RISK MANAGEMENT

Risk Probabilit Severity Risk Score Mitigation


y (P) (S) (PxS)
1 = low 1 = low
5 = high 5 = high
Loss of internet 1 5 5 System will use formulas and
connection leads to algorithm so that student can
loss of student’s resume the exam where left
data while student without losing their data.
is attempting paper
Loss of valuable 3 5 15 Transmit data to cloud after every
data by accident update to the project.
Failure of webcam 3 3 9 Use of multiple cameras to
mitigate the risk.
Misuse or illegal 2 3 6 End to end encryption so that no
use of data can one will be able to mishandle it.
harm student
privacy
Failure to meet 3 3 9 Use of Gantt chart for scheduling
deadlines time and setup milestones ahead
of the final due date