When a transformer is energized, a large inrush current occurs for a few cycles as the transformer
energizes the core. Typically the outer windings are considered the primary windings. If the inner
(secondary) windings are used to initially energize the transformer, much larger inrush currents can
occur due to the inner coils closer proximity to the transformer’s core. These larger inrush currents
can cause unintended tripping of circuit breakers and fuses and should be avoided. Primary in
relation to the transformer is not defined by voltage but by which coil is the outer coil.
In the PV/Solar grid-tie applications the primary side of transformer is often incorrectly identified
as the side connected to the solar inverter. In practice; the transformer will initially be energized
from the side tied to the facility/utility grid. After the transformer is energized from facility/utility
grid it will send power to the inverter. The current (load) will remain idle until inverter pushes
current back through the transformer to the facility/utility grid when the PV plant generates power.
At this point the transformer is being used in a bi-directional application with no additional
energizing inrush currents when the PV source is generating power
https://americas.hammondpowersolutions.com/en/resources/solar-pv-applications 1/4
6/13/2021 Determine Primary Side of Transformer in Solar PV Applications
energizing inrush currents when the PV source is generating power.
Hammond Power Solutions’ transformers are intended to be energized on the side indicated as
primary. This allows proper control of energizing inrush currents.
In most applications, HPS has seen a Delta connection successfully used for the connection to the
facility/utility grid even if the facility/utility grid power is Wye-Neutral. This typically satisfies
A Wye-N with a neutral connected to the facility/utility grid can result in circulating currents
through the neutral and transformer overheating. This occurs most often when the PV array is not
generating, but there may still be heavy single-phase loads at facility.
HPS can provide transformers with any combination of delta, wye and wye-N connections on
either the primary or secondary. This technical paper largely describes utility-interactive systems
only. Systems that have no utility connection or can switch out utility connections require
additional considerations.
https://americas.hammondpowersolutions.com/en/resources/solar-pv-applications 2/4
6/13/2021 Determine Primary Side of Transformer in Solar PV Applications
Our Company
Investor Relations
News
Careers
Contact
Products
Industries
Resources
https://americas.hammondpowersolutions.com/en/resources/solar-pv-applications 3/4
6/13/2021 Determine Primary Side of Transformer in Solar PV Applications
Resources
Partner Locator
Legal
Accessibilty
Privacy
https://americas.hammondpowersolutions.com/en/resources/solar-pv-applications 4/4