Professional Documents
Culture Documents
Well Background constraint was a driving factor in determining the value of the
The GB783-2 well was drilled in 2000 as a directional pre-completion/DST information. Previous developments
appraisal well and two geologic sidetracks (ST) were drilled have shown a “learning curve effect” which required changes
below the 9-5/8 inch drilling liner; the second ST obtained a in the completion design of subsequent wells to optimize well
whole core. The 9-5/8 inch drilling liner in the original well productivity. The objective of the pre-completion/DST was to
was suspected of having casing wear from previous operations identify these design changes and/or reservoir issues in
and did not have sufficient clearance to run the desired size 8- advance and thus allow sufficient time to determine an
1/16 inch production liner. effective solution to overcome these issues for the “batch”
completion/DST ahead of the batch completions improved the ensure the necessary equipment was supplied from the DST
economics of the field development. contractors.
Based on the outcome of the value of information exercise, the The design of the equipment for the pre-completion/DST
pre-completion/DST of the GB 783 A2ST3BP1 well was involved both temporary and permanent equipment that would
recommended to and then approved by the operator’s be placed in the well. The downhole completion would be
management team. The drilling schedule for the development utilized to provide access to the reservoir and prevent sand
wells was then prepared to ensure conclusion of the GB 783 production both during the DST and ultimately later while
Another key issue that involved significant planning was oil Contingency planning is required for operational problems
spill response. Due to the nature of producing the oil to the that may occur during deepwater DST and clean-up
drilling rig and then transferring it to the storage barge, three operations, regardless of whether a DP or moored rig is used.
parties were involved in oil spill response. The drilling Performing deepwater well testing in DP mode requires
contractor was responsible for spill response due to spills from additional contingency plans to allow time to disconnect and
the rig, the storage barge for spills from the barge, and the secure the well in case of an emergency.
operator had overall responsibility as leaseholder from the
government. An Oil Transfer Bridging Document was The restrictions inherent to hydraulic control systems as a
Performing well testing in a DP mode has a unique risk due to Green zone – normal operating status:
situations which could cause the rig to move away in an A safe working envelope between 0 – 50 feet rig offset
uncontrolled manner from it’s desired position. The (<0.61° LFJA). The DP system is operating normally with the
conditions causing a position loss can be listed as follows: back-up system available.
• Drift off: due to power loss (generators and thrusters) Blue zone – degraded operational status:
• Drive off: due to thruster’s control or reference error. Rig offset between 51 – 70 feet and/or LFJA exceeding 0.61°.
This is an advisory area indicating that disconnect limitations
• Fire onboard A double-hulled barge was moored to the rig to store the fluids
• Secure well prior to upcoming adverse weather produced during the DST. The bow of the barge was moored
• Leak between SSTT and Surface Flow Tree to the port side of the Ensco 7500 rig using the hawser method
• Leak below SSTT (see Figures 5 and 6). The hawser method uses a tugboat to
maintain the barge in position away from the rig by
• Oil export and storage operational problems (loss of barge
positioning) connecting the hawser tugboat’s tow cable to the stern of the
barge and engaging its clutch to a sufficient level of power to
maintain barge position.
Some of the above conditions were covered with the standard
rig emergency preparedness procedures already in place on the
In the event of a drive-off or drift-off situation, it was
Ensco 7500 for drilling operations. However, specific
recognized that the barge would be able to maintain position
emergency preparedness procedures were required for the well
testing and oil export operations. relative to the Ensco 7500 using the hawser method. The
contingency plan for barge positioning problems or fire related
problems in or on the fluid export package was the inclusion
The emergency disconnect sequence was designed to be
of a rapid response mooring and oil export hose disconnection
initiated at the driller's panel, following direct communication
system. This quick disconnect system was installed on both
from the DP operator via audible and visual alarms which
the rig and barge ends of the mooring and oil export lines. It
warned personnel of the situation. The SSTT control system
was recognized that prematurely disconnecting the barge in
was not interfaced with the rig’s BOP disconnect system.
the event of a DP vessel excursion could create additional
Only reliable and well-proven equipment and technologies
should be used in well control systems. The BOP and SSTT hazards than if the barge remained attached to the rig. Any
situation or condition that would require an emergency barge
control systems were kept independent of each other with
and rig disconnection would be dealt with under the
procedures in place to ensure a coordinated emergency
response. instruction of the persons in charge of the export operation.
The type of valve selected was the Formation Isolation Valve seal assembly, PBR assembly, quick-latch mandrel, and the
(FIV). The FIV is an isolation ball valve which was well test seal assembly. The PBR/seal assembly was shear
positioned below the circulating housing in the gravel-pack pinned in the “stroked-out” position while running in the hole.
assembly. The valve is opened and closed by a mechanical
shifting tool. The shifting tool was run on the end of the This assembly was run below the DST string assembly, which
washpipe during the frac-packing operations and closed the contained the downhole test tools, subsea test tree, and surface
FIV during the retrieval of the service tool. The function of flow tree. A shifting tool on the bottom of the DST string was
the FIV was to eliminate fluid losses after the frac-pack, utilized to shift open the formation isolation valve to regain
Traditional subsea DST operations generally require a space- The actual DST string installation was accomplished
out (pipe trip) to determine the correct space-out of the DST successfully without any space-out runs. The lower
equipment inside the wellbore. A space-out run can be time completion interface was installed within 1.5 ft of the
consuming and costly in deepwater applications. There are calculated depth and the subsea fluted hanger and ram closure
three components that need to be accurately spaced-out to points were within ¼ inch of calculated depths. Overall, this
function properly: the completion interface equipment, the method was very successful in saving two round trips to the
SSTT, and the surface flow tree. The completion interface subsea wellhead.
equipment must provide access to the lower completion. The
SSTT must be positioned properly inside the subsea BOP The FIV was utilized to isolate the lower completion from the
stack to allow the pipe rams to close against the slick joint and wellbore after the DST string was retrieved and the well was
shear rams shear across the shear joint. Additionally, the temporarily abandoned. This eliminated the need for any
surface flow tree must be spaced-out correctly to provide the LCM pills and left the well in position upon re-entry to be
proper stick-up above the rig floor. Spacing out all three flowed back to the TLP with the completion already “cleaned-
components in a single trip without a space-out run is up”.
challenging, but it can be performed successfully with proper
planning and measurements. Data Acquisition
The DST was conducted with real-time surface data acquistion
A sealbore receptacle / seal assembly configuration was only. The surface process facility parameters were recorded
designed to interface the DST string with the lower and analyzed with a proprietary system that allowed real time
completion equipment. This design allowed landing of the monitoring of well and process performance. The surface data
DST string without performing a space-out run. A polish bore acquisition package is a PC based data management system
receptacle (PBR) / seal assembly was run on the bottom of the designed for use on DST’s or well clean-up operations. The
DST string and latched into the GP packer assembly (lower system recorded data from multiple dedicated pressure,
completion). The configuration, shown in Figure 7, consisted temperature and flow rate sensors throughout the welltest
of an inner string w/ FIV shifting tool on bottom, anchor latch package. This allowed the test engineer to simultaneously
8 SPE 90557
perform multiple operations on the data, both real-time and generator were placed on the starboard side pipe rack. The
historic. port side pipe rack was used to store the various completion
hardware components and transportation baskets. The large
A real-time surface readout (SRO) system of downhole storage space of the rig helped to minimize movement of
pressure and temperature data was evaluated for use during the equipment and allowed placing and hooking up equipment off
DST. The SRO system utilized acoustic signals to transmit the critical path. Figure 9 shows the layout of the rig with the
information up the workstring from the bottom hole separation and storage equipment placed on the rig.
transmitter through repeater subs located in the workstring to a
Live fluid samples (2 x 600 cc) were required to be collected While the Ensco 7500 had large deck areas, the process
from the well via sampling chambers run on slickline. The equipment and 3 x 500 bbl storage tanks filled both riser
samples were desired to validate previously collected MDT decks. Computer aided drawings of the layout on the rig were
wireline sample properties associated with flow assurance developed and discussed with rig personnel prior to the
predictions related to asphaltenes and wax/paraffin deposition. CWOP’s. The piping between the different vessels in the
The sampling program was based upon retrieving the samples process area made it difficult to walk between the different
above the asphaltene flocculation pressure estimated to be components. A late modification to the hook up identified on
~7000 psia. The sampler activation timer was set to open 4 the rig was to place grating above the piping as a walkway to
hours after the sampling chambers reached the downhole allow easy access and minimize trip hazards. Additional
target depth. Upon retrieval, the pressure compensated lighting was also used in the process area to better illuminate
chambers were reconditioned at reservoir temperature for 24 the gauges and sensors as well as allow quicker detection of
hours prior to transfer into the pressure compensated shipment any leaks if they would develop.
vessels at 1000 psia over reservoir pressure.
The system was designed to process a maximum rate of
Surface Facility Design 10,000 bpd. The system included methanol injection at the
The Ensco 7500, a 5th generation semi-submersible, contained subsea test tree to prevent hydrate occurances during any
four large storage areas that were utilized to position the well planned or un-planned shut-ins. Process and instrument
testing equipment. The rig had two large, 50 ft x 90 ft riser drawings were also developed and reviewed with operator
decks in addition to two 50 ft x 110 ft pipe decks. The oil and facility personnel to ensure proper instrumentation was
gas separation equipment was placed on the starboard side included in the system.
riser deck and temporary storage tanks were placed on the port
side riser deck with a capacity of 1500 bbls. The subsea test Barge / Mooring System
tree control spools, control cabin, methanol tanks, and steam MMS regulations for well testing in the Gulf of Mexico
SPE 90557 9
prohibit the burning of produced liquids and only allow the initial hydrocarbons to reach the rig at night was primarily due
flaring of gas with approval of a flare permit. The welltest to the risk of separation equipment upsets. These upsets could
operation was challenged with designing a process system that result in oil carryover to the burner boom which might not be
could export the produced liquids to an ocean-going barge visually detected and cause an oil spill or sheen.
moored to a DP semi-submersible rig.
The well testing operations began by displacing the workstring
The barge vendor worked closely with the Magnolia team to with an underbalanced fluid to unload the well. This provided
ensure that any issues with mooring the barge and storing of ~1500 psi underbalance to the formation. The well was ready
A USCG approved oil transfer hose with a quick release The system was again cleaned and an additional surge tank
system was selected to transfer liquids from the rig to the was installed downstream on the low-pressure separator to
barge. Both ends of the transfer hose were equipped with a serve as a slug catcher. The system now included a “slug
dual barrier shut-off system. Additionally, the hose was fitted catcher” downstream of both the LP separator and surge tank.
with external buoyancy to prevent damage to the DP thrusters The well was opened for the third time at 1730 hours on June
in the event of a quick disconnect. The barge vendor prepared 20th. The well was opened to a maximum choke setting of
a Magnolia specific barge mooring operations procedure as 24/64 inch and flowed at an average stabilized rate of 3700
well as their RCP (Responsible Carrier Program). BOPD. The well was temporarily choked back and
subsequently shut-in again after 6 hours of flow due to the
The well test flow back package was designed with three transfer pumps at the surge tank not working properly. The
stages of separation to optimize gas break-out. The separation transfer pumps were repaired and the well was brought back
design was based upon delivering oil to the storage barge with online at 0350 hours on June 21st. The wellbore again was
a Reid vapor pressure < 12 psi. The produced liquids were ramped to a maximum choke setting of 32/64 inch and
directed from the welltest area to dedicated oil transfer storage produced at a constant rate of 7200 BOPD for 5 hours. The
tanks. The fluid was then transferred to the oil storage barge well was shut-in again due to high oil storage tank levels. An
via high rate transfer pumps. evaluation of the actual flow rates and flow periods indicated
that the majority of the well test objectives had been
DST Execution accomplished and the well flow testing was then considered
The issue of when to open the well was an item discussed complete. The wellbore remained shut-in downhole for an
between the operator, the drilling contractor, and the welltest additional 33.5 hours to obtain pressure transient data.
company. There were no written policies within these Concurrent with the downhole shut-in, fluid samplers were run
companies governing when the well could be unloaded, on slickline inside the DST string to recover pressurized
although there was a historical unwritten rule of opening only samples of the “live” oil located immediately above the tester
during daylight hours. After discussing the issue between the valve. The samples were successfully recovered at a pressure
parties and the operator’s management team, it was decided to above both the saturation pressure and asphaltene flocculation
open the well so that the initial flow of hydrocarbons would pressure.
arrive at surface during daylight hours. Since the test string
was full of completion brine, this allowed opening the well Overall, three unplanned shut-ins were performed on the well
several hours prior to dawn but also prevented initially during the well testing period, two of which were related to
opening the well late in the day. The decision not to allow liquid carry-over to the gas flare. Both carry-over volumes
10 SPE 90557
were extremely small, however, these carry-over events • Increase the NPSHa by ensuring the suction line is air-
required the unplanned shut-in of the well and subsequent tight (sight glasses not fitted to the suction line)
cleaning of the flare lines. Post-event analysis determined that • Utilize a high volume double acting diaphram pump
the primary cause of the liquid carry-over events was related instead of a centrifugal pump, if possible.
to operating the separator liquid level too high when foaming
conditions were present. The processed fluid temperature and Prior to disassembling the surface facilities, the equipment and
low vessel operating pressure were favorable to create foam, lines were flushed with water to remove any hydrocarbons and
which pushed some liquid hydrocarbons into the gas line, prevent potential spills. The fluids in the separators and surge
permeability will affect the overall development plan for the DST portion of the project to ensure proper attention to detail.
field and completion designs. Also, reservoir boundaries were Advance planning meetings with the regulatory agencies as
identified by the pressure transient data which support the well as multiple CWOP sessions with rig and third party
geological model. Again, this information will affect the service personnel helped to improve the planning process.
overall development plan. Experienced facility engineers and operators should review the
proposed surface facility layout to help identify potential
The completion itself performed exceptionally well and there problems.
were no issues related to sand production. The gravel
Well testing from a DP vessel in a deepwater environment can 2. Schuberth, P.C.; Garcia, E. M; Walker, M.W. and Akers, T.J.;
be performed safely and efficiently given sufficient planning “Key Initiatives Improve Production Testing Performance,
Deepwater West Africa”, SPE 79813, presented at the 2003
time. A person should be devoted full time to planning the
12 SPE 90557
Magnolia
Magnolia
GB 783 - A2 ST3
Temporary Abandonment Sketch - Final
RHOB_Density
A2st3bp1 Completion Interval 1.65 2.65
NPOR_Neutron
0.6 0
16000
18600
18700 16100
18800 16200
0.0ft - 0.26ft
Rig Offset
AFT Mooring
Well Test Area
Hawser Tug
Cenac 24,000bbl Barge
FWD Mooring
FWD
Prevailing Weather
Snap-Latch Assembly
40 ft PBR assembly
Anchor-Latch Assembly
Figure 7 – Lower Completion Interface Equipment Figure 8 – BOP / SSTT Space-Out Schematic
SPE 90557 19
16
Barge Mooring lines Oil Transfer Hose Barge Mooring lines
DST BHA
18
9
9
20 19
19
7
7500
ENSCO
H
1
4
17
14
SSTT LANDING STRING
20 19
19
7
20 19
10
1
STARBOARD RISER DECK 1
4
13 12
FRAC HANGER
FRAC BOAT POSITION
ELECTRIC TRANSFER PUMPS - U-4 B60-B W/40HP ELECTRIC MOTOR @ (STARBOARD)
2150RPM 480 VOLT - 3 PHASE SIZE 3 STARTER
WELL TEST PRSSURISED LAB CABIN - 380-480v 3 phase 50/60hz RIG LAYOUT SHOWING WELL TEST AREA
STEAM GENERATOR 480v 3 phase
DST WORKSHOP 480v 3 phase