With reference to above letter, I have come to Hyderabad for Peer
Review. On dated 16.06.2021, I have visited the site along with NHAI, PDy.GM (Tech.), Smt. K.P.Saraswathi and the personnel of SM Consultant (Mr.Ramakant & Mr. Degaru) of Package-I site.
Package-I comes in the Gadwal District in the State of Telangana.
Package-I starts from Ch.202.900 to Ch.242.200 total length is 39.3 km.
Construction Cost:
1. Cost of shifting of utilities RWS Rs. 2,00,00,000/- (Rupees Two Crores
Only) 2. Cost of shifting of utilities Electrical Rs.43,95,00,000/- (Rupees Fourty Three Crore Ninety Five Lakhs Only)
The provision of electrical utilities is as under:
1. EHT lines
Sl.No. Ch. Length(km) Crossings Reason for shifting / not
shifting From To 400KV 132KV 1 218.893 219.105 0.221 1 Tower in ROW to be shifted. 2 220.222 220.614 0.398 Tower is in the center of the road hence tower to be shifted. 3 226.610 226.671 0.117 Road clearance is very less as per IE rule 1956 rule 77.hence tower to be shifted. 4 236.000 236.000 0.06 Tower not to be shifted the clearance is 9.96m as per IE rule 1956 rule 77. The minimum clearance for 400kv is 8.84m while at present the available clearance is 9.96m As per site visit, it is found that tower at serial number 1,2,3 of above chart to be shifted but the tower at serial number 4 which is 400kv tower not to be shifted. The shifting of 400 KV tower is costly affair.the approximate cost of shifting will be 1.5cr Therefore, it will be big saving in the DPR cost.
The detail of HT line and LT line given below:
Sl.no Description Quantity
1 11/04 KV Transformers 10 Nos. 2 11 KV crossing 44 Nos. 3 LT crossing 58 Nos. 4 Total length of 11 KV 3.71 Kms line to be shifted 5 Total length of LT lines 4.489 Kms. is
Financial expenditure of electrical utility
Sl.No Description Cost as per Cost comes Saving in
DPR (in after peer rupees (in Cr.) review (in Cr.) Cr.) 1 Cost of shifting of utilities 43.95 31.4 12.5 electrical
In Electrical review of Package – I, it is found that Extra High Tension
line shifting of 400 KV not to be done. Hence, the approximate saving of Rs.1.5 Cr. Worked out.
Regarding HT line and LT shifting the cost estimate received from
Telangana Division is Rs.5,24,21,793/- this covers the approximately 68% area of total HT and LT line. Therefore, this is justified to reduce the cost of Electrical Utility in the DPR approximately 25%. Therefore, the saving of Electrical Utilities is approximately Rs.12.5 Cr.
1. It is advised to DPR Consultant to collect HT and LT line balance
estimates for the shifting of HT/LT lines.
2. It is also advised to obtain the map of the estimates prepared and
sanctioned by the Power Distribution Company.
This review is submitted to you.
Yours faithfully,
Ashok Kumar Dixit
Superintending Engineer (Retd.), MP Electricity Board, Govt. of Madhya Pradesh Copy to: 1. The Regional Officer, NHAI, Regional Office, Hyderabad – For information. 2. The GM (Tech.) AP & TS, NHAI, HQ, New Delhi – For information. 3. The Project Director, NHAI, PIU-Hyderabad – For information.