing more orders. The optimum order size is the quantity that will result in the
total of the ordering and holding costs being minimised.
The EOQ model assumes a world of certainty where the usage and delivery of inventory can
be predicted accurately and management can therefore avoid stock-out costs and concentrate
on achieving the optimal balance between ordering costs and holding costs.
However this is unlikely to be the case in reality for most companies. The EOQ model
ignores two types of risk:
a) Uncertainty over the time it takes for the order to be delivered i.e. the lead time. The lead
time is neither zero as assumed by the model or necessarily predictable.
b) The rate at which inventory is used may not be constant, demand may be subject to
fluctuations and the overall annual demand may be difficult to predict with accuracy.
The company can cope with these two risk elements, to a certain extent, by holding a buffer
inventory. The buffer inventory level can be calculated by weighing up the cost of stock-outs
and the costs of holding additional inventory. The determination of lead time and dealing
with uncertainty of demand requires subjective managerial judgement as does determining
the cost of stock-outs since many of the costs involved are difficult to quantify.
Briefly discuss the relevance of the concept 'Cash is King' in today's economic
environment.
The importance of strong cash flow is aptly stated in the common expression "cash is king." The
premise of this is that having cash puts you in a more stable position with better buying power.
While you can borrow money at times, cash affords you greater protection against loan defaults
or foreclosures. Cash flow is distinct from cash position. Having cash on hand is critical, but
cash flow indicates an ongoing ability to generate and use cash.
In the world of investments, investors who favor the 'cash is king' phrase may opt to buy short-
term debt instruments versus buying high-priced securities. If employing a strategy of holding a
lot of cash, an investor should work with a financial planner to estimate future cash needs and
rates of inflation. Cash, cash equivalents and some short-term debt instruments lose spending
power over time if they do not offer a return that keeps up with the rate of inflation. This can
cause holders of cash as a long-term investment to experience a negative return over time.
The phrase also refers to the ability of a corporation or a business to have enough cash on hand
to cover short-term operations, buy assets such as equipment and machinery or acquire other
facilities. More businesses fail for lack of cash flow than for lack of profit.
In recent years since the global financial crisis, tech companies such as Apple and Amazon have
been hoarding cash on their balance sheets as opposed to spending it. In 2017, market disruptor
Amazon made an extremely large cash outlay to purchase Whole Foods, sending panic through
the grocery industry and putting the stock of companies such as Kroger into a temporary tailspin.
Cash gave Amazon the power to make that large purchase and disrupt the markets.
When deciding how much cash to hold for operating purposes, a company needs to
strike a balance between the cost of holding too little cash and the cost of holding too
much cash.
-
According to the trade-off theory, we can identify two costs of holding cash. If we assume
that managers maximize shareholder wealth, the main cost experienced by holding cash is
the opportunity cost of the capital invested in liquid assets.
On the other hand, if managers don't maximize shareholders' value, they increase their cash
holdings to increase assets under their control and so to be able to increase their managerial
discretion.
As a result, the cost of cash holdings will increase and include the agency cost of managerial
discretion.
The main advantage of holding cash is that the firm saves transaction costs to raise funds and
does not have to liquidate assets to make payments. Consequently, firms will hold more cash
when it is likely to incur higher transactions costs to convert non-cash assets to cash.
Alternatively, firms will tend to hold lower amount of cash when the opportunity costs of
cash retention are greater.
Factoring and Invoice Discounting are both financial services that can release the funds tied up
in your unpaid invoices, involving a provider who agrees to advance money against outstanding
debtor balances.
The essential difference between Factoring and Invoice Discounting lies in who takes control of
the sales ledger and responsibility for collecting payment:
With Factoring, the provider takes the role of managing the sales ledger, credit control
and chasing customers for settlement of their invoices.
With Invoice Discounting, your business retains control of its own sales ledger and
chases payment in the usual way.
Another difference between Factoring and Invoice Discounting is in the area of
confidentiality:
With Factoring, the customer settles their invoice directly with the Factoring company; so
customers are more likely to be aware of your Factoring arrangement.
With Invoice Discounting, your customers still pay you directly; there is no need for
them to know that a third party is involved
Overdraft is a temporary facility obtained by the companies to meet their ultra-short term cash
shortage/requirement. One needs to bear in mind that such facility comes with a high cost and should
be used as a stop-gap management of funds or as an emergency activity rather than a routine funding
activity. Higher dependence on overdraft for working capital financing indicates poor working capital
management and a liquidity constraint faced by the company. Only temporary working capital should
be financed by bank overdraft. The permanent working capital should be financed by long-term
financing.
Your CFO sent you an email asking for your explanations on the factors that should be
considered in determining the most appropriate mix of short term financing(e.g.
overdraft) and long term financing (e.g. fixed term bank loan).
Reply the email to CFO stating briefly the factors asked by him.
Cost:
Financial strength and stability of operations
Form of organization and legal status
Purpose and time period
Risk profile
Control
Effect on credit worthiness
Flexibility and ease
Tax Benefits
State TWO ways in which an accepted bill of exchange can be used by the holder.
post, email and telephone to recover an overdue debt. Despite this, the customer has
still not paid and the credit controller is considering other actions that could be taken
to recover the debt.
can encourage rapid settlement of debts particularly if the customer has no other sources of
supply for the goods or services. It will avoid any further outstanding debt but may not result
in payment of the existing debt if the customer can obtain supply of goods or services from
other suppliers.
The credit control department could use a debt collection agency to collect the debt from
the customer. This should result in rapid settlement of the debt and allow the credit control
department to concentrate on other customers. It would however involve further expense
as the agency would charge a fee for the collection. The quality of service varies
considerably and the company must be careful to select an agent whose approach to the
The credit control department could take legal action to recover the debt. This is normally
payment and would avoid the need to go to court. It may not be cost effective to take court
action but it may discourage other customers from delaying payment.
When deciding where to invest short term cash surpluses, it is necessary to consider the
following two types of risk:
(i) Default risk;
(ii) Interest rate risk.
Explain what is meant by each of the TWO types of risk listed above. Your answer
should include an example of each type of risk.
Default risk
This refers to potential doubt about the payment of interest or the eventual repayment of the
capital invested. Investments in government securities are generally considered to have very
low default risk however the recent financial crisis has shown that even investment in
government securities is not risk free. Investment in equities is generally considered high risk
and is not a suitable form of short-term investment.
Interest rate risk
This refers to the risk that market interest rates will change and the investor will be worse off.
Interest rates cannot be predicted with any degree of accuracy. Variable rate bank deposits
will leave the company vulnerable to a fall in interest rates. If the investment is in a fixed rate
term deposit, whilst the investor will receive a guaranteed return, there will be an opportunity
cost if market interest rates increase above the fixed rate.
A company has recently sold part of its trading operations and is reviewing
potential long term investment opportunities for the funds. Until a suitable
opportunity is identified the funds are being held in a bank deposit account but the
company is considering the following alternative short-term investments:
(i) Certificate of deposit
(ii) Bill of exchange
Instructions:
Describe the alternative short-term investments in terms of their risk, return and
liquidity.
Certificates of deposit
These are securities that are issued by a bank as an acknowledgement that funds have been
deposited. Certificates of deposit are traded on the money market and so the holder can sell
them to obtain immediate cash at any time. They are therefore a suitable option in terms of
liquidity and have a low risk. Interest is paid on the deposit at a fixed rate based on current
market interest rates at the date of issue but this will reflect the low risk involved. They are
therefore subject to interest rate risk since if market rates increase they lose the opportunity
for higher rates.
They normally have maturities from three months to five years. The lower end of this time
marketability the upper end of this time range gives flexibility. The company however would
also be exposed to capital risk as the value of the investment changes in response to market
interest rate movements.
Bills of exchange
A bill of exchange is an unconditional order by one person/company to pay another a given
sum of money at a specified future date. These are tradeable and have a short date normally
within 180 days. There is a particularly active market in bills that are payable by top-quality
banks although it is also possible to buy bills that have been accepted by trading companies.
These would therefore be a suitable option in terms of liquidity. They are issued at a discount
to the face value with the yield on the bill dependent on the credit worthiness of the drawee
and market interest rates. They are therefore subject to interest rate risk since if market rates
increase they lose the opportunity for higher rates. They are also subject to default risk
depending on the credit worthiness of the drawee.
Why is it necessary to consider risk & uncertainty when making appraisal of an
investment, explain?
If risk and uncertainty were not considered, managers might make mistake of placing too
much confidence in the results of investment appraisal, or they may fail to monitor
investment projects in order to ensure that expected results are in fact being achieved.
Investment appraisal analysis and forecast the return on the investment and the return is
subject to probable risks and uncertainties, hence it is critical to consider it in the investment
appraisal as an important step to try to ensure a return on the investment.
Sensitivity analysis is a management tool that helps in determining how different values of
an independent variable can affect a particular dependent variable.
Advantages
It compels the decision maker to identify the variables which affect the cashflow
forecasts. This helps him in understanding the investment project in totality.
It indicates the critical variables for which additional information may be obtained.
The decision maker can consider actions which may help in strengthening the "weak
spots" in the project.
It helps to expose inappropriate forecasts and thus guides the decision maker to
concentrate on relevant variables.
Disadvantages
It does not provide clear cut results. The terms optimistic and pessimistic could mean
different things to different people.
It fails to focus on the interrelationship between underlying variables. For example
sales volume may be related to price and cost but we analyse each variable differently.
Discuss the use of sensitivity analysis in decision modeling. Identify some real examples
of sensitivity analysis.
Sensitivity analysis is one of the tools that help decision makers with more than a solution to
a problem. It provides an appropriate insight into the problems associated with the model
under reference. Finally the decision maker gets a decent idea about how sensitive is the
optimum solution chosen by him to any changes in the input values of one or more
parameters.
Uses of Sensitivity Analysis
Risk and uncertainty is part and parcel of every business. Business managers
have to make their decisions considering and analyzing the risk and uncertainty
to
have a very good understanding of the risk management methods, process, tools and
techniques.
Briefly explain you understanding regarding the enterprise risk management (ERM)
framework.
management and other personnel, applied in strategy setting and across the enterprise,
designed to identify potential events that may affect the entity, and manage risk to be
within its risk appetite, to provide reasonable assurance regarding the achievement of
entity objectives It is important to establish an ERM Framework because it enables a firm
to gain a clear view of its overall risk level.
Following steps are need to be taken to establish an ERM Framework, the potential benefits
that can be expected, and the challenges that may be faced.
(a) Setting common language around risk
(b) Establishing risk management steering committee
(c) Defining roles and responsibilities of the committee
(d) Risk identification
(e) Risk prioritization
(f) Risk monitoring and reporting
In a recent senior management meeting, it has been discussed which one is the best
method to be considered when evaluating a capital expenditure projects and based on
which, the investment decision can be made reliably and precisely. As an expert on the
subject matter you are asked to state the reasons why the net present value investment
appraisal method is preferred to other investment appraisal methods?
The net present value investment appraisal method is preferred to other investment
appraisal methods for the following reasons:
NPV uses cash flows. Cash flows from a project can be used for a number of corporate
purposes (e.g. dividends, other capital-budgeting projects, interest payments). By
contrast, other forms of inflow such as earnings with ARR are an artificial construct.
NPV uses all cash flows. Many other capital budgeting techniques including PB ignore
cash flows beyond a particular date.
NPV discounts the cash flows properly. We know the time value of money is a
pervasive factor in human behavior. Other approaches incl. PB and ARR may ignore
this aspect.
NPV relates projects to improvements in shareholder wealth. All projects are
evaluated on the basis that they increase shareholders wealth, rather than some mere
NPV is better than IRR, the next-best alternative. IRR also does most of these as is
closely related to NPV, but can rank inconsistently depending on the scale, timing and
signs of cash flows with mutually exclusive projects. IRR also has an unrealistic
reinvestment rate assumption for interim cash flows.
When management rejects projects with positive NPV because of capital constraints,
they lose opportunities to enhance the value of shareholders.
Suggest three practical ways of dealing with capital rationing so as not to discard
projects with positive NPV.
Practical ways of dealing with capital constraints so as not to lose opportunities to further
increase the value of the company further include the following:
Seek joint venture partners with which to share projects investment requirement
Use licensing or franchising arrangement with other entities to get the product produced
and sold. The firm will earn royalties while avoiding financing of the investment
requirements.
Contract out parts of the project to subcontractors who would finance the project in
advance.
Seek alternative financing such as venture capital and asset securitization.
Seek grants or aid from government or organizations if the project advances an object
the government or such organizations promote or seek to achieve.
In Standard Costing the comparison is made between actual cost and standard cost of
actual output.
On the other hand, in Budgetary Control the comparison is made between the actual and
budgeted performance.
Standard costs do not change due to short-term changes in the conditions, but budgeted
costs may change.
Materiality. The size of the variance may indicate the scale of the problem and the
potential benefits arising from its correction.
Possible interdependencies of variances. Sometimes a variance in one area is related to
a variance in another. For example, a favourable raw material price variance resulting
from the purchase of a lower grade of material, may cause an adverse labour efficiency
variance because the lower grade material is harder to work with.
These two variances would need to be considered jointly before making an investigation
decision.
The inherent variability of the cost or revenue. Some costs, by nature, are quite
volatile (oil prices, for example) and variances would therefore not be surprising. Other
costs, such as labour rates, are far more stable and even a small variance may indicate a
problem.
Adverse or favorable? Adverse variances tend to attract most attention as they indicate
problems. However, there is an argument for the investigation of favourable variances so
that a business can learn from its successes
Trends in variances. One adverse variance may be caused by a random event. A series
of adverse variances usually indicates that a process is out of control.
Controllability/probability of correction.
control (such as the world market price of a raw material) then there is little point in
investigating its cause.
Costs and benefits of correction. If the cost of correcting the problem is likely to be
higher than the benefit, then there is little point in investigating further.
Suggest possible reasons for the following variances:
(i) raw materials total cost variance;
(ii) fixed overhead efficiency variance;
(iii) fixed overhead expenditure variance.
Budgetary control is one of the important tools used by management, yet most
organizations are unable to derive its full benefits.
Identify and explain FOUR reasons that may account for unsuccessful implementation
of a budgetary control system.
Reasons that may account for unsuccessful implementation of Budgetary control system
Lack of clear organizational objectives
Unclear definition of responsibilities
Lack of top management support
Lack of involvement by staff
Poor monitoring and feedback system
Too much exercise of discretional powers by top management.
Lack of understanding of the entire concept and process
Zero-based budgeting (ZBB) is a method of budgeting in which all expenses must be
justified for each new period. The process of zero-based budgeting starts from a "zero base,"
and every function within an organization is analyzed for its needs and costs.
The major advantages of zero-based budgeting (ZBB) are flexible budgets, focused
operations, lower costs, and more disciplined execution. The disadvantages include the
possibilities of resource intensiveness, being manipulated by savvy managers and bias toward
short-term planning.
The objective of a cash budget is to ensure that sufficient cash is available to meet the level
of operations in the various functional and capital budgets. Cash deficits can be identified in
advance and steps taken to ensure that sources of finance will be available to cover any
deficits. Cash budgets can also help a company to avoid cash surpluses by enabling
management to take actions in advance to invest the surplus cash in short-term or long-term
investments as appropriate. The overall aim should be to manage the cash of the company to
ensure that cash is available when required and that the maximum benefit is gained from the
use of any idle funds.
State THREE ways, other than borrowing, of improving the cash flow position of a
business.
The question asks for three methods. Examples that would be rewarded are given below:
e.g. leasing rather than
purchasing outright.
-term investments.
-essential capital expenditure.
-current assets that are no longer required.
.
The participation of managers in the budget setting process has several advantages.
Managers are more likely to be motivated to achieve the budget if they have participated in
the budget setting process. Participation can also reduce the information asymmetry gap that
can arise when targets are imposed by senior management and should result in more realistic
budgets. Imposed budgets are likely to make managers feel demotivated and alienated and
result in poor performance.
Participation however can cause problems; in particular, managers may attempt to negotiate
budget reflects their importance within the organisation. This can result in budgets that are
unsuitable for control purposes. Manager participation is only effective if it is true
participation.
Pseudo participation can be worse for motivation than no involvement at all. The
involvement of managers in the budget setting process is time consuming and the benefits of
participation would need to weighed against the cost of the resources used.
One of the main purposes of budgeting is to act as a control mechanism, with actual results
being compared against budget. Another purpose of a budget is to set targets to motivate
managers and optimise their performance. The participation of managers in the budget
setting process has several advantages. Managers are more likely to be motivated to achieve
the target if they have participated in setting the target. Participation can reduce the
information asymmetry gap that can arise when targets are imposed by senior management.
Imposed targets are likely to make managers feel demotivated and alienated and result in
poor performance. Participation however can cause problems; in particular, managers may
believe that the size of their budget reflects their importance within the organisation. This can
result in budgets that are unsuitable for control purposes.
- Hospital are in the process of preparing the annual
budget for the next financial year using incremental budgeting. The s
directors are concerned that the approach used will result in a budget that does not
reflect the aims and objectives of the hospital. They have requested that the budget
should be produced using zero based budgeting.
Instruction:
Explain the pot - s managers may face when
setting budgets using zero based budgeting.
The hospital has previously used an incremental budgeting system and therefore the potential
difficulties with setting a budget using a zero based budgeting system are as follows:
Zero based budgeting is extremely time consuming; the work involved in the creation of
decision packages and their ranking is considerable. The hospital may not have the resources
available to enable a full zero based budget to be prepared within the timescale required. It
may also require skills that the current management of the hospital do not possess as they
are inexperienced in this type of budgeting. As this is the first time a zero based budgeting
approach has been used it will mean that all activities carried out by the hospital will need to
be reviewed and justified.
There may be difficulty in identifying the activities undertaken by the hospital particularly if
the organisation structure is based on traditional functional departments. This may result in a
tendency to try to cut costs rather than identifying the main drivers behind costs.
The ranking process can be very difficult as value judgements are required. Widely different
activities cannot be compared on quantitative measurement alone.
Value inventory the cost per unit can be used to value inventory in the statement of
financial position (balance sheet).
Record costs the costs associated with the product need to be recorded in the income
statement.
Price products the business will use the cost per unit to assist in pricing the product.
For example, if the cost per unit is $0.30, the business may decide to price the product at
$0.50 per unit in order to make the required profit of $0.20 per unit.
Make decisions the business will use the cost information to make important decisions
regarding which products should be made and in what quantities.
The three major elements of product costs in a manufacturing company are direct materials,
direct labor, and manufacturing overhead.
Cost equations are derived from historical cost data. Once a cost equation has been
established (using methods such as the high/low method which will be revised later in the
course) it can be used to estimate future costs. In the exam, cost functions will be linear:
y = a + bx
variable)
The cost of equipment used in manufacturing is initially reported as the long lived asset
Equipment. However, in each accounting period the company will report part of the
asset's cost as Depreciation Expense.
A retailer's purchase of merchandise is initially reported as the current asset Inventory.
When the merchandise is sold, the cost of the merchandise sold is removed
from Inventory and is reported on the income statement as the expense entitled Cost of
Goods Sold.
No. A variable cost is a cost that varies, in total, in direct proportion to changes in the
level of activity. A variable cost is constant per unit of product. A fixed cost is fixed
in total, but will vary inversely on an average per-unit basis with changes in the level
of activity.
No; differential costs can be either variable or fixed. For example, the alternatives
might consist of purchasing one machine rather than another to make a product. The
difference in the fixed costs of purchasing the two machines would be a differential
cost. Cost of Goods Sold is an expense on the income statement.
Variable cost: The variable cost per unit is constant, but total variable cost changes in
direct proportion to changes in volume.
Fixed cost: The total fixed cost is constant within the relevant range. The average fixed
cost per unit varies inversely with changes in volume.
Mixed cost: A mixed cost contains both variable and fixed cost element
Cost behavior: Cost behavior refers to the way in which costs change in response to
changes in a measure of activity such as sales volume, production volume, or orders
processed
Relevant range: The relevant range is the range of activity within which assumptions
about variable and fixed cost behavior are valid.
Step cost: A step cost is a cost that does not change steadily with changes in activity
volume, but rather at discrete points. The concept is used when making investment
decisions and deciding whether to accept additional customer orders. A step cost is a
fixed cost within certain boundaries, outside of which it will change.
Prime cost: Prime cost is the combination of a manufactured product's costs of direct
materials and direct labor. In other words, prime cost refers to the direct production costs.
Indirect manufacturing costs are not part of prime cost.
Since product costs accompany units of product into inventory, they are sometimes
called inventoriable costs. The flow is from direct materials, direct labor, and
manufacturing overhead to Work in Process. As goods are completed, their cost is
removed from Work in Process and transferred to Finished Goods. As goods are sold,
their cost is removed from Finished Goods and transferred to Cost of Goods Sold.
If fixed cost changes then break-even point also changes. If fixed cost increases then the break-
even point also increases and vise-versa. In this case Company B will do better in a price
competition scenario since its total fixed cost is lower than Company A.
Yes, a cost object is anything for which a company wants to assign costs. For example,
this can be a product, service, project, customer, or activity.
Fixed costs do not change within the relevant range of production. As long as the
production volume remains within the relevant range, the total amount of fixed costs does
not change with a change in production volume.
The fixed cost per unit decreases as increases and increases as production decreases. The
fixed cost is related with the usage of capacity.
Whereas The per unit variable cost remains unchanged as production increases or decreases
while total variable cost increases as production increases and decreases as production decreases.
For example:
Suppose,
Variable per unit is Tk.3
Fixed cost Tk.200 for 50 units.
If we produce 25 units then,
Variable cost is cost per unit is Tk.3
Fixed cost per unit is = (200/25 )= Tk.8
Again,
If we produce 40 units then,
Variable cost is cost per unit is Tk.3
Fixed cost per unit is = (200/40 )= Tk.5.
So, variable cost per unit is fixed but fixed cost per unit is variable (Tk.8 for 25 units, Tk.5 for 40
units).
Per unit fixed cost is not fixed, it is variable. Production output and fixed costs typically
remain the same for a relevant range of output and then it is changes. Therefore, a
company may undertake worse decision by using unit fixed cost. For example, a company
can produce between 1,000 and 2,000 widgets without experiencing an increase in fixed
costs. This allows for multiple production output estimates as fixed costs are easy to
calculate for any output between 1,000 and 2,000 units. A disadvantage, however, is the
increase in per-unit fixed costs when a company operates at the lower range of its
production output.
If all other things remain same, Company B with its higher fixed costs and lower variable
costs will have a higher contribution margin ratio. Therefore, it will tend to realize the
most rapid increase in contribution margin and in profits when sales increase.
In general, labor cost is defined as wages paid to workers during an accounting period on
daily, weekly, monthly.
In theory, labor cost is considered as variable cost because it varies directly with the
production volume. But when the labor cost is paid as daily, weekly or monthly basis
ignoring production volume, it becomes fixed.
In Bangladesh, the industrial growth has been observed in the area of jute, readymade
garments, pharmaceuticals and some agro based sectors. In these industries, labor costs are
paid directly as periodical payment basis rather than relating it with the production
volume. This practice gradually spreads on other industries and thus labor cost becomes a
fixed cost for Bangladeshi industries.
In order to ensure the successful application of Job Costing method, it is essential to consider the
following pre-requisites :
(1) A sound production planning and controlling system.
(2) An appropriate time booking and time keeping system to avoid idle time.
(3) Maintenance of necessary records with regard to job tickets, work order, operation tickets, bills
of materials and tools requirements etc.
(4) Appropriate methods of overhead apportionment and absorption rate.
(5) Effective designing and scheduling of production.
Process Costing is a method of costing. It is employed where each similar units of
production involved in different series of process from conversion of raw materials into finished
output.
The application of process costing where industries adopting costing procedure for continuous or
mass production. Textiles, chemical works, cement industries, food processing industries etc.
In Batch Costing, a lot of similar units which comprise the batch may be used as a
cost unit for ascertainment of cost. Separate Cost Sheet is maintained for each batch by assigning a
batch number. Cost per unit of product is determined by dividing the total cost of a batch by the
number of units of that batch.
Batch costing is used in number drug industries, ready made garment industries, electronic
components manufacture, TV sets, radio etc.
The cost of normal process loss in practice is absorbed by good units
produced under the process. This is known as Normal Process Loss or Normal Wastage. For
exaJll1'le, evaporation, scrap, stamping process etc. The amount realized by the sale of normal
process loss units should be credited to process account.
: The cost of an abnormal process loss unit is equal to the cost of good unit. .
The total cost of abnormal process loss is credited to process account from which it arises. This is
known as Abnormal Process Loss. Such loss may be caused by breakdown of machinery, false
production planning, lack of effective supervision, substandard materials etc., Cost of abnormal
process loss is not treated as cost of the product. In fact, the total cost of abnormal process loss is
debited to Costing Profit and Loss Account.
Abnormal Process Gain may be defined as unexpected gain in production
under normal conditions. The process account under which abnormal gain arises is debited with
abnormal gain. The cost of abnormal gain is computed on the basis of normal production.
Predetermined overhead rates are the rates used to apply manufacturing overhead to
work-in-process inventory.
Predetermined overhead rates are the rates used to charge overhead cost to jobs in
production.
Selection of right base is important to have right predetermined overhead rates because
predetermined overhead rates are used to charge overhead cost and applied as the basis of
determining the cost of a product. Since, the predetermined overhead rates are used for
costing inventories and play an important role in establishing product cost, an accurate
predetermined overhead rate should be measured. The accuracy of predetermined
overhead rate largely depends on
:
The difference between actual and normal costing systems involves the procedure for
applying manufacturing overhead to work in process inventory.
Under actual costing, applied overhead is based on the actual overhead rate
(calculated at the end of period) multiplied by the actual amount of the cost driver
used.
Under normal costing, applied overhead is based on the predetermined overhead rate
(calculated at the beginning of period) multiplied by the actual amount of the cost
driver used.
: The primary benefit of using a
predetermined overhead rate instead of an actual overhead rate is to provide timely
information for decision making, planning and control. Also the predetermined rate
removes fluctuations inherent in monthly actual overhead rates.
: It is something which is assigned a separate measure of cost because
management need such cost information. For example, responsibility centers, products,
projects and so on.
: It is a collection of costs that are to be assigned to cost objects. Costs are often
pooled because they have the same cost driver. An example of cost pool is all costs related
to material handling in a manufacturing firm.
: It is some factor or variable that is used to allocate costs in a cost pool
to cost objects. An example of a cost allocation base may be the weight of materials handled
for each production department that uses material handling services.
:
The difference between cost allocation bases and cost drivers is that cost drivers are
allocation bases but not all allocation bases are cost drivers. Ideally allocation bases
should be cost drivers; that is, there should be a cause and effect relationship between the
costs in the cost pool and the allocation base. In practice, some allocation bases do not have
this relationship or the relationship is imperfect. Under these circumstances, the accuracy of
cost allocations can be questioned.
The basic difference between absorption and variable costing is due to the
handling of fixed manufacturing overhead.
Under absorption costing, fixed manufacturing overhead is treated as a product
cost and hence is an asset until products are sold.
Under variable costing, fixed manufacturing overhead is treated as a period cost
and is charged in full against the current period s income.
:
It includes an element of fixed overheads in inventory values, in accordance with IAS 2
Analysing under/over absorption of overheads is a useful exercise in controlling costs
of an organisation.
In small organisations, absorbing overheads into the cost of products is the best way of
estimating job costs and profits on jobs.
s
volumes.
income statement).
ision-making process.
If production and sales are equal, net operating income should be the same under
absorption and variable costing. When production equals sales, inventories do not
increase or decrease and therefore under absorption costing fixed manufacturing
overhead cost cannot be deferred in inventory or released from inventory.
If production exceeds sales, absorption costing will usually show higher net operating
income than variable costing. When production exceeds sales, inventories increase and
therefore under to the next period. In contrast, all of the fixed manufacturing overhead
cost of the current period will be charged immediately against income as a period cost
under variable costing.
Absorption costing part of the fixed manufacturing overhead cost of the current period
will be deferred in inventory
Under absorption costing, fixed manufacturing overhead costs are included in product
costs, along with direct materials, direct labor, and variable manufacturing overhead. If
some of the units are not sold by the end of the period, then they are carried into the
next period as inventory.
The fixed manufacturing overhead cost attached to the units in ending inventory follow
the units into the next period as part of their inventory cost. When the units carried over
as inventory are finally sold, the fixed manufacturing overhead cost that has been carried
over with the units is included as part of that period s cost of goods sold.
The break-even point is the level of sales at which profits are zero. It can also be defined
as the point where total revenue equals total cost, and as the point where contribution
margin total equals total fixed cost.
A Break-even chart lets the businesses to determine what they need to sell, monthly or
annually, to cover the costs of doing business-- its break-even point.
The Break-even chart determines a break-even point based on fixed costs, variable costs per
unit of sales and revenue per unit of sales.
(i) The break-even point will increase when the variable expenses increase without a
corresponding increase in the selling prices.
(ii) The break-even point will also increase when the amount of fixed costs and expenses
increases.
: See above.
Selling price is constant. The price of a product or service will not change as
volume changes.
Costs are linear and can be accurately divided into variable and fixed elements. The
variable element is constant per unit, and the fixed element is constant in total over
the relevant range.
In multi-product companies, the sales mix is constant.
In manufacturing companies, inventories do not change. The number of units
produced equals the number of units sold.
Segregation of total costs into its fixed and variable components is difficult to do.
Fixed costs are unlikely to stay constant as output increases beyond a certain range
of activity.
The analysis is restricted to the relevant range specified and beyond that the results
can be unreliable
Besides volume, other elements like inflation, efficiency, capacity and technology
can affect costs
Impractical to assume sales mix remain constant since this depend on the changing
demand levels.
The assumption of linear property of total cost and total revenue relies on the
assumption that unit variable cost and selling price are constant. However, this is
likely to be valid within relevant range only
The margin of safety is the excess of budgeted (or, actual) sales over the break-even
volume of sales. The formula for its calculation is:
Margin of safety = Total budgeted (or, actual) sales Break even sales
For example, a company truck carrying some goods from city A to city B, is loaded with one more ton of
goods. The relevant cost is the cost of loading and unloading the additional cargo, and not the cost of the
fuel, driver salary, etc. It is due to the fact that the truck was going to the city B anyhow, and the
expenditure was already committed on fuel, drive salary, etc. It was a sunk cost even before the decision
of sending additional cargo.
Relevant costs are also referred to as differential costs. They differ among different alternatives. They are
expected future costs and relevant to decision making.
Future Cash Flows Cash expense, which will be incurred in future because of a decision, is a relevant
cost.
Avoidable Costs Only the costs, which can be avoided if a particular decision is not implemented, are
relevant for decision making.
Opportunity Costs Cash inflows, which would have to be sacrificed as a result of a decision, are relevant
costs.
Incremental Costs Only the incremental or differential costs related to the different alternatives, are
relevant costs.
Irrelevant Cost: Irrelevant costs are costs which are independent of the various decisions or alternatives.
They are not considered in making a decision. Irrelevant costs may be classified into two categories viz.
sunk costs and costs which are same for different alternatives.
Sunk cost is a cost which is already incurred. It cannot be changed by any current or future action. For
example if a new machine is purchased to replace an old machine; the cost of old machine would be sunk
cost. Irrelevant costs are fixed costs, sunk costs, book values, etc.
Sunk Cost Sunk costs refer to the expenditures which have already been incurred. Sunk costs are
irrelevant, as they do not affect the future cash flows.
Committed Costs Future costs, which cannot be altered, are not relevant as they will have to be incurred
irrespective of the decision made.
Non-cash expenses Non-cash expenses like depreciation are not relevant as they do not affect the cash
flows of a firm.
Overheads General and administrative overheads, that are not affected by the alternative decisions, are
not relevant.
Avoidable costs are expenses that can be avoided if a decision is made to alter the course of a
project or business..
For example, a manufacturer with many product lines can drop one of the lines, thereby
eliminating associated expenses such as labor and materials.
Corporations looking for methods to reduce or eliminate expenses often analyze avoidable costs
associated with underperforming or non-profitable product lines
A relevant cost is a cost that differs in total between the alternatives in a decision.
An incremental cost (or benefit) is the change in cost (or benefit) that will result from some
proposed action.
An opportunity cost is the benefit that is lost or sacrificed when rejecting some course of action.
A sunk cost is a cost that has already been incurred and that cannot be changed by any future
decision.
No. Not all fixed costs are sunk only those for which the cost has already been irrevocably incurred.
A variable cost can be a sunk cost, if it has already been incurred.
No. Variable costs are relevant costs only if they differ in total between the alternatives under
consideration.
No. A variable cost is a cost that varies in total amount in direct proportion to changes in the level of
activity. A differential cost is the difference in cost between two alternatives. If the level of activity is
the same for the two alternatives, a variable cost will not be affected and it will be irrelevant.
No. Only those future costs that differ between the alternatives under consideration are relevant
Normally, cost written-off as depreciation is irrelevant when it is related to a past cost. But
cost of new equipment that will be acquired in future and will then be written-off as
depreciation is often relevant.
Throughput accounting
because the concept of throughput has
similarities to the concept of contribution. However there is a major difference in the definition of
contribution in two systems or, more specifically, in what is described as a variable cost. The
traditional marginal costing approach assumes that direct labor is a variable cost. In the short term,
throughput accounting treats labor as a fixed cost. Furthermore, throughput accounting uses the total
of direct materials purchase in the period in the calculation of throughput rather than the cost of
material actually used, as in the case with marginal costing.
The only totally variable cost is the purchase cost of raw material and components that are bought
from external suppliers.
A bottleneck may be a machine whose capacity limits the output of the whole production process. The
aim is to identify the bottlenecks and remove them, or, if this is not possible, ensure that they are fully
utilized at all times.
that constraint is the fastest and most effective path to improved profitability.
The Theory of Constraints is a methodology for identifying the most important limiting factor (i.e.
constraint) that stands in the way of achieving a goal and then systematically improving that
constraint until it is no longer the limiting factor. In manufacturing, the constraint is often referred to
as a bottleneck.
The Theory of Constraints takes a scientific approach to improvement. It hypothesizes that every
complex system, including manufacturing processes, consists of multiple linked activities, one of
1.
2. Decide how to exploit the bottlenecks
3. Subordinate everything else to the decision in Step 2
4.
5. If, in the previous steps, a bottleneck has been broken, go beck to Step 1.
Fast improvement (a result of focusing all attention on one critical area the system constraint)
Reduced lead times (optimizing the constraint results in smoother and faster product flow)
is an activity that consumes resources and for which overhead costs are identified and
allocated. For each cost pool, there should be a cost driver.
Pricing: Pricing decision will be improved because the price will be based on more accurate data.
Decision making: This should also be improved. For example, research, production and sales
effort can be directed towards the most profitable products.
Performance management should be improved. The more realistic overhead should result in
more accurate budgets and should improve the process of performance management.
Sales strategy: This should be more soundly based. For example, target customers with products
that appeared unprofitable under absorption costing but are actually profitable, and vice versa.
In these situations, ABC will often result in significantly different product or service overhead costs,
compared with traditional absorption costing.
Advantages:
It provides a more accurate cost per unit. As a result, pricing, sales strategy, performance
management and decision making should be improved.
It provides much better cost understanding.
Fairer allocation of costs.
Better cost control.
Can be used in complex situations.
ABC can be used in service industries easily.
Disadvantages:
Not always relevant. ABC will be of limited benefit of the overhead is a small proportion of the
overall cost.
Still need arbitrary cost allocation.
Need to choose appropriate drivers and activities
ABC can be more complex to explain to the stakeholder of the costing exercise.
Expensive to operate.
This should enable management to control such costs more easily, the variances reported will be more
meaningful and this will help management to control costs. The cost drivers identified under an ABC
system provide information to management to enable them to take actions to improve the overall
profitability of the company. Cost driver analysis will provide information to management on how
cost can be controlled and managed.
This can also be seen as the tradeoff between cash flow versus profits.
Working capital is the capital available for conducting the day to day operations of an
over current liabilities.
Working capital management is the management of all aspects of both current assets and
current liabilities, to minimise the risk of insolvency while maximising the return on assets.
Overtrading happens when a business expands too quickly without having the
financial resources to support such a quick expansion. If suitable sources of finance are not
obtained, overtrading can lead to business failure.
High revenue growth but low gross and operating profit margins
Persistent use of a bank overdraft facility
Significant increases in the payables days and receivables days ratios
Significant increase in the current ratio
Very low inventory turnover ratio
Low levels of capacity utilisation
Managing the Risk of Overtrading The most effective steps to avoid overtrading are essentially
those that would be taken as part of a sensible cash flow and working capital management. For example:
is a detailed plan outlining the acquisition and use of financial and other resources
over a given time period. As such, it represents a plan for the future expressed in formal
quantitative terms.
involves the use of budgets to control the actual activities of a firm.
Planning : A budgeting process forces a business to look to the future. This is essential
for survival since it stops management from relying on ad hoc or poorly co-ordinated
planning.
Control : Actual results are compared against the budget and action is taken as
appropriate.
Communication: The budget is a formal communication channel that allows junior and
senior managers to converse.
Co-ordination : The budget allows co-ordination of all parts of the business towards a
common corporate goal.
Evaluation : The budget may be used to evaluate the actions of a manager within the
business in terms of the costs and revenues over which they have control.
Motivation : The budget may be used as a target for managers to aim for. Reward should
be given for operating within or under budgeted levels of expenditure. This acts as a
motivator for managers.
Authorisation: The budget acts as a formal method of authorisation to a manager for
expenditure, hiring staff and the pursuit of plans contained within the budget.
Delegation : Managers may be involved in setting the budget. Extra responsibility
may motivate the managers. Management involvement may also result in more realistic
targets.
Budgets provide a
organization.
Budgets force managers to think about and plan for the future.
The budgeting process provides a means of allocating resources to those parts of the
organization where they can be used most effectively.
The budgeting process can uncover potential bottlenecks before they occur.
Budgets coordinate the activities of the entire organization. Budgeting helps to ensure that
everyone in the organization is pulling in the same direction.
Budgets define goals and objectives that can serve as benchmarks for evaluating subsequent
performance.
#Approaches to budgeting
There are a number of different budgetary systems:
-based budgeting
-forward control
##Imposed style : An imposed/top-down budget is 'a budget allowance which is set without
permitting the ultimate budget holder to have the opportunity to participate in the budgeting
process'
Advantages of imposed style
There are a number of reasons why it might be preferable for managers not to be involved in
setting their own budgets:
(1) Involving managers in the setting of budgets is more time consuming than if senior managers
simply imposed the budgets.
(2) Managers may not have the skills or motivation to participate usefully in the budgeting
process.
(3) Senior managers have the better overall view of the company and its resources and may be
better-placed to create a budget which utilizes those scarce resources to best effect.
(4) Senior managers also are aware of the longer term strategic objectives of the organisation and
can prepare a budget which is in line with that strategy.
##Participative budgets : Participative/bottom up budgeting is 'A budgeting system in which all
budget holders are given the opportunity to participate in setting their own budgets'
Advantages of participative budgets
(1) The morale of the management is improved. Managers feel like their opinion is listened to,
that their opinion is valuable.
(2) Managers are more likely to accept the plans contained within the budget and strive to
achieve the targets if they had some say in setting the budget, rather than if the budget was
imposed upon them. Failure to achieve the target that they themselves set is seen as a personal
failure as well as an organisational failure.
(3) The lower level managers will have a more detailed knowledge of their particular part of the
business than senior managers and thus will be able to produce more realistic budgets
##Incremental budgets :
actual results and adds (or subtracts) an incremental amount to cover inflation and other known
changes.
It is suitable for stable businesses, where costs are not expected to change significantly. There
should be good cost control and limited discretionary costs.
##Zero-based budgeting
activities to which the budget relates were being undertaken for the first time. Without approval,
It is suitable for:
(1) Inefficient or obsolete operations can be (1) It emphasises short-term benefits to the
identified and discontinued detriment of long term goals
(2) ZBB leads to increased staff involvement at all (2) The budgeting process may become too rigid
levels since a lot more information and work is and the organisation may not be able to react to
required to complete the budget unforeseen opportunities or threats
(3) It responds to changes in the business (3) The management skills required may not be
environment present
(4) Knowledge and understanding of the cost (4) Managers may feel demotivated due to the
behaviour patterns of the organisation will be large amount of time spent on the budgeting
enhanced process
##Rolling budgets
A budget (usually annual) kept continuously up to date by adding another accounting period (e.g.
month or quarter) when the earliest accounting period has expired.
Suitable if:
Disadvantages of rolling
Advantages of rolling budgets
budgets
(1) Planning and control will be based on a more (1) Rolling budgets are more costly and time
accurate budget consuming than incremental budgets
(2) Rolling budgets reduce the element of (2) May demotivate employees if they feel that they
uncertainty in budgeting since they spend a large proportion of their time
concentrate on the short-term when the degree budgeting or if they feel that the budgetary targets
of uncertainty is much smaller are constantly changing
operating costs.
sts. If we can control the causes (drivers) of
costs, then costs should be better managed and understood.
the short-term many overhead costs are not controllable and do not
vary directly with changes in the volume of activity for the cost driver. The only cost variances
to report would be fixed overhead expenditure variances for each activity.
outlines the way in which these plans are to be accomplished. The master budget is composed of
a number of smaller, specific budgets encompassing sales, production, raw materials, direct
labor, manufacturing overhead, selling and administrative expenses, and inventories. The master
budget generally also contains a budgeted income statement, budgeted balance sheet, and cash
budget.
##
Do you agree? Explain.
No, although this is clearly one of the purposes of the cash budget. The principal purpose is to
provide information on probable cash needs during the budget period, so that bank loans and
other sources of financing can be anticipated and arranged well in advance.
Chapter 06,07,08 Standard Costing
#Standard costing: A standard cost for a product or service is a predetermined unit cost set
under specified working conditions.
Control: the standard cost can be compared to the actual costs and any differences
investigated.
Planning: standard costing can help with budgeting.
Performance measurement: any differences between the standard and the actual cost can be
used as a basis for assessing the performance of cost centre managers.
Inventory valuation: an alternative to methods such as LIFO and FIFO.
Accounting simplification: there is only one cost, the standard.
The large scale repetition of production allows the average usage of resources to be determined.
Standard costing is less suited to organisations that produce non homogenous products or
where the level of human intervention is high.
#Types of standard
Attainable standards
conditions.
Basic standards
-term standards which remain unchanged over a period of years.
Current standards
meaningless information.
rove upon current
working conditions and, as a result, employees may feel unchallenged.
Ideal standards
short, no inefficiencies.
Risk-There are a number of possible outcomes and the probability of each outcome is known
Risk.
Uncertainty- There are a number of possible outcomes and the probability of each outcome is
not known uncertainty.
RISK UNCERATINTY
1.Risk can be measured 1. IT cannot be measured
2.Controllable 2. Uncontrollable
3.Probablities assigned 3.probanlites not assigned
4.risk is objective 4.uncertainty is subjective
5.risk can be transferred into another risk 5.it cannot be transferred
An expected value summarizes all the different possible outcomes by calculating a single weight
average. it is the long run average (mean).
Advantages Disadvantages
1. Takes risk into account by considering the 1. The probabilities used are usually very
probability of each possible outcome. subjective.
2. The information is reduced to a single number 2. The EV is merely a weighted average
resulting in easier decisions. and therefore has little meaning for a one-
off project.
3.Calculations are relatively simple 3. The EV gives no indication of the
dispersion of possible outcomes about the
EV.
4. The EV may not correspond to any of the
actual possible outcomes.
Maximas- The maximax rule involves selecting the alternative that maximizes the
maximum pay-off achievable.
This approach would be suitable for an optimist who seeks to achieve the best results if
the best happens.
Maximin- The maximin rule involves selecting the alternative that maximises the
minimum pay-off achievable.
This approach would be appropriate for a pessimist who seeks to achieve the best results if
the worst happens.
The minimax regret rule The minimax regret strategy is the one that minimises the
maximum regret. It is useful when probabilities for outcomes are not available or where
the investor is risk averse and wants to avoid making a bad decision.
Pay off tables A pay off table is simply a table that illustrates all possible profits/losses
Perfect information- The forecast of the future outcome is always a correct prediction. if a firm
can obtain a 100% accurate prediction they will always be able to undertake the most beneficial
course of action for that prediction.
Imperfect information- The forecast is usually correct, but can be incorrect. Imperfect
information is not as valuable as perfect information.
A decision trees is diagrammatic representation of a decision problem, where all possible courses
of action are represented, and every possible outcome of each course of action is shown.
Decision trees should be used where a problem involves a series of decision being made and
several outcomes arise during the decision making process.
Time series analysis A time series is a series of figures recorded over time, e.g.
unemployment over the last 5 years, output over the last 12 months etc.
Advantages:-
Forecast are based on clearly understood assumption
Trend lines can be reviewed after each successive time period
Forecasting accuracy can possibly be improved with experience
The reliability of the forecast can be assessed
Disadvantages:-
There is an assumption that what has happened in the past is a reliable guide to the future
There is an, assumption that a straight line trend exists
There is an assumption that seasonal variation are constant
Linear regression To take account of two observations a more advanced calculation is used
known as linear regression which uses a formula to estimate the linear relationship between the
variables as follows: y = a + bx