Client’s Addition(NNPC)

1. The use 12mm(Horizontal) and 10mm(Vertical) iron rod for the


basket of the mast foundation

2. Foundation extension to 3.1m by 3.1m due to the pilling of the


ground instead of 2.7m by 2.7m

3. Mixture(Mortar) schedule to be 4:6 per 1 bag(4 headpans of


sand and 6 headpans of chippings to 1 bag of cement).

4. Use of guide wires(10mm) for the balancing of the mast

5. Dept of excavation of the guide wire anchor points to be 2.5m