You are on page 1of 42

Project management

ITIL® 4 Practice Guide


AXELOS.com

1st
May
2020

AXELOS Copyright View Only –


Not for Redistribution © 2020
2 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Contents
1 About this document 3
2 General information 4
3 Value streams and processes 21
4 Organizations and people 29
5 Information and technology 35
6 Partners and suppliers 39
7 Important reminder 40
8 Acknowledgments 41

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 3
for Redistribution © 2020

1 About this document


This document provides practical guidance for the project management practice. It is split into
five main sections, covering:
● general information about the practice
● the practices processes and activities and their role in the service value chain
● the organizations and people involved in the practice
● the information and technology supporting the practice
● considerations for partners and suppliers for the practice.

1.1 ITIL® 4 QUALIFICATION SCHEME


Selected content from this document is examinable as a part of the following syllabus:

● ITIL Leader – Digital and IT Strategy


Please refer to the syllabus document for details.

AXELOS Copyright View Only –


Not for Redistribution © 2020
4 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

2 General information
2.1 PURPOSE AND DESCRIPTION
Key message

The purpose of the project management practice is to ensure that all projects in the organization
are successfully delivered. This is achieved by planning, delegating, monitoring, and maintaining
control of all aspects of a project, and ensuring motivation for the people involved.

ITIL architect’s note


When the architecture of ITIL 4 was designed, it seemed a revolutionary decision to include the
project management practice in the scope of ITIL. The ability to manage projects effectively is
important to every organization, especially if it is good at tailoring various methods to its needs
and environment. Therefore, project management was added. However, as we were working
through details of the practices, we came to a conclusion that this is not enough, as projects
should never be managed in isolation; they should contribute to a greater purpose defined by an
organization and/or a programme. As a result, this practice guide covers project and programme
management; the purpose of the practice can be updated to the following:
The purpose of the programme and project management practice(s) is to ensure that all projects
in the organization are successfully delivered and contribute to creation of value for stakeholders
of the organization and its programmes.
The practice is referred to as PPM (programme and project management) in this guide; in the
sections and paragraphs focused on project management or programme management specifically,
we used specific terms referring to projects or programmes.
We hope that this expansion of the scope will prove to be valuable for the practitioners, and we
plan to reflect it in the next editions of ITIL Foundation and other ITIL publications with references
to project management.
Programme and project management play an integral part in planning and introducing changes to
an organization while optimizing the use of resources, accounting for risks, and linking changes to
achieve the expected value.
A programme may be comprised of projects across different areas of the organization. For
example, the launch of a new product or service may rely on projects running in the sales,
marketing, distribution, and IT departments, all of which are focused on delivering the outcome
required by the programme. A programme can be a standalone programme, but more often it
forms part of a portfolio (see the portfolio management practice guide for more information).
A project is typically focused on delivering a specific output; a programme’s focus is on the
outcomes and benefits of enabling value for the organization and other stakeholders. Programmes
usually last longer than individual projects.
Both programmes and projects are distinguished from ongoing operations (often called ‘business as
usual’) as they:
● introduce significant changes
● are temporary structures
● bring risks and opportunities above and beyond the normality of business as usual.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 5
for Redistribution © 2020

2.2 TERMS AND CONCEPTS


An important element of a profession is a body of knowledge that is distinctive to the professional
group. For the past 50 years, project management associations around the world have made
serious attempts to conduct themselves as professional associations and spent a considerable time
and effort in developing bodies of knowledge (BoKs) and their associated certification
programmes.
A BoK is a resource; providing the concepts, functions, and activities that make up the professional
standards and provides key information to successful delivery of that profession’s core functions.
In this case, the core function is programme and project management.
All project management BoKs describe how projects should be directed, managed, and delivered,
however they all differ in terminology and lifecycle, which is why it is important to understand
which BoK is behind the project that is driving the change. The main project management BoKs are
the APM body of knowledge (APMBoK®), and the PMI body of knowledge (PMBoK®), although there
are others to do with change management (CMBoK) and cybersecurity (CYBoK).
In this practice guide, key terms and definitions are based on AXELOS PPM BoKs and methods,
including:
● PRINCE2®
● PRINCE2 Agile®
● Managing Successful Projects®
● P3O®.

2.2.1 Programme
Definition: Programme

A temporary, flexible structure created to coordinate, direct, and oversee the implementation of a
set of related projects and activities in order to deliver outcomes and benefits related to the
organization’s strategic objectives.

The focus of programmes is to deliver outcomes and benefits rather than outputs or products. A
programme coordinates the projects within its boundaries and is more concerned with stakeholder
engagement, communication, and direction when compared to projects.
The programme endeavours to gradually deliver changes in organizational capabilities through the
related projects that run under its category. A group of projects structured around distinct step
changes in capability and benefit delivery is called a 'tranche'. These gradual changes allow the
organization to realize benefits during the programme rather than waiting for the whole
programme to end.
The typical lifecycle or transformational flow of a programme is described in Managing Successful
Programmes (MSP). This is shown in Figure 2.1.

AXELOS Copyright View Only –


Not for Redistribution © 2020
6 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Figure 2.1 MSP transformational flow

2.2.2 Project
Definition: Project

A temporary structure that is created for the purpose of delivering one or more products according
to an agreed business case.

The focus of projects is to deliver outputs (products or other deliverables) within defined
parameters of time, cost, and quality. By doing so, those outputs are of value to the organization.
These outputs also allow the organization to realize benefits, but, in traditional (waterfall)
projects, those benefits are primarily driven-out after the projects are completed.
The typical lifecycle of a traditional linear (waterfall) project as described in Managing Successful
Projects with PRINCE2® is shown in Figure 2.2.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 7
for Redistribution © 2020

Figure 2.2 PRINCE2 project management processes

An Agile approach works similarly to a programme but in a highly compressed timeframe. The agile
delivery is planned in increments, and it is expected that benefits are generated at the
deployment of each increment. Therefore, the organization receives its benefits as early as
possible.
The typical lifecycle of an Agile project as described in PRINCE2 Agile® is shown in Figure 2.3.

Figure 2.3 PRINCE2 Agile project management processes

2.2.3 Agile
The term ‘agile’ is very broad and is viewed in many different ways within the agile community.
There is a set of well-known frameworks referred to as ‘Agile methods’, and there are also well-
known behaviours, concepts, and techniques that are recognized as characterizing the agile way of
working. However, there is no single definition of agile that accurately encapsulates them all,
although the Agile Manifesto 1, which is shown in Figure 2.4, comes quite close.

1
https://agilemanifesto.org/ [Accessed 30th April 2020]

AXELOS Copyright View Only –


Not for Redistribution © 2020
8 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Figure 2.4 The Agile Manifesto 2001

Agile became so popular because it helped to address the new demands being placed on how
software was delivered. It needed to be produced more frequently while retaining a specified level
of quality to meet the demands of the digital age. (For more on agile software development see
the software development and management practice guide and ITIL® 4: High-velocity IT, section
4.2).

In contrast to the traditional methods of delivery, the Agile phases are shorter, more iterative, and
incremental. There is also a move to achieve early delivery of benefits by deploying products at
the earliest opportunity, as described in Figure 2.5.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 9
for Redistribution © 2020

Figure 2.5 Agile versus waterfall

On the left of figure 2.5, the incremental Agile approach allows for multiple deployments
throughout the project. The waterfall delivery on the right tends to allow for a single delivery at
the end of the project.

2.2.4 Traditional (waterfall)


‘Waterfall’ was the first software development methodology, inherited from the manufacturing
and construction industry where you can or cannot afford to iterate (after you have built a tower
or a bridge you cannot go back to "improve" the foundation). However, because software is prone
to frequent change, waterfall is not always the best solution.
Waterfall is often mentioned alongside Agile, but the two approaches contrast each other. The
main difference between them is that waterfall doesn't react well to frequent changes, which is
why it acquires a bad reputation in the software development community, where frequent changes
are normal.
During the waterfall approach, a project is completed in distinct stages (see Figure 2.5) and moved
step by step towards the ultimate release to the customer, business, or consumer. There is a big
design upfront and then the plan is executed in a linear fashion with the hope of no changes in the
designs.
In the Agile space, there is enough design upfront to get the project moving, with the absolute
knowledge that the design will evolve and that change is inevitable. With the digitization of many
aspects of organizations, Agile methods are being successfully applied to many digital solutions,
not just software development. These include digital marketing, publishing, and other content-
related activities, digital infrastructure, and digital communications. Non-digital projects that are
focused on flexible, evolving resources (organizations, communities, partnerships, knowledge) also
benefit from this Agile approach.

2.2.5 Holistic approach


The project management practice is not limited to managing the progress of projects; it should
contribute to value co-creation and the overall strategy of an organization. In order to achieve
this, the project management approach of the organization should be holistic. PRINCE2 describes

AXELOS Copyright View Only –


Not for Redistribution © 2020
10 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

seven key aspects of project management that should be addressed continually as part of the
practice. They are known as seven PRINCE2 themes, and are outlined in Table 2.1.

Table 2.1 PRINCE2 key themes

Theme Purpose Answers the question

Business case To establish mechanisms to judge whether the project Why?


is (and remains) desirable, viable, and achievable as a
means to support decision-making in its (continued)
investment.

Organization To define and establish the project’s structure of Who?


accountability and responsibilities.

Quality To define and implement the means by which the What?


project will verify that products are fit for purpose.

Plans To facilitate communication and control by defining How?


the means of delivering the products.
How much?

When?

Risk To identify, assess, and control uncertainty and, as a What if?


result, improve the ability of the project to succeed.

Change To identify, assess, and control any potential and What is the impact?
approved changes to the project baselines.

Progress To establish mechanisms to monitor and compare Where are we now?


actual achievements against those planned, provide a
forecast for the project objectives and the project’s Where are we going?
continued viability, and control any unacceptable
deviations. Should we carry on?

2.2.6 Tailoring
An organization usually develops an approach to PPM based on one or more BoKs, methods, and
frameworks. Regardless of the selected sources of best practice, organizations should tailor their
guidance to suit the organization’s specific needs, capabilities, and constraints. Tailoring is an
ongoing activity that is usually done through interval-based and event-based reviews of the PPM
approach (see section 3.2.1).

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 11
for Redistribution © 2020

2.2.7 Directing, managing, and delivering


There are three key levels of control in the PPM practice: direction, management, and delivery. In
programmes and projects, these three layers have ‘air-gaps’ between them in order to allow the
levels of management to exercise control without micro-managing the layer below. These ‘air-
gaps’ are constructed with a controlled connectivity between the layers so that each layer can
work within the parameters laid down by the layer above. This is known as management by
exception, where only exceptions to those parameters are brought to the attention of the upper
layer for a decision. Figure 2.6 shows an example of this approach.

Figure 2.6 Directing, managing projects, and delivering products in an organization

2.2.8 Managing programmes


To manage a programme successfully, it requires:
● leadership
● vision
● focus on value.

2.2.8.1 Leadership
Programmes translate the strategic objectives of the organization into specific purposes and
objectives for individual projects. Leading and directing a programme provides the bridge between
strategic objectives, business operations, and project delivery. Therefore, the key principles for
effective leadership includes:
● the ability to create a compelling vision portraying a beneficial future and communicate it to a
range of stakeholders
● empowered decision-making, giving individuals the autonomy to fulfil their roles effectively
● visible commitment and authority
● relevant skills and experience to provide active management.

2.2.8.2 Vision
A vision is a picture of a better future and is the vital focus and enabler for the acceptance,
motivation, and activity alignment of the large community of stakeholders involved in any
programme. The vision statement encapsulates the vision and is used to communicate a high-level
impression of the desired ‘to-be’ state. A good vision statement:
● is written as a future state: a snapshot of the organization in the future
● can be easily understood by a wide variety of stakeholders
● is written for the broadest groupings of stakeholders as the target audience
● describes a compelling future

AXELOS Copyright View Only –


Not for Redistribution © 2020
12 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

● matches the degree of the transformational change with the boldness of the vision conveyed
● avoids target dates, unless the vision is truly time-dependent
● is sufficiently flexible
● is short and memorable.

2.2.8.3 Focus on value


Value drives many aspects of programme management, which means it is the centre of programme
management; programmes are primarily driven by the need to enable value by delivering benefits.
Definition: Benefit

A measurable improvement resulting from an outcome perceived as an advantage by one or more


stakeholders.

Figure 2.7 illustrates the extent of the impact of benefits management within a programme.

Figure 2.7 The extent of the impact of benefits management within a programme

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 13
for Redistribution © 2020

2.2.9 Directing projects


To direct a project successfully, the duties of a project board include:
● Accountability The project board is accountable to programme or corporate management for
the success or failure of the project within the constraints defined in a project mandate.
● Unified direction This is about teamwork at project board level. While each project board
member has accountability for satisfying the interests of a particular stakeholder category, it is
crucial that a cohesive overall direction for the project is agreed and communicated.
● Effective delegation Project board members must delegate effectively using the PRINCE2
organization structure and controls designed for this purpose. A key feature of the method in
this respect is the implementation of management stages: delegating the day-to-day
management of the project to the project manager on a stage-by-stage basis. The project board
defines the framework for how projects will be executed to ensure consistency across the
enterprise.
● Cross-functional integration The project management team is a temporary, almost always
cross-functional, structure that is set up with specific responsibility for the project. Project
board members must ensure that this is recognized and respected in the functional or line
management organizations and that the project board’s authority is not undermined.
● Commitment of resources Project board members are responsible for committing the resources
necessary for the successful completion of the project. It is an important criterion that,
collectively, they should be able to deliver all the resources required for the success of the
project.
● Effective decision-making The project board makes the key decisions in the project. Decision-
making is the means by which control is exerted, and PRINCE2 provides an optimized framework
for this purpose.
● Support for the project manager The project manager is the focus of the day-to-day
management of the project, which is often a busy and stressful role. The project board can
relieve some of this stress and remove some of the obstacles by demonstrating visible and
sustained support for the project manager.
● Effective communication The project manager must ensure communication is timely and
effective, both within the project and with the key external stakeholders.

2.2.10 Managing projects


Managing projects under an Agile approach requires a slightly different style compared with a
waterfall project method. In traditional projects, the project manager is much more central to the
decision-making process on a day-to-day basis. Whereas in an Agile situation, the team is
empowered to make decisions within set parameters, and the project manager facilitates the
evolution of the products rather than directs the work.
To enable collaboration and self-organization, a project manager should:
● trust the team to deliver and not be as involved
● leave the team to work independently and not stifle their creativity
● trust the people who know best to deliver the right solution
● ensure that the project board understands exactly what ‘empowerment’ means so that the team
will be supported and not overruled
● involve the team in release planning for a truly honest view of what can be released and when
● focus on having a stable team to drive innovation and the right solution
● insist on customer involvement all the way through and that they deliver input when required
● ensure that the team recognises that the customer is fully integrated into the team so that they
deliver the business need.

AXELOS Copyright View Only –


Not for Redistribution © 2020
14 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

To maintain transparency and communication, a project manager should:


● clearly communicate the product vision to the team so that they know what they are building
and why
● deliver something frequently that the customer/user can relate to in order to get fast feedback
● ensure the whole team, including the customer, is involved in the vision to gain maximum
motivation
● ensure the team has a minimum viable product that is truly a ‘minimum’
● ensure the project board and senior stakeholders understand MoSCoW prioritization techniques
so that their expectations can be set early
● engage with and understand the project stakeholders to avoid misunderstandings
● understand and communicate the benefits and any threats to them so that the team does not
fixate on products alone
● ensure the needs of the customer representative are being met and that the evolving solution
meets the business need.

To maintain a healthy and inspiring work environment, a project manager should:


● work with the team managers to ensure the team bonds well
● make sure the team is trained in Scrum and has a good grounding in Agile delivery
● ensure the team knows what type of Agile approach is being used so that it can be tailored
appropriately
● be clear about the delivery process with the stakeholders so as to set their expectations
properly
● collaborate with product owners
● ensure the team is set up to make releases on demand so that the technical infrastructure does
not get the way of release delivery
● ensure the team is co-located as much as possible to promote collaboration and communication
● ensure the team understands the role of the ‘servant leader’ so that they understand the
difference between coaching and direction.

To successfully plan, monitor, and control, a project manager should:


● attend the daily stand-ups to know the status of the project
● focus on removing problems so that there are no blockers for the work
● make sure retrospectives are held frequently to improve delivery
● make sure the team knows ‘what to fix’ versus ‘what to flex’ to maximize the value to the
business
● ensure the project information/reports (team boards) are intelligible to enable progress
tracking
● ensure project level requirements are prioritized as soon as possible to assist in focusing on the
business need
● use product-based planning and link the products to benefits so that the right outputs are
created at the right time with a view to delivering benefits early
● agree the reporting metrics to have confidence that progress is reported correctly
● synchronize sprint teams across the project to keep the interfaces relevant
● ensure the teams are not continually deferring the ‘difficult’ stuff to later sprints to avoid the
integrity of the evolving solution becoming compromised.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 15
for Redistribution © 2020

2.2.11 Delivering products in an Agile environment


The delivery of products in an Agile environment relies on considering two major aspects that are
inextricably linked:
● what to fix and what to flex
● prioritization and timeboxing/sprints.

2.2.11.1 What to fix and what to flex

Figure 2.8 Applying tolerances to a project

Table 2.2 demonstrates PRINCE2 Agile views.


Table 2.2 How PRINCE2 Agile views tolerances for the six aspects of a project

Aspect Tolerance guidance Summary

Time Zero tolerance for all extra time on all levels of plan. Fix

Cost Zero tolerance for all extra cost on all levels of plan. Fix

Risk Zero tolerance for risks above the level that the project board decides Fix & flex
must be escalated. Tolerances may be used for risks that are below
this level.

Scope Not everything the project aims to create is of equal importance, so Fix & flex
they can be prioritized.

AXELOS Copyright View Only –


Not for Redistribution © 2020
16 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Zero tolerance for those products that are essential.

Tolerances may be used for products that are desirable but not
essential.

Quality Not all acceptance criteria and quality criteria are of equal Fix & flex
importance, so they can be prioritized.

Project product description: zero tolerance for the customer’s quality


expectations and acceptance criteria that are essential.

Tolerances may be used for the customer’s quality expectations and


acceptance criteria that are desirable but not essential.

Product descriptions (in general): zero tolerance for the quality


criteria that are essential.

Tolerances may be used for the quality criteria that are desirable but
not essential.

Benefits Zero tolerance for the level that is defined as ‘minimum viability’ in Fix & flex
the business case.

Tolerances may be used above the level that is defined as ‘minimum


viability’ in the business case.

2.2.11.2 Prioritization and timeboxing/sprints


Having decided what to fix and what to flex, the team needs to apply prioritization to those
aspects they are going to flex in order to remain within the set timeframes.
Prioritization may be based on the MoSCoW technique. The rules are quite specific:
● Must have requirements will provide the minimum viable product, which can be guaranteed to
be delivered. This can be achieved by ensuring that no more than 60% of the effort in the
timeframe is allocated to must have requirements.
● Should have requirements are important but not vital. The business may find it difficult if these
are left out. It may necessitate and leave them with a costly workaround.
● Could have requirements are even less important and can be seen as a wish list with far fewer
consequences on the end solution if left out. It is recommended that up to 20% of the effort of
the timeframe be allocated to this category, providing a 20% tolerance for the timeframe.
● Won’t have (this time) requirements are the requirements that the project team has agreed
will not be delivered in this particular timeframe. This does not mean they will never be
delivered as they may be available later in the project in a different category.
With the priorities set, the team may now carry out the detailed planning at the timebox or sprint
planning level, bearing in mind the percentages allocated to the various MoSCoW priorities. The
timebox is a fixed period of time (usually between 2 to 4 weeks) during which a number of
iterations are carried out by the developers with the sole intent of delivering as much as possible
in that period. However, the first care is to deliver the must have requirements followed by the
‘shoulds’ and then the ‘coulds’. If time is running low, the business decides which of the ‘coulds’
will be abandoned first so that the higher priority requirements can be accommodated. This means
that the business must adopt a new mindset regarding what it will and will not receive. However,
as they are complicit in the delivery, nothing will come as a surprise.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 17
for Redistribution © 2020

2.3 SCOPE
The PPM practice draws on the abilities of the managers to plan, monitor, and control all aspects
of a programme or project and motivate all those involved to achieve the objectives on time and
to the specified cost, quality, and performance. This is achieved by:
● defining and continually aligning the project management approach with the stakeholders
● ensuring the project management approach is adopted and embedded in the organization
● directing projects
● managing projects
● continually reviewing the practice for improvements.
There are several activities and areas of responsibility that are not included in the PPM practice,
although they are still closely related to programme and project management. These are listed in
Table 2.3, along with references to the practices in which they can be found. It is important to
remember that ITIL practices are merely collections of tools to use in the context of value
streams; they should be combined as necessary, depending on the situation.
Table 2.3 Activities related to the PPM practice described in other practice guides

Activity Practice guide

Establishing and managing contracts with suppliers Supplier management


and partners participating in projects

Creating and changing resources and products within Service design


projects
Change enablement

Release management

Deployment management

Software development and management

Infrastructure and platform management

Workforce and talent management

Managing and implementing improvements Continual improvement

Managing organizational changes Organizational change management

Managing project risks Risk management

Optimizing project portfolios Portfolio management

2.4 PRACTICE SUCCESS FACTORS


Definition: Practice success factor

A complex functional component of a practice that is required for the practice to fulfil its purpose.

A practice success factor (PSF) is more than a task or activity, as it includes components of all four
dimensions of service management. The nature of the activities and resources of PSFs within a
practice may differ, but together they ensure that the practice is effective.
The PPM practice includes the following PSFs:

AXELOS Copyright View Only –


Not for Redistribution © 2020
18 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

● establishing and maintaining an effective approach to programme and project management


across the organization
● ensuring the successful realization of programmes and projects.

2.4.1 Establishing and maintaining an effective approach to programme


and project management across the organization
Establishing the use of best practice for programmes and projects within the organization is
relatively easy. A champion must select the most appropriate methods that fit the culture and
style of the organization and then attract the investment required for the training, tools, and
techniques that will be required for practitioners to operate the methods successfully.
Maintaining the approaches may become more complex as time passes, the organizational changes
and the drivers for change within the organization adapt to external forces. This can challenge
current approaches if they have not been adjusting. In order for this to happen, the methods and
approaches to programme and project management need to be assessed as part of the general
ongoing assessment of the health of the organization as a whole.
Maturity models, such as P3M3, can be used to assess the currency of the methods, tools and
techniques as well as competence of the project management professionals in an organization, so
that they stay aligned with the developing needs and aspirations of the organization. The reports
from these assessments should be used to correct or adjust any area that appears to fall short of
delivering the service expected of that method.
Any changes to existing standards must be notified to the practice community along with any
education or briefings; this is so that the latest thinking transitions over previous versions are
seamless and the methods grow and evolve naturally.

2.4.2 Ensuring the successful realization of programmes and projects


Project and programme success is predominantly about benefit delivery. A post implementation
review may point out a few failings in the technical delivery that should be addressed before
trying the project a second time. Learning from experience is important, therefore reviews,
embedding lessons, and feedback are essential.
Ensuring consistency in the delivery of programmes and projects requires an observance of the
guidance, as well as the application of project/programme assurance to ensure the guidance is
followed. However, this does not always culminate in a successful delivery if the benefits are not
forthcoming. Therefore, assurance needs to be more holistic in its approach than just checking
against a guide or standard. Projects are also about people: those providing the requirements and
resources, creating the products, and agreeing the investment. These stakeholders need to be
satisfied that the project is delivering to the best of its ability on behalf of others.
There are many reasons why projects might fail, this can include: setting unrealistic expectations,
poor methodology and requirements, inadequate resources, poor project management, and
untrained team members. However, these things can be avoided by adopting effective practices
and project management techniques that will help to establish a clear understanding of
expectations and processes between all the stakeholders.
Generally, there is a simple set of five rules that can help prevent projects failing:
● begin with the end in mind: start with a clear project scope
● build a project plan: visualize everything that needs to be done on a timeline
● do not be so connected to the plan: things can change and so does the plan

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 19
for Redistribution © 2020

● check, update, and monitor: check the timeline for progress, update the timeline with actual
performance, monitor the use of your resources
● keep an eye on the quality: you cannot retrofit quality and poor quality delivers poor benefits.

It is also important to look for signs showing that the project may be in trouble. Some of them
could be:
● team morale starts to decline
● quality of outputs starts to deteriorate
● lack of communication.

In organizations that embrace Agile, the ITIL guiding principles provide a useful extension to the
five rules above:
● focus on value
● start where you are
● progress iteratively with feedback
● collaborate and promote visibility
● think and work holistically
● keep it simple and practical
● optimize and automate.

2.5 KEY METRICS


The effectiveness and performance of the ITIL practices should be assessed within the context of
the value streams to which each practice contributes. As with the performance of any tool, the
practice’s performance can only be assessed within the context of its application. However, tools
can differ greatly in design and quality, and these differences define a tool’s potential or
capability to be effective when used according to its purpose. Further guidance on metrics, key
performance indicators (KPIs), and other techniques that can help with this can be found in the
measurement and reporting practice guide
Key metrics for the PPM practice are mapped to its PSFs. They can be used as KPIs in the context
of value streams to assess the contribution of the practice to the effectiveness and efficiency of
those value streams. Some examples of key metrics are given in Table 2.4.
Table 2.4 Examples of key metrics for the practice success factors

Practice success factors Key metrics

Establishing and maintaining an Stakeholders’ satisfaction with the PPM approach


effective approach to programme
and project management across the Stakeholders’ satisfaction with the benefits provided by
organization programmes and projects

Number and impact of deviations from the agreed approach

Number and impact of project or programme failures because


of the approach’s ineffectiveness

Alignment of the PPM approach with relevant industry


standards and best practices

Ensuring the successful realization of Number and percentage of projects being completed on time
programmes and projects and budget

AXELOS Copyright View Only –


Not for Redistribution © 2020
20 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Percentage of benefits realized from each project and


programme

Stakeholders’ satisfaction with the benefits provided by


programmes and projects

Stakeholders’ satisfaction with the progress and management


of programmes and projects

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 21
for Redistribution © 2020

3 Value streams and processes


3.1 VALUE STREAMS CONTRIBUTION
Like any other ITIL management practice, the PPM practice contributes to multiple value streams.
It is important to remember that a value stream is never formed of a single practice. The PPM
practice combines with other practices to provide high-quality services to consumers. The main
value chain activities to which the practice contributes are:
● design and transition
● obtain/build.
The contribution of the PPM practice to the service value chain is shown in Figure 3.1.

Figure 3.1 Heat map of the contribution of the PPM practice to value chain activities

AXELOS Copyright View Only –


Not for Redistribution © 2020
22 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

3.2 PROCESSES
Each practice may include one or more processes and activities that may be necessary to fulfil the
purpose of that practice.
Definition: Process

A set of interrelated or interacting activities that transform inputs into outputs. A process takes
one or more defined inputs and turns them into outputs. Processes define the sequence of actions
and their dependencies.

The PPM practice activities form five major processes:


● managing the organization’s approach to PPM
● directing projects
● managing projects
● managing product delivery.

3.2.1 Managing the organization’s approach to PPM


This process is focused on defining, agreeing, communicating, and promoting an organization-wide
common approach to programme and project management. It includes the activities listed in Table
3.1 and transforms the inputs into outputs.
Table 3.1 Inputs, activities, and outputs of the managing a common approach to PPM process

Key inputs Activities Key outputs

Organization’s strategy Develop and agree the PPM Updated PPM approach and
approach procedures
Stakeholders’ requirements for
PPM Communicate and embed the PPM knowledge articles,
PPM approach training, and awareness
Budgetary/financial materials
considerations and related Review and adjust the PPM
information approach

Organization’s portfolio approach

Legal requirements,
considerations, and related
information

Organization’s services,
customers, and partners and
suppliers information

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 23
for Redistribution © 2020

Figure 3.2 shows a workflow diagram of the process

Figure 3.2 Workflow of the managing a common approach to PPM process

Table 3.2 provides examples of the process activities.


Table 3.2 Activities of the managing a common approach to PPM process

Activity Example

Develop and agree the The PPM approach defines how the organization delivers change through
PPM approach programmes and projects.

There are various models that can be used to assist an organization in the
delivery of change, and these can be found in the TSO publication Portfolio,
Programme and Project Offices (2013). However, the three main functional
areas that are common to all models is that they provide the following
services:
● decision support
● delivery support
● centre of excellence.

Decision support

This has a focus on supporting management decision-making and may align


with strategy, prioritization, benefits management, dashboard reporting,
management information, and provision of oversight, scrutiny, and
challenge. These are key services at the portfolio level but rely on
supporting information from the programmes and projects.

Delivery support

This functional area focuses on supporting the delivery of change and these

AXELOS Copyright View Only –


Not for Redistribution © 2020
24 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

services may be delivered through a central flexible resource pool of


delivery staff with capacity planning and HR processes. The delivery staff
within the resource pool may be programme or project resources deployed
to support specific programmes or projects as they are launched.
Alternatively, they may be internal programme or project specialists who are
employed at programme or project start-up to ensure a fast-track or
consistent start-up process is being used, or even to assist the programme or
project manager in the development and delivery of the programme or
project.

Centre of excellence

This functional area focuses on the development of standard methods and


processes, developing consistent working practices and ensuring they are
deployed appropriately and well. It may include capability support through
training and coaching, internal consultancy (in tailoring the standards and
guidance), knowledge management, tools support and independent
assurance. The function generally exists within a portfolio office but may
have evolved as a separate independent CoE office.

The approach should be defined and agreed between the stakeholders, and
then defined in more detail in the following workflows and procedures:
● managing programmes
● directing projects
● managing projects
● managing product delivery.

Communicate and The agreed approach and procedures are communicated and discussed with the
embed the PPM PPM stakeholders across the organization. To educate the involved teams and
approach embed the approach and procedures, PMO may choose to run trainings and
knowledge sharing events. Stakeholders may decide the level of formality for
the trainings for different groups. For the people involved in the PPM practice
daily, policies and controls may be created for a formal training as a
prerequisite and periodic awareness trainings.

External communications on the PPM approach and procedures should be


prepared and published in the agreed channels to onboard the third parties
involved in programmes and projects.

Review and adjust the PPM stakeholders monitor and review the adoption, compliance, and
PPM approach effectiveness of the agreed sourcing strategy and procedures. This is done on
event-based (project failure or project-related incidents, conflicts, crises,
complaints, and so on) and interval-based basis. The resulting findings and
initiatives are used as input for continual improvement.

3.2.2 Directing projects


The purpose of the directing projects process is to enable the project board to be accountable for
the project's success by making key decisions and exercising overall control while delegating the
day-to-day management of the project to the project manager. This process includes the activities
listed in Table 3.3 and transforms the inputs into outputs.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 25
for Redistribution © 2020

Table 3.3 Inputs, activities, and outputs of the directing projects process

Key inputs Activities Key outputs


The organization’s PPM approach Authorize initiation Approved project brief, business
case, and stage or exception
Project brief Authorize the project
plan
Project product description Authorize a stage or exception
Lessons learnt
plan
Business case
Risk register
Give ad hoc direction
Stage or exception plan
Approved product descriptions
Authorize project closure
User acceptance documents
Project reports

Figure 3.3 shows a workflow diagram of the process

Figure 3.3 Workflow of the directing projects process

Table 3.4 describes the activities of the process.

Activity Description

Authorize initiation The project board is provided with enough information to conclude that the project
looks viable (or not). They then review and authorize the project manager to carry
out more detailed research, or reject the initiation.

Authorize the The project board now has a full and worthwhile business case, an achievable
project delivery plan, and analysis of the key risks to review. On this information they may or
may not authorize the project manager to start delivering the project.

Authorize a stage orAt pre-determined intervals throughout the project (usually at the end of each
exception plan increment) the project board will need to re-evaluate the validity of the project
based on an updated business case, delivery plan, and risk and issue situation. On
this information they may or may not authorize the project manager to continue
delivering the project.

An exception will require further scrutiny to ensure the remedial actions are likely to
be effective and do not jeopardize the project further.

An exception review may serve as an input into the PPM approach review.

Give ad hoc The project board may review and offer informal guidance or respond to requests for

AXELOS Copyright View Only –


Not for Redistribution © 2020
26 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

direction advice at any time during the project.

Analysis of this escalation may serve as an input into the PPM approach review.

Authorize project The controlled close of a project is as important as the controlled start. There must
closure be a point when the objectives of the original and current versions of the project
initiation documentation and delivery plan are reviewed and assessed to understand
whether the objectives have been met. Lessons learnt should be logged, and the
analysis of the project may serve as an input into the PPM approach review.

3.2.3 Managing projects


The purpose of the managing projects process is to enable the project manager to be responsible
for the day-to-day tasks of running the project on behalf of the project board. This process
includes the activities listed in Table 3.5 and transforms the inputs into outputs.
Table 3.5 Inputs, activities, and outputs of the managing projects process

Key inputs Activities Key outputs

Organization’s project Starting up a project Business case


management approach and
procedures Initiating a project Project brief

Programme plan Controlling a stage Stage plan

Lessons learnt Managing a stage boundary Project team

Project mandate Closing a project Project plan

Project product description Project status reports

Lessons learnt

Risk register
Figure 3.4 shows a workflow diagram of the process.

Figure 3.4 Workflow of the managing projects process

Table 3.6 provides examples of the process activities.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 27
for Redistribution © 2020

Table 3.6 Activities of the managing projects process

Activity Example

Starting up a To ensure that the prerequisites for initiating a project are in place by answering the
project question ‘Do we have a viable and worthwhile project?’

Initiating a project To establish solid foundations for the project, enabling the organization to
understand the work that needs to be done to deliver the project product before
committing to a significant spend.

Controlling a stage To assign work to be done, monitor such work, deal with issues, report progress to
the project board, and take corrective actions to ensure the management stage
remains within tolerance.

Lessons learnt from this activity may serve as an input into the PPM approach review.

Managing a stage To enable the project manager to provide the project board with sufficient
boundary information to be able to review the success of the current stage, approve the next
stage plan, review the updated delivery plan, and confirm the viability of the
business case.

Lessons learnt from this activity may serve as an input into the PPM approach review.

Closing a project To provide a fixed point at which the acceptance of the project product is confirmed
and recognize the objectives have been met.

Lessons learnt from this activity may serve as an input into the PPM approach review.

3.2.4 Managing product delivery


The purpose of the managing product delivery process is to enable the solution development teams
to create an evolving solution in accordance with the business priorities and staying within the
timeframes, costs, and quality stipulated by the business. Table 3.7 includes the activities in the
process and transforms the inputs into outputs.
Table 3.7 Inputs, activities, and outputs of the managing product delivery process

Key inputs Activities Key outputs

Organization’s project Accept a work package Delivered and accepted work


management approach and package
procedures Execute a work package
Lessons learnt
Work packages Deliver a work package
Proposed improvements
Project backlog

User stories

Product description

Figure 3.5 shows a workflow diagram of the process.

AXELOS Copyright View Only –


Not for Redistribution © 2020
28 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Figure 3.5 Workflow of the managing product delivery process

Table 3.8 provides examples of the process activities.

Activity Example

Accept a work Before a work package is allocated to a team, there should be agreement between
package the project manager and team leader as to what is to be delivered.

Execute a work The work is executed and monitored according to the requirements in the work
package package.

The team performs an analysis of the execution, logs the lessons learnt, and proposes
improvements to the process or PPM approach.

Deliver a work Just as the work package was accepted from the project manager, the notification of
package its completion must be returned to the project manager.

The work packages described in the table may take the form of a traditional work package: a set
of information about one or more required products collated by the project manager to pass
responsibility for work or delivery formally to a team manager or team member.
Under an Agile approach, the work packages may take a slightly different form but with the same
desired outcomes. In this case they will be discreet timeboxes or sprints with associated products
to be completed within the timebox or sprint according to the business priorities of those
products.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 29
for Redistribution © 2020

4 Organizations and people


4.1 ROLES, COMPETENCIES, AND RESPONSIBILITIES
The practice guides do not describe the roles of practice owners or managers that should exist for
all practices. They focus instead on specialist roles that are specific to each practice. The
structure and naming of each role may differ from organization to organization, so any roles
defined in ITIL should not be treated as mandatory, or even recommended. Remember, roles are
not job titles. One person can take on multiple roles and one role can be assigned to multiple
people.
Roles are described in the context of processes and activities. Each role is characterized with a
competency profile based on the model shown in Table 4.1.
Table 4.1 Competency codes and profiles

Competency Competency profile (activities and skills)


code

L Leader Decision-making, delegating, overseeing other activities, providing


incentives and motivation, and evaluating outcomes

А Administrator Assigning and prioritizing tasks, record-keeping, ongoing reporting,


and initiating basic improvements

C Coordinator/Communicator Coordinating multiple parties, maintaining


communication between stakeholders, and running awareness campaigns

М Methods and techniques expert Designing and implementing work techniques,


documenting procedures, consulting on processes, work analysis, and continual
improvement

Т Technical expert Providing technical (IT) expertise and conducting expertise-


based assignments

The role accountable for all PPM activities is usually the practice owner. The competency profile
for this role is CLA, though the importance of each of these competencies varies from activity to
activity. Examples of other roles which are responsible for PPM activities are listed in Table 4.2,
together with the associated competency profiles and specific skills.

AXELOS Copyright View Only –


Not for Redistribution © 2020
30 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Table 4.2 Examples of the roles involved in PPM activities

Process activity Responsible roles Competency Specific skills


profile

Managing the organization’s approach to PPM

Develop and agree the PMO head LMTC Good knowledge of the
PPM approach organization, its services,
Portfolio manager market, stakeholders, culture,
nature of the changes, and
Programme manager projects
Project manager Expertise in project
management approaches,
Scrum master methods, and BoKs, both
waterfall and agile
Agile coach
Expertise in building processes,
Business analyst
workflows, and procedures
External consultant
Communication and
coordination

Communicate and PMO head CLM Good understanding of the


embed the PPM organizational culture and
approach and Portfolio manager internal stakeholders
procedures
Programme manager Good knowledge of the agreed
approach and procedures
Project manager
Excellent leadership and
Business analyst communication skills
External consultant

Organizational change
manager

Knowledge manager

HR manager

Review and adjust the PMO head LMC Decision making


PPM approach and
procedures Portfolio manager Good knowledge of the
organization, its services,
Programme manager market, stakeholders, culture,
nature of the changes, and
Project manager projects
Scrum master Expertise in project
management approaches,
Agile coach methods, and BoKs, both
waterfall and agile
Business analyst

External consultant

Directing projects

Authorize initiation PMO head LC Decision making

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 31
for Redistribution © 2020

Authorize the project Portfolio manager Stakeholder management

Authorize a stage or Programme manager Value assessment


exception plan
Project board member Good knowledge of the
Give ad hoc direction organization, its services,
Customer representative market, stakeholders, culture,
Authorize project nature of the changes, and
closure Senior user projects
Product owner

Project sponsor

Managing projects

Starting up a project Project manager MCT Expertise in project


management approaches,
Initiating a project Scrum master methods, and BoKs, both
waterfall and agile
Controlling a stage Agile coach
Communication skills
Managing a stage Project team member
boundary Stakeholder management
Scrum team member
Closing a project Resources management
External consultant
Subject matter knowledge
Project coordinator

Service delivery manager

Business analyst

Managing product delivery

Accept a work Scrum team member TMC Technical knowledge


package
Scrum master Subject matter knowledge
Execute a work
package Agile coach Work package/task assessment

Deliver a work Development team member Resource and time management


package
Product owner Teamwork, communication,
and collaboration skills
Business analyst
Agile methods knowledge

4.1.1 Programme manager


The responsibilities of the programme manager typically include:
● day-to-day management of the programme, including taking the programme forward from
appointment, supervising, and controlling and closing the programme
● being the day-to-day agent on behalf of the programme sponsors, ensuring the successful
delivery of the new capability
● planning and designing the programme and proactively monitoring its overall progress, resolving
issues, and initiating corrective action where appropriate
● developing and implementing the programme’s governance framework
● effectively coordinating the projects and their interdependencies

AXELOS Copyright View Only –


Not for Redistribution © 2020
32 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

● managing and resolving any risks and other issues that may arise
● maintaining the overall integrity and coherence of the programme and developing and
maintaining the programme environment to support each individual project within it
● managing the programme’s budget and monitoring the expenditures and costs against benefits
as the programme progresses
● facilitating the appointment of individuals to the project delivery teams
● ensuring that the delivery of outputs or services from the projects meets programme
requirements in line with the programme blueprint, and is to the appropriate quality, on time,
and within budgets
● facilitating the development of the blueprint with input and approval of the relevant
stakeholders
● managing the blueprint and ensuring that the capabilities delivered are aligned with it
● managing the performance of the programme team
● maximizing the efficient allocation of resources and skills across the projects within the
programme
● managing internal and external suppliers to the programme
● managing communications with stakeholders
● initiating extra activities and other management interventions where gaps in the programme are
identified or issues arise
● reporting on the progress of the programme at regular intervals to the programme sponsors.

The skillset of a programme manager is more focused on decision-making and business


management.

4.1.2 Project manager


The project manager is the single focus for the day-to-day management of a project. This person
has the authority to run the project on behalf of the project board within the constraints laid
down by the project board. The role of the project manager must not be shared.
The skills needed for a project manager are more ‘hard-skills’, oriented to execute some
responsibility or some activity in different areas of knowledge.

The project manager’s professionalism is based on the proficiency in the following competency
areas:
● management control
● benefits management
● financial management
● stakeholder engagement
● risk management
● organizational governance
● resource management.

The project manager is responsible for the work in the managing projects and managing product
delivery process. The project manager also delegates responsibility for the managing product
delivery process to the team manager(s).

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 33
for Redistribution © 2020

As the single focus for the day-to-day management of a project, there are many different aspects
to the project manager role, some of which are shown in Figure 4.1.

Figure 4.1 The facets of the project manager role

4.1.3 Team manager


The team manager’s prime responsibility is to ensure that the products are produced to an
appropriate quality, as defined by the project manager, and adheres to the set timescale and cost
accepted by the project board. The team manager is accountable to, and takes direction from, the
project manager.

4.1.4 Scrum master


The Scrum master serves the product owner in several ways, including:
● ensuring that the goals, scope, and product domain are well understood by everyone on the
Scrum team
● finding techniques for effective product backlog management
● helping the Scrum team understand the need for clear and concise product backlog items
● understanding product planning in an empirical environment
● ensuring the product owner knows how to arrange the product backlog to maximize value
● understanding and practising agility
● facilitating scrum events as requested or needed.

AXELOS Copyright View Only –


Not for Redistribution © 2020
34 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

The Scrum master serves the development team in several ways, including:
● coaching the development team in self-organization and cross-functionality
● helping the development team to create high-value products
● removing impediments to the development team’s progress
● facilitating Scrum events as requested or needed
● coaching the development team in organizational environments in which Scrum is not yet fully
adopted and understood.

The Scrum master serves the organization in several ways, including:


● leading and coaching the organization in its Scrum adoption
● planning Scrum implementations within the organization
● helping employees and stakeholders understand Scrum and practical product development
● causing a change that increases the productivity of the Scrum team
● working with other Scrum masters to increase the effectiveness of the application of Scrum in
the organization.

4.2 ORGANIZATIONAL STRUCTURES AND TEAMS


The structure of project teams may vary from project to project, and depends heavily on the
approach taken for project management.
In PRINCE2, there are nine roles which are defined with specific responsibilities. They relate to
project direction, project management, and project delivery; although in the case of project
delivery, PRINCE2 only refers to the team manager and not the members of the delivery team. The
roles are listed below:
● project board
● executive
● senior user
● senior supplier
● project manager
● team manager
● project assurance
● change authority
● project support.

Please refer to the Managing Successful Projects with PRINCE2® for the detailed description of the
roles.
Agile approaches have a more simplified roles list that usually includes a team member, team
manager (e.g. Scrum master), product owner, and sometimes business analyst. It also does not
have a project manager role.
The structure of the team should be decided for each project based on the organization’s
approach to project management and scale and complexity of the project.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 35
for Redistribution © 2020

5 Information and technology


5.1 INFORMATION EXCHANGE, INPUTS/OUTPUTS
The effectiveness of the PPM practice is based on the quality of the information used. This
information includes, but is not limited to, information about:
● customers, users, and other project stakeholders
● the product of project, user, and customer requirements
● the organization’s approach to change and projects
● the market environment and consumer groups
● services and their architecture and design
● the partners and suppliers used in the project, including contracts on the services they provide
● the organization’s strategy, portfolio, and programmes.
This information may take various forms, depending on the nature of the projects. The key inputs
and outputs of the practice are listed section 3.

5.2 AUTOMATION AND TOOLING


In some cases, the PPM practice can significantly benefit from automation. Where this is possible
and effective, it may involve the solutions outlined in Table 5.1.
Table 5.1 Automation solutions for PPM activities

Process Means of automation Key functionality Impact on


activity the
effectiveness
of the
practice

Managing the organization’s approach to PPM

Develop and Collaboration and Collaboration, information exchange Medium


agree the PPM communication tools
approach Workflow modelling, visualization,
Mind mapping and activities, and responsibilities
brainstorming tools mapping

Workflow modelling and


visualization tools,
communication and
collaboration tools

Communicate Communication and Support of promotion, training, and Medium


and embed collaboration tools, awareness
the PPM presentation tools,
approach portals

Review and Collaboration and Collaboration, information exchange, Medium


adjust the communication tools, report creation and distribution,
PPM approach reporting tools, dashboarding
visualization tools

AXELOS Copyright View Only –


Not for Redistribution © 2020
36 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Process Means of automation Key functionality Impact on


activity the
effectiveness
of the
practice

Directing projects

Authorize Communication and Collaboration and remote work, High


initiation collaboration tools dashboarding

Workflow automation Business process, workflow, and


tools approval automation

Authorize the Communication and Collaboration and remote work, High


project collaboration tools dashboarding

Workflow automation Business process, workflow, and


tools approval automation

Authorize a Communication and Collaboration and remote work High


stage or collaboration tools
exception Business process, workflow, and
plan Workflow automation approval automation
tools
Reports creation and publishing,
Reporting tools dashboarding

Documentation tools Documents depository and archive

Give ad hoc Communication and Collaboration and remote work Low


direction collaboration tools

Authorize Communication and Collaboration and remote work High


project collaboration tools
closure Business process, workflow, and
Workflow automation approval automation
tools
Reports creation and publishing,
Reporting tools dashboarding

Documentation tools Documents depository and archive

Managing projects

Starting up a Communication and Collaboration and remote work High


project collaboration tools
Documents depository and archive
Documentation tools
Business process, workflow, and
Workflow automation approval automation
tools
Reports creation and publishing,

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 37
for Redistribution © 2020

Process Means of automation Key functionality Impact on


activity the
effectiveness
of the
practice
dashboarding
Reporting tools

Initiating a Communication and Collaboration and remote work High


project collaboration tools
Documents depository and archive
Documentation tools
Business process, workflow, and
Workflow automation approval automation
tools
Scope, statement of work, backlog,
Project management tasks assignment, risks, timeframe
tools control

Controlling a Communication and Collaboration and remote work High


stage collaboration tools
Documents depository and archive
Documentation
management tools Business process, workflow, and
approval automation
Workflow automation
tools Reports creation and publishing,
dashboarding
Reporting and
distribution tools Scope, work breakdown structure,
schedule, resources, budget
Project management management, risks, task assignment
tools and control

Backlog management, task


assignment and Kanban boards,
sprints management, user
stories/epic management

Retrospective and risks and lessons


learnt logging

Managing a Communication and Collaboration and remote work High


stage collaboration tools
boundary Documents depository and archive
Documentation
management tools Business process, workflow, and
approval automation
Workflow automation
tools Reporting, dashboarding, data
visualization
Reporting tools
Scope, statement of work, backlog,
Project management tasks assignment, risks, timeframe
tools control

Budget management Costs consolidation, budget

AXELOS Copyright View Only –


Not for Redistribution © 2020
38 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

Process Means of automation Key functionality Impact on


activity the
effectiveness
of the
practice
tools management and reporting, financial
analysis

Closing a Communication and Collaboration and remote work High


project collaboration tools
Business process, workflow, and
Workflow automation approval automation
tools
Reports creation and publishing,
Reporting tools dashboarding

Documentation tools Documents depository and archive

Retrospective and risks and lessons


learnt logging

Managing product delivery

Accept a work Communication and Collaboration and remote work High


package collaboration tools
Business process, workflow, and
Workflow automation approval automation
tools
Backlog items /work packages /tasks
Backlog management assignment and control
tools

WBS management tools

Execute a Communication and Collaboration and remote work High


work package collaboration tools
Workflow and approval automation
Workflow automation
tools

Deliver a work Communication and Collaboration and remote work High


package collaboration tools
Workflow and approval automation
Workflow automation
tools Reports creation and publishing,
dashboarding, automated
Reporting tools notifications

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 39
for Redistribution © 2020

6 Partners and suppliers


Very few services are delivered using only an organization’s own resources. Most, if not all, depend
on other services, often provided by third parties outside the organization (see section 2.4 of ITIL
Foundation: ITIL 4 Edition for a model of a service relationship). This means that organizations use
suppliers in their projects for the resources in all four dimensions of service management. This
includes, but is not limited to, supplier’s products and services, competencies and expertise, tools
and data, market presence, strategic relationships, and so on.
Where organizations aim to ensure fast and effective project management, they usually try to
agree close cooperation with their partners and suppliers, removing formal bureaucratic barriers in
communication, collaboration, and decision-making (see the supplier management practice guide
for more information).
External resources involved in the projects should be properly integrated and onboarded to align
the approach, teamwork assumptions, culture, communication channels, and tools. Relationships
with the suppliers should be constantly monitored and managed, with conflicts, exceptions and
issues resolved as soon as possible. Exceptions should be used for review of the supplier
agreements, both formal and informal, and re-alignment.
Where appropriate, parties should agree on how the project deliverables will be defined and how
the acceptance and handover procedures will work. The definition of the work package should be
central to this.
The practice-specific roles and teams described in section 4.1 are sometimes outsourced. Usually,
outsourcing is easier if the organization has its own project management centre of excellence (e.g.
PMO) and is used to integrate external project management specialists into the project teams.
Outsourcing can also benefit if the supplier shares the same approach and processes in managing
projects.
Organizations switch from outsourcing the function or process in the overall project management
to outsourcing a specific competency. This way, the organization gets knowledge and experience it
lacks but retains decision-making, control, and responsibility for the project within the
organization.

AXELOS Copyright View Only –


Not for Redistribution © 2020
40 Project management AXELOS Copyright View Only – Not
for Redistribution © 2020

7 Important reminder
Most of the content of the practice guides should be taken as a suggestion of areas that an
organization might consider when establishing and nurturing their own practices. The practice
guides are catalogues of topics that organizations might think about, not a list of answers. When
using the content of the practice guides, organizations should always follow the ITIL guiding
principles:
● focus on value
● start where you are
● progress iteratively with feedback
● collaborate and promote visibility
● think and work holistically
● keep it simple and practical
● optimize and automate.

More information on the guiding principles and their application can be found in section 4.3 of ITIL
Foundation: ITIL 4 Edition.

AXELOS Copyright View Only –


Not for Redistribution © 2020
AXELOS Copyright View Only – Not Project management 41
for Redistribution © 2020

8 Acknowledgments
AXELOS Ltd is grateful to everyone who has contributed to the development of this guidance.
These practice guides incorporate an unprecedented level of enthusiasm and feedback from across
the ITIL community. In particular, AXELOS would like to thank the following people.

8.1 AUTHORS
Richard Rose.

8.2 CONTRIBUTORS
Raymundo Sanchez Tico, Mauricio Corona.

8.3 REVIEWERS
John Edmonds, Allan Thomson, Michael Macgregor, Dinara Adyrbai, Roman Jouravlev, Erika Flora.

AXELOS Copyright View Only –


Not for Redistribution © 2020

You might also like