You are on page 1of 27

Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant

Location : LISP IV, Malvar, Batangas


Subject : Key Issues and Concerns
Date : February 08, 2021

Noodle Building
Approved Materials & Color for Flooring;
F2 2mm thk Homogeneous Vinyl Sheet @ LG - Engr. Maintenace
Room & MTG 101
F3 300x300mm Homogeneous Vinyl Tiles @ Stair & LG Training
Room
Hygienic Floor Drain for Level 1 (Process Area)
Details of;
W3 - 10mm thk Tempered Glass @ LG MTG 101 and Level 2
Viewing Corridor
W6 - Wiremesh Wall @ N2/NK-NN and N6/NK-NN
Additional Toilet @ Lower Ground
Coving Details for Polyurethane Flooring @ Level 1,2 and 3
Details of Louvers and Roll Up Doors
CONCERNS:
at Level 3 Utility Deck (Metal Sdings) Inside Gutter at N2/NT-NU

Details of 10mm thk Tempered Glass at Level 2 Viewing Corridor Support for Interior Sidings (50mm thk PIR 0.40mm thk )
Railing Details for Scrubber Area??? Railing Details for Stair (Actual)
BOILER
Storm Louver Details

CUP BUILDING
Storm Louver L201 and L202
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Architectural Material's
Date : March 10, 2021

QUANTITY
MATERIALS BUILDINGS STATUS of SRF RESPONSIBLE REMARKS
QTY UNIT

WALL PANEL

50MM THK PRE PAINTED (PIR) METAL PANEL UPW M500 SUPPLIER: Puyat On Going Inst. of Interior
NOODLE BLDG 1,087.90 sq.m Approved
By Puyat Steel (Off White) Steel Sidings 75%

SUPPLIER: Pajora
DC WAREHOUSE 5,681.50 sq.m Approved On Going Installation
Steel
PACKAGING & SUPPLIER: Pajora
803.20 sq.m Approved On Going Installation
GA.24 PRE-PAINTED G.I SHEET ON STEEL FRAME (RIB SEASONING Steel
TYPE) by PAJORA (OFFWHITE) LEASEN SUPPLIER: Pajora
BOILER 553.92 sq.m Approved Already Installed
Steel
SUPPLIER: Pajora Waiting for the Area to be
SILO 1,093.50 sq.m Approved
Steel ready
FLOOR TILES
2MM THK HOMOGENEOUS VINYL SHEET, SEAMLESS
NOODLE BLDG 590.19 sq.m Approved Designer Pending Approved Color
(ARMSTRONG)

NOODLE BLDG 10,145.00 pcs Approved Designer Pending Approved Color

300MM X 300MM HOMOGENEOUS VINYL TILES PACKAGING &


2,627.00 pcs Approved Designer Pending Approved Color
(ARMSTRONG) SEASONING

SS OIL 550.00 pcs Approved Designer Pending Approved Color


NOODLE BLDG 305.00 pcs Pending Designer
PACKAGING &
495.00 pcs Pending Designer Pending Approved Color
SEASONING

SS OIL 270.00 pcs Pending Designer Pending Approved Color


600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES

DC WAREHOUSE 72.00 pcs Pending Designer Pending Approved Color

SILO 50.00 pcs Pending Designer Pending Approved Color

NOODLE BLDG 86.00 pcs Pending Designer Pending Approved Color

PACKAGING 440.00 pcs Pending Designer Pending Approved Color

300MM X 300MM VITRIFIED UNGLAZED FLOOR TILES


SS OIL 334.00 pcs Pending Designer Pending Approved Color

DC WAREHOUSE, 50.00 pcs Pending Designer Pending Approved Color

NOODLE BLDG 475.00 pcs Pending Designer Pending Approved Color

PACKAGING &
798.00 pcs Pending Designer Pending Approved Color
SEASONING
300MM X 600MMVITRIFIED GLAZED WALL TILES
DC WAREHOUSE 125.00 pcs Pending Designer Pending Approved Color

SS OIL 506.00 pcs Pending Designer Pending Approved Color

FLOOR FINISHES
SUPPLIER: Waiting for the Area to be
NOODLE BLDG 260.76 sq.m Approved
Tradetek Inc. ready
PACKAGING & SUPPLIER: Waiting for the Area to be
3,646.28 sq.m Approved
SEASONING Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
DC WAREHOUSE 8,449.29 sq.m Approved
Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
SEALED CONCRETE (ASHFORD) CUP 1,651.77 sq.m Approved
Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
SILO 470.32 sq.m Approved
Tradetek Inc. ready
PREMIX & RAW SUPPLIER: Waiting for the Area to be
855.00 sq.m Approved
WAREHOUSE Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
MESS HALL 115.10 sq.m Approved
Tradetek Inc. ready

On Going Application
NOODLE BLDG 2,832.05 sq.m Approved SUPPLIER: IIPI Inc.
43%
6MM THK MEDIUM DUTY POLYURETHANE CONCRETE
FLOORING SYSTEM (FLOWFRESH)
Waiting for the Area to be
SS OIL 387.00 sq.m Approved SUPPLIER: IIPI Inc.
ready

3MM THK MEDIUM DUTY POLYURETHANE CONCRETE On Going Application


NOODLE BLDG 2,304.89 sq.m Approved SUPPLIER: IIPI Inc.
FLOORING SYSTEM (FLOWFRESH) 43%

On Going Application
NOODLE BLDG 804.00 sq.m Approved SUPPLIER: IIPI Inc.
28%
9MM THK HEAVY DUTY POLYURETHANE CONCRETE
FLOORING SYSTEM (FLOWCRETE)
Waiting for the Area to be
SS OIL 477.42 sq.m Approved SUPPLIER: IIPI Inc.
ready

4MM THK EPOXY FLOORING BOILER 434.89 sq.m for Approval


PLAIN CEMENT, THROWELLED FINISH NOODLE BLDG sq.m

WALL FINISHES
NOODLE BLDG (Lower
35,831.00 pcs Approved SRBC Balance Stair Wall
Ground)
NOODLE BLDG (Level
16,659.00 pcs Approved SRBC Balance Stair Wall
1)
NOODLE BLDG (Level
10,503.00 pcs Approved SRBC Balance Stair Wall
2)
NOODLE BLDG (Level
7,242.00 pcs Approved SRBC Balance Stair Wall
3)
PACKAGING & Waiting for the Area to be
12,915.00 pcs Approved SRBC
SEASONING ready

DC WAREHOUSE 5,665.00 pcs Approved SRBC On Going Installation


CHB 6'' @ 450psi
SS OIL 13,345.00 pcs Approved SRBC On Going Installation

BOILER 1,025.00 pcs Approved SRBC Already Installed

CUP 28,211.00 pcs Approved SRBC On Going Installation

Waiting for the Area to be


SILO 3,890.00 pcs Approved SRBC
ready
Waiting for the Area to be
MESS HALL 9,754.00 pcs Approved SRBC
ready
PREMIX & RAW Waiting for the Area to be
12,809.00 pcs Approved SRBC
WAREHOUSE ready
Waiting for the Area to be
MRF 8,248.00 pcs Approved SRBC
ready
GUARD HOUSE 1 7,700.00 pcs Approved SRBC
ECO BRICKS Delivery Date: 3/23/2021
GUARD HOUSE 2 1,509.00 pcs Approved SRBC
On Going Fabrication
NOODLE BLDG - SUPPLIER: SR B Waiting Drop Wall Details
391.00 sq.m Approved
10MM THK TEMPERED GLASS ON POWDER COATED Viewing Corridor Cruz
ALUMINUM FRAMING
NOODLE BLDG -
53.25 sq.m
Meeting Room
1-6MM THK BOTH FACED FIBER CEMENT BOARD ON Waiting for the Details of
NOODLE BLDG 1,722.20 sq.m Approved SUPPLIER: UP Rise
LIGHT GAUGE FRAME Framing
Waiting for the Details of
9MM THK CEMENT BOARD COLUMN CLADDING NOODLE BLDG 2,910.00 sq.m Approved SUPPLIER: UP Rise
Framing
2-16MM THK BOTH FACED FIRESTOP BOARDS ON G.I Waiting for the Details of
NOODLE BLDG 125.00 sq.m Approved SUPPLIER: UP Rise
STUDS (BORAL) Framing
SUPPLIER: Phil.
ROCKWOOL INSULATION NOODLE BLDG 1,847.20 sq.m Approved Waiting for the Delivery
Insu. Co.
WIREMESH WALL NOODLE BLDG 30.40 sq.m
CEILING FINISHES

SUPPLIER: World On Going Framing


NOODLE BLDG 1,692.00 pcs Approved
Home Depot Installation

PACKAGING & SUPPLIER: World Waiting for the Area to be


125.00 pcs Approved
SEASONING Home Depot ready

SUPPLIER: World Waiting for the Area to be


DC WAREHOUSE 11.00 pcs Approved
Home Depot ready

13MM THK MOISTURE RESISTANT GYPSUM BOARD ON SUPPLIER: World Waiting for the Area to be
SS OIL 376.00 pcs Approved
METAL FRAMING (BORAL) Home Depot ready

SUPPLIER: World Waiting for the Area to be


CUP 282.00 pcs Approved
Home Depot ready

SUPPLIER: World Waiting for the Area to be


SILO 22.00 pcs Approved
Home Depot ready

PREMIX & RAW SUPPLIER: World Waiting for the Area to be


26.00 pcs Approved
WAREHOUSE Home Depot ready
600MM X 600MM ACOUSTIC CEILING TILES SUPPLIER: World Waiting for the Area to be
NOODLE BLDG 1,122.00 pcs Approved
(ARMSTRONG) Home Depot ready

METAL CEILING SS OIL 477.32 sq.m Pending for Approval

WATER PROOFING

Waiting for the Area to be


NOODLE BLDG 671.06 sq.m Approved Premier Cleantech
ready

PACKAGING & Waiting for the Area to be


380.70 sq.m Approved Premier Cleantech
SEASONING ready
Waiting for the Area to be
DC WAREHOUSE 126.17 sq.m Approved Premier Cleantech
ready
Waiting for the Area to be
SS OIL 129.00 sq.m Approved Premier Cleantech
ready
ROOFDECK (MEMBRANE) Waiting for the Area to be
CUP 368.20 sq.m Approved Premier Cleantech
ready
Waiting for the Area to be
MESS HALL 30.52 sq.m Approved Premier Cleantech
ready
PREMIX & RAW Waiting for the Area to be
243.85 sq.m Approved Premier Cleantech
WAREHOUSE ready
Waiting for the Area to be
GUARD HOUSE 1 44.44 sq.m Approved Premier Cleantech
ready
Waiting for the Area to be
GUARD HOUSE 2 24.96 sq.m Approved Premier Cleantech
ready
Waiting for the Area to be
WASHBAY (CEMENTITIOUS) NOODLE BLDG 143.75 sq.m Approved Premier Cleantech
ready
PACKAGING &
807.85 sq.m Approved Premier Cleantech Already Applied
SEASONING
RETAINING WALL (VOLTEX)
DC WAREHOUSE 413.60 sq.m Approved Premier Cleantech Already Applied

DOORS & WINDOWS


SUPPLIER:
NOODLE BLDG 7.00 sets Pending Shop Drawing Approval
Metrotech
STEEL DOOR 2100 x 1800 Ga. 18 45mm thk Hollow Core Epoxy
PACKAGING & SUPPLIER:
Painted Finish, with complete necessary hardwares, all in 2.00 sets Pending Shop Drawing Approval
SEASONING Metrotech
accordance with Architect's specification, with viewing glass
SUPPLIER:
SS OIL 2.00 sets Pending Shop Drawing Approval
Metrotech

SUPPLIER:
NOODLE BLDG 26.00 sets Pending Shop Drawing Approval
Metrotech

SUPPLIER:
DC WAREHOUSE 2.00 sets Pending Shop Drawing Approval
Metrotech
STEEL DOOR 2100mm x 900mm Ga. 18 45mm thk Hollow Core
SUPPLIER:
Epoxy Painted Finish, with complete necessary hardwares, all in SS OIL 3.00 sets Pending Shop Drawing Approval
Metrotech
accordance with Architect's specification with viewing glass
SUPPLIER:
CUP 11.00 sets Pending Shop Drawing Approval
Metrotech

SUPPLIER:
SILO 4.00 sets Pending Shop Drawing Approval
Metrotech

SUPPLIER:
STEEL DOOR2100x1800 Steel Door with 6mm Thk Wire Mesh NOODLE BLDG 3.00 sets Pending Shop Drawing Approval
Metrotech

SUPPLIER:
NOODLE BLDG 1.00 sets Pending Shop Drawing Approval
Metrotech

PACKAGING & SUPPLIER:


TOILET DOORS 2100mm x 900mm Ga. 18 45mm thk Hollow 5.00 sets Pending
SEASONING Metrotech
Core Epoxy Painted Finish with Louver, with complete necessary
hardware all in accordance with Architect's specification SUPPLIER:
DC WAREHOUSE 1.00 sets Pending
Metrotech
Core Epoxy Painted Finish with Louver, with complete necessary
hardware all in accordance with Architect's specification

SUPPLIER:
SS OIL 3.00 sets Pending
Metrotech
SUPPLIER:
NOODLE BLDG 6.00 sets Pending Shop Drawing Approval
Metrotech
PACKAGING & SUPPLIER:
6.00 sets Pending Shop Drawing Approval
SEASONING Metrotech
MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18 45mm
OSM as per Meeting last
thk Hollow Core Epoxy Painted Finish with complete necessary DC WAREHOUSE 36.00 sets Pending
week
hardwares, all in accordance with Architect's specification
SUPPLIER:
CUP 2.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER:
SILO 1.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER: Approved Shop Drawing
STORM LOUVER with HEPA FILTER NOODLE BLDG 4.00 sets Approved
Metrotech 02/27/2020
SUPPLIER: Approved Shop Drawing
NOODLE BLDG 14.00 sets Approved
Metrotech 02/27/2021
SUPPLIER:
STORM LOUVER with INSECT SCREEN BOILER 4.00 sets Approved On Going Fabrication
Metrotech
SUPPLIER: Approved Shop Drawing
CUP 19.00 sets Approved
Metrotech 02/27/2021
FIXED WINDOWS NOODLE BLDG 82.00 sets Approved JNSTW Date of Delivery:
AWNING WINDOWS NOODLE BLDG 3.00 sets Approved JNSTW 03/30/2021

FIXTURES

NOODLE BLDG 1.00 sets

DC WAREHOUSE 1.00 sets


WATER CLOSET PACKAGING &
10.00 sets
SPECS DIV.10 SEC10800 PART 2.01 All toilet SEASONING
Approved DESIGNER
fixtures, fittings and bathroom accessories shall be as manufactured SS OIL 4.00 sets
by AMERICAN STANDARD, BRAVAT or approved equal.
PREMIX & RAW
4.00 sets
WAREHOUSE
MESS HALL 8.00 sets
GUARD HOUSE 1 2.00 sets
GUARD HOUSE 2 1.00 sets
NOODLE BLDG 1.00 sets
DC WAREHOUSE 1.00 sets
PACKAGING &
10.00 sets
SEASONING
PREMIX & RAW
LAVATORIES 5.00 sets Approved DESIGNER
WAREHOUSE
SS OIL 5.00 sets
MESS HALL 2.00 sets
GUARD HOUSE 1 2.00 sets
GUARD HOUSE 2 1.00 sets
DC WAREHOUSE 1.00 sets
PACKAGING &
5.00 sets
SEASONING
MALE URINAL PREMIX & RAW
SPECS DIV.10 SEC10800 PART 2.02 All Urinal shall WAREHOUSE 3.00 sets for Approval of Sensorized
PENDING DESIGNER
be by AMERICAN STANDARD, or approved equal. Urinal
SS OIL 2.00 sets
MESS HALL 1.00 sets
GUARD HOUSE 1 2.00 sets
GUARD HOUSE 2 1.00 sets
NOODLE BLDG 120.00 pcs
DC WAREHOUSE 42.00 pcs
HYGIENIC FLOOR DRAIN (100mm) PACKAGING &
15.00 pcs
SEASONING
SS OIL 6.00 pcs
PACKAGING &
12.00 pcs
SEASONING
PREMIX & RAW
3.00 pcs
WAREHOUSE
FLOOR DRAIN
SS OIL 7.00 pcs
GUARD HOUSE 1 3.00 pcs
GUARD HOUSE 2 1.00 pcs
MESS HALL 15.00 pcs
HAND DRYER SS OIL 3.00 sets
KITCHEN SINK MESS HALL 5.00 sets
NOODLE BLDG 5.00 sets
DC WAREHOUSE 1.00 sets
PACKAGING &
4.00 sets
MIRROR SEASONING
4100mm x 1200mm 1/4" thk. Distorition
PREMIX & RAW
Free Mirror on 3/4" thk. Plywood Backing 2.00 sets
WAREHOUSE
600mm x 1200mm 1/4" thk.
Distorition Free Mirror on 3/4" thk. Plywood Backing SS OIL 2.00 sets
MESS HALL 3.00 sets
GUARD HOUSE 1 2.00 sets
GUARD HOUSE 2 1.00 sets

PAINTING WORKS
NOODLE BLDG 13,002.92 sq.m Approved SRBC On Going Application
Waiting for the Area to be
DC WAREHOUSE 708.14 sq.m Approved SRBC
ready
PACKAGING & Waiting for the Area to be
1,605.50 sq.m Approved SRBC
SEASONING ready
Waiting for the Area to be
SKIMCOAT SS OIL 2,025.73 sq.m Approved SRBC
ready
Waiting for the Area to be
CUP 4,305.14 sq.m Approved SRBC
ready
Waiting for the Area to be
SILO 622.00 sq.m Approved SRBC
ready
BOILER 195.00 sq.m Approved SRBC On Going Application

METAL FABRICATION
STAIR RAILINGS
STAIR 1 NOODLE BLDG 38.70 LM SRBC
STAIR 2 NOODLE BLDG 38.70 LM SRBC
STAIR 3 NOODLE BLDG 35.50 LM SRBC
STAIR 4 NOODLE BLDG 35.50 LM Approved SRBC Start of Installation
Materials By
STAIR 5 NOODLE BLDG 35.50 LM SRBC 03/22/2021
Designer
STAIR 6 NOODLE BLDG 24.40 LM SRBC
STAIR 7 NOODLE BLDG 24.40 LM SRBC
STAIR 8 NOODLE BLDG 24.40 LM SRBC

Prepared By: Approved by: Submitted to:

ANDREW MANALO JOSEPH EDGAR CAYA CIELO LINDA C.


Architect - SRBC PIC Engr. - SRBC Architect - DCCD
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Architectural Material's
Date : April 02. 2021

QUANTITY TARGET DATE


STATUS of RESPON - DATE
MATERIALS TARGET OF START OF TARGET REMARKS
QTY UNIT SRF SIBLE ORDERED
DELIVERY INSTALL. ACCOMPLISH
MESS HALL BUILDING
ROOFING
SUPPLIER: Waiting for the Waiting for the
Ga.24 Pre-painted long span G.I Sheet 182.34 sq.m Approved Not yet Installed 30-Jan-21
Puyat Steel Approved Color Area to be ready
Waiting for the
Roofing Insulation 182.34 sq.m
Area to be ready

Waiting for the


Ga.24 Pre-painted G.I Flashing (includes 300mm overlapping) 24.40 lm
Area to be ready

Waiting for the


Ga.24 Pre-painted G.I Ridge Roll (includes 300mm overlapping) 21.96 lm
Area to be ready
Waiting for the
Ga.24 SS Gutter tig welded (includes 300mm overlapping) 43.92 lm
Area to be ready
Waiting for the
Ga.24 SS Gutter hanger @300mm spacing 128.00 pcs
Area to be ready
Waiting for the
Hardware Accessories (tekscrew, rivets, sealant, touch up paint, 1.00 lot
Area to be ready
FLOOR TILES
For Approval of Waiting for the
300mm x 300mm Homogeneous Vinyl Tiles 202.06 sq.m Designer 6-Jan-00
Color Approved Color
Pending Approved
Waiting for the
600mm x 600mm Vitrified Unglazed Floor Tiles 30.38 pcs Approved Designer 14-Jan-00 Color - for Follow
Approved Color
Up
Waiting for the
300mm x 300mm Vitrified Unglazed Floor Tiles 126.41 pcs Approved Designer 6-Jan-00
Approved Color
FLOOR FINISHES
SEALED CONCRETE (ASHFORD)
SUPPLIER: Waiting for the
STAIR 1 Approved 31-Dec-99
Tradetek Inc. Area to be ready
87.36 sq.m
SUPPLIER: Waiting for the
STAIR 2 Approved 31-Dec-99
Tradetek Inc. Area to be ready

WALL FINISHES
On Going On Going On Going
CHB 6'' @ 450psi - LEVEL 2 1,421.34 sq.m Approved SRBC 20-Apr-21
Installation Installation Installation
300X600MM VITRIFIED GLAZED WALL TILES
Waiting Approved
T101/T102/T103 74.11 sq.m Approved Designer
Color
CEILING FINISHES

13mm thk moisture resistant gypsum board on metal framing

Waiting for the


DISHWASHING AREA sq.m For P.O SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
KITCHEN sq.m For P.O SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
TOILET 101 69.43 sq.m For P.O SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
T102 sq.m For P.O SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
T103 sq.m For P.O SRBC 6-Feb-21 5-Apr-21
Area to be ready
600mm x 600mm acoustic ceiling tiles
Waiting for the
MESS HALL For P.O SRBC 5-Apr-21 12-Apr-21 12-Apr-21 22-Apr-21
Area to be ready
202.06 sq.m
Waiting for the
WAITING AREA For P.O SRBC 5-Apr-21 12-Apr-21 16-Apr-21 26-Apr-21
Area to be ready
Exposed Slab Soffit, Painted Finish
Open Area in Level 2
WATER PROOFING
Premier Waiting for the
ROOFDECK (MEMBRANE) sq.m For P.O 25-Mar-21 5-Apr-21 6-Apr-21 11-Apr-21
Cleantech Area to be ready
MALE TOILET
FEMALE TOILET
ROOF DECK
CONCRETE TOPPING
DOORS & WINDOWS
2100 x 900 Ga 18 Epoxy Painted Steel Door, with complete necessary
sets Approved Metrotech PO Mar-15-21 30-Mar-21 31-Mar-21 5-Apr-21 For P.O.
hardwares, all in accordance with Architect's specification

2100 x 900 Ga 18 Epoxy Painted Steel Door w/ Louver, with complete


sets Approved Metrotech PO Mar-15-21 30-Mar-21 31-Mar-21 10-Apr-21
necessary hardwares, all in accordance with Architect's specification

Waiting for Waiting for Accessories Shop


1200 x 2400 10mm thk. Tinted Tempered Glass on Aluminum Framing sets 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
Approval Approval Drawing Approval

FIXTURES
WATER CLOSET
SPECS DIV.10 SEC10800 PART 2.01 All toilet fixtures,
sets Approved SRBC 18-Mar-21 28-Apr-21 28-Apr-21 1-May-21 For Deliver
fittings and bathroom accessories shall be as manufactured by AMERICAN
STANDARD, BRAVAT or approved equal.
LAVATORIES sets Dis Approved DESIGNER
MALE URINAL
SPECS DIV.10 SEC10800 PART 2.02 All Urinal shall be by
sets Dis Approved DESIGNER
AMERICAN STANDARD, or approved equal.

HYGIENIC FLOOR DRAIN (100mm) pcs None Yet SRBC

MIRROR
4100mm x 1200mm 1/4" thk. Distorition Free Mirror on
3/4" thk. Plywood Backing sets
600mm x 1200mm 1/4" thk. Distorition Free Mirror on 3/4"
thk. Plywood Backing

PAINTING WORKS

SKIMCOAT sq.m Approved SRBC 26-Feb-21 2-Mar-21 2-Mar-21 3-Apr-21 For Order

Waiting Approved
EXTERIOR AND INTERIOR WALL Designer
Color
METAL FABRICATION
STAIR RAILINGS
STAIR 1 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
For Actual
STAIR 2 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
Measurement
WINDOW STEEL RAILINGS lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21

LEGEND
Prepared By: Approved by: Submitted to: Waiting for the Approval
HOLD
ALEXANDRA JANE UY JED ELLER CIELO LINDA C. PEREZ On Going Installation
Site Architect - SRBC Project Manager. - SRBC Architect - DCCD Already Installed
Waiting for the Area to be ready
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Architectural Material's
Date : April 02. 2021

QUANTITY TARGET DATE


STATUS of RESPON - DATE
MATERIALS TARGET OF START OF TARGET REMARKS
QTY UNIT SRF SIBLE ORDERED
DELIVERY INSTALL. ACCOMPLISH
NOODLE BUILDING
ROOFING

25mm thk Insulated (PIR) Roofing System (0.60mm Outer Metal Skin and SUPPLIER:
4,815.00 sq.m Approved Already Installed Already Installed 23-Jan-21 30-Jan-21 Already Installed
0.40mm Inner Metal Skin) UPR 250 by Puyat Steel (OFF WHITE) Puyat Steel

WALL PANEL
On Going On Going Inst. of
50MM THK PRE PAINTED (PIR) METAL PANEL UPW M500 By SUPPLIER:
1,087.90 sq.m Approved Installation of 17-Feb-21 18-Feb-21 5-Apr-21 Interior Sidings
Puyat Steel (Off White) - INTERIOR SIDINGS Puyat Steel
Interior Sidings 95%
FLOOR TILES
2MM THK HOMOGENEOUS VINYL SHEET, SEAMLESS Waiting for the
590.19 sq.m Approved Designer 15-Apr-21 15-Apr-21 22-Apr-21
(ARMSTRONG) Approved Color
Waiting for the
300MM X 300MM HOMOGENEOUS VINYL TILES (ARMSTRONG) 10,145.00 pcs Approved Designer 15-Apr-21 15-Apr-21 30-Apr-21
Approved Color
Pending Approved
Waiting for the Color - for Follow
600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES 305.00 pcs Pending Designer 15-Apr-21 15-Apr-21 22-Apr-21
Approved Color Up
Waiting for the
300MM X 300MM VITRIFIED UNGLAZED FLOOR TILES 86.00 pcs Pending Designer 15-Apr-21 15-Apr-21 22-Apr-21
Approved Color
Waiting for the
300MM X 600MMVITRIFIED GLAZED WALL TILES 475.00 pcs Pending Designer 15-Apr-21 15-Apr-21 22-Apr-21
Approved Color
FLOOR FINISHES
SEALED CONCRETE (ASHFORD)
SUPPLIER: Waiting for the
ENGR. MAINTENANCE TOOL ROOM (LOWER GROUND) 259.16 sq.m Approved 13-Nov-20 20-Apr-21 20-Apr-21 21-Apr-21
Tradetek Inc. Area to be ready
SUPPLIER: Waiting for the
ALKALINE TANKS 47.00 sq.m Approved 13-Nov-20 20-Apr-21 20-Apr-21 21-Apr-21
Tradetek Inc. Area to be ready

6MM THK MEDIUM DUTY POLYURETHANE CONCRETE FLOORING On Going


SYSTEM (FLOWFRESH) Application 63%

SUPPLIER: Waiting for the Waiting for the


PROCESS AREA (LEVEL 1) 1,918.80 sq.m Approved 10-Apr-21 10-Apr-21 12-Apr-21
IIPI Inc. Area to be ready Area to be ready

SUPPLIER: Waiting for the Waiting for the


COOLING AREA (LEVEL 1) 370.64 sq.m Approved 10-Apr-21 10-Apr-21 12-Apr-21
IIPI Inc. Area to be ready Area to be ready

SUPPLIER:
PACKAGING AREA1 (LEVEL 1) 1,367.76 sq.m Approved DONE 8-Apr-21 8-Apr-21 10-Apr-21 DONE
IIPI Inc.

3MM THK MEDIUM DUTY POLYURETHANE CONCRETE FLOORING On Going


SYSTEM (FLOWFRESH) Application 74%
SUPPLIER:
ROLLER AREA (LEVEL 1) 472.32 sq.m Approved DONE 25-Mar-21 5-Apr-21 6-Apr-21 DONE
IIPI Inc.
SUPPLIER:
MIXER (LEVEL 2) 472.32 sq.m Approved DONE 25-Mar-21 29-Mar-21 31-Mar-21 DONE
IIPI Inc.

SUPPLIER: Waiting for the Waiting for the


HOPPER (LEVEL 3) 472.32 sq.m Approved 25-Mar-21 19-Apr-21 22-Apr-21
IIPI Inc. Area to be ready Area to be ready

SUPPLIER: Waiting for the


PACKAGING AREA 2 887.93 sq.m Approved 25-Mar-21 25-Mar-21 28-Mar-21 DONE
IIPI Inc. Area to be ready

9MM THK HEAVY DUTY POLYURETHANE CONCRETE FLOORING On Going


SYSTEM (FLOWCRETE) Application 28%

SUPPLIER: Waiting for the Waiting for the


PROCESS AREA EQUIPMENT LINE (LEVEL 1) 934.80 Approved 12-Apr-21 12-Apr-21 14-Apr-21
IIPI Inc. Area to be ready Area to be ready

WALL FINISHES
On Going On Going On Going On Going
CHB 6'' @ 450psi - LOWER GROUND 481.81 sq.m Approved SRBC 19-Apr-21
Installation Installation Installation Installation
On Going On Going On Going On Going
CHB 6'' @ 450psi - LEVEL 2 196.50 sq.m Approved SRBC 20-Apr-21
Installation Installation Installation Installation
On Going On Going On Going On Going
CHB 6'' @ 450psi - LEVEL 3 1,585.83 sq.m Approved SRBC 20-Apr-21
Installation Installation Installation Installation
DRYWALL 1-
6mm thk Both Faced Fiber Cement Board on light gauge frame
On Going Framing
LOWER GROUND 326.99 sq.m Approved SRBC 12-Feb-21 10-Mar-21 29-Mar-21 10-Apr-21
Installation
On Going Framing
LEVEL 1 (COOLING AREA & PACKAGING 1) 239.72 sq.m Approved SRBC 12-Feb-21 10-Mar-21 22-Mar-21 14-Apr-21
Installation
LEVEL 2 (MIXER) 81.95 sq.m Approved SRBC 12-Feb-21 10-Mar-21 8-Mar-21 18-Mar-21 DONE
On Going Framing
LEVEL 2 (PACKAGING 2) 223.93 sq.m Approved SRBC 12-Feb-21 10-Mar-21 22-Mar-21 11-Apr-21
Installation
Waiting for the
LEVEL 3 (HOPPER) 289.53 sq.m Approved SRBC 12-Feb-21 10-Mar-21 7-Apr-21 17-Apr-21
Area to be ready
On Going Framing
VIEWING CORRIDOR 96.00 sq.m Approved SRBC 12-Mar-21 15-Mar-21 15-Mar-21 6-Apr-21
Installation
Waiting for the
9MM THK CEMENT BOARD COLUMN CLADDING - Exterior Wall 2,910.00 sq.m Approved SRBC 15-Mar-21 22-Mar-21 27-Mar-21 21-Apr-21
Details of Framing
DRYWALL
On Going Framing
2-16mm THK both Faced Firestop Boards on G.I studs @ Lower 124.50 sq.m Approved SRBC 12-Mar-21 15-Mar-21 5-Apr-21 14-Apr-21
Installation
Ground (Engr. Maintenance Office)
10MM THK TEMPERED GLASS ON POWDER COATED ALUMINUM Waiting for the
391.00 sq.m Approved JNSTW 15-Feb-21 24-Mar-21 26-Mar-21 27-Mar-21
FRAMING - Viewing Corridor Area to be ready
10MM THK TEMPERED GLASS ON POWDER COATED ALUMINUM Shop Drawing Shop Drawing for
53.25 sq.m JNSTW 26-Mar-21 15-Apr-21 16-Apr-21 23-Apr-21
FRAMING - @ Lower Ground Meeting Room for Approval Approval
WIREMESH WALL (50MM BI PIPE & CYCLONE WIRE)
FRONT EXTERIOR WALL 70.63 sq.m Pending SRBC 7-Apr-21 9-Apr-21 10-Apr-21 16-Apr-21 Waiting for the
REAR ELEVATION 48.56 sq.m Pending SRBC 7-Apr-21 9-Apr-21 15-Apr-21 21-Apr-21 Approval
300X600MM VITRIFIED GLAZED WALL TILES
T101/T102/T103 190.00 pcs Pending Designer Waiting Approved
WASHBAY 125.00 pcs Pending Designer Color
CEILING FINISHES
13MM THK MOISTURE RESISTANT GYPSUM BOARD ON METAL
FRAMING (BORAL)
Waiting for the
HALLWAY 158.46 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
STO/VISUALS ROOM 32.24 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
TOILET 101 7.32 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
WASHBAY 69.12 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
ANTE ROOM 40.20 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
ROLLER AREA 373.60 sq.m Approved Designer 6-Feb-21 26-Mar-21 8-Apr-21 23-Apr-21 HOLD

PACKAGING AREA1 1,369.58 sq.m Approved SRBC 6-Feb-21 26-Mar-21 29-Mar-21 13-Apr-21 HOLD - 3/22/2021

MIXER 467.12 sq.m Approved Designer 6-Feb-21 HOLD


On Going Framing
VIEWING CORRIDOR 446.14 sq.m Approved SRBC 6-Feb-21 26-Mar-21 26-Mar-21 10-Apr-21
Installation
Waiting for the
PACKAGING AREA 2 1,366.27 sq.m Approved SRBC 6-Feb-21 7-Apr-21 8-Apr-21 23-Apr-21
Area to be ready
HOPPER 467.12 sq.m Approved Designer 6-Feb-21 HOLD
Waiting for the
STAIR 74.88 sq.m Approved SRBC
Area to be ready
600MM X 600MM ACOUSTIC CEILING TILES (ARMSTRONG)
Waiting for the
TRAINING ROOM 260.00 sq.m Approved SRBC 5-Apr-21 12-Apr-21 12-Apr-21 22-Apr-21
Area to be ready
Waiting for the
ENGR. MAINTENANCE OFFICE 117.28 sq.m Approved SRBC 5-Apr-21 12-Apr-21 16-Apr-21 26-Apr-21
Area to be ready
Waiting for the
MTG 101 26.78 sq.m Approved SRBC 5-Apr-21 12-Apr-21 19-Apr-21 27-Apr-21
Area to be ready
WATER PROOFING
Premier Waiting for the
ROOFDECK (MEMBRANE) 671.06 sq.m Approved 25-Mar-21 5-Apr-21 6-Apr-21 11-Apr-21
Cleantech Area to be ready
Premier Waiting for the
WASHBAY (CEMENTITIOUS) 143.75 sq.m Approved 25-Mar-21 20-Apr-21 21-Apr-21 28-Apr-21
Cleantech Area to be ready
DOORS & WINDOWS
STEEL DOOR 2100 x 1800 Ga. 18 45mm thk Hollow Core Epoxy Painted
Accessories Shop
Finish, with complete necessary hardwares, all in accordance with 7.00 sets Pending Designer PO Mar-15-21 30-Mar-21 31-Mar-21 5-Apr-21
Drawing Approval
Architect's specification, with viewing glass
STEEL DOOR 2100mm x 900mm Ga. 18 45mm thk Hollow Core Epoxy
Accessories Shop
Painted Finish, with complete necessary hardwares, all in accordance with 26.00 sets Pending Designer PO Mar-15-21 30-Mar-21 31-Mar-21 10-Apr-21
Drawing Approval
Architect's specification with viewing glass
Accessories Shop
STEEL DOOR2100x1800 Steel Door with 6mm Thk Wire Mesh 3.00 sets Pending Designer PO Mar-15-21 30-Mar-21 31-Mar-21 4-Apr-21
Drawing Approval
TOILET DOORS 2100mm x 900mm Ga. 18 45mm thk Hollow Core
Accessories Shop
Epoxy Painted Finish with Louver, with complete necessary hardware all 1.00 sets Pending Designer PO Mar-15-21 30-Mar-21 31-Mar-21 2-Apr-21
Drawing Approval
in accordance with Architect's specification
MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18 45mm thk
SUPPLIER: Verify Actual
Hollow Core Epoxy Painted Finish with complete necessary hardwares, all 6.00 sets Pending
Metrotech Dimension on Site
in accordance with Architect's specification

SUPPLIER: Approved Shop


STORM LOUVER with HEPA FILTER 4.00 sets Approved 1-Mar-21 29-Mar-21 6-Apr-21 8-Apr-21
Metrotech Drawing 02/27/2020

SUPPLIER: Approved Shop


STORM LOUVER with INSECT SCREEN 14.00 sets Approved 1-Mar-21 8-Apr-21 9-Apr-21 15-Apr-21
Metrotech Drawing 02/27/2021

600X600mm 10mm thk. Tinted Tempered glass panels on poder coated


2.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
aluminum frame - W101 (T101 & T102)
1000X1700mm 10mm thk. Tinted Tempered glass panels on poder coated ALUMINUM
1.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21 FRAME
aluminum frame - W102 (ENG MAIN. OFFICE)
ALREADY ON
1700X3000mm 10mm thk. Tinted Tempered glass panels on poder coated SITE FOR
1.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
aluminum frame - W103 (ENG MAIN. OFFICE) INSTALLATION
1000X1150mm 10mm thk. Tinted Tempered glass panels on poder coated
16.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
aluminum frame - STAIR
4000X1150mm 10mm thk. Tinted Tempered glass panels on poder coated
4.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
aluminum frame - LG ANTE ROOM & OPEN
2200X1150mm 10mm thk. Tinted Tempered glass panels on poder coated
6.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
aluminum frame - L 2 (VIEWING CORRIDOR)
GLASS TO
2400X600mm 10mm thk. Tinted Tempered glass panels on poder coated FOLLOW
3.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
aluminum frame - ALKALINE & VIEWING CORRIDOR

4000X650mm 10mm thk. Tinted Tempered glass panels on poder coated


55.00 sets Approved JNSTW 16-Mar-21 4/13/2021 4/14/2021 22-Apr-21
aluminum frame - PROCESSS AREA

FIXTURES
WATER CLOSET
SPECS DIV.10 SEC10800 PART 2.01 All toilet fixtures,
3.00 sets Approved SRBC 18-Mar-21 28-Apr-21 28-Apr-21 1-May-21
fittings and bathroom accessories shall be as manufactured by AMERICAN
STANDARD, BRAVAT or approved equal.
LAVATORIES 1.00 sets Dis Approved DESIGNER
MALE URINAL for Approval of
SPECS DIV.10 SEC10800 PART 2.02 All Urinal shall be by Sensorized Urinal
4.00 sets Dis Approved DESIGNER and Faucet
AMERICAN STANDARD, or approved equal.

Waiting for the


HYGIENIC FLOOR DRAIN (100mm) 120.00 pcs SRBC
SAMPLE

MIRROR
4100mm x 1200mm 1/4" thk. Distorition Free Mirror on
3/4" thk. Plywood Backing 5.00 sets
600mm x 1200mm 1/4" thk. Distorition Free Mirror on 3/4"
thk. Plywood Backing

PAINTING WORKS
On Going
SKIMCOAT 13,002.92 sq.m Approved SRBC 26-Feb-21 2-Mar-21 2-Mar-21 3-Apr-21
Application

Waiting Approved
EXTERIOR AND INTERIOR WALL Pending Designer
Color
METAL FABRICATION
STAIR RAILINGS
STAIR 1 38.70 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
STAIR 2 38.70 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
On Going
STAIR 3 35.50 lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21
Installation
STAIR 4 35.50 lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21
STAIR 5 35.50 lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21
STAIR 6 24.40 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21 Already Installed
STAIR 7 24.40 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21 Already Installed
STAIR 8 24.40 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21 Already Installed

LEGEND
Prepared By: Approved by: Submitted to: Waiting for the Approval
HOLD
ANDREW MANALO JED ELLER CIELO LINDA C. PEREZ On Going Installation
Architect - SRBC Project Manager. - SRBC Architect - DCCD Already Installed
Waiting for the Area to be ready
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Plan
Date : September 17, 2021

ITEM TOTAL APRIL MAY


DESCRIPTION UNIT
NO. QTY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
SS OIL
A WALL FINISHES
CHB 150mm thk @ 450psi - Exterior & Interior
Exterior Wall 959.22 sq.m
Interior Wall 525.3 sq.m
Plastering & Skimcoat
Exterior Wall 1918.44 sq.m
Interior Wall 1050.6 sq.m
B CEILING FINISHES
13mm thk moisture resistant gypsum board on metal framing
Packaging Area 387.63 sq.m
HALLWAY 206.87 sq.m
T101 17.1 sq.m
T102 14.3 sq.m
METAL CEILING 477.42 sq.m
D FLOORING FINISHES
300mm x 300mm Homogeneous Vinyl Tiles 75 sq.m
600mm x 600mm Vitrified Unglazed Floor Tiles 103 sq.m
300mm x 300mm Vitrified Unglazed Floor Tiles 30 sq.m

387.63 sq.m
6mm thk medium duty polyurethane concrete flooring system

477.42 sq.m
9mm thk Heavy duty polyurethane concrete flooring system

E DOORS & WINDOWS

2100 x 900 Ga 18 Epoxy Painted Steel Door w/ Louver, with


complete necessary hardwares, all in accordance with 3.00 sets
Architect's specification

2100 x 900 Ga 18 Epoxy Painted Steel Door, with complete


necessary hardwares, all in accordance with Architect's 1.00 sets
specification
2100 x 900 Ga 18 Epoxy Painted Steel Door, with complete
necessary hardwares, all in accordance with Architect's 1.00 sets
specification- Fire Exit Door
Window
4000mmx600mm 10mm thk tinted tempered glass window 6.00 sets
2000mmx600mm storm louvers with insect screen 1.00 set
4000mmx600mm storm louvers with insect screen 3.00 set
F PAINTING WORKS
150mm thk CHB
Ext wall 959.22 sq.m
Int Wall 2,009.82 sq.m
Conrete beams and columns 745.45 sqm
H FIXTURES
TOILET 4 set
URINAL - SENSORIZED 2 set
FAUCET - SENSORIZED 5 set
MIRROR
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Plan
Date : September 17, 2021

ITEM APRIL MAY


DESCRIPTION TOTAL QTY UNIT REMARKS
NO.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8
NOODLE BUILDING
A WALL FINISHES
CHB 150mm thk @ 450psi - Exterior & Interior
Stair 1 (LG to Level 3) 356.6 sq.m On Going @ Level 3
Stair 2 (LG to Level 3) 356.6 sq.m On Going @ Level 3
Stair 3 (LG to Level 3) 344.13 sq.m On Going @ Level 2
Stair 4 (LG to Level 3) 264.1 sq.m On Going @ Level 2
Stair 5 (LG to Level 3) 264.1 sq.m On Going @ Level 2
Level 2 (Packaging Area 2 GL NY / N2-N6) 196.5 sq.m BEAM - CONCRETE POURING
Lower Ground Engineering Room 167.81 sq.m TWO LAYER
Plastering & Skimcoat
Interior Wall 1908.16 sq.m
Exterior Wall 8690.64 sq.m
additional Zocalo for water
Zocalo (95.50m x 0.20m) Utility Deck (for water stoppage) 19.10 sq.m
stoppage
10mm Thk Tempered Glass on Powder Coated aluminum
Framing System
Waiting for the Area to be
Lower Ground MTG 101 53.25 sq.m
ready

Level 2 (Viewing Corridor) 286.44 sq.m Framing Done - for skimcoat

DRYWALL 1-
6mm thk Both Faced Fiber Cement Board on light gauge frame
Lower Ground 326.99 sq.m Framing On-Going
Level 1 (Cooling Area & Packaging 1) 239.72 sq.m Framing On-Going
Level 2 (Packaging 2) 223.93 sq.m Framing On-Going
Waiting for the Area to be
Level 3 (Hopper) 289.53 sq.m
ready
DRYWALL 2-
Waiting for the Area to be
16mm THK both Faced Firestop Boards on G.I studs @ 124.5 sq.m
ready
Lower Ground (Engr. Maintenance Office)
Wiremesh wall (50mm BI Pipe & Cyclone Wire)
Front Exterior Wall 70.63 sq.m Waiting for the Area to be
Rear Elevation 48.56 sq.m ready
WALL CLADDING Waiting for the Area to be
9mm thk cement board column - EXTERIOR WALL ready
B CEILING FINISHES
13mm thk moisture resistant gypsum board on metal framing
HALLWAY LOWER GROUND 137.65 sq.m
STO/VISUALS ROOM LOWER GROUND 31.4 sq.m
TOILET 101 (LOWER GROUND) 7.32 sq.m
WASHBAY 276.24 sq.m
ANTE ROOM LOWER GROUND 53.19 sq.m
ROLLER AREA LEVEL 1 472.32 sq.m
PACKAGING AREA1 LEVEL 1 1367.76 sq.m HOLD- as per Designer
MIXER (LEVEL 2) 472.32 sq.m
VIEWING CORRIDOR LEVEL 2 445.31 sq.m Waiting for other Trades
PACKAGING AREA 2 (LEVEL 2) 1367.74 sq.m
HOPPER LEVEL 3 472.32 sq.m
STAIR LEVEL 3 124.91 sq.m
600mm x 600mm acoustic ceiling tiles
TRAINING ROOM 261.34 sq.m
Waiting for the Area to be
ENGR. MAINTENANCE OFFICE 114.11 sq.m
ready
MTG 101 27.96 sq.m
C WATERPROOFING
Membrane
UTILITY DECK 445.3 sq.m Waiting for the Area to be
ROOF DECK (STAIR) 183.12 sq.m ready
ALKALINE TANKS (RC DECK) 45.96 sq.m
Cementitious
WASHBAY (X4) 17.25 sq.m
D FLOORING FINISHES
Sealed concrete (Ashford)
ENGR. MAINTENANCE TOOL ROOM (LOWER
259.16 sq.m
GROUND) Waiting for the Area to be
ready
ALKALINE TANKS 47 sq.m

2mm thk Homogeneous Vinyl Sheet, seamless


Pending Approved Color By
ENGR. MAINTENANCE OFFICE 115.4 sq.m
the Designer
MTG 101 27.4 sq.m Pending Approved Color By
the Designer
VIEWING CORRIDOR 445 sq.m
300mm x 300mm Homogeneous Vinyl Tiles
HALLWAY (Lower Ground) 158.37 sq.m
Pending Approved Color By
STO/VISUALS ROOM (Lower Ground) 32.15 sq.m
the Designer
TRAINING ROOM (Lower Ground) 259.88 sq.m
STAIR 1 90.87 sq.m
STAIR 2 102.87 sq.m
Waiting for the Area to be
STAIR 3 102.87 sq.m
ready
STAIR 4 108.8 sq.m
STAIR 5 108.8 sq.m
600mm x 600mm Vitrified Unglazed Floor Tiles
WASH BAY 69.06 sq.m
Pending Approved Color By
ANTE ROOM (LOWER GROUND) 39.97 sq.m the Designer

300mm x 300mm Vitrified Unglazed Floor Tiles - TOILET Pending Approved Color By
86 pcs
101 (LOWER GROUND) the Designer
3mm Thk Medium Duty Polyurethane Concrete Flooring
System
ROLLER AREA (LEVEL 1) 472.32 sq.m
On Going Application 43%
MIXER (LEVEL 2) 472.32 sq.m
Waiting for the Area to be
HOPPER (LEVEL 3) 472.32 sq.m
ready
6mm thk medium duty polyurethane concrete flooring
system
PROCESS AREA (LEVEL 1) 1918.8 sq.m
COOLING AREA (LEVEL 1) 370.64 sq.m On Going Application 43%
PACKAGING AREA1 (LEVEL 1) 1367.76 sq.m

9mm thk Heavy duty polyurethane concrete flooring system

PROCESS AREA EQUIPMENT LINE (LEVEL 1) 934.8 sq.m On Going Application 28%

E DOORS & WINDOWS


STEEL DOOR 2100 x 1800 Ga. 18 45mm thk Hollow Core
Epoxy Painted Finish, with complete necessary hardwares, all Waiting for the Approval of
7.00 sets
in accordance with Architect's specification, with viewing Shop Drawings
STEEL DOOR 2100mm x 900mm Ga. 18 45mm thk Hollow
glass
Core Epoxy Painted Finish, with complete necessary Waiting for the Approval of
26.00 sets
hardwares, all in accordance with Architect's specification with Shop Drawings
viewingDOOR2100x1800
STEEL glass Steel Door with 6mm Thk Wire
3.00 sets
Mesh
Hollow Core Epoxy Painted Finish with Louver, with complete
1.00 sets
necessary hardware all in accordance with Architect's
Waiting for the Area to be
GLASS DOOR 1.00 sets
ready
MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18
45mm thk Hollow Core Epoxy Painted Finish with complete Waiting for the Approval of
6.00 sets
necessary hardwares, all in accordance with Architect's Shop Drawings
specification
AWNING WINDOWS 87.00 sets
STORM LOUVER with INSECT SCREEN by
18.00 sets On Going Fabrication
MTETROTECH
F PAINTING WORKS
SKIMCOAT 13,002.92 sq.m
INTERIOR WALLS 954.09 sq.m
Waiting for the Approval Color
EXTERIOR WALLS 4,345.33 sq.m by the Designer

ELEVATOR WALL
G STAIR RAILINGS
Stair 3 (LG to Level 3) 344.13 sq.m
Stair 4 (LG to Level 3) 264.1 sq.m
Stair 5 (LG to Level 3) 264.1 sq.m
H FIXTURES
TOILET
URINAL - SENSORIZED
FAUCET - SENSORIZED
MIRROR
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Construction Schedule
Date : September 17, 2021

APRIL MAY
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
PACKAGING & SEASONING
A WALL FINISHINGS
150 mm thk CHB Wall including reinforcement ;in cement and sand mortar (1:3)
Exterior Wall 1,109.60 sq.m
Interior Wall 380.00 sq.m
Plastering & Skimcoat
Exterior Wall 2,219.20 sq.m
Interior Wall 760.00 sq.m
B CEILING FINISHES
13MM THK MOISTURE RESISTANT GYPSUM BOARD ON
125.00 pcs
METAL FRAMING
D FLOOR TILES
600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES 495.00 pcs
300MM X 300MM VITRIFIED UNGLAZED FLOOR TILES 440.00 pcs
300MM X 600MMVITRIFIED GLAZED WALL TILES 798.00 pcs
300MM X 300MM HOMOGENEOUS VINYL TILES 2,627.00 pcs
E FLOOR FINISHES
SEALED CONCRETE (ASHFORD) 3,646.28 sq.m
F WATER PROOFING
ROODECK (MEMBRANE) 55.68 sq.m
G DOORS & WINDOWS

2100 x 1800 Ga. 18 45mm thk Hollow Core Epoxy Painted Finish,
with complete necessary hardwares, all in accordance with Architect's 2.00 sets
specification, with viewing glass

TOILET DOORS 2100mm x 900mm Ga. 18 45mm thk Hollow Core


Epoxy Painted Finish with Louver, with complete necessary hardware 5.00 sets
all in accordance with Architect's specification

MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18 45mm


thk Hollow Core Epoxy Painted Finish with complete necessary 6.00 sets
hardwares, all in accordance with Architect's specification

A.9 PAINTING WORKS


Walls
150mm thk CHB 1,854.03 sq.m
Conrete beams and columns sq.m
Ceiling
13mm thk moisture resistant gypsum board on metal framing 310.73 sq.m
Slab soffit sq.m
Exposed Steel Structure, epoxy painted 3,594.00 sq.m
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Construction Schedule
Date : September 17, 2021

APRIL
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
CUP BUILDING
A WALL FINISHINGS

150 mm thk CHB Wall including reinforcement ;in cement and sand mortar (1:3)

Exterior Wall 532.26 sq.m


Interior Wall 1,800.33 sq.m
Plastering & Skimcoat
Interior Wall 1,800.33 sq.m
Exterior Wall 2,864.85 sq.m
Concrete Gutter 65.00 lm
B FLOOR FINISHES

SEALED CONCRETE (ASHFORD) 2,140.00 sq.m

C DOORS & WINDOWS


2100x900 steel Door 3.00 sets
2100x900 steel Door with Panic Exit Device 8.00 sets
2100x1800 Double Steel Door 2.00 sets
Roll Up Door
3000x3000 mm Roll Up Door 2.00 sets

3763mmx3100mm storm Ga.16 Storm Louvers Epoxy


19.00 set
Painted Finish
3125 x 500 mm 12mm thk tempered glass window 4.00 set
3763x3500mm Wire Mesh 19mm 4.00 set
Stair railing metal fabrication 302.00 lm
D PAINTING WORKS
Walls
150mm thk CHB
Int Wall 2,864.85 sq.m
Ext wall 1,800.33 sq.m
E OTHERS
Trench Gratings
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : MATERIAL DELIVERY REPORT - BOILER
Date : September 17, 2021

APRIL
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
BOILER
A WALL FINISHINGS
Plastering & Skimcoat
Exterior Wall 269.64 sq.m
B FLOOR FINISHES

4mm thk Plain Concrete Epoxy Flooring 448.69 sq.m

C DOORS & WINDOWS


2100mm x 900mm Ga. 18 45mm thk Hollow Core Epoxy Painted
Finish, with complete necessary hardwares, all in accordance with 1.00 sets
Architect's specification

Storm louver 4.2m x 3.6mH 4.00 set

Steel louver @ roof ventilator 2.00 set

E PAINTING WORKS
Walls
150mm thk CHB
Ext wall 269.64 sq.m
Conrete beams and columns 107.52 sq.m
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Construction Schedule
Date : September 17, 2021
Area :

ITEM APRIL MAY


DESCRIPTION TOTAL QTY UNIT
NO.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
ADMIN BUILDING
A WALL FINISHES
150 mm thk CHB Wall including reinforcement ;in
cement and sand mortar (1:3)
Exterior Wall 1,107.23 sq.m
Interior Wall 1,233.82 sq.m
Plastering & Skimcoat
Exterior Wall 2,214.46 sq.m
Interior Wall 2,467.65 sq.m
DRYWALL
2-16mm THK both Faced Firestop 1,068.00 sq.m
Boards on G.I studs
10mm Thk Tempered Glass on Powder coated aluminum
855.22 sq.m
Framing System
Decorative Stone 247.90 sq.m
Double Glaze Low-E Tempered Glass on Heavy Duty
Powder Coated Aluminum Frame with Aluminum Brise 898.10 sq.m
Soleil

B CEILING FINISHES
13mm thk moisture resistant gypsum board on metal
708.015 sq.m
framing
600mm x 600mm acoustic ceiling tiles 2583.063 sq.m
9mm THK Fiber Cement Board on Metal Framing,
66 sq.m
Painted Finish

C FLOORING FINISHES
750mm x 1500mm x 10mm THK Floor Tiles 153.3 sq.m

2mm THK Homogeneous Vinyl Sheet, Seamless 1526.931 sq.m

300mm x 300mm x 3mm THK Homogeneous Vinyl Tiles 816.27 sq.m

600mm x 600mm Vitrified Unglazed Floor Tiles 499.59 sq.m

600mm x 600mm x 3mm THK Carpet Loop Tiles 542.052 sq.m

Sealed concrete (Ashford) 222.8625 sq.m

D DOORS & WINDOWS


DOOR 2100 x 1800 - Waiting for the Schedule of Doors
38.00 sets
and Windows
DOOR 2100 x 900 - Waiting for the Schedule of Doors
10.00 sets
and Windows

E PAINTING WORKS
150mm thk CHB 2,214.46 sq.m
2-16mm THK both faced firestop boards on G.I studs
2,136.00 sq.m
with rockwool insulation
Conrete beams and columns 5,106.00 sq.m
Ceiling
13mm thk moisture resistant gypsum board on metal
708.02 sq.m
framing

9mm THK Fiber Cement Board on Metal Framing 66.00 sq.m

F FIXTURES
Water Closet 29.00 set
Lavatories 29.00 set
Male Urinal 14.00 set
Kitchen Sink 5.00 set

Prepared By: Approved by: Approved by: Submitted to: Noted By:

ANDREW MANALO JOSEPH EDGAR CAYA JED ELLER CIELO LINDA C. PEREZ LEWIS DAVE C. BURCE
Architect - SRBC PIC Engr. - SRBC Project Manager Architect - DCCD Construction Manager - DCCD
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Balance of Works - NOODLE BUILDING
Date : September 17, 2021

GMQ QTY ACCOMPLISHMENT


DATE
ITEM NO. MATERIALS LOCATION STATUS
NEEDED
QTY UNIT
A ARCHITECTURAL WORKS
A.1 MASONRY WORKS
LOWER GROUND 2,866.48 sq.m
LEVEL 1 1,332.72 sq.m
CHB 6'' (EXTERIOR & INTERIOR)
LEVEL 2 840.24 sq.m
LEVEL 3 579.36 sq.m
CHB 4'' (for CATCH BASIN) 42.40 sq.m

A.2 ROOFING
INSULATED PANEL ROOFING SYSTEM ROOFING 4,709.32 sq.m
A.3 WALL PANEL
50MM THK PRE PAINTED (PIR) METAL PANEL INTERIOR WALL 1,988.20 sq.m
EXTERIOR WALL 1,665.72 sq.m

A.4 FLOOR TILES

2MM THK HOMOGENEOUS VINYL SHEET, SEAMLESS -


590.38 sq.m
ENGR.OFFICE, MTG 101, VIEWING CORRIDOR

300MM X 300MM HOMOGENEOUS VINYL TILES -


11,021.00 pcs
LOWER GROUND, STAIR 1 - 4
600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES -
340.00 pcs
WAHBAY & ANTEROOM
300MM X 300MM VITRIFIED UNGLAZED FLOOR TILES -
86.00 pcs
LOWER GROUND TOILET 101

300MM X 600MMVITRIFIED GLAZED WALL TILES -


475.00 pcs
LOWER GROUND TOILET 101

TILE ADHESIVE 1,074.18 sq.m


A.6 FLOOR FINISHES
SEALED CONCRETE (ASHFORD) 261.00 sq.m
6MM THK MEDIUM DUTY POLYURETHANE
2,832.05 sq.m
CONCRETE FLOORING
3MM THK MEDIUM SYSTEM
DUTY POLYURETHANE
2,304.89 sq.m
CONCRETE FLOORING
9MM THK HEAVY DUTYSYSTEM (LEVEL 2) CONCRETE
POLYURETHANE
935.04 sq.m
FLOORING SYSTEM
A.5 WALL FINISHES
10MM THK TEMPERED GLASS ON POWDER COATED
391.00 sq.m
ALUMINUM FRAMING
1-6MM THK BOTH FACED FIBER CEMENT BOARD ON
1,722.20 sq.m
LIGHT GAUGE FRAME
9MM THK CEMENT BOARD COLUMN CLADDING 2,910.00 sq.m
2-16MM THK BOTH FACED FIRESTOP BOARDS ON G.I
125.00 sq.m
STUDS
ROCKWOOL INSULATION 1,847.20 sq.m
WIREMESH WALL 30.40 sq.m

A.7 CEILING FINISHES


METAL FURRING pcs
13MM THK MOISTURE RESISTANT GYPSUM BOARD ON METAL FRAMING 1,750.00 pcs
600MM X 600MM ACOUSTIC CEILING TILES 1,121.00 pcs
A.8 WATER PROOFING

ROOFDECK (MEMBRANE) 1,051.96 sq.m

WASHBAY (CEMENTITIOUS) 51.72 sq.m

A.9 DOORS
STEEL DOOR& WINDOWS
2100 x 1800 Ga. 18 45mm thk Hollow Core
Epoxy Painted Finish, with complete necessary hardwares, all 7.00 sets
in accordance with Architect's specification, with viewing glass
STEEL DOOR 2100mm x 900mm Ga. 18 45mm thk Hollow
Core Epoxy Painted Finish, with complete necessary
26.00 sets
hardwares, all in accordance with Architect's specification with
viewing glass
STEEL DOOR2100x1800 Steel Door with 6mm Thk Wire
3.00 sets
Mesh
TOILET DOORS 2100mm x 900mm Ga. 18 45mm thk Hollow
Core Epoxy Painted Finish with Louver, with complete
1.00 sets
necessary hardware all in accordance with Architect's
specification
GLASS DOOR 1.00
MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18
45mm thk Hollow Core Epoxy Painted Finish with complete
6.00 sets
necessary hardwares, all in accordance with Architect's
specification
AWNING WINDOWS 87.00 sets

STORM LOUVER with INSECT SCREEN 18.00 sets

A.11 PAINTING WORKS


SKIMCOAT 13,002.92 sq.m
EXTERIOR WALLS 4,345.33 sq.m
INTERIOR WALLS 954.09 sq.m
ELEVATOR WALL
A.10 FIXTURES
TOILET
MIRROR
Project: PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location: LISP IV, Malvar, Batangas
Subject: SRF AND RFI
Date: September 17, 2021

RFI
ITEM NO. DESCRIPTION PROJECT STATUS
PTMN-CSAP-AR-SRBC-MH-RFI-001 VERIFICATION OF WINDOW T102 & CALLOUTS OF 2ND FLOOR DOOR MESS HALL
PTMN-CSAP-AR-SRBC-MH-RFI-002 MESS HALL AUTOCAD FILE MESS HALL RECEIVED
PTMN-CSAP-AR-SRBC-MH-RFI-003 WALL WITH STEEL DECORATIVE RAILINGS MESS HALL

PTMN-CSAP-AR-SRBC-SB1-RFI-001 VERIFICATION OF WALL 9 SPECIFICATIONS & MATERIALS IN SB 1 SECURITY BLDG. 1


PTMN-CSAP-AR-SRBC-SB1-RFI-002 EXTERIOR AND INTERIOR WALL PAINT COLOR SECURITY BLDG. 1

SRF
CSAP-SRF-MESS HALL-AR-001 SHOP DRAWINGS OF STEEL DOOR BY METROTECH MESS HALL

CSAP-SRF-MESS HALL-AR-002 SHOP DRAWINGS OF TOILET PARTITION BY G.S. GO BROS., INC. MESS HALL

SHOP DRAWINGS OF TOILET PARTITION BY JEBSEN INT'L TRADING


CSAP-SRF-MESS HALL-AR-002 MESS HALL
CORP.
CSAP
CSAP-SRF-AR-002 ASHFORD FORMULA CONCRETE FLOOR TREATMENT MESS HALL
GA 24 PRE PAINTED HI RIB G.I. ROOFING & DOUBLE BUBBLE DOUBLE
CSAP-SRF-AR-006 MESS HALL
FOIL INSULATION BY PAJORA

CSAP-SRF-AR-013 300X300MM HOMOGENEOUS VINYL TILES MESS HALL

19MM THK DOUBLE SIDED PE ALUMINIZED BACKING FOR INSULATION


CSAP-SRF-AR-014 BY AEROFOAM
MESS HALL, SB1&2

CSAP-SRF-AR-022 SHOP DRAWINGS OF TEMPERED GLASS BY JNSTW MESS HALL, SB1&2

CSAP-SRF-AR-024 SHOP DRAWINGS OF TEMPERED GLASS BY ICON RBR GLASS & MESS HALL, SB1&2
ALUMINUM SUPPLY
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Construction Schedule
Date : September 17, 2021

APRIL
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
DC WREHOUSE
A WALL FINISHES
Ga.24 Pre-Painted G.I Sheet on Steel Frame (Rib Type) - SIDINGS 3508.28 sq.m

150 mm thk CHB Wall including reinforcement ;in cement and sand
mortar (1:3)
Exterior Wall 339.76 sq.m
Interior Wall 14.31 sq.m
Plastering & Skimcoat sq.m
Exterior Wall 679.52 sq.m
Interior Wall 28.62 sq.m
B CEILING FINISHES

13MM THK MOISTURE RESISTANT GYPSUM BOARD ON


30 sq.m
METAL FRAMING - LEVEL 2 (Required Ceiling Height)

C ROOFING
25mm thk Roofing Insulated Panel
D FLOOR FINISHES
SEALED CONCRETE (ASHFORD)
600mm x 600mm Vitrified Unglazed Floor Tiles
300mm x 300mm Vitrified Unglazed Floor Tiles
E DOORS & WINDOWS
2100mm x 900mm Ga. 18 45mm thk Hollow Core Epoxy Painted
Finish, with complete necessary hardwares, all in accordance with 2 sets
Architect's specification
2100mm x 900mm Ga. 18 45mm thk Rockwool Core Epoxy
Painted Finish with complete necessary panic device and hardwares 5 sets
all in accordance with Architect's specification
2100mm x 900mm Ga. 18 45mm thk Hollow Core Epoxy Painted
Finish with Louver, with complete necessary hardware all in 36 sets
accordance with Architect's specification
Motorized Roll up Door
3000mm x 3200mm Ga. 18 45mm thk Hollow Core Epoxy Painted
Finish with complete necessary hardwares, all in accordance with 1 sets
Architect's specification
F PAINTING WORKS
Walls
150mm thk CHB 74.90 sq.m
Conrete beams and columns
Ceiling
13mm thk moisture resistant gypsum board on metal framing 30.00 sq.m
RC Canopy sq.m
Exposed Steel Structure, epoxy painted sq.m
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : MATERIAL DELIVERY REPORT - SILO
Date : September 17, 2021

GMQ QTY
DATE
ITEM NO. MATERIALS STATUS
NEEDED

QTY UNIT
A ARCHITECTURAL WORKS
A.1 MASONRY WORKS
CHB 6'' (EXTERIOR & INTERIOR) 3,890.00 pcs 12/7/2020
CHB 4'' (for CATCH BASIN) 290.00 pcs 12/1/2020
10 mm Ø REBARS @ 610mm Bothways 282.00 pcs 12/1/2020
CEMENT ( Filler, Mortar & Plastering) 545.00 bags 12/1/2020
SAND ( Filler, Mortar & Plastering) 44.60 cu.m 12/1/2020

A.2 ROOFING
GA 24 LONGSPAN PRE PAINTED HI-RIB G.I. ROOFING WITH
19MM THK BUBBLE WRAP INSULATION (VERBAL as per meeting 716.53 sq.m
last 10/24/2020)
A.3 WALL PANEL

GA.24 PRE-PAINTED G.I SHEET ON STEEL FRAME (RIB TYPE) 1,365.77 sq.m
A.4 FLOOR TILES
600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES 50.00 pcs 12/21/2020
TILE ADHESIVE 16.61 sq.m 12/21/2020

A.6 FLOOR FINISHES


SEALED CONCRETE (ASHFORD) 470.32 sq.m 1/4/2021
A.7 CEILING FINISHES
13MM THK MOISTURE RESISTANT GYPSUM BOARD ON METAL
22.00 pcs 1/5/2020
FRAMING
A.8 DOORS & WINDOWS
STEEL DOOR 2100mm x 900mm Ga. 18 45mm thk Hollow Core Epoxy
Painted Finish, with complete necessary hardwares, all in accordance 1.00 sets 2/22/2021
with Architect's specification with viewing glass

MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18 45mm thk


Hollow Core Epoxy Painted Finish with complete necessary hardwares, 1.00 sets 3/3/2021
all in accordance with Architect's specification

AWNING WINDOWS 1.00 sets 2/22/2021


SLIDING WINDOWS 2.00 sets 2/22/2021
STORM LOUVER with INSECT SCREEN 3.00 sets 3/8/2021
A.9 FIXTURES
TOILET
MIRROR

A.10 METAL FABRICATION


STAIR RAILINGS
STAIR 6,7,8 STEEL STRINGER (C12X20.7)
STAIR 6,7,8 6MM THK BENDED CHEQUERED PLATE
STAIR 9,10 STEEL STRINGER (C12X20.7)
STAIR 9,10 6MM THK BENDED CHEQUERED PLATE

A PLUMBING WORKS

DMV PVC for SOIL, WASTE and DRAINAGE Pipes CSAP-SRF-PL-004

ATLANTA PPR for Indoor Pipes CSAP-SRF-PL-004

ATLANTA HDPE for Outdoor Pipes CSAP-SRF-PL-004

HydroVar (HDPE) CSAP-SRF-PL-002


THERMOVAR (PPR) CSAP-SRF-PL-001

You might also like