You are on page 1of 20

1.

------IND- 2017 0207 D-- EN- ------ 20170608 --- --- PROJET

Federal Highway Research Institute


(Bundesanstalt für Straßenwesen)

Additional Technical Contract Conditions


and Guidelines for Civil Engineering
Works

ZTV-ING

Part 5
Tunnel construction

Section 5
Waterproofing

Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing

Notified in accordance with Directive (EU) 2015/1535 of the European Parliament and of the Council of
9 September 2015 laying down a procedure for the provision of information in the field of technical regulations and of
rules on Information Society services (OJ 241 of 17.9.2015, p. 1).

2 Version: 2017/05
Contents Page

5.1.2 Protective layers and protective


1 General...................................................4
measures .............................................. 16
1.1 Fundamentals .........................................4
5.2 Bored tunnel construction method ....... 17
1.2 Definitions ...............................................4
5.2.1 General ................................................. 17
1.3 Scope ......................................................4
5.2.2 Installation of protective layer ............... 17
1.4 Requirements for participants .................4
5.2.3 Installation of plastic geomembranes ... 17
2 Application criteria ...............................8 5.2.4 Joint design .......................................... 17
2.1 General ...................................................8 5.2.5 Joining technique ................................. 17
2.2 Sealing classes .......................................8 5.2.6 Re-injection in the block joint................ 18
5.2.7 Re-sealing work .................................... 18
3 System fundamentals...........................8
5.2.8 Installing the protective layer in the
3.1 General ...................................................8 base ...................................................... 18
3.2 Cut and cover construction method ........8 5.2.9 Laying aids ........................................... 18
3.3 Bored tunnel construction method ..........9
6 Quality assurance .............................. 18
3.4 Pressure relief systems ..........................9
6.1 Evidence required before starting
3.5 Transitions/connections to waterproofing work ............................... 18
waterproofing systems ............................9
6.2 Internal quality control of construction
4 Waterproofing elements and work by the contractor .......................... 19
installation components ....................10 6.2.1 General ................................................. 19
4.1 General .................................................10 6.2.2 Inspections of incoming goods ............. 19
4.1.1 Cut and cover construction method ......10 6.3 Client monitoring of the construction of
4.1.2 Bored tunnel construction method ........10 the plastic geomembrane waterproofing
system .................................................. 19
4.2 Plastic geomembranes (KDB) ..............10
6.4 Execution documentation ..................... 19
4.2.1 General .................................................10
4.2.2 Cut and cover construction method ......11 7 Invoicing and compensation ............. 20
4.2.3 Bored tunnel construction method ........11
4.3 Protective and drainage layer ...............11
4.3.1 General .................................................11
4.3.2 Cut and cover construction method ......11
4.3.3 Bored tunnel construction method ........11
4.4 Installation components ........................11
4.4.1 Fastening components .........................11
4.4.2 Profile strips ..........................................11
4.4.3 Venting and re-injection devices in the
block joint ..............................................11
4.4.4 Testing and injection system for re-
sealing...................................................12

5 Execution requirements .....................16


5.1 Cut and cover construction method ......16
5.1.1 Laying plastic geomembranes ..............16

Version: 2017/05 3
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
1 General geomembranes (KDB) for cut and cover and bored
road tunnels. The regulations on cut and cover
construction apply accordingly to the necessary
1.1 Fundamentals waterproofing of trough constructions with plastic
(1) Part 5 Section 5 only applies in combination geomembranes, e.g. where groundwater is subject
with Part 1 General. to corrosive chemical attack.
(2) The recommendations on waterproofing (2) Sections 1 and 2 apply to concrete structures
systems in tunnel construction (EAG-EDT) issued used with plastic geomembranes and waterproof
by the German Geotechnical Society (Deutschen concrete structures (WUB-KO), unless otherwise
Gesellschaft für Geotechnik e.V. – DGGT] contain provided in these regulations.
additional explanations.
1.4 Requirements for participants
1.2 Definitions (1) Only persons with proven in-depth expertise
and practical experience in waterproofing work in
(1) Waterproofing system tunnel construction can be entrusted with
consists of sealing and protective elements. (see executing waterproofing measures in tunnel
Figure 5.5.1 and 5.5.2). construction. Site managers must have at least five
years’ and foremen at least three years’ practical
(2) Waterproofing experience with waterproofing work in tunnel
is a construction measure to protect the structure construction.
against the penetration of mountain water (general (2) Jointing work can only be carried out by
term). In this Section, a bound waterproof layer welders with valid test certificates issued by the
made of plastic geomembranes (KDB) is also German Association for Welding and Related
referred to as waterproofing. Processes [Deutscher Verband für Schweißen und
(3) The definitions in Figures 5.5.1 and 5.5.2 also verwandte Verfahren e.V. – DVS], Guideline
apply. DVS 2212-3.
(3) Site managers and supervisors must have
1.3 Scope practical experience of relevant waterproofing work
and have sufficient knowledge of how to carry out
(1) This Section applies to the technical such work properly.
construction and maintenance of new road tunnels.
It deals with waterproofing systems with plastic

Tunnelquerschnitt Tunnel cross section


Einzelheit "A" Item A

4 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
bodenseitige Schutzschicht z.B. Schutzbeton Ground-side protective layer e.g. protective
(bewehrt) concrete (reinforced)
Kunststoffdichtungsbahn (KDB) Plastic geomembrane (KDB)
bauwerksseitige Schutzschicht (Geotextil) Structure-side protective layer (geotextile)
Konstruktionsbeton (WUB-KO) Structural concrete (WUB-KO)
Abdichtungssystem Waterproofing system
Einzelheit "B" Item B
Konstruktionsbeton (WUB-KO) Structural concrete (WUB-KO)
luftseitige Schutzschicht Sohle (z.B. Airside protective layer base (e.g. plastic protective
Kunststoffschutzbahn) layer)
Kunststoffdichtungsbahn Plastic geomembrane
Schutzschicht (Geotextil) Protective layer (geotextile)
Unterbeton Concrete sublayer

Fig. 5.5.1: Definitions (example: Cut and cover tunnel with plastic geomembrane waterproofing)

Version: 2017/05 5
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing

Querschnitt mit geschlossener Sohle Cross section with enclosed base


Spritzbetonauβenschale Outer shotcrete shell
Abdichtungssystem Waterproofing system
Betoninnenschale Inner concrete shell
Luftseite Airside
Einzelheit "A" Item "A"
Luftseite Airside

6 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
Wasserseite/Bergseite Waterside/mountainside
Betoninnenschale Inner concrete shell
Kunststoffdichtungsbahn (KDB) Plastic geomembrane (KDB)
bergseitige Schutzschicht (Geotextil) Mountainside protective layer (geotextile)
ggf. Dränelemente Drainage elements where applicable
Abdichtungsträger Waterproofing supports
Spritzbetonauβenschale Outer shotcrete shell
Abdichtungssystem Waterproofing system
Einzelheit "B" Item B
Luftseite Airside
Betoninnenschale Inner concrete shell
luftseitige Schutzschicht Sohle (z.B. Airside protective layer base (e.g. plastic protective
Kunststoffschutzbahn) layer)
KDB Plastic geomembrane
bergseitige Schutzschicht (Geotextil) Mountainside protective layer (geotextile)
ggf. Dränelemente Drainage elements where applicable
Abdichtungsträger Waterproofing supports
Spritzbetonauβenschale Outer shotcrete shell
Wasserseite/Bergseite Waterside/mountainside
Abdichtungssystem Waterproofing system

Fig. 5.5.2: Definitions (example: bored tunnel)

Version: 2017/05 7
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
2 Application criteria (3) It must be able to withstand potential
movements, e.g. temperature deformations, from
the surrounding structural elements without
2.1 General damage.
The main criteria for selecting the waterproofing (4) The waterproofing must be secured against
system are water pressure, the sealing class damage e.g. from rough contact areas, punctual
required and the chemical composition of water load or being driven over during the installation
and in-situ soil. phase.
(5) The waterproofing must be continuously dense
2.2 Sealing classes regardless of adjoining structural elements.
(1) The sealing classes as per Table 5.5.1 must be Installation material such as fastening components
observed in respect of sealing requirements. or injection nozzles must not reduce the
effectiveness of the waterproofing.
(2) When waterproofing with plastic
geomembranes, sealing class 1 must be met. The
requisite waterproofing systems must be taken 3.2 Cut and cover construction
from Tables 5.5.2 and 5.5.3. method
(3) No water must escape via the testing and (1) The waterproofing systems are regulated in
injection system, the injection hoses or the block Table 5.5.2.
joints. In the case of demonstrably damaged (2) Cut and cover tunnels (rectangular or vault
plastic geomembranes, e.g. water entering via the cross section) are generally executed as
testing and injection system or via the block joints, waterproof concrete structures as per Section 2
sealing class 1 is not achieved. without external waterproofing.
(3) When waterproofing plastic geomembranes
3 System fundamentals against non-pressurised water the plastic
geomembrane must not end in horizontal or slightly
3.1 General inclined roof surfaces (danger of water seeping
underneath). The plastic geomembrane should be
(1) In bored tunnel construction, waterproofing is attached with a connecting strap or terminal strip at
executed using plastic geomembranes joined least 30cm below the transition edge from the
together as a flexible and stretchable layer within horizontal to the vertical plane. If the tunnel ceiling
narrow confines between the outer and inner shell. is attached to the wall with a construction joint, the
The plastic geomembrane must be secured plastic geomembrane must extend from below at
against the outer shell with a protective layer. In least 20cm beyond the construction joint.
cut and cover tunnels, the plastic geomembrane is
on the outside of the bearing construction and (4) If traffic routes are covered with a covering less
must be secured on the structure side and on the than 1.00m, waterproofing as per Part 7 Sections 1
ground side with a protective layer. to 3 must be provided for the tunnel ceiling.

(2) The waterproofing must not be used to reduce


shearing forces.

Table 5.5.1: Sealing classes

Sealing class Moisture characteristics Sealing requirements


The structure must be sealed so that no damp patches can be detected on
1 completely dry
the insides.
The construction must be sealed so that only isolated and slight damp can
be detected on the insides (e.g. due to discolouration). No traces of water
2 largely dry must be apparent on the hand after touching slightly damp patches with a
dry hand. Blotting paper or absorbent newspaper placed on the patches
should not discolour due to moisture absorption.
The structure must be sealed so that only isolated and locally limited moist
patches occur on the insides. Moist patches are those where moisture is
3 capillary moisture clearly visible in the structure and blotting paper or absorbent newspaper
placed on these patches discolours due to moisture absorption but there is
no dripping water.

8 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
(8) With single-layer all-round waterproofing against
pressurised water, external joint tape (partitioning
3.3 Bored tunnel construction joint tape) must be applied all the way around each
method block joint.
(1) The waterproofing systems are regulated in
(9) With all-round pressure-retaining waterproofing,
Table 5.5.3.
a testing and injection system must be provided to
(2) Shotcrete tunnels are generally waterproofed allow for the resealing of grouting between the
using a plastic geomembrane layer (see Figure plastic geomembrane and the inner shell.
5.5.2).
(10) If water column pressure is greater than 30m
(3) When waterproofing against non-pressurised above the tunnel floor, the need for special
water, it must be permanently ensured that no measures must be investigated. The DGGT
water pressure load can occur due to the tunnel’s Recommendations on waterproofing systems in
position over the mountain water table and/or due tunnel construction – EAG-EDT contain instructions
to the installation of more reliably effective pressure and examples.
reduction devices such as drainage works.
(4) With the standard drained construction method, 3.4 Pressure relief systems
waterproofing against non-pressurised water
(1) With extremely high water pressure, pressure
remains restricted to the tunnel vault (umbrella
relief systems such as relief openings may be used
waterproofing). In this case, the plastic
in the tunnel lining. They must be connected to a
geomembrane ends at the vault base/base edge at
closed pipe system with water pressure limitation.
the height of the drainage works. In a chemically
corrosive environment, the plastic geomembrane (2) For longer tunnel structures, if the geological
must also pass through the base. conditions are suitable, a partition can be inserted
in sections with varying water pressure by installing
(5) If in-situ mountain water can be conducted away
embankment rings and injection foam.
unpressurised in the long term, umbrella
waterproofing with 2mm-thick plastic geomembrane
is sufficient. 3.5 Transitions/connections to
waterproofing systems
(6) If the surrounding water/soil mixture is
chemically corrosive, all-round waterproofing with The transition from cut and cover to bored tunnel
2mm-thick plastic geomembrane is necessary even construction and/or the connections and
with non-pressurised water. penetrations to other waterproofing systems must
be executed with profile strips or loose and fixed
(7) If a constant flow of water is to be expected
flange constructions or bonded connectors.
when water pressure builds up and mountain water
cannot be drained off without pressure, all-round
pressure-retaining waterproofing with 3mm-thick
plastic geomembrane must be provided.

Table 5.5.2: Waterproofing systems in cut and cover tunnel structures

Waterproofi Hydrostatic Chemical Sealing elements in the waterproofing system


ng pressure attack on Ceiling/vault/wall Floor (where Block joint Construction
geometry above tunnel concrete as necessary) joint (if
floor [mWC] per DIN 4030 available)

slightly to
moderately 3mm plastic geomembrane - -
Umbrella
chemically
none corrosive -
Waterproof concrete structures1) inner joint tape
highly
chemically 3mm plastic geomembrane -
corrosive
all-round slightly to
up to ca. 25 moderately inner joint tape
Waterproof concrete structures1) Sheet metal joint
(0.25 MPa) chemically with steel tabs
corrosive

Version: 2017/05 9
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
highly
Waterproof concrete structure + 3mm plastic inner joint tape
chemically Sheet metal joint
geomembrane with steel tabs
corrosive
1)
Standard construction (See Section 2)

Table 5.5.3: Waterproofing systems in bored tunnel structures (shotcrete construction)

Waterproofi Hydrostatic Chemical Sealing elements in the waterproofing system


ng geometry pressure attack on
above tunnel concrete as Vault Floor (where Block joint Construction Other
floor [mWC] per DIN 4030 necessary) joint (if
available)
2mm
slightly to plastic - - - -
moderately geomembr
Umbrella 1)
chemically ane
none corrosive
Waterproof concrete inner joint tape
Sheet metal joint -
structures4) with steel tabs
highly
chemically 2mm plastic geomembrane - - -
corrosive
Testing and
slightly to 3mm plastic outer partitioning
injection hose injection
moderately geomembrane1) joint tape
all-round chemically
system2)
up to ca. 30
3),4) corrosive Waterproof concrete inner joint tape
(0.3 with steel tabs
Sheet metal joint -
structures4)
MPa)
highly Testing and
outer partitioning
chemically 3mm plastic geomembrane
joint tape
injection hose injection
corrosive system2)
1) Standard construction
2) can only be used in consultation with the client.
3) with water pressure > 30 mWC (0.3 MPa) special measures must be taken, determined in each individual case
4
) See Section 1

4 Waterproofing elements and (2) Profile strips and other waterproofing support
measures must be used as additional installation
installation components components.

4.1 General 4.1.2 Bored tunnel construction method


(1) The materials in the waterproofing systems and (1) The waterproofing consists of the plastic
installation components must be compatible with geomembrane and a protective layer on the
each other and with the adjoining building mountain side (see Figure 5.5.2). An additional
materials and components and should also be internal protective layer must be provided in the
weldable where applicable. The installation base area. In the event of water penetration
components must not reduce waterproofing through the outer shell in drained tunnels a
function either in installed condition or in service drainage layer must also be laid between the
condition. shotcrete outer shell and the mountainside
(2) In special cases, if the waterproofing elements protective layer.
and installation components are subject to long- (2) Fastening components, profile strips and
term stress due to high temperatures, pressure or testing, injection systems where applicable and
chemical attack for example, specific requirements other waterproofing support measures must be
must be determined in individual cases for the used as additional installation components.
waterproofing elements and installation
components.
4.2 Plastic geomembranes (KDB)
4.1.1 Cut and cover construction method
4.2.1 General
(1) The waterproofing consists of the plastic
geomembrane and a protective layer on the The plastic geomembranes must meet the
ground side and on the structure side. requirements of the technical delivery conditions

10 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
and technical test specifications for plastic (4) The protective concrete must be at least 7cm
geomembranes and associated profile strips thick and reinforced with a Q 131 A mat.
(TL/TP KDB).
(5) The plastic protective strips must be at least
3mm thick and be compatible with the plastic
4.2.2 Cut and cover construction method geomembranes.
The plastic geomembranes must have signal (6) If the base waterproofing is driven over and/or if
coating on the ground side around the wall and concentrated load of more than 400 kN/m2 are
ceiling area to indicate damage during laying or introduced, e.g. by the formwork carriage, the
subsequent work. protective layer must be made of reinforced
protective concrete.
4.2.3 Bored tunnel construction method
4.4 Installation components
The plastic geomembranes must have signal
coating on the inside of the tunnel to indicate
damage during laying or subsequent work. 4.4.1 Fastening components
(1) The plastic geomembrane may not be
4.3 Protective and drainage layer penetrated by the fasting systems.
(2) If rondelles are used, the nail must not punch
through when the fastening element is inserted. To
4.3.1 General
avoid damaging the plastic geomembrane, the
Protective layers with or without drainage function elements must be designed so that the nail head is
and drainage layers of geosynthetic materials must placed deep and the spacer does not tilt.
meet the requirements of the technical delivery
(3) The fastening element must be designed to
conditions and technical test specifications for
avoid overstressing the plastic geomembrane. If
protective and drainage layers of geosynthetic
the connections between the plastic geomembrane
materials (TL/TP SD).
and the fastening element is overstressed, the
break must be made in the fastening element
4.3.2 Cut and cover construction method (predetermined breaking point).
(1) Geotextiles must be used as a protective layer
4.4.2 Profile strips
on the structure side between the concrete
structure and the plastic geomembrane around the (1) With pressure-retaining waterproofing, an outer
wall and ceiling area. A plastic protective layer or profile strip (partitioning joint tape) with dimensions
protective concrete must be laid in the base area as per Figure 5.5.3 must be installed in the block
on the structure side. joints.
(2) Depending on the framework conditions, (2) The profile strips must meet the requirements
protective layers with or without a drainage of the technical delivery conditions and technical
function on the ground side must be provided. test specifications for plastic geomembranes and
associated profile strips.
(3) Table 5.5.4 details the types of protective layer
on the ground side required for the various (3) Working joints are not generally sealed with
components. profile strips (see Table 5.5.3), but are given an
injection hose for grouting as required.
(4) Combinations of the protective layer types
mentioned are possible.
4.4.3 Venting and re-injection devices in the
block joint
4.3.3 Bored tunnel construction method
When there is pressure-retaining waterproofing on
(1) Geotextiles must be installed as a mountainside
both sides of the block joint, at least six radially
protective layer without drainage function.
integrated hoses or pipes with an internal diameter
(2) Depending on the framework conditions, of ca. 20mm must be inserted in the stop anchor
drainage layers of geosynthetic materials must be interspace for venting and scheduled re-injection in
laid on the mountainside. the area around the block joints (see 5.2.4). The
layout of the re-injection or vent hose is set out in
(3) Reinforced protective concrete or protective
Figure 5.5.4, Figure 5.5.5 and Figure 5.5.6
layers of plastic protective strips must be used to
(element 1 in each case).
protect the base waterproofing.

Version: 2017/05 11
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
4.4.4 Testing and injection system for re- grouting hoses must be protected against closure
sealing during concreting and protected during top joint
injection (see Section 1). The distance between
(1) A testing and injection system must be provided
grouting hoses must be no more than 3m in
for pressure-retaining waterproofing. The elements
longitudinal and circular direction. The layout of the
of the testing and injection system are shown in
injection devices in the field area is set out in
Figure 5.5.4 (see elements 3 and 4) and described
Figure 5.5.4 (see element 4).
in more detail in paragraphs (2) and (3). The
elements of the testing and injection system must (4) The contractor is free to lay additional grouting
also be provided with openings for scheduled top hoses in the side walls at its own expense. The
joint injection as per Section 1. number of additional openings for formwork
carriages is limited to four.
(2) One radially integrated grouting hose must be
inserted in the ridge area and two radially (5) To avoid damaging the plastic geomembrane,
integrated grouting hoses must be inserted in the all vent and (re-)grouting hoses in the testing and
side walls on each side of the block joint to re-seal injection system must be designed so that they do
the partitioning joint tape as required with stop not change position when the concrete is laid.
anchor interspace distant from the joint. The layout
(6) If there is a leak in the waterproofing, the
of the grouting hose around the block joints is set
testing and injection system must allow water to
out in Figure 5.5.4, Figure 5.5.5 and Figure 5.5.6
exit as well as allow for grouting or injection.
(element 3 in each case).
(7) Fillers for re-injection or injection and their use
(3) The areas adjacent to the partitioning joint
are regulated in Part 3 Section 5.
tapes must be fitted with radially integrated
grouting hose for re-sealing as required. The

Table 5.5.4: Protective layer types depending on installation site of protective layer for cut and cover tunnels

Type of protective layer Installation site of protective layer


Base Wall Tunnel ceiling Vault
Rectangular cross Rectangular cross Vault cross section
section section
Protective concrete X X X 1)
Plastic protective strips X X X X
Geotextiles/drainage mats X X X X
Protective walls X X 1)
1) only in exceptional cases

12 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing

a
h
e b i

r
f1 f

c d
p g

Breiten Dicken Profilierung

a b p c d n e f f1 g h i r
[mm] [mm] [mm] [mm] [mm] [-] [mm] [mm] [mm] [mm] [mm] [mm] [mm]

600 200-220 50-60 4-5 3-4 6 70 30-35 26 5 4 12-14 3

a Gesamtbreite des Fugenbandes g Breite der Sperranker am Fuß oberhalb


b Breite des Dehnteils der Ausrundung
c Dicke der Grundplatte h Breite der Sperranker an der schmalsten
d Dicke der Anschweißenden Stelle (ohne Rippen)
e Achsabstand der Sperranker i Breite der Kopfverstärkung an den
f Gesamthöhe des Fugenbandes Sperrankern
f1 Höhe der Sperranker über der Grundplatte n Anzahl der Sperranker
(ohne Rippen) p Breite der Anschweißenden
r Radius der Ausrundung für den Anschluss
an die Grundplatte

Breiten Widths
Dicken Thicknesses
Profilierung Profiling
Gesamtbreite des Fugenbandes Overall width of joint tape
Breite des Dehnteils Width of elongation part
Dicke der Grundplatte Thickness of base plate
Dicke der Anschweißenden Thickness of welding ends
Achsabstand der Sperranker Centre distance of stop anchors
Gesamthöhe des Fugenbandes Overall height of joint tape
Höhe der Sperranker über der Grundplatte (ohne Height of stop anchor above base plate (without
Rippen) ridges)
Breite der Sperranker am Fuß oberhalb der Width of stop anchor at the foot above smoothing
Ausrundung
Breite der Sperranker an der schmalsten Stelle Width of stop anchor at the narrowest point (without
(ohne Rippen) ridges)
Breite der Kopfverstärkung an den Sperrankern Width of head reinforcement on stop anchors
Anzahl der Sperranker Number of stop anchors
Breite der Anschweißenden Width of welding ends
Radius der Ausrundung für den Anschluss an die Radius of smoothing for connection to the base
Grundplatte plate

Fig. 5.5.3: Basic dimensions of partitioning joint tape, bored tunnel construction method

Version: 2017/05 13
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing

Schnitt Firstlinie Section at ridge line

14 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
luftseitige Schutzschicht Sohle air-side protective layer base (e.g. plastic
(Kunststoffdichtungsbahn) geomembrane)
Kunststoffdichtungsbahn (KDB) Plastic geomembrane (KDB)
Bergseitige Schutzschicht (Geotextil) mountainside protective layer (geotextile)
Spritzbetonauβenschale mit outer shotcrete shell with waterproofing supports
Abdichtungsträger
Schottfugenband Partitioning joint tape
Entlüftungs-/ Nachverpressschläuche bzw. - Vent/re-injection hoses or pipes
rohre
Entlüftungsventil Schottfugenband Partitioning joint tape vent valve
Verpressschläuche für Injection hoses for re-sealing
Nachdichtungsarbeiten
Verpressschläuche für Injection hoses for re-sealing; distance ≤ 3m in
Nachdichtungsarbeiten; Abstand ≤ 3m in longitudinal and circular direction
Längs- und Ringrichtung
Hinweis: Nachbetonier- bzw. NB: Re-concreting or re-injection devices on the
Nachverpressseinrichtungen des formwork carriage as per Section 1 point 7.3.1
Schalwagens gemäβ Abschnitt 1 Nr. 7.3.1 (2) and (3) filler tubes for scheduled top joint
(2) und (3) sowie Einfüllstutzen für die injection as per Section 1 point 7.3.5 are not
planmäβige First- spaltverpressung gemäβ illustrated.
Abschnitt 1 Nr. 7.3.5 sind nicht dargestellt.
Detail Detail
"Schottfugenband First" "Partitioning joint tape on ridge"
"Schottfugenband Sohle" "Partitioning joint tape at base"

Fig. 5.5.4: Venting and re-injection devices as well as testing and injection system for pressure-retaining waterproofing, bored
tunnel construction method

Version: 2017/05 15
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing

Firstlinie Ridge line


Ulme Side walls
Schottfugenband Partitioning joint tape
Blockfuge Block joint
Entlüftungs- Vent/re-injection hoses or
/Nachverpressschläuche pipes
Entlüftungs- und Vent and re-injection hoses bzw. -rohre
Nachverpressschläuche or pipes in outer and inner Entlüftungsventil Partitioning joint tape vent
bzw. –rohre im äuβeren und stop anchor interspace Schottfugenband valve
inneren Sperranker- Verpressschläuche für Injection hoses for re-sealing
zwichenraum Nachdichtungargeiten
Entlüftungsventil für den Vent valve for the space Rand des Fugenbandes Edge of joint tape
Raum zwichen KDB und between the plastic
Schottfugenband geomembrane and the
partitioning joint tape Fig. 5.5.6 Venting and re-injection devices around
Verpressschläuche für eine Injection hoses to re-seal the the block joints, execution
eventuell erforderliche partitioning joint tape as
Nachdichtung des required, all with the stop
Schottfugenbandes, alle im anchor interspace distant 5 Execution requirements
fugenfernen Sperranker- from the joint.
zwichenraum
5.1 Cut and cover construction
Fig. 5.5.5: Vent and re-injection devices around the block joints, method
bored tunnel construction method

5.1.1 Laying plastic geomembranes


(1) The plastic geomembranes must be laid loose
and welded to an entire area.
(2) The plastic geomembrane must be welded to
the connecting strap or held with a terminal strip at
all ends of the waterproofing.

5.1.2 Protective layers and protective


measures
(1) Areas that are sealed and released for further
work must be protected against expected effects
and stress such as weather conditions immediately
after laying.
(2) When filling the excavation pit the waterproofing
must not be damaged. The maximum grain size of

16 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
the fill material must not exceed 8mm up to 20cm 5.2.4 Joint design
above the protective layers. The area must be filled
(1) When waterproofing against unpressurised
in accordance with the additional technical contract
water, an additional reinforcing plastic
conditions and guidelines for earthworks in road
geomembrane strip at least 0.50m wide or a plastic
construction [Zusätzliche Technische
protective layer with the same thickness as the
Vertragsbedingungen und Richtlinien für
plastic geomembrane must be laid centrally above
Erdarbeiten im Straßenbau – ZTV E-StB].
the block joint on the airside of the plastic
(3) Geotextile protective layer membranes must geomembrane and welded on both sides. Provision
overlap by at least 10cm and must be secured in must be made for venting.
position.
(2) With pressure-retaining waterproofing, the
partitioning joint tape (Figure 5.5.3) must be welded
5.2 Bored tunnel construction onto the plastic geomembrane on both edges and
method must be water-pressure tight (see 5.2.5). The
connection must be so firm that it is impossible to
subsequently remove the partitioning joint tape from
5.2.1 General
the plastic geomembrane.
(1) A sealing support must be provided as a
(3) If large-scale movements are expected around
separate layer (see Section 1).
the block joint when waterproofing against
(2) The plastic geomembranes must be laid loose unpressurised water, the use of a partitioning joint
and welded to an entire area. tape as per Figure 5.5.3 must be reviewed.
(3) With all-round waterproofing against pressurised (4) In the ridge area, all interspaces between studs
water a bulkhead must be provided on each block must be vented (Figure 5.5.4, Figure 5.5.5 and
joint. To do this, joint tapes running all the way Figure 5.5.6, element 1 in each case).
around the plastic geomembrane (partitioning joint
(5) To prevent an airlock when concreting between
tape) must be welded and set in concrete in the
the plastic geomembrane and the partitioning joint
inner shell.
tape, an opening must be made in the partitioning
joint tape (Figure 5.5.4, Figure 5.5.5 and Figure
5.5.6, element 2 in each case).
5.2.2 Installation of protective layer
(6) If movements in excess of 5mm are expected
(1) The geotextile must be fastened with suitable
between the blocks, special measures must be
fastening elements or aids.
taken around the block joint (e.g. padding).
(2) The membranes must overlap by at least 10cm.
5.2.5 Joining technique
5.2.3 Installation of plastic geomembranes
(1) The seams between plastic geomembranes and
(1) The plastic geomembranes must be fastened the seams between the plastic geomembrane and
using fastening elements so that they are subject to the profile strip must meet the requirements of
as little load as possible when the inner shell is DVS 2225-5. The joint seams between the plastic
being concreted and so that wrinkling is avoided. geomembranes must be executed with welding
machines (heat-welding). The seams between the
(2) Insufficiently attached fastening elements must
plastic geomembrane and the profile strip must be
be removed and replaced before welding the plastic
executed either with hand-held welders or with
geomembrane.
welding machines.
(3) The following minimum requirements must be
(2) The individual plastic geomembranes must
met for the number of fastening points:
overlap by at least 8cm. Connections to the loosely
– Base: 1 pcs/m2, laid plastic geomembrane must be executed as an
overlap seam with test channel.
– Side walls: 2 pcs/m2 and
(3) With T-joints, the last welded seam must be
– Ridges: 3 pcs/m2.
continuously testable.
(4) The plastic geomembrane must not be driven
(4) Cross joints are not permitted.
over before a protective layer is installed in the
base (see 5.2.8). (5) The width of individual seams on an overlap
seam with test channel must be at least 15mm.
(6) The test channel on the welding seam for
connecting two plastic geomembranes must be

Version: 2017/05 17
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
between 10 and 20mm wide, depending on the 5.2.9 Laying aids
material.
Laying aids (scaffolding, laying carriages, etc.) must
(7) The sealing of overlap seams with test channel be designed so that they do not damage the plastic
must be tested with pressurised air as per DVS geomembranes.
2225-5.
(8) If at individual points such as recesses or cuts 6 Quality assurance
the welding seam between the plastic
geomembranes cannot be formed as an overlap
seam with test channel, an overlap seam without 6.1 Evidence required before starting
test channel at least 30mm wide (full seam) created waterproofing work
with a hand-held welder is permissible. Sealing
(1) The contractor must submit the following
must be demonstrated by vacuum testing as per
product certifications to the client in good time (no
DVS 2225-5.
later than 4 months) before starting waterproofing
(9) Adhesive joints and swell welding are not work:
permissible.
a) For standardised European products, i.e. plastic
(10) Welding seam connections of loosely laid geomembranes and geotextile or geotextile-
plastic geomembranes are not permitted without related protective and drainage layers:
special measures at ambient temperatures below
− CE documents
5°C and relative humidity over 80%.
(11) Butt joints of profile strips must be executed − Test reports with the results of initial
with a heater bar with guide mechanism. After inspection of incoming goods as per the
jointing the butt seam, the weld bead that forms technical delivery conditions and technical
must be carefully removed. The maximum test specifications for plastic geomembranes
permissible offset between stop anchor axes is and associated profile strips and the
2mm. technical delivery conditions and technical
test specifications for protective and
(12) The ambient and welding conditions must be drainage layers of geosynthetic materials or
documented during execution. test reports for valid suitability testing and
valid external production control (FÜ-P) and
5.2.6 Re-injection in the block joint a valid certificate of conformity as per the
technical delivery conditions and technical
Scheduled re-injection when executing the inner
test specifications for plastic geomembranes
shell must be carried out as per Section 1.
and associated profile strips and the
technical delivery conditions and technical
5.2.7 Re-sealing work test specifications for protective and
drainage layers of geosynthetic materials.
(1) During re-sealing work to remove leaks in
pressure-retaining waterproofing, a testing and b) For products not standardised in Europe, i.e.
injection system must be provided around the block profile strips, plastic protective strips and
joints (see 4.4.4). The testing and injection system drainage layers not classified under geotextiles.:
may only be used after approval by the client. − Test reports for valid suitability testing and,
(2) Any necessary re-sealing grouting or injection for profile strips, valid external production
work must be executed as per Part 3 Section 5. control as per the technical delivery
conditions and technical test specifications
5.2.8 Installing the protective layer in the base for plastic geomembranes and associated
profile strips and the technical delivery
(1) A protective layer must be installed and
conditions and technical test specifications
subsequent work conducted to avoid the
for protective and drainage layers of
penetration of foreign matter and concrete in the
geosynthetic materials
protective layer and the plastic geomembrane.
(2) The protective layer must be secured against (2) The contractor must also submit the execution
displacement during the construction stage. schedule and the QS plan.
(3) The contractor may not start waterproofing work
until after the client has given its approval.

18 Version: 2017/05
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
6.2 Internal quality control of defined in the Construction Tendering and Contract
construction work by the Regulations.
contractor
6.2.2 Inspections of incoming goods
6.2.1 General
(1) The contractor must have the necessary
(1) Work must be subject to ongoing internal quality inspections of incoming goods carried out by an
control. accredited independent conformity assessment
body. The competence of the conformity
(2) On delivery, the contractor must identify
assessment body shall be determined in
products in respect of the product characteristics
accordance with the Additional Technical Contract
and documentation set out in the technical delivery
Conditions and Guidelines for Civil Engineering
conditions and technical test specifications for
Works, Part 1, Section 1, Table A 1.1.1, line 1.
plastic geomembranes and associated profile strips
and the technical delivery conditions and technical (2) Samples for inspections of incoming goods shall
test specifications for protective and drainage be taken on the contractor’s initiative by the person
layers of geosynthetic materials and check that they responsible for supervising the construction of the
are in order. plastic geomembrane waterproofing system (see
6.3) or by the local construction supervision body.
(3) Certificates of conformity must be checked as
Sampling is done upon delivery at the building site
appropriate during waterproofing work using the
or alternatively at the manufacturing plant from the
reports on the valid external production control or
batch ready for delivery.
during inspections of incoming goods for each
delivery. (3) The contractor must submit the test reports on
the inspection of incoming goods to the client and
(4) All documents required under 6.4 as well as the
release the client’s products for installation.
technical delivery conditions and technical test
specifications for plastic geomembranes and
associated profile strips and the technical delivery 6.3 Client monitoring of the
conditions and technical test specifications for construction of the plastic
protective and drainage layers of geosynthetic geomembrane waterproofing
materials must be submitted to the client. system
(5) The waterproofing laid must be examined to rule In the case of tunnels with highly challenging
out the occurrence of any wrinkles when concreting waterproofing characteristics, e.g. tunnels with all-
the inner shell or overfilling using the cut and cover round pressure-retaining waterproofing subject to
construction method. The contractor must conduct water pressure of over 10 mWC, special
the tests, log the results and forward these to the supervision of the waterproofing work must be
client. The client must be informed in advance of carried out by a suitably qualified body. The
the date when the testing is to be carried out. qualification requirements for this body and the
tasks are set out in the recommendations on
(6) Testing the joint seams between plastic
waterproofing systems in tunnel construction (EAG-
geomembranes and between plastic
EDT) issued by DGGT working group 5.1 on
geomembranes and profile strips must be jointly
plastics in geotechnology and hydraulic
conducted and logged by both contractor and
engineering. If it has the relevant qualifications, the
client. DVS 2225-5 applies. The reports shall be
local construction supervision body may also
forwarded to the client.
undertake the independent supervision of
(7) Before and after installing the inner shell waterproofing work.
reinforcement, the waterproofing must be checked
for damage. The contractor must provide the client
6.4 Execution documentation
with report.
Project-related documentation must be forwarded
(8) Injection procedures carried out as scheduled
by the contractor to the client on an ongoing basis
and/or as necessary must be logged and the
as well as in a final document. The documentation
reports forwarded to the client.
must cover at least the following points:
(9) The contractor must ensure that individual
a) Description and explanation of the construction
components are accessible for checking finished
method and schedule for the waterproofing
partial deliveries.
work,
(10) If finished partial deliveries are released to
b) Description of materials, products, installation
allow subsequent partial deliveries such as the
components and building aids used,
inner shell, this does not qualify as acceptance as

Version: 2017/05 19
Additional technical contract conditions and guidelines for civil engineering works – Part 5 Tunnel
construction – Section 5 Waterproofing
c) Data sheets for the waterproofing elements and
description of installation components,
d) Evidence of internal quality control of
construction:
– CE documents,
– Results of suitability testing and external
production control and/or inspections of
incoming goods as per the technical delivery
conditions and technical test specifications
for plastic geomembranes and associated
profile strips and the technical delivery
conditions and technical test specifications
for protective and drainage layers of
geosynthetic materials including test reports
and certificate of conformity,
– As-built laying plan (joint seam plan),
– Results of joint seam testing
– Installation dates or periods and
– Records of grouting procedures, as
scheduled and as necessary, including
subsequent grouting procedures.
e) Results of cross-checks and
f) Photographs of key structural stages.

7 Invoicing and compensation


(1) Sealing supports, plastic geomembranes,
drainage layers and protective layers shall be
invoiced individually according to surface area.
Profile strips shall be invoiced according to length.
(2) The surface area shall be determined by
multiplying the theoretical outer periphery of the
inner shell by the length in the tunnel axis.
Openings, recesses and niches with a surface area
of up to 2.50m² shall be discounted.
(3) Measures and applications used to make the
waterproofing ready to use and functional, e.g.
laying carriages, anchoring tracks, welding tracks
together and/or with the profile strips, and tightness
testing shall not be remunerated separately.
(4) Profile strips and reinforcing strips must be
provided as separate positions in the specifications.
(5) The contractor shall bear the costs of
inspections of incoming goods.

20 Version: 2017/05

You might also like