Admin Building:-

i-Wooden Doors except Washrooms (Completed)

ii-Aluminium Doors & Windows (Completed)


iii-False Ceiling except washrooms (Completed)
iv-Washrooms & Kitchen False Ceiling Work (Completed)
v-Khaprail Tiles (Completed)
vi-Porceline Tiles
vii-Carpet Tiles(Completed)
viii-Explosion Proof Doors

ix-Paint Work
x-SS Handrailling
xi-Washrooms Wooden Doors
xii-Electrical Cable laying (Completed)
xiii-Electrical Lights, Light Fixtures
xiv-Electrical DBs, CBs, Sockets, Switches

xv-Plumbing Water Supply pipelines, Sewage Water Pipelines


xvi-Plumbing Sanitary Hardwares
Staff Accommodation:-
i-Wooden Doors

ii-Aluminium Doors and Windows


iii- Wood Work (Completed)
iv- False Ceiling

v- Porceline Tiles

vi-SS Handrailling
vi-Explosion Proof Doors
vii-Paint Work
viii-Electrical Cable laying

ix-Electrical Lights, Light Fixtures


x-Electrical DBs, CBs, Sockets, Switches

xi-Plumbing Water Supply pipelines, Sewage Water Pipelines


xii-Plumbing Sanitary Hardwares
Cafeteria:-
i-Wooden Doors

ii-Aluminium Doors and Windows


iii- False Ceiling

iv- Porceline Tiles


v-Explosion Proof Doors
vi-Paint Work
vii-Electrical Cable laying

viii-Electrical Lights, Light Fixtures


ix-Electrical DBs, CBs, Sockets, Switches

x-Plumbing Water Supply pipelines, Sewage Water Pipelines

xi-Plumbing Sanitary Hardw ares (Completed)