Procedure
(PCP-2020)
Introduction(1.0)
➢ The objective of the PCP is to ensure transparency,
fairness, uniformity and efficiency in the procurement/
contract/ tendering process across SAIL Plants/units.
➢ The procedure is applicable to all purchases/contracts,
unless specified otherwise
➢ In exceptional cases, deviation may be permitted for
recorded reasons with the specific approval of Chief
Executive officers & reported to CVO & CMMG.
(Clause 1.4)
Raising of Indents
Estimated Value
Preparation of Technical Specification
Scrutiny of Indents
Action on Indent By MM Deptt/Contract Cell
Selection of mode of tendering
Invitation to Tenders
Opening/Scrutiny/Order of Tenders
Post Contractual Activities
3
RAISING OF INDENTS
Raising of Indents
(PCP-2020 Clause 2.1, 2.2
& 2.3)
4
RAISING OF INDENTS-CHECK POINTS
6
RAISING OF INDENTS –COMMON PITFALLS
10
Preparation of Technical Specifications
Check Points to avoid common pitfalls
✓ Technical Specification should be clear, Non-
conflicting.
✓ Quantity should be worked out properly so that
post contractual deviations in quantity may be
avoided.
✓ As per PCP-2020 Clause 2.3.2 “The overall quality
of the jobs to be executed along with the expected
Performance Guarantees should be clearly
indicated in the indent.”
✓ Inspection Clause should be clearly mentioned in
the indent (PCP Clause 2.3.4)
Preparation of Technical Specifications –Check
Points to avoid common pitfalls
Open/Global Tender
(PCP-2020 Clause 5.2)
Single Tender
(Proprietary Items)
(PCP-2020 Clause 5.4.1)
Single Tender
(Other than Proprietary Items)
(PCP-2020 Clause 5.4.2)
Open/Global Tender
(PCP-2020 Clause 5.2)
18
Mode of Tendering (PCP-2020 Clause 5.0):
Check Points : Check Points to avoid common pitfalls
22
Repeat Orders (PCP-2020 Clause 5.5) –
Check Points to avoid common pitfalls
✓ For Original order in normal course through LTE/ OT. Emergency orders
shall not be considered.
✓ Not more than 2 years after Original order.
✓ No price escalation for firm price orders.
✓ No Repeat Order in case of downward price trend.
✓ Not more than 2 Repeat Orders to be placed.
✓ The quantity/scope considered for ordering is not more than 100% of the
original ordered quantity/scope, for each repeat order.
✓ The original order was not placed on the basis of a higher price for earlier
delivery
✓ Sanction of Competent Authority for repeat order shall be obtained
✓ In exceptional cases, a third repeat order can be placed with the approval
of CEO after recording justification.
23
Rate Contracts of Plant/Unit /Sister Plant/SAIL (PCP-2020
Clause 5.6) :-Check Points to avoid common pitfalls
24
Procurement on GeM (PCP-2020 Clause 5.7):
Check Points to avoid common pitfalls
25
Emergency Contract (PCP-2020 Clause 5.1.2 and 5.8) :
Check Points to avoid common pitfalls
28
Invitation to Tenders:
Check Points to avoid common pitfalls
✓ In case of medicines, chemicals and other items having limited
shelf life, the left over shelf life of each item at the time of
delivery should be at least 80%. (PCP-2020 Clause 6.8)
✓ In emergency, the left over shelf life equal to 120% of the
consumption period of such items may be accepted with the
approval of the Competent Authority. (PCP-2020 Clause 6.8)
✓ Order distribution shall be clearly mentioned in the tender
documents (Pl. Ref. PCP-2020 Clause 6.8)
✓ As per PCP-2020 Clause 6.9: In case of Open / Global tenders,
other than for capital schemes,
➢ To bring the prices of the foreign suppliers and the Indian suppliers
at par, the RBI reference rate should be considered for exchange
rate conversion.
➢ “forward premium rate” should be considered for the period of
delivery
29
Invitation to Tenders:
Check Points to avoid common pitfalls
✓ Clear stipulation should be made in the tender documents
regarding taking justification of quoted price from the L-1
tenderer /PBG (as an additional security) if the quoted price is
less than the lower limit of the estimated price (Ref. PCP-2020
Clause 6.12 & 10.1)
✓ If agents / dealers / stockists of foreign companies quote along
with manufacturer, only the offer of Principal / OEM will be
considered as valid. (Ref. PCP-2020 Clause 6.14)
✓ One agent cannot represent two suppliers / Principal / OEM or
quote on their behalf in a particular tender. (Ref. PCP-2020 Clause
6.14)
✓ For all tenders / Contracts / Long Term Agreements (LTAs) valuing
Rs.20 crores and above, the tenderer(s) / bidder(s) /
contractor(s) has to enter into an “Integrity Pact” with SAIL. (Ref.
PCP-2020 Clause 6.15)
30
Opening/Scrutiny /Ordering of Tenders:
Check Points to avoid common pitfalls
✓ As per PCP -2020 Clause 6.19 “In all technically complex Projects
cases, pre-bid discussions after floating of tender and before
submission of bids should be held…”
✓ As per PCP -2020 Clause 6.20 “For high value purchase orders /
contracts costing Rs. 2 crores and above, the Tender Committee
should be constituted with the approval of the competent
authority, at least seven days before opening the tender…”
✓ As per PCP-2020 Clause 7.7 “For opening the tenders, a minimum
of X+2 offers should have been received ('X' is the number of
supplier / contractor on whom order is to be placed).
✓ As per PCP-2020 Clause 7.7 (a) “In case of open / global tenders,
if less than the specified (X + 2)numbers of offers are received;
same can be processed without going for re-tender / tender
opening date extension with the approval of the authority one
stage higher than the authority competent to approve the
enquiry proposal or Chief Executive.” 31
Opening/Scrutiny /Ordering of Tenders:
Check Points to avoid common pitfalls
✓ As per PCP-14 Clause 7.7 (b) “In case of LTE, if less than specified
X + 2 number of offers are received in the first attempt, a second
attempt may be made by inclusion of new vendors or extension
of due date if there is no scope of adding new vendors…”
✓ As per PCP-14 Clause 7.8 “Offers received against Single Tender
cases can be opened before or after the tender opening date by
the dealing MM Dept. / Contract Cell Executive.”
✓ As per PCP-14 Clause 7.11 “Delayed / Late Tenders will not be
opened.”
✓ As per PCP-14 Clause 7.14 “Any modification to the original
tender after due date of tender opening shall also be treated as
unsolicited and rejected.”
✓ As per PCP-14 Clause 7.15 “Tenders not accompanied by
requisite Earnest Money, where Earnest Money is stipulated in
the tender condition, shall be treated as invalid.”
32
Opening/Scrutiny /Ordering of Tenders:
Check Points to avoid common pitfalls
✓ All the correspondence in respect of clarifications /
confirmations, whether it be technical or commercial
shall be dealt through MM Dept. / Contract Cell /
Contracting Department only till the final placement of
order (As per PCP-2020 Clause 7.19 ).
✓ The unopened hard copies of price bids of the parties whose
offers have not been techno-commercially accepted should be
returned to the parties within 10 days from the date of price bid
opening. (As per PCP-2020 Clause 7.30 )
✓ In addition to the price bids, invalid, unsolicited and late offers
are also to be returned back to parties within 10 days of tender
opening. (As per PCP-2020 Clause 7.30 )
33
Earnest Money(8.0)
EMD protects Company against irresponsible offers but it should not be so
high as to discourage tenders
Non requirement of EMD/ Reduced EMD*, in OTE should be decided by
HOMM/CC on case to case basis with the approval of Competent Authority.
The amount of EMD to be specified in NIT in terms of absolute value as per
indicative schedule in PCP.
MSEs/PSUs & Co-operative Societies/Start-ups as recognized by
Department of Industrial Policy & Promotion (DIPP) etc. may be exempted#
from submission of EMD as per Govt. Policy.
Earnest Money may preferably be submitted in the form of online transfer -
NEFT, RTGS, SWIFT.
Proof of such transfer to be submitted with the offer in the envelope titled
EMD.
Earnest Money (8.0)
EMD can also be submitted demand draft, pay order, Banker's Cheque or Bank
Guarantee (BG) from any scheduled commercial bank except co-op. & Gramin banks.
No request for adjustment of earlier dues should be entertained.
EMD will not be accepted in cash.
Registered contractors may opt one time non-adjustable EMD for contracts.
Refund of EMD
within 7 days from the date of rejection of offers
unsuccessful tenderers within fifteen (15) days from determination of L-1
within 15 (fifteen) days of submission of Performance Guarantee / Security Deposit or 30 (thirty) days of
successful completion of contract, whichever occurs earlier.
In place of EMD, Bidders may require to sign a Bid Securing declaration that “they
will be suspended for the period of one year from being eligible to submit Bids for
contracts.”
If EMD has been taken, the decision on the tender is delayed by more than 30 Days
from the last date of receiving the bids the EMD should be returned BSD may be
obtained.
Scrutiny of Quotations (9)
For single part quotations:
quotations to be forwarded after scrutiny within 2 days of opening to Tender
Committee / indenter.
If L-1 price beyond permissible range of variation, indenter should
comment on reasonability of quoted price.
In LTE, bids cannot be rejected on the basis of incapability.
No change in specifications, in case changes required, re-tendering to be
done.
In case of 2/3 part tendering:
The techno-commercial bids after its opening shall be evaluated by the
indenter/ Tender Committee
Indenter to be scrutinize technical part and MM Dept./Contract Dept. to
scrutinize commercial part.
A comparative statement of techno-commercial scrutiny of all the
tenders shall be prepared by the indenter / Tender Committee.
Revised Price Bid (9.2.3)
In case, tenderers desire to update their price bids citing reasons, it may be
permitted only under exceptional circumstances to be recorded in writing
and with the approval of C/A.
In such cases, all the acceptable tenderers may be permitted to submit
incremental/decremental /revised price-bids.
If additional items included, tenderers to submit a separate price bid for the
additional items only.
The initial price bid and revised price bid/increment-decrement shall be
opened together.
In case any specific adverse report is received against a tenderer, as an
information or upon enquiry made by SAIL in respect of capabilities and
performance of the tenderer the quotation / tender of that tenderer is liable
to be rejected after recording the reasons and with the approval of the
competent authority.
Opening of Price Bids (9.4)
After completion of the techno-commercial scrutiny the price
bids shall be opened and evaluated.