Professional Documents
Culture Documents
6 Design and Construction of The First GRS Integrated BR 2016 Transportation G
6 Design and Construction of The First GRS Integrated BR 2016 Transportation G
Transportation Geotechnics
journal homepage: www.elsevier.com/locate/trgeo
a r t i c l e i n f o a b s t r a c t
Article history: The bridge across the Pavlovski potok stream in the village of Žerovinci in northeast
Received 15 July 2015 Slovenia is a part of the investment into the modernisation of the Pragersko–Hodoš railway
Revised 4 July 2016 line, one of the biggest investments in the infrastructure in Slovenia at the moment. Its
Accepted 6 July 2016
design was accompanied by very short deadlines and a deep layer of soft foundation soil.
Available online 15 July 2016
For this reason the reinforced concrete abutments of a nearby railway bridge were founded
on 24 m deep piled foundations. Short deadlines and a limited budget forced the authors of
Keywords:
this paper to find an alternative solution. Deep piled foundations were replaced by shallow
Reinforced soil
Geosynthetics
foundations made of compacted fill material reinforced with geosynthetics. The bridge was
GRS integrated bridge completed by the end of 2014. From the results of previous laboratory tests that were
Deformation obtained within the scope of the EU co-funded research project ‘‘Research voucher”, the
Compacted fill basic characteristics of the building materials for the geosynthetic reinforced soil (GRS)
bridge abutments, as well as the deformation properties of the typical reinforced soil were
obtained. These data were used for the design of the abutments. The staged construction
procedure of full height rigid (FHR) facings for the GRS retaining walls (RW) was used
for the construction of this GRS integrated bridge. Partial pre-stressing of geogrids and con-
sequently the increased stiffness of the reinforced soil was achieved by following the
staged construction procedure. The bridge system consisted of a cast-in-situ RC slab, which
was placed on top of the GRS immediately behind the FHR facings, i.e. the bridge was con-
structed as a simply-supported slab supported by a pair of GRS abutments, without the use
of bearings. Thus the described bridge across the Pavlovski potok combines two
approaches for GRS integrated bridge design, one of which has been used in Japan
(Tatsuoka et al., 2009), with full structural integration of the deck onto the pair of FHR fac-
ings, other being proposed by the FHWA (Adams et al., 2010), without full integration of
the deck onto the GRS RWs. A system for the monitoring of structure performance was
established in order to ensure optimization of this kind of structure. Data for this GRS inte-
grated bridge, which were obtained during the construction works were compared to sim-
ilar data obtained from the construction of a nearby railway bridge with reinforced
concrete abutments. The comparison provides a good basis for future decisions when
choosing the type of bridge abutments.
Ó 2016 Elsevier Ltd. All rights reserved.
⇑ Corresponding author.
E-mail address: stanislav.lenart@zag.si (S. Lenart).
http://dx.doi.org/10.1016/j.trgeo.2016.07.003
2214-3912/Ó 2016 Elsevier Ltd. All rights reserved.
S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34 27
Introduction
existing bridge was constantly flooded due to the insuffi- bridge across the Pavlovski potok is rather short, the
cient water flow capacity of its box-shaped culvert. authors decided not to take a risk with the first structurally
The existing bridge (Fig. 1) was demolished and fully GRS integrated bridge in this part of the world. They
replaced by a new one. It was proposed that a reinforced therefore decided to construct the bridge system with
concrete slab, integrated onto a pair of geosynthetic rein- the bridge deck placed on top of the GRS, immediately
forced soil bridge abutments, should be built. The distance behind the FHR facings, i.e. to construct the bridge as a
between the facings of the abutments is 5.50 m. Since the single-span simply-supported beam, without using a pair
crossing of the stream and the road is at a skewed angle of bearings, i.e. it is supported by the two GRS abutments.
(i.e., not perpendicular, since the road crosses the stream Thus the bridge across the Pavlovski potok stream, pre-
at an angle of 114°), a parallelogram-shaped slab was cho- sented in this paper, combines the two approaches, the
sen for the design of the RC superstructure (Fig. 2). A lon- one used in Japan and the other proposed by the FHWA,
gitudinal cross-section of the bridge is shown in Fig. 3. for GRS integrated bridge design.
In Japan, but not elsewhere in the world, the staged
construction of GRS retaining walls (RW) with full height
rigid (FHR) facings has a long tradition (Tatsuoka et al., Geotechnical conditions
1997). As shown in Fig. 3, after site preparation (temporary
excavation works), soil bags (gabions) are placed at the No preliminary geological–geotechnical investigations
shoulder of each soil layer during the construction process of the ground had been performed at the exact location
(Fig. 11a). The soil bags function as a temporary but stable of the bridge. Instead, all the available data and results
facing structure during the construction works, since they from investigations performed for the design of another
resist the earth pressure generated by the compaction bridge located 50 m upstream and supported by deep
works and by further backfilling at higher levels. After suf- foundations using piles were taken into account. Table 1
ficient deformation of the subsoil and the backfill has summarizes the geological–geotechnical data, including
occurred during the construction of the geosynthetic- the results of standard penetration tests, which were
reinforced backfill, the full height rigid (FHR) facings are obtained at the site of the upstream bridge.
constructed by means of cast-in-situ concrete (Fig. 11b) Due to the low shear strength and compressibility of the
in the space between the formwork and the wall face sub-soil as presented by these geotechnical conditions, a
which is wrapped-around with geosynthetic (geogrid) deep piled foundation would have been used if a tradi-
reinforcement (Tatsuoka et al., 1997). As fresh concrete tional bridge were to have been constructed. Due to time
can easily get inside the gravel-filled bags through the and cost limitations, however, it was decided to employ
apertures of the geogrids, which are wrapped-around the GRS bridge abutments with FHR facings that are stage-
gravel bags, there is a strong connection between the fac- constructed in order to ensure good external stability
ings and the reinforcement layers. The procedure sounds while simultaneously minimizing the potential negative
easy and simple, but it has been realised from personal effects of significant ground settlement after completion
communication with its inventors (Tatsuoka et al., 1997) of the bridge.
that high connection strength between the reinforcement The bridge which is described in this paper consists of
layers and the FHR facing is crucial for proper performance an RC simply-supported slab, supported by a pair of
of GRS RWs with FHR facings. In fact, there was a case geosynthetic reinforced soil abutments, as shown in
where a contractor, who had insufficient previous experi- Fig. 3. This type of construction is effective for the reduc-
ence, was not able to achieve such a good connection tion of construction time and costs, while simultaneously
between the facings and the reinforcement layers. For this eliminating the need for the use of heavy construction
reason, and having in mind the fact that the span of the machinery as well as alleviating the bumps in front of
Fig. 3. Longitudinal cross-section of newly designed bridge supported by reinforced soil abutments.
Table 1
Geological–geotechnical data obtained from investigations that were performed for a bridge that was located 50 m upstream.
and behind the bridge, which usually occur due to differen- of 25 kPa, which corresponded to the expected on-site con-
tial settlement. A detailed view showing how the bridge ditions. The vertical load was then continuously applied to
deck rests on the GRS soil abutments is shown in Fig. 4. the top of the specimen in order to define the correspond-
ing stress–strain relationship (Figs. 5–7). The results of
these laboratory tests were analysed so that they could
Preliminary research including laboratory testing be properly applied to the in-situ conditions.
Other important properties (maximum shear resis-
Within the scope of the available funds of the EU co- tance, initial load curve, and equivalent elastic properties
funded research project (‘‘Research voucher”), some pre- obtained in the case of very small unloading and reloading
liminary research and laboratory tests were performed cycles) were analysed in order to take into account their
(Lenart, 2014; Lenart et al., 2014) in order to obtain all possible effect on the behaviour of such a composite mate-
the required data for the design of the GRS bridge rial when used to construct bridge abutments. The test
abutments. results have been reported in detail by Lenart (2014).
In the first phase of the testing, the basic characteristics
of the building materials (i.e. the gradation curve and com-
paction properties of the backfill material, and the tensile Design of the bridge abutments
strength of the geosynthetic reinforcement) and their
interaction (i.e. the soil-geosynthetic interface strength) Besides the dead weight of the structure, traffic loads,
were evaluated. too, were taken into account for the design of bridge and
In the second phase, the results from large scale labora- its abutments. The load model LM1, which provides a pair
tory tests were analysed in order to define the deformation of tandem axles on each conventional lane (600 kN and
properties of typical geosynthetic-reinforced soil. A 400 kN), accompanied by a uniform load (9 kN/m2 and
prismatically-shaped composite specimen (with dimen- 2.5 kN/m2), was used, as defined in EN 1991-2: Actions
sions of 910 910 2130 mm) made of well compacted on structures. Part 2: General actions – traffic loads on
granular backfill reinforced with intermediate geosyn- bridges. The bridge superstructure, i.e. slab deck, is sup-
thetic layers was constructed. The vertical spacing of the ported directly at the top of the abutment as a simply-
geosynthetic layers was 30 cm. A confining pressure was supported beam. A bearing width of 0.85 m was defined.
applied to the test specimen by means of a partial vacuum Due to the limited bearing stress acting on the GRS
30 S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34
Fig. 4. Detail showing how the bridge deck rests on one of the geosynthetic reinforced soil abutments.
Fig. 7. Optically measured (GOM Aramis) vertical strain of the GRS specimen at failure.
Fig. 8. Estimated bearing stresses due to traffic loads (load model LM1).
Fig. 9. Detail of the space between the top of the facing and bottom of the
Construction of the new bridge
bridge superstructure (i.e. slab deck).
Fig. 13. Construction of the GRS abutments by placing gravel bags on the
shoulder of each layer and compaction of the backfill.
Fig. 11. (a) Procedure for constructing the retaining structure without the
use of a temporary supporting system, and (b) construction of the full
height rigid (FHR) facings by means of cast-in-situ concrete: A – the initial
shallow foundation (levelling pad) for the facing, B – the gabion bags,
C – the geosynthetic reinforcement layer, D – the backfill material, and H Fig. 14. Detail of the facing before concreting, showing at the front the
– the cast-in-situ concrete facing (after Tatsuoka et al., 1997). already installed tube of a horizontal inclinometer.
S. Lenart et al. / Transportation Geotechnics 8 (2016) 26–34 33
Foundations
Concreting works
This structure consisted of rocks placed in concrete, and
provided a control channel for the stream, extending for Piles, pile caps, steel-reinforced concrete abutments,
another 5.0 m from each side of the abutments. The bridge wing walls of RC retaining structures, and approach slabs
deck was placed directly on the top of the geosynthetic- become unnecessary when the described GRS technology
reinforced backfill of the bridge abutments using a thin is used, which significantly reduces the amount of concrete
layer of embedded concrete (having the width of the bear- needed. Based on data obtained from the nearby newly-
ings). Some of the construction phases of the GRS bridge built railway bridge, which had steel-reinforced concrete
abutments are shown in Figs. 13 and 15. abutments founded on deep piled foundations, the quan-
tity of concrete works needed when constructing such con-
Results of observations and field monitoring ventional bridge abutments was compared to the case of
the integrated GRS bridge across the Pavlovski potok
In order to obtain information which would be relevant stream. The results showed that, in the case of steel-
to further research into the behaviour of GRS abutments, reinforced concrete abutments, nearly 120 m3 of extra con-
strain gauges were attached at some of the installed geo- crete would have been needed in comparison with the
grid layers. The strain values in the geogrid could be geosynthetic reinforced soil abutments (Table 2).
directly obtained at the construction site and were Since less concrete was needed, less formwork, too, was
recorded and monitored before and during the installation needed. However, despite that the fact that only single-
of the geogrid, as well as during construction of the abut- sided formwork was needed to construct the facing struc-
ments (Fig. 12). Monitoring will also take place in the ture of the GRS abutments, their implementation was
future in order to evaluate the effect of different types of rather complex since ground with good loadbearing capac-
loads on the behaviour of GRS abutments. ity was not available to support the formwork.
Up until the end of the construction works, approxi- In the design, the GRS facings were considered mostly
mately 1/3rd (1.5 cm) of the final expected settlement as a scour protection measure. As the design was based
had occurred. In a case of a piled foundation, the rest of on the characteristics of a simply-supported beam, struc-
the settlement would probably occur as a differential set- tural integrity between the bridge deck and the facings
tlement behind or in front of the bridge. This, however, is was not necessary. The aim was to not increase the vertical
not expected in the case of the bridge presented in this load acting on the abutments due to the self-weight of the
paper. In order to monitor any uneven settlements in the facing structure. For this reason a minimum thickness of
Table 2
Comparison of the amounts of concrete needed for bridge abutments at Žerovinci in case of GRS bridge abutments and reinforced concrete abutments.
the facing structure, equal to 15 cm, was decided upon. technology, which is widely used in Japan, with the GRS
Also, minimum structural reinforcement was installed in integrated bridge system construction approach presented
the facings in order to ensure their rigidity and to prevent by the FHWA (USA). Thus the bridge system consists of a
the occurrence of any kind of cracks in the concrete bridge deck which is placed on top of the GRS, immediately
(Fig. 14). behind the FHR facings, i.e. it is acts as a simply-supported
In order to ensure uniform thickness of the facing struc- beam with its ends supported on a pair of GRS abutments.
ture (15 cm) throughout the whole height of the abutment, The experience gained from the design and construction of
the gabion bags have to be placed in their outer vertical the bridge presented in this paper indicates the many sig-
position very precisely, with only small deviations. This is nificant advantages of GRS bridge abutments compared to
because, when vibrating the cast-in-situ concrete, addi- conventional steel-reinforced concrete cantilevered abut-
tional problems can arise, in the case of relatively thin RC ments. The presented solution is beneficial particularly
facing structures, if the front face of the gabion bags is for short span bridges that need to be designed and built
not precisely achieved. In order to avoid such problems, in a very short time.
in the presented case self-compacting concrete was used.
It should be noted that this problem becomes less serious Acknowledgements
when the thickness of the FHR facings is increased, e.g. to
30 cm, which corresponds to the practice in Japan. The authors of this paper are especially grateful to the
Slovenian Ministry of Education, Science, Culture and
Static load design Sport, which enabled the research and development of
the presented technology by co-funding the research pro-
Since the bridge deck is constructed as a slab which is jects of Slovenian companies (‘‘Research voucher”) in
simply-supported by a pair of GRS abutments, the internal 2013 and 2014. Special thanks also go to the construction
mid-span bending moment line is much greater than in the company Pomgrad, d. d., which built the bridge described
case of a frame structure. Thus more reinforcement is in the paper. Last but not least, the authors would like to
needed in the lower zone, and less in the upper zone. Also, express their thanks to Professor Fumio Tatsuoka for his
a longer RC slab has to be provided in order to provide the valuable advice and encouraging approach during the
necessary bearing area. design and construction of the presented bridge.
The time needed to construct the GRS abutments was Adams MT, Lillis CP, Wu JTH, Ketchart K. Vegas mini pier experiment and
postulate of zero volume change. In: Proc. 7th int. conf. on
significantly reduced due to the simple construction pro- geosynthetics, Nice, France. p. 389–94.
cesses and techniques in comparison with steel- Adams MT, Nicks JE, Stabile T, Wu JTH, Schlatter W, Hartmann J.
reinforced concrete abutments. GRS bridge abutments Geosynthetic reinforced soil integrated bridge system – interim
implementation guide, report no. FHWA-HRT-11-026. McLean,
can be constructed within a couple of weeks without being VA: FHWA; 2010.
influenced by outside weather conditions. Taking into Brady KC. Performance of a reinforced earth bridge abutment at
account the provisions of the Slovenian legislation, con- Carmarthen, Research report III, Transport and Road Research
Laboratory, Crowthorne, Berkshire; 1987.
crete bridge decks have to be constructed in the conven- DRD. Reinforced soil slopes ensure faster and cheaper bridge
tional way using formwork, steel-reinforcement, and construction, <http://www.niras.com/current-events/news/2014>,
cast-in-situ concrete. In the case of high water levels, 2014 [as on 13.05.2014].
Helwany SMB, Wu JTH, Froessl B. GRS bridge abutments – an effective
pumping from excavated areas may also be needed when
means to alleviate bridge approach settlement. Geotext Geomembr
following this conventional construction method. The use 2003;21(3):177–96.
of precast concrete (PC) bridge decks is not allowed in Herold A. The first permanent road-bridge abutment in Germany built of
geosynthetic-reinforced earth. Nizza: International Geosynthetics
Slovenia. However, the use of such PC bridge decks would
Society; 2002.
significantly reduce the construction time in this kind of Lenart S. Final report about the development of reinforced soil bridge
project, with a short span bridge. abutments, P 320/13-710-8. Department of Geotechnics and
Infrastructure, ZAG Ljubljana – the Slovenian National Building and
Civil Engineering Institute; 2014 [in Slovenian].
Conclusions Lenart S, Koseki J, Miyashita Y, Sato T. Large-scale triaxial tests of dense
gravel material at low confining pressures. Soil Found 2014;54
(1):45–55.
The first GRS integrated bridge with FHR facings in Eur- Tatsuoka F, Tateyama M, Uchimura T, Koseki J. Geosynthetic-reinforced
ope was constructed across the Pavlovski potok stream in soil retaining walls as important permanent structures, Mercer
the village of Žerovinci at the end of 2014. Its design was Lecture. Geosynth Int 1997;4(2):81–136.
Tatsuoka F, Hirakawa D, Nojiri M, Aizawa H, Nishikiori H, Soma R,
accompanied by very short deadlines and a thick layer of
Tateyama M, Watanabe K. A new type of integral bridge comprising
soft foundation soil, where deep pile foundations would geosynthetic-reinforced soil walls. Geosynth Int 2009;16(4):301–26.
become necessary in the case of the conventional type of Vidal H. Reinforced Earth. Paris: Annales de I’Institut Technique du
abutments, using steel-reinforced concrete. Due to the lack Batiment et des Travaux Publics; 1972.
Wu JTH, Lee KZZ, Pham T. Allowable bearing pressure of bridge sills on
of previous experience with the staged construction of GRS GRS abutments with flexible facing. J Geotech Geoenviron Eng
RW with FHR facings, the authors decided to combine this 2006;132(7):836–41.