You are on page 1of 24

Modeling Guidelines for Very Fast Transients

in Gas Insulated Substations


Report Prepared by the Very Fast Transients Task Force
of the IEEE Working Group on Modeling and Analysis of System Transients

Contributing Members: J.A. Martinez (Co-chairman), D. Povh (Co-chairman), P. Chowdhuri, R.


Iravani, A. J.F. Keri

circuit breaker operation.


Abstract- This document is aimed at providing modeling guidelines
for digital simulation of very fast transients (VFT) in gas insulated The generation and propagation of VFT from their original
substations (GIS). A short explanation about the origin of VFT location throughout a GIS can produce internal and external
overvoltages, their propagation and effects on GIS equipment is
overvoltages. The main concern are internal overvoltages
included. The document presents modeling guidelines of GIS
components proposed in some previous works. The accuracy of
between the center conductor and the enclosure. However,
digital computations using these guidelinesis also discussed. Several external VFT can be dangerous for secondary and adjacent
examples corresponding to actual cases with detailed data input equipment. These external transients include transient voltages
and validated simulation results are presented. between the enclosure and ground at GIS-air interfaces,
voltages across insulating spacers in the vicinity of GIS current
Keywords: Gas Insulated Substations, Very Fast Transients, transformers, when they do not have a metallic screen on the
Modeling, Digital Simulation. outside surface, voltages on the secondary terminals of GIS
instrument transformers, radiated electromagnetic fields (EMF)
which can be dangerous to adjacent control or relay equipment.
1. INTRODUCTION
VFT can also occur during switching of vacuum breakers and
An accurate representation of each component of a system is with certain lightning conditions. The objective of this
essential for a reliable simulation of its transient performance, document is to present an explanation of the VFT phenomena
This representation must be done taking into account the that can occur in GIS and provide guidelines for representing
frequency range of the transients to be simulated. Very Fast GIS components in digital simulations. Some examples with
Transients (VFT) belong to the highest frequency range of detailed input data are presented. A discussion about the
transients in power systems. Component models to be used in accuracy of the simulations and their verification with field
VFT simulations must be suitable for frequencies varying from measurements is also included.
100 kHz up to 50 MHz [21].

VFT arise within a gas-insulated substation (GIS) any time there 2. BACKGROUND
is an instantaneous change in voltage. Most often this change
occurs as the result of the opening or closing of a disconnect 2.1 ORIGINOF VFTIN GIS
switch, but other events, such as the operation of a circuit
breaker, the closing of a grounding switch, or the occurrence of VFT overvoltages are generated in a GIS during disconnector
a fault, can also cause VFT. These transients generally have a or breaker operations, or by line-to-ground faults. During a
very short rise time, in the range of 4 to 100 ns, and are disconnector operation a number of pre- or restrikes occur due
normally followed by oscillations having frequencies in the to the relatively slow speed of the moving contact. Figure 1
range of 1 to 50 MHz. Their magnitude is in the range of 1.5 to shows the simplified configuration used to explain the general
2.0 per unit ofthe line-to-neutral voltage crest, but they can also switching behavior and the pattern of voltages on closing and
reach values as high as 2.5 per unit. These values are generally opening ofa disconnector at a capacitive load [4], [17].
below the BIL of the GIS and connected equipment of lower
voltage classes. VFT in GIS are of greater concern at the During closing, as the contacts approach, the electric field
highest voltages, for which the ratio of the BIL to the system between them will rise until sparking occurs. The first strike
voltage is lower. Some equipment failures and arcing problems will almost inevitably occur at the crest of the power frequency
between grounded parts have occurred at system voltages above voltage, due to the slow operating speed. Thereafter current will
420 kV, they have been correlated with disconnect switch and flow through the spark and charge the capacitive load to the

6-1
source voltage. As it does so, the potential difference across the In case of power transformers feeding the GIS, overall
contacts falls and the spark will eventually extinguish. The transients with frequencies in the range of 20 to 100 kHz can be
behavior on opening is very nearly a complete reversal of the observed caused by the oscillation of the whole system
above description. consisting of the GIS and the transformer,

In case ofa line-to-ground fault, the voltage collapse at the fault Due to the travelling wave behavior of the VFT, the
location occurs in a similar way as in the disconnector gap overvoltages caused by disconnector switches show a spatial
during striking. Step-shaped travelling surges are generated and distribution. Normally the highest overvoltage stress is reached
injected to GIS lines connected to the collapse location. The rise at the open end of the load side. The maximum value of the
time of these surges depend on the voltage preceding the local VFT overvoltages is dependent on the voltage drop at the
collapse. disconnectorjust before striking and on the location considered.

For the calculation of VFT stresses, the trapped charge


2.2 PROPAGATION OF VFT IN GIS remaining on the load side of the disconnector must be taken
into consideration. For a normal disconnector with a slow
VFT in GIS can be divided into internal and external. Internal speed, the maximwn trapped charge reaches 0.5 pu resulting in
transients can produce overvoltages between inner conductors a most unfavorable voltage collapse of 1.5 pu. For these cases,
and the encapsulation, external transients can cause stress on the resulting overvoltages are in the range of 1.7 pu and reach
secondary and adjacent equipment. A summary about the 2.0 pu for very specific cases. For a high speed disconnector,
propagation and main characteristics of both types of the maximwn trapped charge could be 1.0 pu and the highest
phenomena follows. overvoltages reach values up to 2.5 pu. Extremely high values
of more than 3.0 pu have been reported. It can be shown,
however, that these values have been derived by calculation
2.2.1 Internal transients using unrealistic simplified simulation models.

Breakdown phenomena across the contacts of a disconnector An example ofthese transient phenomena measured in an actual
during a switch operation or line-to-ground faults generate very GIS is given in Figure 2, where one prestrike of a disconnector
short rise time travelling waves which propagate in either switching is depicted showing the steep voltage transients at the
direction from the breakdown or fault location. Surges travelling supply and load sides. The basic frequency component of the
throughout GIS and to other connected equipment are reflected VFT in the MHz range, the overall transient and the steady state
and refracted at every transition point. As a consequence of waveform are also shown.
multiple reflections and refractions, travelling voltages can
increase above the original values and very high frequency The two following examples will be useful to illustrate the
oscillations occur. generation of VFT in GIS, and the influence of some
parameters on the frequency and maximum values of these
The propagation of VFT throughout GIS can be analyzed by transients. Figure 3 shows a very simple case, a GIS bus duct
representing GIS sections as low-loss distributed parameter represented as a lossless distributed parameter transmission line
transmission lines. Each section may be characterized by a surge is fed from a step-shaped source. The reflections of the
impedance and a transit time. Travelling waves are reflected and travelling wave at both terminals ofthe duct will produce at the
refracted at every point where they encounter a change in the open terminal a pulse-shaped transient of constant magnitude -
surge impedance. The generated transients depend on the GIS 2 pu - and constant frequency. The frequency of this pulse can
configuration and on the superposition of the surges reflected be calculated from the following expression
and refracted on line discontinuities like breakers, "T" junctions
or bushings. The main frequencies depend on the length of the
GIS sections affected by the disconnector operation and are in
the range of 1 to 50 MHz.
1
f
4 1 (1)
The internal damping of the VFT influencing the highest
frequency components is determined by the spark resistance. being t the transit time ofthe line. If the propagation velocity is
Skin effects due to the aluminum enclosure can be neglected. close to that of light, the frequency, in MHz, of the voltage
The main portion of the damping of the VFT occurs by generated at the open terminal will be
outcoupling at the transition to the overhead line.

6-2
2.2.2Externaltransients
75
f
d (2) An internally generated VFT propagates throughout the GIS
and reaches the bushing where it causes a transient enclosure
where d is the duct length, in meters. In this case, d = 12 m, then voltage and a travelling wave that propagates along the
the frequency is 6.25 MHz, which corresponds to a period of overhead transmission line. An explanation about the generation
160 ns, as shown in Figure 3.b. Therefore, the main reason why of external transients and some comments on their main
VFT are generated in GIS is due to the short length of ducts. characteristics follow.

Each GIS section, represented as a lossless distributed a) Transient enclosure voltages


parameter transmission line, may be characterized by a surge
impedance and a transit time. In the previous case, the surge Transient enclosure voltages (TEV), also known as transient
impedance of the bus was 50 Q; however, this value was ground potential rise (TGPR), are short duration high voltage
unimportant because the supplying source was assumed ideal. transients which appear on the enclosure ofthe GIS through the
Figure 3.b shows the simulation result obtained with a more coupling of internal transients to enclosure at enclosure
realistic representation of the source, R = 10 Q. One can discontinuities. The usual location for these voltages is the
observe than now the frequency is still the same, but the transition GIS-overhead line at an air bushing, although they
maximum overvoltage at the open terminal is lower than 2 pu, can also emerge at other points such as visual inspection ports,
and the transient is damped. At the end, the voltage value at this insulated spacers for C'l's or insulated flanges at GIS/cables
terminal is equal to that of the source. The equivalent interfaces. The simplified circuit shown in Figure 5 will be used
impedance at the source side ofan actual GIS disconnector will to explain the generation ofTEV [20].
be different from a pure resistance; this representation has be
considered here to facilitate the introduction to VFT generation. At the GIS-air interface three transmission lines can be
distinguished : the coaxial GIS transmission line, the
As mentioned above, trapped charge remaining on the load side transmission line formed by the bushing conductor and the
of a disconnector must be taken into consideration. Figure 3.c overhead line, the GIS enclosure-to-ground transmission line.
shows that the voltage at the open terminal can reach 3 pu ifthe Each ofthem has a different surge impedance. When an internal
transient is started with a 1 pu trapped charge on the wave propagates to the gas-to-air bushing, a portion of the
transmission line. This increase is due to the fact that now the transient is coupled onto the overhead line-to-ground
travelling wave is a 2 pu step, which duplicates at the open transmission line, and a portion is coupled onto the GIS
terminal; the fmal 3 pu value is the result of subtracting the enclosure-to-ground transmission line. The latter constitutes the
remaining trapped charge. A more accurate simulation should TEV.
assume that the equivalent impedance at the source side is not
negligible and a lower trapped charge. The second plot of In general, TEV waveforms have at least two components, the
Figure 3.c depicts the new results with a non-zero source first one has a short initial rise time and is followed by high
resistance and a lower trapped charge. frequency oscillations determined by the lengths of various
sections ofthe GIS, they are concentrated in the range of5 to 10
Maximum voltages can reach higher values in more complex MHz. The second component is of lower frequency, hundreds
GIS configurations. Figure 3 shows a "T" junction GIS ofkHz, and is often associated with the discharge of capacitive
network. The simulations performed with the previous case devices with the earthing system.
were repeated with this new configuration. All bus ducts had the
same surge impedance - 50 Q - and the same propagation
velocity, that of light. The simulations show that node 4 in
Figure 4.a is the open terminal where overvoltages are higher.
From the new plots one can deduce that VFT as higher as 4.5 pu
can be generated; however, as with the previous case, a realistic
simulation cannot neglect the source impedance. In addition, the
value of the trapped charge has to be accurately evaluated as it
will have an important influence on the maximum generated
overvoltage; the second plot of Figure 4.c was obtained
assuming' that the trapped charge was 0.5 pu.

6-3
Ie
0>---------

a) Diagramof the capacitive circuit

:. ; : :
" :;

b) Openingoperation

[JD.1S pu TRAPPED CHARGE

+-+-1-+-+H-+-+-+-IH-+-+-1H--+~H-J,--t-H~-!-..j.....,I4-+-J,........J~----,

.. ..

c) Closingoperation

Figure 1. Variationofload and source side voltages during disconnector switching [4].

6-4
Source side Load side

1.5 -------ooop-oo-......----. 1 . 5 - - - - - - - - - - - - -......


Us (p.u.) UL(P·U.)
1.0
a 11.0 ~......-...+-~~
1 0.5 I----!~+_f_-+_-~~_+__#______t

o tl 200 400 600 800 1000 o t1 200 400 600 800 1000
----.. t (lIS) - -..... t(ns)

1.5 1.5
Us (p.u.) UL(P·U.)

I I
1.0 1.0
b
0.5 0.5

0 t1 2 4 6 8 10 0 t1 2 4 6 8 10
• t (I-Ls) - -..... t(l-Ls)

1.5 ....-----.----,----r-----, 1.5


Us (p.u.) UL(P·U.)

1 1
1.0 1.0
c r'
,....-J
I
I
0.5 ~_--+--""_-+-_ _+--_--1 0.5 I

I
I
I
I
I

o t1 90 t2 180 210 360 o t1 90 t2 180 210 360


- -.... t(lJ.s) - -..... t(lJ.s)

I I
1.5 1.5
Us (p.u.) UL(P·U.)
d 1.0 t----:::II~~___+__----I 1.0 I

0.5 0.5

o 1 t1 2 3 4 5
o 1 t1 2 3 4 5
- -.... t(ms) - -.... t(ms)

a) steepvoltage transients
b) basic frequency component of the VFT in the MHZ range
c) overall transients in the kHZ range
d) low frequency transient and steadystatecondition

Figure2. Transients on the sourceand load side of a GIS due to disconnector switching.

6-5
®

Length = 12 m

a) Scheme of the network

I i

If,.,.]
- , I} WOO l - ·_ · , 1} NU(JC» - f ll /rllJOO' "" ( 2 /NtJ()(M

R=O R=lOQ

b) Simulation results without trapped charge

L :

f····

: :

1{,./
••• • ,~ ~ lJOQI
'IN' - ",/rfUOO1

R=O R= 10Q

c) Simulation results with trapped charge

Figure 3. Generation ofVFTs in a GIS bus duct.

6-6
@

Leng th =

a) Scheme of the network

.....
...:"; :...r . L.':
..... L.!
•_ ••• • · · · 0 • •• :•.: : : ·· ~: : LF:l
...: . ..:

- r ' } I'iI.lOO· • • • • t f'NUoo.


'/116)
- ( ' j IollJDOI

R=O R= IOn

b) Simulation results withouttrapped charge

. .....
i i
[...: I.
j r···-~
LoT'O ...f·-· :...:".. : ~ ..:
'...:

- ( I jMJOO , - ( 1) """00 '


'Ina)

R=O R= IOn

c) Simulation results with trapped charge

Figure4. Generation ofVFTs in a GIS with a bifurcation point.

6-7
!ove~he.ad
Both components are damped quickly as a result of the lossy
nature of the enclosure-to-ground plane transmission mode.
E TEV generally persists for a few microseconds. The magnitude
translDlSSlon
varies along the enclosure; it can be in the range of 0.1 to 0.3 pu
.. line
Ir-~~-...... of the system voltage, and reaches the highest magnitude near
the GIS-air interface.

The TEV wave which couples onto the enclosure encounters


earthing connections which form transmission line
discontinuities and attenuate TEV. Mitigation methods include
grounding using low surge impedance, short length leads and
the installation of metal-oxide arresters across any insulating
spacers.

b) Transients on overhead connections


a) Propagation of travelling waves caused by a disconnector
operation A portion of the VFT travelling wave incident at a gas-air
transition is coupled onto the overhead connection and
inside coaxial bus duct 2 on overhead line propagates to other components. This propagation is lossy and
3 between ground and encapsulation results in some increase of the waveform rise time, although
transients can have rise times in the range of 10 to 20 ns if the
air connection is relatively short. In general, external waveforms
have two different characteristics
* the overall waveshape is dictated by lumped circuit
parameters, such as the capacitance of voltage
transformers or line and earthing inductance; the rise time
is in the range of a few hundred nanoseconds
* a fast front portion which is dictated by transmission line
c; effects; it has a rise time in the range of 20 ns and is
usually reduced in magnitude due to discontinuities in the
transmission path.

The fast rise time of the initial portion is possible as capacitive


b) Equivalent circuit components, such as bushings, are physically long and
distributed, and they cannot be treated as lumped elements.

The magnitude of the rise time portion of external transients is


generally lower than that of internal VFT, the voltage rate-of-
rise can be in the range of 10-30 kV/I1S. However, as VFT occur
during normal conditions in GIS and each disconnector
operation can generate tens to hundreds of individual transients,
possible aging on the insulation of external components must be
considered. These overvoltages can cause stress on adjacent
equipment, and resonance phenomena can occur in exposed
transformers.

c) Transient electromagnetic fields


c) Single-line diagram
EMF are radiated from the enclosure and can cause some stress
Figure 5. Diagram to explain the generation ofTEV [20]. on secondary equipment, especially when sophisticated
computer-controlled equipment may be affected. Their
frequency depends on the GIS arrangement, but is typically in

6-8
the range of 10 to 20 MHz. the external enclosure to be perfectly earthed. IfTEV have to be
considered, it is necessary to add one more mode (enclosure-
ground) since at these high frequencies, the earth connections
2.3 EFFECTS ON EQUIPMENT assume significant impedance values.

The level reached by VFT overvoltages originated by A short explanation about the representation of the most
disconnector switching or line-to-ground faults inside a GIS are important GIS components follows.
below the BIL of substation and external equipment. However,
aging of the insulation of external equipment due to frequent a) Bus ducts
VFT must be considered. For a range of frequencies lower than 100 MHz, a bus duct can
be represented as a lossless transmission line. The surge
TEV is a low energy phenomenon, and it is not considered impedance and the travel time can be calculated from the
dangerous to humans. The main concern is in the danger of the physical dimensions of the duct. Empirical corrections are
surprise-shock effect. TEV can also cause interference with or usually needed to adjust the propagation velocity. Experimental
even damage to the substation control, protection and other results show that the propagation velocity in GIS ducts is close
secondary equipment, and radiate EMF which may induce to 0.95 - 0.96% of the speed of light [14], [24]. The error
voltages and currents within electric circuits. committed by ignoring skin effect losses is usually negligible.

The main effects caused by VFr to equipment and the Other devices such as elbows or closed disconnectors can also
techniques which can be used to mitigate these effects are be modeled as lossless transmission lines.
summarized in Table 1.
b) Surge arresters
A surge arrester model should take into account the steep front
3. MODELING GUIDELINES
wave effect : the voltage developed across the arrester for a
given discharge current increases as the time to crest of the
Due to the travelling nature of VFT, modeling of GIS
current increases, and reaches crest prior to the crest of the
components makes use of electrical equivalent circuits
discharge current. A detailed model must represent each internal
composed of lumped elements and distributed parameter lines.
shield and block individually, and include the travel times along
At very high frequencies, the skin losses can produce a
shield sections, as well as capacitances between these sections,
noticeable attenuation. However, due to the geometrical
capacitances between blocks and shields, and the blocks
structure of GIS and the enclosure material, skin losses are
themselves. The model shown in Table 2 considers two
usually neglected, which gives conservative results. Only the
sections, represented as lossless transmission lines, and a
dielectric losses in some components, e.g. capacitively graded
capacitance paralleled by a resistance between sections.
bushing, need be taken into account.
Experimental results show that switching operations do not
The next two subsections present modeling guidelines to
produce voltages high enough to cause MOVs to conduct.
represent GIS equipment in computation of internal transients
Although sophisticated models have been developed to
and TEV.
represent an MOV, only its capacitance needs to be taken into
account.
3.1 COMPUTATION OF INTERNAL TRANSIENTS
c) Circuit breakers
All the distributed parameter lines take into account the internal The representation of a circuit breaker is very complicated due
mode (conductor-enclosure) only, assuming that the external to internal irregularities. In addition, circuit breakers with
enclosure is perfectly grounded. If TEV is of concern, then a several chambers contain grading capacitors. As these
second mode (enclosure-ground) is to be considered. Table 2 components are not arranged symmetrically, a circuit breaker
shows the equivalent circuits proposed to represent main has a different transient response depending upon which
components of a typical GIS [17]. More accurate models were terminal is connected to the surge source.
presented in [27].

Distributed parameter models shown in Tables 2 take into


account the internal mode (conductor-enclosure) only, assuming

6-9
TABLE 1- EFFECTS OF VERY FAST TRANSIENTS [17]

EQUIPMENT VFTEFFECTS MITIGATION TECHNIQUES


Direct connected transformers can experience Transformers can withstand the stress built up by steep front waves. In critical cases, it
- an extremely nonlinear voltage distribution along the high voltage winding, might be necessary to install varistors to protect tap changers against very high frequency
TRANSFORMERS connected to the oil-SF6 bushings, due to steep fronted wave impulses transient oscillations.
- extremely high part-winding resonance voltages due to transient oscillations
generated within the GIS.

The insulation system of breakers and loadbreak switches is not endangered by VFf The development of a ground fault by branching of the leader discharge during a
overvoltages generated in adjacent GIS equipment. disconnector operation can be avoided by a proper disconnector design.
DISCONNECTORS Ground faults induced by VFTO have been observed in disconnectors operations, as
& BREAKERS residual leader branches can be activated by enhanced field gradient to ground and
by feeding them with GIS-1l;enerated VFTO.

Breakdown caused by VFT overvoltages is improbable in a well-designed GIS


insulation system during normal operations. However, breakdown values can be
SF 6 INSULATION reduced by insulation irregularities like edges and fissures.
The breakdown probability is very low for low VFTO amplitudes, it increases with
the frequency of the oscillations and the degree of the field homogeneitv.

TEV can cause sparking across insulated flanges and to insulated busbars ofCTs, and TEVs can be minimized
0\
I puncture of insulation which is intended to limit the spread of circulating currents - by a proper design and arrangement of substation mats
1--01
o within the enclosure. - by keeping ground leads as short and straight as possible in order to minimize the
ENCLOSURE inductance
- by increasing the number of connections to ground
- by introducing shielding to prevent internally generated VFT from reaching the
outside of the enclosure
- by installing voltage limiting varistors where spacers must be employed.

BUSHINGS SF6 insulated bushings can be affected as other SF6 equipment. Avoid high impedance in the connection of the last graded layer to the enclosure.
Very few problems have been reported with capacitivelv graded bushings,

CABLES No problems have been experienced on the main insulation. Grounding connections must be modified to eliminate troubles.
VFT effects appear always in grounded circuits and are originated by TEVs.

TEV may interfere with secondary equipment or damage sensitive circuits Correct cable connection procedures may minimize interference. The coupling of
- by raising the housing potential if they are directly connected radiated energy may be reduced
SECONDARY - or via cable shields to GIS enclosure by emitting free radiation which may - by mounting control cables closely along the enclosure supports and other
EQUIPMENT induce currents and voltages in adjacent equipment. grounded structures
- by grounding cable shields at both ends by leads as short as possible
- by using optical coupling services.
Voltage limiting devices may have to be installed.
TABLE 2 - GIS COMPONENT MODELS [17]

COMPONENT EQUIVALENT CIRCUIT NOTES

Bus duct -+'""-)_...,-----J}--


I
Loss-free distributed parameter
~srnissionlUne

Spacer ( C ~ 20 to 30 pF)

Elbow

Spherical shield (C ~ fewpF)

Surge arrester -f) ¢f)


I ..L ~
Closedswitch -f) }-
I

Open switch I

I
I I.---,- (n = numberof breaking
1" 1"
....L....L
chambers)

Closeddisconnector -+--)--.------}--
I

Open disconnector

Disconnector during sparking r =r(t) ; R =a few Q


C =a few tens pF

Bushing(capacitive type) n =numberof equivalent


shields(5 to 8) simulated

Bushing(gas filled) GIS --+"""') ~,AjR C = a few tens pF


u Ie z» 250 Q
Powertransformer parameters evaluated from the
(termination) frequency responseof the
~sformer

Currenttransformer sometimes negligible

Capacitive voltagetransformer

Earth connection

Aerial line or long cable r = surge impedance


(termination)

6-11
A closed breaker can be represented as a lossless transmission winding. Most of this terminal capacitance comes from the
line. The surge impedance is calculated from the diameters of capacitance of the terminal bushing to ground.
the conductor and enclosure. The electrical length is equal to the
physical length. The propagation velocity is also reduced to 0.95 Ifvoltage transfer is not of concern, an accurate representation
- 0.96% of the speed of light. The effect of grading capacitors can be obtained by developing a circuit that matches the
can be ignored. The representation ofa closed circuit breaker is frequency response of the transformer at its terminals, At very
more complicated because the electrical length is increased and high frequencies, the saturation of the magnetic core can be
the speed of progression is decreased due to the effects of the neglected, as well as leakage impedances.
higher dielectric constant of the grading capacitors [24]. If the
intermediate voltages are needed, the breaker is divided into as f) Current transformers
many sections as there are interrupters, all connected by the Insulating gaps are usually installed in the vicinity of current
grading capacitors. transformers. During high voltage switching operations, these
gaps flash over, establishing a continuous path. Travelling
A simpler model consists oftwo equal lengths ofbus connected waves propagate with little distortion. Current transformers can
by a capacitor with a value equivalent to the series combination often be neglected.
ofall the grading capacitors. Parameters ofthe two bus sections
are calculated from the physical dimensions of the breaker. A The parameters needed to represent these models can be
different representation has been proposed for circuit breakers determined either from manufacturer's data or by calculation
which contain pre-insertion resistors [24]. based on the physical sizes ofthe equipment. If neither ofthese
is possible, the capacitance values can be estimated from those
d) Gas to air bushings shown in Table 2, while surge impedances can be estimated
A bushing gradually changes the surge impedance from that of around 50-80 ohms.
the GIS to that ofthe line. A detailed model ofthe bushing must
consider the coupling between the conductor and shielding
electrodes, and include the representation of the grounding 3.2 COMPUTATION OF TEV
system connected to the bushing. A simplified model consists
of several transmission lines in series with a lumped resistor At the frequencies of the VFT caused by dielectric breakdown
representing losses. The surge impedance of each line section within the GIS (breakdown across disconnect switch contacts,
increases as the location goes up the bushing. If the bushing is line-to-ground faults), currents are constrained to flow along
distant from the point of interest, the resistor can be neglected the surface of the conductors and do not penetrate through
and a single line section can be used [24]. More advanced them. The inside and the outside ofthe enclosure are distinct, so
models for capacitively graded bushings were proposed in [9], that transients generated within the GIS do not appear onto the
[16] and [28]. outside surface of the enclosure until discontinuities in the
sheath are encountered. These discontinuities occur at gas-to-air
e) Power transfonners terminations (the most frequent case), GIS-cable transitions, or
A common practice is to model a power transformer as a external core current transformers.
capacitor representing the capacitance ofthe winding to ground.
When voltage transfer has to be calculated, interwinding The modeling ofthe GIS for computation ofTEV must include
capacitances and secondary capacitance to ground must also be the effects ofthe enclosure, the representation of ground straps
represented. At very high frequencies a winding of a and the earthing grid.
transformer behaves like a capacitive network consisting of
series capacitances between turns and coils, and shunt A GIS-air termination can be modeled as a junction of three
capacitances between turns and coils to the grounded core and transmission lines each with its own surge impedance, see
transformer tank. The equivalent capacitance, C; is given by Figure 5. This equivalent network can be analyzed using
lossless transmission line models to determine reflected and
(3) transmitted waves. The basic mechanism ofTEV is defmed by
the refraction of waves from the internal coaxial bus duct to the
where C, and C, are the equivalent series and ground enclosure sheath-to-ground system. The travelling wave incident
capacitances ofthe winding. The equivalent series capacitance, onto the GIS-air termination is reflected at this termination
C s' is more difficult to compute. The details of computation being the magnitude ofthe transmitted wave onto the outside of
have been discussed in [37]. The terminal capacitance to ground the enclosure sheath given by the coefficient
must be added to (3) to obtain the total capacitance of the

6-12
(4)
Z
s
= 60 In 2 12 h (6)
r

where ZI, Z2 and Z3 are the surge impedance of the coaxial bus where r is the strap radius and h the average height of the
duct, the overhead line and the sheath-to-ground system, section.
respectively [5]. The negative sign means that there is an
inversion ofthe waveform with respect to the internal transient. The representation of the earthing grid at TEV frequencies is a
very complex task. Furthermore, this grid may not be designed
TEV propagates back from the gas-to-air termination into the to carry very high frequency currents, as no standards for very
substation on the transmission line defmed by the enclosure and high frequency earthing systems are currently available. A
the ground plane. The first discontinuity in the propagation is simplified modeling may be used by representing the earthing
generally a ground strap. For TEV rise times, most ground grid as a low value constant resistance.
straps are too long and too inductive for effective grounding.
However, ground leads may have a significant effect on the Advanced models for GIS components in computation ofTEV
magnitude and waveshape ofTEV. This effect can be explained might consider a frequency-dependent impedance for ground
by considering two mechanisms [6] : straps, a frequency-dependent model for the enclosure-
to-ground line (which could take into account earth losses) and
* the ground lead may be seen as a vertical transmission line the propagation of phase- to-phase modes on the three
whose surge impedance varies with height; when the enclosures [6].
transient reaches the ground strap, a reflected wave is
originated which reduces the magnitude of the transmitted Distributed parameter models shown in Tables 2 take into
wave, being the reduction expressed by the coefficient account the internal mode (conductor-enclosure) only, assuming
2Z g the external enclosure to be perfectly earthed. IfTEV have to be
considered, it is necessary to add one more mode (enclosure-
2Z g + Z 3 (5) ground) since at these high frequencies, the earth connections
assume significant impedance values. A more detailed model is
where Zg is the surge impedance of the ground strap and then required, see Section 5.3.
Z3 the surge impedance of the enclosure-to-ground
transmission line; as Zg is usually much larger than Z3' the
attenuation produced by the ground strap will be usually 4. VALIDATION
small
The accuracy of a simulation depends on the quality of the
* the portion of the wave which propagates down the ground model of each individual GIS component. In order to achieve
strap meets the low impedance of the ground grid, then a reasonable results even for time periods ofsome micro-seconds
reflected wave will be produced at this point which or for very complex GIS structures, highly accurate models for
propagates back to the enclosure where it will tend to each internal component and also for external components,
reduce the original wave. connected to the GIS, are necessary. Figure 6 shows an example
of how a 420 kV disconnector with an arrangement of spacers,
The representation of a ground lead as a constant surge shielding electrodes and varying diameters can be simulated by
impedance is not strictly correct. In reality, the ground strap has the equivalent circuit derived from its geometry. Figure 6.c
a continuously varying surge impedance, so that a continuous shows the measured step response and the simulation result
reflection occurs as a wave propagates down the lead. An using the equivalent circuit shown in Figure 6.b. An excellent
analysis of the performance of different models for the ground correlation between measurements and calculations can be
lead was presented in [6]; simulation results did show that a observed.
constant inductor model may be adequate for straps with travel
time less than the surge rise time, while a nonuniform
impedance model may be necessary for much larger straps.
Reference [6] proposes to divide a ground strap into sections,
each one represented by a surge impedance calculated from the
following expression

6-13
V<>lt.11!l" I pu

1.5

1 .0

0 .5

- - - - measurement
_ _ simulat ion

o. 0 f-'-.,.-.,.--r--r--r-,--,--,--..-..-..-..-..-..-..-..-..-..-~
m o 50 100 150 200 250 300 350 400 450 500
121--+---'7'0 "I
t1lllo 1115

Figure 7. Comparison of simulationand measurement of


a) Anmngement of GIS equipment disconnect switch inducedovervoltages in a 420 kV GIS.

C02 C03 C04 C05 C06 C07 C08 COg


95.60 95.60 480 1250 480 95.60 95.60
O.21m a.41m a.79m a.125m 0.445m O.26m O.21m

spacer spacer

b) Equivalent circuit

voltage / pu a) Diagramof the substation

Measurement

1+-~----J'-r:'Y--~:----:7'"----t

:1-, _
21 U " I' 111
tiJle / DS o

c) Field measurement and simulation result


CaJ.cuJ.ation

Figure 6. Validationofa 420 kV disconnector operation.


1+-1-"''---I---i~V----'lr-~~-----t

An accuratemodelingof eachindividual GIS component makes


it possible to reproduceVFT waveforms with a relatively high
precision, especiallyin short GIS structures or test equipment. o
Figure 7 demonstrates the accuracy of such techniques by
comparing a computersimulation with a directmeasurement of o 2. 9 J.Ls
a transient waveform in an actual GIS. The simulation
performed neglects the presence of propagation losses which
result in somewhatless damping of the high frequency part of b) Comparison of simulation results and measurements
the waveform. The effects of spacers, flanges, elbows, corona at measuring point M2
shields, and other connection hardware, were included in the Figure 8. Measurement and simulationof overvoltages in a
model. 420 kV GIS at closing of disconnectswitch Q 12.

6-14
Detailed calculations have been made for a 420 kV GIS with 2
Amplitude and frequency ofVFT can be reproduced withgood line feederbays,a transformer and a bus coupler, see Figure9.
accuracy for severalperiods and manydetailsin the waveform The double busbar system also included bus sectionalizers.
can be explained. Figure 8 shows a part of a 420 kV GIS on Single-phase enclosure is applied to the bays and three-phase
which measurements have been made at point M2. By closing enclosure forthebusbars. According to theirinternaldesign, all
disconnect switch Q12, one part of the switchyard has been GIS components have been represented thoroughly by line
connected. The measurements have been reproduced by a sections with the corresponding surge impedance and transit
detailedsimulation. Certain differences in the range of higher time, and by lumped capacitances for spacers and additional
frequencies did occur because the simulation was performed capacitances causedby internalshieldingdevices, see Figures
with a low damping equivalent circuit and measuring 11 to 14.Thethree-phase encapsulated busbarsare represented
instruments didnotcaptureveryhighfrequencies. However, the by surge impedances in positiveand zero sequence system.
main waveformhas been reproduced with sufficient accuracy.
Detailed data are given in Appendix A, Tables Al to A4.
Capacitive grading of thebushingshasbeensimulated assuming
5. CASE STUDIES two representative screens for each. The behavior of the
transformer winding under high-frequency transients has been
As it has been explained above, VFT in GIS are caused by simulated by an equivalent circuit,see Figure 13, proposed by
dielectric breakdowns. The collapsing electric field during a the manufacturer, according to the high-frequency
breakdown produces travelling waveswhichpropagate in both measurements performed in the factory.
directions from the disturbance location. This propagation can
be analyzed and simulated using transmission line theory, and The behavior of the spark in the disconnecting switch during
assuming that propagation losses are negligible. Travelling closing was represented by a fixed resistance of 0.5 ohms in
wavesappearexternally at enclosure transitions, e.g. gas-to-air serieswithan exponentially decreasing resistance, R =R, exp(-
terminations. At these transitions, reflected waves travelling t/T), with Ro = 1012 ohms and T = 1 ns, resulting in a time
back onto the station and transmitted waves coupled onto the duration of voltage breakdown of about IOns. Calculations
outsideof the enclosure sheathsare generated. were performed for a closing operation of the by-pass
disconnecting switch in the line feeder bay 1, see Figure 10,
The magnitude of the travelling waves will depend on their connecting the busbar 1 to the voltage source. Time-step size
source (disconnect switch operation, fault) and the GIS was 0.15 ns. Simulation results are shown in Figure 15 for the
configuration. Depending on the transient of concern, a measuring pointsM1 to M5 :
different modeling is to be considered. Guidelines for * point Ml - node 35 in Figure 13 -, voltage stress at the
simulation of internaland externaltransients werediscussed in connection inside the transformer between bushing and
Section3. transformer winding
* point M2 - node 34 in Figure 13 -, high-frequency
Due to the very high frequencies generated by a dielectric oscillations at the GIS-sideof the transformer bushing are
breakdown withinthe GIS, a digital simulation is restricted to caused mainly by the capacitive grading system of the
calculations duringtheVFTwaveformperiod,usually1or2 us, bushing
If the simulation is performed with an EMTP-like program, * point M3 - node 10 in Figure 11 -, the voltage oscillation
whichuses a constanttimestep size,then the valueof this step near the end of the switchedbusbar SS2 starts from non-
sizewilldependon the shortertransittimein the GIS.Thisstep zero conditions, since part of the feeding voltage on
size must be equal or smaller than one-halfthe shortertransit busbar SSI is capacitively coupled to busbar SS2 via the
time. capacitance of the open circuit breaker in the couplingbay
* point M4 and M5 correspond to nodes 3 in Figure 11 and
Three case studies are included in this section. The first one node 18 in Figure 13,respectively.
presents the simulation of VFT in a 420 kV substation
generated by a closingoperation. Thenexttwo casesarerelated The investigation clearlyshows that very detailed information
to low voltage tests in a 765 kV GIS. Low voltage tests are a of the internal design not only of the GIS but also of the
veryusefultool for development and validation of GISmodels. external equipment, likebushings and transformer windings, is
The first of these two cases presentsthe simulation of internal necessary to achieve reliableresults.
transients, while the secondone is aimedat calculating TEV.

5.1 CLOSING OPERATION IN A 420 kV GIS [35]

6-15
bu. COuPI.~

t~on.fo~"'e~ feede~

Figure 9. Basicarrangement of the 420 kV GIS.

line feede~ 2

bu. .ectionollzer
M4

M3

bus coupler

t~on.for"'er fe.de~

Figure 10. Configuration of the 420 kV GIS used for the simulation.

6-16
Zu".-409 o
btJslxJ SS2 -.4/ _

btJslxJ SSI--------.I--~-----
1 67 10 11

Figure 11 . Arrangement of busbars, including bus


sectionalizer.

_ _--...,;.'4 16
15
'3~' 9
1,0\.
,!>
,\'0
9 4
10
1 1 12
1.3
7
'6 ~ 14

.n
8 IS

22
21 Figure 13. Line feeder.

27
------=2:.:::1....,,~....,,!--I-~---------
28
19 4
29 18
30 17
33 31 16
32 15
34 14
35 13
, 2.' 0 12
11
10
9
8
0.7!> ..F 7

6 .....-----45
Figure 12. Transformerfeeder.

Figure 14. Bus coupler.

6-17
1.0
5.2 LOW VOLTAGE TEST OF A 765kV GIS [24]
voltage - pu

Figures 16 and 17 show the one-line and the connectivity


diagram of a 765 kV test bay. Models used to represent
POINT M1 -+-------------- components of thiscase arepresentedin Table2. Theprocedure
followed to develop these models is detailed in [24]. A
summaryof this procedure follows:
1) Low voltage tests on individual components were
-1.0
performedusing waves with fronts of 4 and 20 ns.
voltage - pu 1.13 - 2) Models based on physical dimensions were developed,
1 .0
assuminga propagationvelocity equal to that of light.
3) Digital models were adjusted so simulation results were
matched to measurements. The main adjustment was to
decreasepropagationvelocity to 0.96 that of light.
POINT M2 --+--------------
Two transientshave been reproduced
-0.5
in the first one, a ramp voltage is applied at t =0
voltage - pu
in the second case, the ramp voltage source is also used
but the transient starts after closing a switch at the instant
the ramp reaches its maximumvalue.

Waveforms obtained for each case at two nodes are shown in


0.5
Figures 18 and 19. It can be observed that waveforms for both
cases are essentiallythe same, except for the first nanoseconds
POINT M3 --+-------------- in the vicinityof the input node DC1. These simulationresults
were validatedby comparison with low voltage measurements.
-0.5
For normal studies,the input wave will be one of three forms
voltage - pu 1 .06 -
1.0 * a ramp voltage with a magnitude determined by the
voltage across the switch

* two ramp currents on opposite sides of the switch such


that the voltage across the switch is equal to zero at the
POINT M4 ---+---------------
crest of the inputs

-0.5 * charge both sides of the switch to the desired value and
close the switch.
voltage - pu 1 .06 _
1.0

POINT M5 --+---------------

-0.5

o time - J.1.S 2

Figure 15. Simulationresults.

6-18
BUSHING

-~/--t---t------:>.---,
UCI
) ) UK

(
Figure 16. One-line diagram ofa 765 kV GIS.

01
10 P F f

@
8
100 ohm @
8 § 8 (0 @ @ @)
®
8
@
8 e 8 e @
0
@) @ @ @ 8
-
2

@ @
0 8 S
@
75 ohm
8 @
@ @ @0 @ T3

75 oIlm

Figure 17. Connectivity diagramof the 765 kV GIS.

6-19
5.3 CALCULATION OF TEV IN A 765kV GIS [24]

Modeling of GIS components to simulate TEVs must include


the effects of
* an enclosure, which cannot be assumed to be continuously
grounded
* the surge impedances and lengths of the grounding
structures
* the resistance of the earth ground.
trn-J
Each GIS component can be represented as a two-phase ideal
a) Voltage at location UC1 transmission line defmed by two modal parameters, ZO and Z 1,
whose values can be approached as follows [24]
Z = 60 In(D/d) Zl = Z/2 Zo = 20000 - Z,
where D is the inside diameter of the enclosure and d is the
outside diameter of the center conductor.

At the bushing, the two modes split with one going up to the
bushing and the other connected to the grounding surge
impedance, see Figure 20.
,---------------------

trn-J TOP OP BUSH:IN'G

AI.....
XAI----
b) Voltage at location UK B

Figure 18. Simulation results with 4 ns ramp. XB

GR.OUND
RES.STANCE

Figure 20. Connection of GIS to an air bushing.

Figures 21 through 24 show simulation results at different


locations produced by a 4 ns ramp as input voltage.

,~
6. CONCLUSIONS

a) Voltage at location VC1 A description of the origin and main characteristics ofVFT in
GIS, as well as their effects on substation and adjacent
equipment, has been summarized in this document. Modeling
guidelines for digital simulation of GIS networks in VFT
studies have been discussed. Their application was illustrated
with three case studies. Although guidelines proposed in this
document neglect propagation losses for many GIS components
and very simple models are proposed for most components,
validation tests have shown that an excellent correlation
,~
between simulation results and field measurements can be
achieved. More accurate models may be needed in some cases
b) Voltage at location UK for which propagation losses at very high frequencies should
Figure 19. Simulation results from closing a switch. not be neglected.

6-20
v(VJ

7. REFERENCES

[1] A. Ecklin, D. Schlicht and A. Plessl, "Overvoltages in


GIS caused by the operation of isolators", Surges in
high-voltage networks, K. Ragaller (Ed.), pp. 115-129,
Plenum Press, 1980.
[2] S. Narimatsu et al., "Interrupting performance of
capacitive current by disconnecting switch for gas
insulated switchgear", IEEE Trans. on Power Apparatus
and Systems, vol. 100, no. 6, pp. 2726-2732, June
Figure 21. Voltage between the center conductor and the 1981.
enclosure at location UCI. [3] S. Matsumara and T. Nitta, "Surge propagation in gas
insulated substation", IEEE Trans. on Power Apparatus
and Systems, vol. 100, no. 6, pp. 3047-3054, June
1981.
[4] S.A. Boggs et al., "Disconnect switch induced transients
and trapped charge in gas-insulated substations", IEEE
Trans. on Power Apparatus and Systems, vol. 101, no.
6, pp. 3593-3602, October 1982.
[5] N. Fujimoto, E.P. Dick, S.A. Boggs and G.L. Ford,
"Transient ground potential rise in gas-insulated
substations - Experimental studies", IEEE Trans. on
Power Apparatus and Systems, vol. 101, no. 6, pp.
Figure 22. Voltage between the enclosure and ground at the 3603-3609, October 1982.
base of the bushing. [6] E.P. Dick, N. Fujimoto, G.L. Ford and S. Harvey,
v(VJ "Transient ground potential rise in gas-insulated
substations - Problem identification and mitigation" ,
IEEE Trans. on Power Apparatus and Systems, vol.
101, no. 6, pp. 3610-3619, October 1982.
[7] L. Blahous and T. Gysel, "Mathematical investigation
of the transient overvoltages during disconnector
switching in GIS", IEEE Trans. on Power Apparatus
and Systems, vol. 102, no. 9, pp. 3088-3097, September
1983.
[8] G. Bernard, J. Massat, G. Ebersohl and G. Voisin,
"Study of electromagnetic transients due to disconnector
Figure 23. Voltage between the center conductor and ground switching in metal enclosed substations", Revue
at location UK. Generate de l'Electricite, no. 11, pp. 667-694, ~
v(VJ 1983.
[9] R.J. Harrington and M.M. EI-Faham, "Proposed
methods to reduce transient sheath voltage rise in gas
insulated substations", IEEE Trans. on Power Apparatus
and Systems, vol. 104, no. 5, pp. 1199-1206, May
1985.
[10] J. Lalot, A. Sabot, J. Kieffer and S.W. Rowe,
"Preventing earth faulting during switching of
disconnectors in GIS including voltage transformers",
IEEE Trans. on Power Delivery, vol. 1, no. 1, pp. 203-
211, January 1986.
Figure 24. Voltage between the center conductor and the [11] S. Ogawa et aI., "Estimation of restriking transient
enclosure at location UK. overvoltage on disconnecting switch for GIS", IEEE

6-21
Trans. on Power Delivery, vol. 1, no. 2, pp. 95-102, no. 1, pp. 316-323, January 1992.
April 1986. [27] Z. Haznadar, C. Carsimamovic and R. Mahmutcehajic,
[12] T. Yoshida et aI., "Distribution of induced grounding "More accurate modeling of gas insulated substation
current in large-capacity GIS using multipoint grounding components in digital simulations of very fast
system", IEEE Trans. on Power Delivery, vol. 1, no. 4, electromagnetic transients", IEEE Trans. on Power Delivery,
pp. 120-127, October 1986. vol. 7, no. 1, pp. 434-441, January 1992.
[13] J. Ozawa et aI., "Suppression of fast transient [28] A. Ardito et aI., "Accurate modeling of capacitively
overvoltage during gas disconnector switching in GIS", graded bushings for calculation of fast transient
IEEE Trans. on Power Delivery, vol. 1, no. 4, pp. overvoltages in GIS", IEEE Trans. on Power Delivery,
194-201, October 1986. vol. 7, no. 3, pp. 1316-1327, July 1992.
[14] N. Fujimoto, H.A. Stuckless and S.A. Boggs, [29] A.M. Miri and M.A. Nothaft, "Simulation of the effects
"Calculation of disconnector induced overvoltages in of ZnO-varistors in reducing the transient ground
gas-insulated substations", Gaseous Dielectrics IV, potential rise between a GIS enclosure and the cable
Pergamon Press, 1986. outlet flange", Proc. of the First European Conference
[15] R. Boersma, "Transient ground potential rises in gas- on Power Systems Transients, pp. 53-60, Lisbon, June
insulated substations with respect to earthing systems", 17-18, 1993.
Electra, no. 110, pp. 47-54, January 1987. [30] H.W. Dommel, "Simulating travelling waves inside and
[16] R. Witzmann, "Fast transients in gas insulated outside GIS enclosures with the EMTP", presented at
substations. Modelling of different GIS components", the Canadian Electrical Association, Toronto, March
5th Int. Symposium on HV Engineering, Paper no. 1994.
12.06, Braunschweig, 23-28 August, 1987. [31] A.M. Miri and C. Binder, "Investigation of transient
[17] CIGRE Working Group 33/13-09, "Very fast transient phenomena in inner- and outer systems of GIS due to
phenomena associated with gas insulated substations", disconnector operation", Proc. ofthe Int. Conference on
CIGRE Paper No. 33-13, 1988. Power Systems Transients, pp. 71-76, Lisbon, SepaThr
[18] CIGRE WG 33/13-09, Monograph on GIS Very Fast 3-7,1995.
Transients, 1988. [32] Y. Yamagata et aI., "Suppression of VFT in 1100 kV
[19] N. Fujimoto and S.A. Boggs, "Characteristics of GIS GIS by adopting resistor-fitted disconnector", IEEE
disconnector-induced short risetime transients incident on Trans. on Power Delivery, vol. 11, no. 2, pp. 872-880,
externally connected power system components", IEEE April 1996.
Trans. on Power Delivery, vol. 3, no. 3, pp. 961-970, [33] M. lanoz, L. Dellera, C.A. Nucci and L. Quinchon,
July 1988. "Modeling of fast transient effects in power networks
[20] J. Meppelink, K. Diederich, K. Feser and D.W. Pfaff, and substations", CIGRE Paper 36-204, 1996.
"Very fast transients in GIS", IEEE Trans. on Power [34] K. Mizuno et aI., "Investigation ofPD pulse propagation
Delivery, vol. 4, no. 1, pp. 223-233, January 1989. characteristics in GIS", IEEE Transmission and
[21] CIGRE Working Group 33.02, Guidelinesfor Distribution Conference Proceedings, pp. 204-212, Los
representation of networks elements when calculating Angeles, September 15-20, 1996.
transients, 1990. [35] IEEE TF on Very Fast Transients (D. Povh, Chairman),
[22] S. Yanabu et aI., "Estimation of fast transient "Modelling and analysis guidelines for very fast
overvoltage in gas-insulated substation", IEEE Trans. on transients", IEEE Trans. on Power Delivery, vol. 11,
Power Delivery, vol. 5, no. 4, pp. 1875-1882, October no. 4, October 1996.
1990. [36] IEC 71-2, Insulation Co-ordination - Part 2 :
[23] A.M. Miri and M. Schelker, "ATP simulation of Application Guide, 1996.
transient ground potential rise in gas-insulated [37] P. Chowdhuri, Electromagnetic Transients in Power
substations", EMTP News, vol. 4, no. 3, pp. 14-21, SepaThr Systems, RSP-John Wiley, 1996.
1991. [38] CIGRE Joint WG 33/23.12, "Insulation co-ordination of
[24] D.L. Nickel, "Very fast transients in Gas-insulated GIS : Return of experience, on site tests and diagnostic
substations", EPRI Report, 1991. techniques", ELECTRA, no. 176, pp. 66-97, February
[25] S. Okabe, M. Kan and T. Kouno, "Analysis of surges 1998.
measured at 550 kV substations", IEEE Trans. on Power
Delivery, vol. 6, no. 4, pp. 1462-1468, October 1991.
[26] H. Toda et aI., "Development of 800 kV gas-insulated
switchgear", IEEE Trans. on Power Delivery, vol. 7,

6-22
APPENDIX A - DATA OF THE 420 kV GIS TABLEA2 - TRANSFORMER FEEDER DATA

TABLE Al - LINE FEEDERDATA Branch Length Z C


(m) (0) (pF)
Branch Length Z C
1 - 2 1.20 95
(m) (0) (pF) 2 - 3 0.75 42
1 - 2 1.20 95 3 - 4 4
2 - 3 0.75 42 4 - 5 0.30 42
3 - 4 0.15 42 5 - 6 0.45 95
4 - 5 0.30 42 6 - 7 0.45 95
5 - 6 0.45 95 7 - 8 0.15 42
6 - 7 0.45 95 7 - 9 0.75 42
7 - 8 0.15 42 9 - 10 0.15 42
7 - 9 0.75 42 10 - 11 0.30 42
9 - 10 4 11 - 12 1.10 95
10 - 11 0.30 42
12 - 13 1.15 95
11 - 12 1.10 95
13 - 14 1.20 95
12 - 13 1.15 95
13 - 15 0.75 42
13 - 14 1.20 95 15 - 16 4
13 - 15 0.75 42 16 - 17 0.30 42
15 - 161) 4 17 - 18 0.65 95
16 - 17 0.30 42 18 - 19 0.40 42
17 - 18 0.65 95 19 - 20 1.10 42
18 - 19 0.40 42 20 - 21 0.30 95
19 - 20 1.10 42 21 - 22 0.70 95
20 - 21 0.30 95 22 - 23 1.10 66
21 - 22 0.70 95 23 - 24 1.15 66
22 - 23 1.10 66 24 - 25 0.70 95
23 - 24 1.15 66 8 - 25 2.30 95
24 - 25 0.70 95
17 - 26 0.80 95
8 - 25 2.30 95
26 - 27 0.90 72
17 - 26 0.80 95
27 - 28 0.80 95
26 - 27 0.90 72 28 - 29 0.90 95
27 - 28 0.60 95
29 - 30 1.50 95
28 - 29 0.60 25
30 - 31 0.80 95
27 - 30 4.00 95 31 - 32 0.60 95
30 - 31 0.15 95
32 - 33 0.60 25
31 - 32 1.50 95
31 - 34 11.0 25
32 - 332) 4.90 95 34 - 35 1) 2.30 126
2 - E 10 2 - E 10
5 - E 14 5 - E 14
6 - E 10 6 - E 10
8 - E 10 8 - E 10
11 - E 24 11 - E 24
13 - E 10 13 - E 10
17 - E 10 17 - E 10
21 - E 10 22 - E 10
22 - E 32 23 - E 32
23 - E 32 24 - E 32
24 - E 32 25 - E 32
25 - E 10 26 - E 10
26 - E 10
27 - E 10
27 - E 10
28 - E 16
29 - E 10 29 - E 10
30 - E 10
31 - E 10
1)by-pass disconnect switch 2) special bushing representation

1)special bushing representation

6-23
TABLE A3 - BUSBARDATA APPENDIX B - DATA OF THE 765 kV GIS
Branch Length Zo ZI C
(m) (0) (0) (PF)
1 - 2 1.80 157 113
Branch Z Travel time
2 - 3 3.70 157 113
(0) (ns)
3 - 4 5.60 157 113
4 - 5 0.90 157 113
UCI - J3 75 6.40
5 - 6 0.85 104 60 J3 - J4 75 48.0
6 - 7 0.15 104 60 J4 - T22 75 2.20
7 - 8 0.20 104 60
T22 - T23 51 1.90
8 - 9 1.80 157 113 J4 - 09 78 2.20
9 - 10 7.40 157 113 09 - 088 68 1.80
10 - 11 1.80 157 113 D88 - 066 59 4.20
1 - E 12 D44 - 022 33 5.80
2 - E 3 D22 - Dl 330 9.10
3 - E 3 J3 - T21 75 2.20
4 - E 3 T21 - T20 51 1.90
8 - E 3 T20 - Tl9 160 0.67
9 - E 3 T19 - T18 65 1.70
10 - E 3 T19 - T17 75 6.80
T17 - T16 65 1.70
T17 - J7 75 8.50
J7 - T24 75 2.20
TABLE A4 - BUS COUPLERDATA T24 - T25 51 1.90
Branch Length Z J7 - T26 75 2.20
C T26 - T27 51 1.90
(m) (0) (pF) T17 - T14 160 0.67
1 - 2 1.20 95 T14 - T13 51 1.90
2 - 3 0.45 42 TI3 - TIl 75 9.90
3 - 4 0.15 42 TIl - T12 65 1.70
4 - 5 0.90 42 TIl - J2 75 7.50
5 - 6 0.60 95 J2 - T9 75 2.20
6 - 7 0.90 72 T9 - TI0 51 1.90
7 - 8 1.00 95 TIO - T28 160 0.67
8 - 9 0.30 66 T28 - J6 75 7.10
9 - 10 4 J6 - UK 75 6.40
10 - 11 0.80 66 T28 - T29 65 1.70
11 - 12 0.85 66 T28 - J5 75 8.80
12 - 13 4 J5 - T30 75 2.20
13 - 14 0.30 66 T30 - T32 51 1.90
14 - 15 0.70 95 J2 - Jl 75 6.70
15 - 16 1.70 95 Jl - T4 75 2.20
16 - 17 0.45 95 T4 - T3 51 1.90
17 - 18 0.45 95 Jl - TS 75 2.20
18 - 19 0.45 42
19 - 20 0.15 42
20 - 21 0.75 42
21 - 22 0.15 42
22 - 23 1.20 95
8 - 14 900
2 - E 10
6 - E 10
7 - E 10
8 - E 32
11 - E 40
14 - E 32
15 - E 10
16 - E 24
17 - E 10

6-24

You might also like