AEROSPACE TRAINING UNIT

ATR42-500 T1 MAINTENANCE COURSE


OUTLINE
ATA No. LEVEL DURATION
PHASE ‘A’ BK-1 III 30 Hours
General Familiarization………………….. (5Hrs) (ATA-00)
Servicing………………………………….. (4Hrs) (ATA-12)
Electrical Power………………………….. (6Hrs) (ATA-24)
Fire Protection……………………………. (4Hrs) (ATA-26)
Fuel system………………………………..(4Hrs) (ATA-28)

PHASE ‘B’ BK- 2, 3, 4 30 Hours


Pneumatic System…………………….. (2)(5Hrs) (ATA-36) III
Indicating and Recording Sys………… (2)(4Hrs) (ATA-31) III
Lights……………………………………… (2)(3Hrs) (ATA-33) I
Automatic Flt. Control system………… (3)(4Hrs) (ATA-22) I
Communication system ………………… (3)(4Hrs) (ATA-23) I
Navigation System ……………………… (4)(3Hrs) (ATA-34) I

PHASE ‘C’ BK- 5 (36Hrs) III 36 Hours


General Engine introduction…………………………………………. (ATA-70)
Engine Control………………………………………………………… (ATA-70)
Engine Fuel & Control…………………………………………………(ATA-73)
Engine Oil system…………………………………………………… (ATA-79)
Engine Air System……………………………………………………..(ATA-75)
Engine Indicating and Recording System…………………………. (ATA-77)
Engine ignition & Starting System …………………………………. (ATA-74 & 80)

PHASE ‘D’ BK- 6 (24Hrs) III 24 Hours


Propeller Systems……………………………………………………. (ATA-61)

PHASE ‘E’ BK- 7, 8 III 42 Hours


Hydraulic Power………………………......(7)(7Hrs) (ATA-29)
Landing Gear Systems. ………………….(7)(14Hrs) (ATA-32)
Flight Control Systems ………………… (8)(14Hrs) (ATA-27)

PHASE ‘F’ BK- 9, 10 III 48 Hours


Equipment and Furnishing……………….(9) (5Hrs) (ATA-25)
Ice and Rain Protection…………………..(9)(5Hrs) (ATA-30)
Oxygen system…………………………… (9)(5Hrs) (ATA-35)
Water and Waste System……………….. (9)(4Hrs) (ATA-38)
Airconditioning & Pressurization ………..(10)(8+5Hrs) (ATA-21)
Structure …………………………………..(10)(5Hrs) (ATA 50)
Doors……………………………………….(10)(4Hrs) (ATA-52)

Courtesy: A.H. Saidi


-------------------------------------------------------------------------------------------