Professional Documents
Culture Documents
8
BENCHMARKING PREPROJECT PLANNING EFFORT
ficient strategic information with which owners can ad- and operations manager were collected through tele-
dress risk and decide to commit resources to maximize phone interviews.
the chance for a successful project. It occurs after busi-
ness planning, where the project idea is initiated, and Project Sample
prior to project execution, where detailed plans, speci- After identification of the data sources and data-col-
fications, and other project specific data are outputs lection method, the data-collection effort began. Com-
(Gibson et al. 1995). panies participating in the study nominated projects that
The initial phase of the study required modeling the met the following requirements:
process. This step was accomplished by a research team
under the guidance of the Construction Industry Institute • Industrial construction projects in North America
(CII), Austin, Tex. The specific research team charged • Projects that exceeded $5,000,000 in final cost
with modeling the preproject-planning process consisted • Projects that had been completed for at least 2
of approximately 16 industry personnel, split among years
owner and contractor personnel, along with an academic
researcher.
Major Low
The resulting model is composed of four major sub- Influence Influence
processes (see Fig. 2). Each subprocess is further defined
by the functions that occur during the subprocess (' 'Pre- High Large E
x
project" 1995): n p
f e
I n
u d
1. Organize for preproject planning. The functions e
include selecting the project team, drafting the charter, n
c u
and preparing the preproject planning plan. e Low Small r
2. Select project alternatives. The functions include lier(orm Perform Execute Operate e
usmess Pre-project Project Facility 5
analyzing the technology, evaluating sites, preparing Planning Planning
scopes and estimates, and evaluating alternative(s). FIG. 1. Influence and Expenditures Curve for Project Life
3. Develop a project definition package. The func- Cycle
tions include analyzing the risks associated with the
project, documenting the project scope and its design,
defining the project's execution approach, establishing
project-control guidelines, and compiling the project
definition package.
4. Decide whether to proceed with the project.
Variable Weights
To refine the index further and take into consideration TABLE 3. Variable Measures
the responses by the project representatives, weights
were established for the index variables. The weights Measure
were derived from one open-ended question proposed to Source Historical data- Interviews-
variables objective subjective
the interviewees to identify important catagories of
(1 ) (2) (3)
preproject-planning effort. The question was: "What are
(a) Organization
your main reasons for your assessment of the level of
effort expended on preproject planning?" (Gibson et al. What organizations Corporate group
1994). Through qualitative analysis of individual re- were represented
How many Number
sponses, variable weights were established and the pre- organizations
project planning index was derived. Applying the How did individuals Team cooperation
weights to the corresponding variables resulted in the work together
following formula for a preproject-planning index value Duration of the plan- Months per million
(Gibson and Hamilton 1994): ning effort
Was there team Turnover ratio Change of personnel
Preproject Planning Index Value = 0.45 continuity
Were there team skills Skills present
. [(groups represented on preproject-planning team Was there team building Techniques used
How money was spent Percent of budget
+ preproject-planning plan)n] + 0.10 Did the team have a Yes/no
charter
. (written charter) + 0.45· [(percent design complete Was a plan developed Yes/no
+ control guidelines developed + execution plan developed)/3] (1) Corporate guidelines Quality
clearly given
The writers calculated index values for all projects. (b) Alternative Selection
Subsequently, the values were divided into equal ranges Alternative technologies Yes/no Thorough evaluation
that established preproject-planning groups: upper third, analyzed
middle third, and lower third. Analysis of the three Technologies considered Number considered
groups and their final performance in terms of project Were alternative sites Yes/no Thorough evaluation
control (cost, schedule, and scope changes) and project analyzed
How many sites were Number considered
operational characteristics (plant use and design capac- considered
ity) was conducted. These areas were examined because Conceptual scopes and Prepared sufficiently
they are significant measures of project success. The re- estimates
sults revealed that the level of preproject planning per- Was the evaluation Formal method used
formed has a statistically significant effect on the ulti- formal
Corporate goals Clear communication
mate success of the project. Additionally, the overall communicated
business success (e.g., return on investment and return
(c) Project-Definition Package
on equality) of the three groups was examined.
Risks identified and Yes/no Adequate
assessed identification
Preproject-Planning Groups' Business Success Design complete at Percent design effort
Table 6 provides a summary of the overall business authorization at authorization
success of the project by preproject-planning groups. Execution approach Yes/no Well defined
The table provides information for each group according defined
to whether the percentage of projects within that group Control guidelines Yes/no Well defined
established
exceeded, met, or fell short of its financial goals. Mea- Was a definition pack- Yes/no
sures of financial goals include internal rate of return, age compiled
return on investment, return on equity, and cash flow rate Scope definition Well defined
of return. As indicated, when the level of preproject appropriate
planning increases, so does the likelihood that the project Was there an emphasis Emphasized
on quality
will meet or exceed its financial goals. For example,
JOURNAL OF MANAGEMENT IN ENGINEERING / MARCH/APRIL 1996/28
mation about the distribution of values. Used in this sec- during preproject planning had a definite effect on the
tion, they will display summary information comparing cost performance. In a comparison of the group average,
the three preproject-planning index groups with the proj- projects within the lower third group had significantly
ect success measures of cost performance, schedule per- higher overruns than those in the middle and upper-third
formance, design capacity attained, plant use, and scope
changes. TABLE 7. Performance by Preproject Planning Groups
The box plot displays summary statistics for the dis- Standard
tribution of the actual values obtained from the project Average deviation Median
questionnaire. It plots the median, the 25th percentile, Preproject planning group (%) (%) (%)
the 75th percentile, and the range. The lower boundary (1) (2) (3) (4)
(a) Cost Performance
TABLE 4. Frequency Distribution: Groups Represented on Upper third -4 7 -3
Preproject-Planning Team" Middle third -2 10 I
Value Frequency Percent Cumulative percent Lower third 16 45 2
(1 ) (2) (3) (4) (b) Schedule Performance
2.00 2 3.2 3.2 Upper third -13 17 -11
3.00 4 6.5 9.7 Middle third 8 24 8
4.00 3 4.8 14.5 Lower third 26 44 23
5.00 I 1.6 16.1
(c) Percent Design Capacity Attainment
6.00 12 19.4 35.5
7.00 6 9.7 45.2 Upper third 102 20 100
8.00 7 11.3 56.6 Middle third 93 16 100
9.00 4 6.5 62.9 Lower third 87 20 95
10.00 2 3.2 66.1 (d) Percent Use
11.00 6 9.7 75.8
12.00 4 6.5 82.3 Upper third 103 19 100
13.00 3 4.8 87.1 Middle third 94 15 100
14.00 I 1.6 88.7 Lower third 85 20 95
15.00 2 3.2 91.9
16.00 2 3.2 95.2
17.00 I 1.6 96.8 lOa
19.00 I 1.6 98.4 c
o
26.00 1 1.6 100.0 s
t
"Median = 8.00; mean = 9.00. 50
p
e
r
TABLE 5. Reclassification of Data f
o
r
Percentile Value range Recoded value m a
(1) (2) (3) a
n
80-100 12-26 5 c
e
60-80
40-60
9-11
7-8
4
3
-50 L-_ _---......- ----_-----J
Lower Third Middle Third Upper Third
20-40 6 2
0-20 2-5 1 Pre-Project Planning Group
FIG. 5. Cost Performance by Preproject-Planning Groups
TABLE 6. Financial Performance versus Authorization
Goals by Groups TABLE 8. Summary Statistics for Cost Performance
Percent Deviation from Authorization
Exceeded or met Fell short
Group (%) (%) Group 25th percentile Mean 75th percentile
(1 ) (2) (3) (1) (2) (3) (4)
Upper third 82 18 Lower third -5.00 15.80 21.25
Middle third 72 28 Middle third -9.50 1.50 5.75
Lower third 66 34 Upper third -9.00 -3.00 -0.50
140
Pre-Project Planning Group U
~ 120
1
FIG. 6. Schedule Performance by Groups I
i 100
z
TABLE 9. Summary Statistics for Schedule Performance a 80
t
Percent Deviation from Authorization i
o 60
Group 25th percentile Mean 75th percentile n
40
(1 ) (2) (3) (4)
Lower third 3.00 26.00 42.50 2()1----_-----_-----t-------'
Lower Third Middle Third Upper Third
Middle third 0.00 16.66 29.00
Pre-Project Planning Group
Upper third -21.00 -21.00 0.00
FIG. 8. Plant Utilization by Preproject-Planning Group
200r----------------------,
D equipment and mechanical and electrical systems. De-
e scriptives of the relationship with preproject-planning
s
i group are given in Fig. 7 and Table lO. The highest value
g
n attained in the lower-third group was lOO%. All other
C 100
values were below their planned design capacity. Con-
a versely, most values in the middle group appear to be at
p
a lOO%. For the upper-third group, 50% of the projects
c were operating between lOO% and 118% at 6 months of
i
t operation.
Y
OL-----t--------I-----oof------'
Upper Third Middle Third Upper Third Plant Utilization
Pre-Project Planning Groups Results of plant utilization were similar to those of
FIG. 7. Design Capacity by Preproject·Pianning Groups design capacity attained and are shown in Fig. 8. Plant
utilization is defined as the percentage of days in a year
groups. Fifty percent of the projects in the upper-third the plant actually produces product. Fifty percent of the
level of efforts had final costs under their authorization projects in the lower-third group were operating at or
budget. The middle-third group also shows better cost below their planned use after 6 months of operation. As
performance than the lower-third group. the level of preproject planning increased, so did the
plant-utilization rate. As with design capacity, the mid-
Schedule Performance dle-third group had values clustered around lOO% and
Schedule performance, as measured in percentage de- those in the upper-third group were operating at 100%
viation from the authorization schedule, was also signif- or above. Table 11 presents the summary statistics.
icantly affected by levels of preproject planning. Fig. 6
and Table 9 reveal this relationship. Once again, 50% of Scope Changes
the projects in the upper-third group came in at or below Good preproject-planning practices should result in a
the authorization schedule. The results change acutely as well-defined project scope and therefore should mini-
the level of planning dropped. The 50-percentile range mize the number of unanticipated scope changes a proj-
for the lower-third group ranged from 3.0% to 42.5% ect experiences. While this is true in theory, the sample
over schedule. Half of the values in the middle-third projects were studied to see if case studies proved it to
group were at or over their timetable for completion. be true in reality. Scope changes, measured in percentage
of actual final project cost, were explored to determine
Design Capacity Attained whether projects scoping lower on the preproject-plan-
One plant operating characteristic measured was the ning effort index had more scope changes than projects
design capacity attained after 6 months of operation. De- with higher index values.
sign capacity refers to the nominal output rate of the The analysis revealed that while the middle third and
facility that is used during engineering and design to size upper third groups had similar results of scope changes
JOURNAL OF MANAGEMENT IN ENGINEERING / MARCH/APRIL 1996 / 31
percentage design complete at authorization. As Fig. 10 as a formal, well-organized business process with spe-
shows, cost performance variation decreases as the per- cific deliverables. It can be benchmarked by combining
centage design complete increases. In other words, by specific variables measures to form a preproject-planning
doing more design before project authorization, one can index.
Analysis of the sample in this research investigation
TABLE 11. Summary Statistics for Plant Use
leads to some broad conclusions. The preproject-plan-
Percent Attainment at Six Months ning-effort level directly affects the cost and schedule
Group 25th percentile Mean 75th percentile performance of a project. Cost performance versus au-
(1 ) (2) (3) (4) thorization estimate increased by 20% on average and
Lower third 65.25 85.57 100.00 schedule performance versus authorization estimate in-
Middle third 94.60 98.00 100.00 creased by 39% on average for the more highly planned
Upper third 100.00 103.03 109.44
projects versus lower planned ones. Comparing the same
groups, design capacity attainment and use improved by
P 50 about 15% on average versus authorization estimate.
e Stated another way, the sample projects were much more
r
c 40 predictable in terms of cost, schedule, utilization, and
e attainment with a higher level of preproject-planning
n 30
t effort.
0 20 The likelihood that a project will meet or exceed its
f financial goals increases as the level of effort preproject
A 10 planning increases. Finally, on average, project scope
c changes after authorization tend to decrease as the level
t 0
u of preproject-planning effort increases. Although these
a results are specific to this sample, the authors believe
I Lower Third Middle Third Upper Third them to be true for the rest of the industry as well.
Pre-Project Planning Group
FIG. 9. Scope Changes by PreproJect-Plannlng Groups
RECOMMENDATIONS
The challenge to the construction industry is to inte-
TABLE 12. Summary Statistics for Scope Changes grate this benchmarking effort into practice by recogniz-
Percent of Final Cost ing the best practices that have been identified. Realistic
Group 25th percentile Mean 75th percentile goals must be established to make sure that these prac-
(1 ) (2) (3) (4) tices are integrated into company procedures. Once in-
Lower third 1.62 11.07 15.73 tegration is complete, the final benchmarking perfor-
Middle third 0.00 2.16 3.79 mance area-action-can begin. Progress must be
Upper third 0.42 2.87 3.99 monitored and operations recalibrated to pursue contin-
ual improvement.
In specific, recommendations that can be made from
C
o 45 the findings of this study fall into two basic areas: or-
~ 40 • • ganizing for preproject planning and having a well-de-
35
fined project scope.
~ 30
r 25 To organize for preproject planning
g 20
•
I I
I
-•...
r 15
r;; I The preproject-planning team should be working
10 ". I
n
~
5
0
•I .1 ". I
• I
with a written charter.
The preproject-planning process should have a pre-
o 5 10 15 20 25 30 35 40 45 project-planning plan.
Percent Design Complete I The more corporate groups with varied interests
FIG. 10. Cost Performance Ratio to Amount of Design providing input during the preproject-planning
Done Prior to Authorization phase the better.
32/ JOURNAL OF MANAGEMENT IN ENGINEERING / MARCH/APRIL 1996