EARNED VALUE ANALYSIS

1 Percentage complete PC
2 Schedule Variance SV
3 Schedule Variance % SV%
4 Cost Variance CV
5 Cost Variance% CV%
6 Cost Performance Index CPI
7 Schedule Performance Index SPI
8 Estimate At Completion EAC
9 Estimate At Completion EAC
10 Estimate At Completion EAC
11 Estimate At Completion EAC
12 To Complete Performance Index TCPI
13 Estimate To Complete ETC
14 Variane At Completion VAC

BCWP BUDGETED COST OF WORK PERFORMED EV


ACWP ACTUAL COST OF WORK PERFORMED AC
BCWS BUDGETED COST OF WORK SCHEDULED PV
BAC BUDGET AT COMPLETION
SV SCHEDULE VARIANCE
CV COST VARIANCE
CPI COST PERFORMANCE INDEX
AC ACTUAL COST
ETC ESTIMATE TO COMPLETE
EAC ESTIMATE AT COMPLETION
PMB PERFORMANCE MEASUREMENT BASELINE
YSIS
BCWP/BAC BAC=BCWP/PC
BCWS-BCWP
SV/BCWP*100
BCWP-ACWP
CV/BCWP*100
BCWP/ACWP
BCWP/BCWS
BAC/CPI
AC+ETC
AC+BAC-BCWP
AC+(BAC-BCWP)/CPI
(BAC-BCWP)/(BAC-ACWP)
EAC-ACWP
BAC-EAC
Problem 1
Data
T=10 DAYS
BCWS= 100,000
ACWP= 65,000
PC= 70%
BCWS= 10,000/PER DAY
BCWP= 70,000

BCWS ACWP PC BCWP BAC SV


10,000
10,000
10,000
10,000
10,000
10,000 65,000 70% 70,000 100000 10,000
10,000
10,000
10,000
10,000
CV SPI CPI EAC VAC ETC TCPI

5,000 1.1666667 1.0769231 93457.944 6542.0561 28,458 0.8571429