You are on page 1of 9

Transportation Geotechnics 8 (2016) 26–34

Contents lists available at ScienceDirect

Transportation Geotechnics
journal homepage: www.elsevier.com/locate/trgeo

Design and construction of the first GRS integrated bridge with


FHR facings in Europe
Stanislav Lenart a,⇑, Matevž Kralj b, Samo Peter Medved b, Jure Šuler c
a
Slovenian National Building and Civil Engineering Institute (ZAG), Dimičeva ulica 12, 1000 Ljubljana, Slovenia
b
Lineal d.o.o., Jezdarska ulica 3, 2000 Maribor, Slovenia
c
University of Ljubljana, Faculty of Civil and Geodetic Engineering, Department of Civil Engineering, Jamova 2, 1000 Ljubljana, Slovenia

a r t i c l e i n f o a b s t r a c t

Article history: The bridge across the Pavlovski potok stream in the village of Žerovinci in northeast
Received 15 July 2015 Slovenia is a part of the investment into the modernisation of the Pragersko–Hodoš railway
Revised 4 July 2016 line, one of the biggest investments in the infrastructure in Slovenia at the moment. Its
Accepted 6 July 2016
design was accompanied by very short deadlines and a deep layer of soft foundation soil.
Available online 15 July 2016
For this reason the reinforced concrete abutments of a nearby railway bridge were founded
on 24 m deep piled foundations. Short deadlines and a limited budget forced the authors of
Keywords:
this paper to find an alternative solution. Deep piled foundations were replaced by shallow
Reinforced soil
Geosynthetics
foundations made of compacted fill material reinforced with geosynthetics. The bridge was
GRS integrated bridge completed by the end of 2014. From the results of previous laboratory tests that were
Deformation obtained within the scope of the EU co-funded research project ‘‘Research voucher”, the
Compacted fill basic characteristics of the building materials for the geosynthetic reinforced soil (GRS)
bridge abutments, as well as the deformation properties of the typical reinforced soil were
obtained. These data were used for the design of the abutments. The staged construction
procedure of full height rigid (FHR) facings for the GRS retaining walls (RW) was used
for the construction of this GRS integrated bridge. Partial pre-stressing of geogrids and con-
sequently the increased stiffness of the reinforced soil was achieved by following the
staged construction procedure. The bridge system consisted of a cast-in-situ RC slab, which
was placed on top of the GRS immediately behind the FHR facings, i.e. the bridge was con-
structed as a simply-supported slab supported by a pair of GRS abutments, without the use
of bearings. Thus the described bridge across the Pavlovski potok combines two
approaches for GRS integrated bridge design, one of which has been used in Japan
(Tatsuoka et al., 2009), with full structural integration of the deck onto the pair of FHR fac-
ings, other being proposed by the FHWA (Adams et al., 2010), without full integration of
the deck onto the GRS RWs. A system for the monitoring of structure performance was
established in order to ensure optimization of this kind of structure. Data for this GRS inte-
grated bridge, which were obtained during the construction works were compared to sim-
ilar data obtained from the construction of a nearby railway bridge with reinforced
concrete abutments. The comparison provides a good basis for future decisions when
choosing the type of bridge abutments.
Ó 2016 Elsevier Ltd. All rights reserved.

⇑ Corresponding author.
E-mail address: stanislav.lenart@zag.si (S. Lenart).

http://dx.doi.org/10.1016/j.trgeo.2016.07.003
2214-3912/Ó 2016 Elsevier Ltd. All rights reserved.
S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34 27

Introduction

The use of geosynthetic reinforced soil (GRS) technol-


ogy has become common practice in the design of retain-
ing structures and embankments for infrastructure
projects all over the world. This is due to cost savings,
the simple and rapid construction technique, the reduced
construction time, the reduced environmental effects, good
seismic performance, and some other factors. Also, a num-
ber of studies have been conducted over the last two dec-
ades with the aim of investigating the size of the surcharge
load which can be applied to the top of GRS structures, and
the applicability of GRS technology to the construction of Fig. 1. The previously existing bridge before the reconstruction works
bridge supporting structures such as bridge piers and abut- were performed.
ments (Tatsuoka et al., 1997, 2009; Adams et al., 2002; Wu
et al., 2006). Particularly in the case of soft foundation
ground, there are two main reasons to use GRS abutments fully structurally integrated into the top of a pair of full-
instead of traditional piles: (1) to reduce the overall costs height rigid (FHR) facings of GRS walls (described later in
of the project, and (2) to reduce or potentially eliminate this paper). On the other hand, the FHWA (Adams et al.,
the ‘‘bridge bumps” which arises from differential settle- 2010) developed a bridge system in which a single-span
ment between approach embankments and traditionally simply-supported deck is placed, without structural inte-
reinforced-concrete (RC) bridge abutments supported by gration, on top of the GRS, immediately behind the facings.
piles (Helwany et al., 2003). The same reasons were rele- The latter typically consist of modular blocks. The advan-
vant to the design of the new bridge over the Pavlovski tages of the GRS integrated bridge when the deck is fully
potok stream in the village of Žerovinci (in north-eastern structurally integrated onto the top of a pair of FHR facings,
Slovenia), which is presented in this paper. The other two as presented by Tatsuoka et al. (2009), are as follows: (1)
important reasons are: (1) the very short deadlines defined the construction and maintenance of bearings becomes
by the investor for the opening of the bridge for traffic unnecessary, (2) the reinforced-concrete deck becomes
within a period of two months at the end of 2014 (this more slender due to a significant reduction in the bending
included both the design and the construction of the moment resulting from the flexural resistance at the con-
bridge), and (2) a deep layer of soft foundation soil, which nection between the deck and the facing, (3) seismic stabil-
encouraged the authors to propose the use of GRS inte- ity is increased significantly due to the increased structural
grated bridge abutments. integrity and reduced weight of the deck, and (4) due to
Since the Terre Armee patent was first presented to the the greater structural integrity and smaller cross-section
world of geotechnical engineering (Vidal, 1972), the use of of the deck, the bridge’s resistance to tsunami or similar
reinforced soil technology in different applications has water flows during floods is significantly increased. It
undergone continuous worldwide development, including should be noted that the GRS integrated bridge, as pre-
in Europe. The first UK reinforced soil bridge abutments sented by the FHWA, does not benefit from any reduction
were constructed at Carmarthen in 1981 (Brady, 1987), in the mid-span bending moment, which is a feature of
whereas in Germany the first permanent bridge abutments frame-type bridge structures having deck-facing structural
made of geosynthetic reinforced earth were built for the integrity, as proposed by Tatsuoka et al. The FHWA type of
crossing of the River Gera in Arnstadt, in 1996 (Herold, GRS integrated bridge is constructed as a single simply-
2002). On the other hand, the Danish Road Directorate supported deck supported by a pair of abutments, and is
reported in 2013 (DRD, 2014) about the first reinforced soil therefore more appropriate for short span bridges. In any
bridge abutments which were constructed in Denmark on case both systems have been successfully implemented
the Tvaervej Nord northern link road. On this occasion, into practice over the last few years.
numerous advantages were reported regarding the use of
bridge abutments of this kind, and the report states that
GRS bridge abutments will be used in the future without Design of the Bridge across the Pavlovski potok Stream
reservation (DRD, 2014). However, there remain some seri- in Žerovinci
ous problems with GRS bridge abutments as long as bridge
deck bearings are used. Thus, the elimination of such bear- The bridge across the Pavlovski potok stream in the vil-
ings is an important feature of the GRS integrated bridge lage of Žerovinci in north-eastern Slovenia is a part of the
concept. This concept allows integration of the bridge deck investment into the modernisation of the Pragersko–Hodoš
onto the top of the GRS without the use of bearings. railway-line, which is the biggest investment in the infras-
Pioneering work in this field, although with some basic tructure in Slovenia at the moment. In order to maintain
differences, was performed in Japan by Tatsuoka and his roads and the local traffic infrastructure, the Municipality
colleagues (Tatsuoka et al., 2009), and in the USA by the of Ormož decided to invest in the construction of a new
FHWA (Adams et al., 2010). Tatsuoka et al. (2009) sug- bridge on the roadway designated 802,501 across the
gested the use of a continuous deck with both of its ends Pavlovski potok stream. In a case of high water levels the
28 S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34

existing bridge was constantly flooded due to the insuffi- bridge across the Pavlovski potok is rather short, the
cient water flow capacity of its box-shaped culvert. authors decided not to take a risk with the first structurally
The existing bridge (Fig. 1) was demolished and fully GRS integrated bridge in this part of the world. They
replaced by a new one. It was proposed that a reinforced therefore decided to construct the bridge system with
concrete slab, integrated onto a pair of geosynthetic rein- the bridge deck placed on top of the GRS, immediately
forced soil bridge abutments, should be built. The distance behind the FHR facings, i.e. to construct the bridge as a
between the facings of the abutments is 5.50 m. Since the single-span simply-supported beam, without using a pair
crossing of the stream and the road is at a skewed angle of bearings, i.e. it is supported by the two GRS abutments.
(i.e., not perpendicular, since the road crosses the stream Thus the bridge across the Pavlovski potok stream, pre-
at an angle of 114°), a parallelogram-shaped slab was cho- sented in this paper, combines the two approaches, the
sen for the design of the RC superstructure (Fig. 2). A lon- one used in Japan and the other proposed by the FHWA,
gitudinal cross-section of the bridge is shown in Fig. 3. for GRS integrated bridge design.
In Japan, but not elsewhere in the world, the staged
construction of GRS retaining walls (RW) with full height
rigid (FHR) facings has a long tradition (Tatsuoka et al., Geotechnical conditions
1997). As shown in Fig. 3, after site preparation (temporary
excavation works), soil bags (gabions) are placed at the No preliminary geological–geotechnical investigations
shoulder of each soil layer during the construction process of the ground had been performed at the exact location
(Fig. 11a). The soil bags function as a temporary but stable of the bridge. Instead, all the available data and results
facing structure during the construction works, since they from investigations performed for the design of another
resist the earth pressure generated by the compaction bridge located 50 m upstream and supported by deep
works and by further backfilling at higher levels. After suf- foundations using piles were taken into account. Table 1
ficient deformation of the subsoil and the backfill has summarizes the geological–geotechnical data, including
occurred during the construction of the geosynthetic- the results of standard penetration tests, which were
reinforced backfill, the full height rigid (FHR) facings are obtained at the site of the upstream bridge.
constructed by means of cast-in-situ concrete (Fig. 11b) Due to the low shear strength and compressibility of the
in the space between the formwork and the wall face sub-soil as presented by these geotechnical conditions, a
which is wrapped-around with geosynthetic (geogrid) deep piled foundation would have been used if a tradi-
reinforcement (Tatsuoka et al., 1997). As fresh concrete tional bridge were to have been constructed. Due to time
can easily get inside the gravel-filled bags through the and cost limitations, however, it was decided to employ
apertures of the geogrids, which are wrapped-around the GRS bridge abutments with FHR facings that are stage-
gravel bags, there is a strong connection between the fac- constructed in order to ensure good external stability
ings and the reinforcement layers. The procedure sounds while simultaneously minimizing the potential negative
easy and simple, but it has been realised from personal effects of significant ground settlement after completion
communication with its inventors (Tatsuoka et al., 1997) of the bridge.
that high connection strength between the reinforcement The bridge which is described in this paper consists of
layers and the FHR facing is crucial for proper performance an RC simply-supported slab, supported by a pair of
of GRS RWs with FHR facings. In fact, there was a case geosynthetic reinforced soil abutments, as shown in
where a contractor, who had insufficient previous experi- Fig. 3. This type of construction is effective for the reduc-
ence, was not able to achieve such a good connection tion of construction time and costs, while simultaneously
between the facings and the reinforcement layers. For this eliminating the need for the use of heavy construction
reason, and having in mind the fact that the span of the machinery as well as alleviating the bumps in front of

Fig. 2. Plan view of the newly designed bridge.


S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34 29

Fig. 3. Longitudinal cross-section of newly designed bridge supported by reinforced soil abutments.

Table 1
Geological–geotechnical data obtained from investigations that were performed for a bridge that was located 50 m upstream.

Depth [m] Description Soil properties


0.0–0.5 Sandy gravel
0.5–3.0 Sandy clay with inclusions of gravel and sand (N1)60 = 6
3.0–5.0 Clayey and silty sand (N1)60 = 8, c0 = 1.6 kPa, u0 = 25.7°, w = 33.5%, Ip = 14.3%
5.0–8.0 Silty sand (N1)60 = 12, w = 29.1%, Ip = 10.4%
8.0–11.0 Decayed stratified marl (N1)60 = 24
11.0–17.0 Sandy marl (N1)60 = 36
17.0–23.3 Sandy–silty clay (N1)60 = 32
23.3–26.3 Sandy marl–solid
Water level depth: 2.7 m

and behind the bridge, which usually occur due to differen- of 25 kPa, which corresponded to the expected on-site con-
tial settlement. A detailed view showing how the bridge ditions. The vertical load was then continuously applied to
deck rests on the GRS soil abutments is shown in Fig. 4. the top of the specimen in order to define the correspond-
ing stress–strain relationship (Figs. 5–7). The results of
these laboratory tests were analysed so that they could
Preliminary research including laboratory testing be properly applied to the in-situ conditions.
Other important properties (maximum shear resis-
Within the scope of the available funds of the EU co- tance, initial load curve, and equivalent elastic properties
funded research project (‘‘Research voucher”), some pre- obtained in the case of very small unloading and reloading
liminary research and laboratory tests were performed cycles) were analysed in order to take into account their
(Lenart, 2014; Lenart et al., 2014) in order to obtain all possible effect on the behaviour of such a composite mate-
the required data for the design of the GRS bridge rial when used to construct bridge abutments. The test
abutments. results have been reported in detail by Lenart (2014).
In the first phase of the testing, the basic characteristics
of the building materials (i.e. the gradation curve and com-
paction properties of the backfill material, and the tensile Design of the bridge abutments
strength of the geosynthetic reinforcement) and their
interaction (i.e. the soil-geosynthetic interface strength) Besides the dead weight of the structure, traffic loads,
were evaluated. too, were taken into account for the design of bridge and
In the second phase, the results from large scale labora- its abutments. The load model LM1, which provides a pair
tory tests were analysed in order to define the deformation of tandem axles on each conventional lane (600 kN and
properties of typical geosynthetic-reinforced soil. A 400 kN), accompanied by a uniform load (9 kN/m2 and
prismatically-shaped composite specimen (with dimen- 2.5 kN/m2), was used, as defined in EN 1991-2: Actions
sions of 910  910  2130 mm) made of well compacted on structures. Part 2: General actions – traffic loads on
granular backfill reinforced with intermediate geosyn- bridges. The bridge superstructure, i.e. slab deck, is sup-
thetic layers was constructed. The vertical spacing of the ported directly at the top of the abutment as a simply-
geosynthetic layers was 30 cm. A confining pressure was supported beam. A bearing width of 0.85 m was defined.
applied to the test specimen by means of a partial vacuum Due to the limited bearing stress acting on the GRS
30 S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34

Fig. 4. Detail showing how the bridge deck rests on one of the geosynthetic reinforced soil abutments.

Fig. 6. Stress–strain relationship for a typical sample of the investigated


reinforced soil.

Fig. 5. View of a vertical loading test being performed in the laboratory


test which was performed on the GRS specimen (Fig. 6), a
on a geosynthetic reinforced soil test specimen.
safety factor of 2.66 is obtained.
Even though the requirements for the fulfilment of the
abutment, the presented solution is, in general, restricted ultimate limit state are met, determination of the potential
to bridges with relatively short spans. It should be noted vertical deformation of the GRS abutments is crucial for
that this limitation is less evident when the bridge deck their serviceability. It can be estimated by multiplying
is fully structurally integrated onto the top of the FHR fac- the height of the abutment with the vertical strain
ings, thus forming a frame-type bridge structure, as is done obtained from the performance test (Fig. 6). To make sure
in the practice used in Japan. that the slab deck would not bear onto the facings due to
Fig. 8 shows the calculated bearing stresses due to traf- vertical deformation of the GRS abutments, a clear space
fic loads in the case of the bridge across the Pavlovski needs to be provided between the facings and the bottom
potok stream when using the load model LM1. Similarly, edge of the superstructure (Adams et al., 2010). As, in the
the bearing stresses due to other kind of loads (i.e. dead present case, the bridge deck was cast in situ, a layer of
weight, temperature differences, traffic accelerations, expanded polystyrene (EPS) foam was used to fill in the
etc.) were calculated and combined according to EN gap (Fig. 9).
1991-2. It was estimated that the maximum design vertical Furthermore, other applicable permanent and transient
pressure amounted to 305 kPa. When this value is com- external pressures and loads (vertical and horizontal) on
pared to the strength achieved in the case of the laboratory the GRS abutment were calculated. The external stability
S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34 31

Fig. 7. Optically measured (GOM Aramis) vertical strain of the GRS specimen at failure.

Fig. 8. Estimated bearing stresses due to traffic loads (load model LM1).

Fig. 10. Construction of the gravel foundation, before wrapping the


foundation with geosynthetics.

Fig. 9. Detail of the space between the top of the facing and bottom of the
Construction of the new bridge
bridge superstructure (i.e. slab deck).

The foundations for the abutments were first built,


using well-compacted gravelly soil, which was wrapped-
of the abutments was evaluated in the design phase by around with a layer of geosynthetic (Fig. 10). This step
looking at the possibilities of direct sliding of the abut- was followed by the construction of the geosynthetic rein-
ment, insufficient ground bearing capacity, and global sta- forced soil mass of the bridge abutments. Each layer of the
bility as potential external failure mechanisms. geosynthetic (geogrid Miragrid GX 80/80, with a nominal
32 S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34

tensile strength of 80 kN/m at an elongation of 10%) was


installed at a vertical spacing of 30 cm, whereas the inter-
mediate layers which were needed at critical positions
(beneath the bridge bearings) were installed at a vertical
spacing of 10 cm.
The load-bearing direction of the geogrid used in this
project was always oriented in a direction perpendicular
to the facing structure in order to ensure good behaviour
of the abutment. The construction procedure for the
retaining structures without the use of a temporary sup-
port system (Fig. 11) involved construction of the bridge
abutments made of geosynthetic-reinforced soil. Partial
pre-stressing of the geogrid, resulting in an increase in
Fig. 12. The measured values of the horizontal strains in one of the
the stiffness of the reinforced soil, was thus achieved dur- geosynthetic layers depending on the distance of the strain gauges from
ing the construction of the abutments. First the geogrid the abutment facing.
was arranged with wrapping around the gabion bags. This
was followed by the placing of the backfill material, which
was then compacted until the required dry density was
achieved. Fig. 12 shows the development of horizontal
strains in the geogrid after compaction of the backfill
material at various distances from the abutment facing. A
high level of pre-stressing of the geogrid was achieved dur-
ing compaction (>0.1%) near the abutment facings.
Both GRS bridge abutments were built within a period
of less than 10 days due to the simplicity of the construc-
tion processes involved (Fig. 13). The concrete facing struc-
tures were built using appropriate formwork and cast-in-
situ concrete. Since the bridge crossed a water channel,
the foundations of the reinforced concrete facings were

Fig. 13. Construction of the GRS abutments by placing gravel bags on the
shoulder of each layer and compaction of the backfill.

located at a depth of 150 cm in order to prevent scouring


beneath the GRS mass. The ends of the horizontal layers
of the geogrid reinforcement were rigidly connected to
the vertical steel reinforcement inside the facing structure
by means of additional strips (anchors) (Fig. 14). In order to
provide scour protection, four wing walls were extended
into a rip-rap structure at the bottom of the water channel.

Fig. 11. (a) Procedure for constructing the retaining structure without the
use of a temporary supporting system, and (b) construction of the full
height rigid (FHR) facings by means of cast-in-situ concrete: A – the initial
shallow foundation (levelling pad) for the facing, B – the gabion bags,
C – the geosynthetic reinforcement layer, D – the backfill material, and H Fig. 14. Detail of the facing before concreting, showing at the front the
– the cast-in-situ concrete facing (after Tatsuoka et al., 1997). already installed tube of a horizontal inclinometer.
S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34 33

future, horizontal inclinometers were installed in both


abutments. At the time of writing of this paper only initial
readings had been made.
Some interesting information and data which were
obtained during the construction of the first integrated
GRS bridge with FHR facings in this part of the world are
given below.

Foundations

Considering the geological structure of the ground at


the construction site, in case of conventional reinforced-
concrete bridge abutments, deep piled foundations using
piles with a diameter of 100 cm and a length of 24 m
would have been needed, as in the case of the nearby rail-
way bridge, which is located 50 m upstream. The geosyn-
thetic reinforced soil technology significantly reduced the
construction costs and time.
Fig. 15. Concreting works of the GRS abutments.

Concreting works
This structure consisted of rocks placed in concrete, and
provided a control channel for the stream, extending for Piles, pile caps, steel-reinforced concrete abutments,
another 5.0 m from each side of the abutments. The bridge wing walls of RC retaining structures, and approach slabs
deck was placed directly on the top of the geosynthetic- become unnecessary when the described GRS technology
reinforced backfill of the bridge abutments using a thin is used, which significantly reduces the amount of concrete
layer of embedded concrete (having the width of the bear- needed. Based on data obtained from the nearby newly-
ings). Some of the construction phases of the GRS bridge built railway bridge, which had steel-reinforced concrete
abutments are shown in Figs. 13 and 15. abutments founded on deep piled foundations, the quan-
tity of concrete works needed when constructing such con-
Results of observations and field monitoring ventional bridge abutments was compared to the case of
the integrated GRS bridge across the Pavlovski potok
In order to obtain information which would be relevant stream. The results showed that, in the case of steel-
to further research into the behaviour of GRS abutments, reinforced concrete abutments, nearly 120 m3 of extra con-
strain gauges were attached at some of the installed geo- crete would have been needed in comparison with the
grid layers. The strain values in the geogrid could be geosynthetic reinforced soil abutments (Table 2).
directly obtained at the construction site and were Since less concrete was needed, less formwork, too, was
recorded and monitored before and during the installation needed. However, despite that the fact that only single-
of the geogrid, as well as during construction of the abut- sided formwork was needed to construct the facing struc-
ments (Fig. 12). Monitoring will also take place in the ture of the GRS abutments, their implementation was
future in order to evaluate the effect of different types of rather complex since ground with good loadbearing capac-
loads on the behaviour of GRS abutments. ity was not available to support the formwork.
Up until the end of the construction works, approxi- In the design, the GRS facings were considered mostly
mately 1/3rd (1.5 cm) of the final expected settlement as a scour protection measure. As the design was based
had occurred. In a case of a piled foundation, the rest of on the characteristics of a simply-supported beam, struc-
the settlement would probably occur as a differential set- tural integrity between the bridge deck and the facings
tlement behind or in front of the bridge. This, however, is was not necessary. The aim was to not increase the vertical
not expected in the case of the bridge presented in this load acting on the abutments due to the self-weight of the
paper. In order to monitor any uneven settlements in the facing structure. For this reason a minimum thickness of

Table 2
Comparison of the amounts of concrete needed for bridge abutments at Žerovinci in case of GRS bridge abutments and reinforced concrete abutments.

Element Amounts of concrete needed [m3] Difference


RC abutments GRS abutments [m3] [%]
Piles (D = 100 cm L = 24 m) 75 – 75 100
Pile caps (120/120 cm) 23 – 23 100
Abutments (d = 50 cm) 21 9 12 57.1
Wing walls (d = 30 cm) 7 5 2 28.5
Approach slabs 12 – 12 100
Superstructure 35.5 42 6.5 18.3
Total 173.5 56 117.5 67.7
34 S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34

the facing structure, equal to 15 cm, was decided upon. technology, which is widely used in Japan, with the GRS
Also, minimum structural reinforcement was installed in integrated bridge system construction approach presented
the facings in order to ensure their rigidity and to prevent by the FHWA (USA). Thus the bridge system consists of a
the occurrence of any kind of cracks in the concrete bridge deck which is placed on top of the GRS, immediately
(Fig. 14). behind the FHR facings, i.e. it is acts as a simply-supported
In order to ensure uniform thickness of the facing struc- beam with its ends supported on a pair of GRS abutments.
ture (15 cm) throughout the whole height of the abutment, The experience gained from the design and construction of
the gabion bags have to be placed in their outer vertical the bridge presented in this paper indicates the many sig-
position very precisely, with only small deviations. This is nificant advantages of GRS bridge abutments compared to
because, when vibrating the cast-in-situ concrete, addi- conventional steel-reinforced concrete cantilevered abut-
tional problems can arise, in the case of relatively thin RC ments. The presented solution is beneficial particularly
facing structures, if the front face of the gabion bags is for short span bridges that need to be designed and built
not precisely achieved. In order to avoid such problems, in a very short time.
in the presented case self-compacting concrete was used.
It should be noted that this problem becomes less serious Acknowledgements
when the thickness of the FHR facings is increased, e.g. to
30 cm, which corresponds to the practice in Japan. The authors of this paper are especially grateful to the
Slovenian Ministry of Education, Science, Culture and
Static load design Sport, which enabled the research and development of
the presented technology by co-funding the research pro-
Since the bridge deck is constructed as a slab which is jects of Slovenian companies (‘‘Research voucher”) in
simply-supported by a pair of GRS abutments, the internal 2013 and 2014. Special thanks also go to the construction
mid-span bending moment line is much greater than in the company Pomgrad, d. d., which built the bridge described
case of a frame structure. Thus more reinforcement is in the paper. Last but not least, the authors would like to
needed in the lower zone, and less in the upper zone. Also, express their thanks to Professor Fumio Tatsuoka for his
a longer RC slab has to be provided in order to provide the valuable advice and encouraging approach during the
necessary bearing area. design and construction of the presented bridge.

Construction time References

The time needed to construct the GRS abutments was Adams MT, Lillis CP, Wu JTH, Ketchart K. Vegas mini pier experiment and
postulate of zero volume change. In: Proc. 7th int. conf. on
significantly reduced due to the simple construction pro- geosynthetics, Nice, France. p. 389–94.
cesses and techniques in comparison with steel- Adams MT, Nicks JE, Stabile T, Wu JTH, Schlatter W, Hartmann J.
reinforced concrete abutments. GRS bridge abutments Geosynthetic reinforced soil integrated bridge system – interim
implementation guide, report no. FHWA-HRT-11-026. McLean,
can be constructed within a couple of weeks without being VA: FHWA; 2010.
influenced by outside weather conditions. Taking into Brady KC. Performance of a reinforced earth bridge abutment at
account the provisions of the Slovenian legislation, con- Carmarthen, Research report III, Transport and Road Research
Laboratory, Crowthorne, Berkshire; 1987.
crete bridge decks have to be constructed in the conven- DRD. Reinforced soil slopes ensure faster and cheaper bridge
tional way using formwork, steel-reinforcement, and construction, <http://www.niras.com/current-events/news/2014>,
cast-in-situ concrete. In the case of high water levels, 2014 [as on 13.05.2014].
Helwany SMB, Wu JTH, Froessl B. GRS bridge abutments – an effective
pumping from excavated areas may also be needed when
means to alleviate bridge approach settlement. Geotext Geomembr
following this conventional construction method. The use 2003;21(3):177–96.
of precast concrete (PC) bridge decks is not allowed in Herold A. The first permanent road-bridge abutment in Germany built of
geosynthetic-reinforced earth. Nizza: International Geosynthetics
Slovenia. However, the use of such PC bridge decks would
Society; 2002.
significantly reduce the construction time in this kind of Lenart S. Final report about the development of reinforced soil bridge
project, with a short span bridge. abutments, P 320/13-710-8. Department of Geotechnics and
Infrastructure, ZAG Ljubljana – the Slovenian National Building and
Civil Engineering Institute; 2014 [in Slovenian].
Conclusions Lenart S, Koseki J, Miyashita Y, Sato T. Large-scale triaxial tests of dense
gravel material at low confining pressures. Soil Found 2014;54
(1):45–55.
The first GRS integrated bridge with FHR facings in Eur- Tatsuoka F, Tateyama M, Uchimura T, Koseki J. Geosynthetic-reinforced
ope was constructed across the Pavlovski potok stream in soil retaining walls as important permanent structures, Mercer
the village of Žerovinci at the end of 2014. Its design was Lecture. Geosynth Int 1997;4(2):81–136.
Tatsuoka F, Hirakawa D, Nojiri M, Aizawa H, Nishikiori H, Soma R,
accompanied by very short deadlines and a thick layer of
Tateyama M, Watanabe K. A new type of integral bridge comprising
soft foundation soil, where deep pile foundations would geosynthetic-reinforced soil walls. Geosynth Int 2009;16(4):301–26.
become necessary in the case of the conventional type of Vidal H. Reinforced Earth. Paris: Annales de I’Institut Technique du
abutments, using steel-reinforced concrete. Due to the lack Batiment et des Travaux Publics; 1972.
Wu JTH, Lee KZZ, Pham T. Allowable bearing pressure of bridge sills on
of previous experience with the staged construction of GRS GRS abutments with flexible facing. J Geotech Geoenviron Eng
RW with FHR facings, the authors decided to combine this 2006;132(7):836–41.

You might also like