3 / 3 pts
Mr. Imbestigador is contemplating whether to investigate the efficiency variance in its
variable manufacturing costs. The investigation will cost P10, 000. If the production
departments are formed to be operating improperly, the company will incur P25, 000 (in
addition to the cost of investigation) to correct the operations.
If the production departments are operating improperly and Mr. Imbestigador fails to
investigate, operating costs from various inefficiencies are expected to amount to P40,
000.
1. What is the expected value of the act “Investigate” if the probability of improper
C
operations is 60%?
A. P15,000
B. P10,000
C. P25,000
D. P 5,000
2. What is the expected value of the act “Do not investigate” if the probability of
B
The expected value of making the component part is P39,200.
Buying the part is the better alternative.
The expected value of buying the component part is P32,800.
Question 38
1 / 1 pts
In the Gantt chart below, each of the bars represents the expected time necessary to
complete the activity and the shaded regions represent the portions completed:
the project is on schedule.
Correct!
Activity C is one month behind schedule.
activities A and B are still in progress.
the project is ahead of schedule.
Question 39
2 / 2 pts
In a PERT network, the optimistic time (to) for a particular activity is 3 weeks, the most
likely time I is 5 weeks, and the pessimistic time (tp) is 7 weeks.
A
2. The best estimate of the standard deviation for the activity is
A. 4 weeks.
B. 2/3 week.
C. 5 weeks
D. 1 2/3 weeks.
Answer 1:
Correct!A
Answer 2:
Correct!B
Question 40
1 / 1 pts
In a PERT network, slack is the
path that requires the longest completion time.
Correct!
time (number of days, weeks, etc.) an activity can be delayed without forcing a delay for
the entire project.
most likely time estimate for an activity.
average of the time estimates for an activity.