Noodle Building
Approved Materials & Color for Flooring;
F2 2mm thk Homogeneous Vinyl Sheet @ LG - Engr. Maintenace
Room & MTG 101
F3 300x300mm Homogeneous Vinyl Tiles @ Stair & LG Training
Room
Hygienic Floor Drain for Level 1 (Process Area)
Details of;
W3 - 10mm thk Tempered Glass @ LG MTG 101 and Level 2
Viewing Corridor
W6 - Wiremesh Wall @ N2/NK-NN and N6/NK-NN
Additional Toilet @ Lower Ground
Coving Details for Polyurethane Flooring @ Level 1,2 and 3
Details of Louvers and Roll Up Doors
CONCERNS:
at Level 3 Utility Deck (Metal Sdings) Inside Gutter at N2/NT-NU
Details of 10mm thk Tempered Glass at Level 2 Viewing Corridor Support for Interior Sidings (50mm thk PIR 0.40mm thk )
Railing Details for Scrubber Area??? Railing Details for Stair (Actual)
BOILER
Storm Louver Details
CUP BUILDING
Storm Louver L201 and L202
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Architectural Material's
Date : March 10, 2021
QUANTITY
MATERIALS BUILDINGS STATUS of SRF RESPONSIBLE REMARKS
QTY UNIT
WALL PANEL
50MM THK PRE PAINTED (PIR) METAL PANEL UPW M500 SUPPLIER: Puyat On Going Inst. of Interior
NOODLE BLDG 1,087.90 sq.m Approved
By Puyat Steel (Off White) Steel Sidings 75%
SUPPLIER: Pajora
DC WAREHOUSE 5,681.50 sq.m Approved On Going Installation
Steel
PACKAGING & SUPPLIER: Pajora
803.20 sq.m Approved On Going Installation
GA.24 PRE-PAINTED G.I SHEET ON STEEL FRAME (RIB SEASONING Steel
TYPE) by PAJORA (OFFWHITE) LEASEN SUPPLIER: Pajora
BOILER 553.92 sq.m Approved Already Installed
Steel
SUPPLIER: Pajora Waiting for the Area to be
SILO 1,093.50 sq.m Approved
Steel ready
FLOOR TILES
2MM THK HOMOGENEOUS VINYL SHEET, SEAMLESS
NOODLE BLDG 590.19 sq.m Approved Designer Pending Approved Color
(ARMSTRONG)
PACKAGING &
798.00 pcs Pending Designer Pending Approved Color
SEASONING
300MM X 600MMVITRIFIED GLAZED WALL TILES
DC WAREHOUSE 125.00 pcs Pending Designer Pending Approved Color
FLOOR FINISHES
SUPPLIER: Waiting for the Area to be
NOODLE BLDG 260.76 sq.m Approved
Tradetek Inc. ready
PACKAGING & SUPPLIER: Waiting for the Area to be
3,646.28 sq.m Approved
SEASONING Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
DC WAREHOUSE 8,449.29 sq.m Approved
Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
SEALED CONCRETE (ASHFORD) CUP 1,651.77 sq.m Approved
Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
SILO 470.32 sq.m Approved
Tradetek Inc. ready
PREMIX & RAW SUPPLIER: Waiting for the Area to be
855.00 sq.m Approved
WAREHOUSE Tradetek Inc. ready
SUPPLIER: Waiting for the Area to be
MESS HALL 115.10 sq.m Approved
Tradetek Inc. ready
On Going Application
NOODLE BLDG 2,832.05 sq.m Approved SUPPLIER: IIPI Inc.
43%
6MM THK MEDIUM DUTY POLYURETHANE CONCRETE
FLOORING SYSTEM (FLOWFRESH)
Waiting for the Area to be
SS OIL 387.00 sq.m Approved SUPPLIER: IIPI Inc.
ready
On Going Application
NOODLE BLDG 804.00 sq.m Approved SUPPLIER: IIPI Inc.
28%
9MM THK HEAVY DUTY POLYURETHANE CONCRETE
FLOORING SYSTEM (FLOWCRETE)
Waiting for the Area to be
SS OIL 477.42 sq.m Approved SUPPLIER: IIPI Inc.
ready
WALL FINISHES
NOODLE BLDG (Lower
35,831.00 pcs Approved SRBC Balance Stair Wall
Ground)
NOODLE BLDG (Level
16,659.00 pcs Approved SRBC Balance Stair Wall
1)
NOODLE BLDG (Level
10,503.00 pcs Approved SRBC Balance Stair Wall
2)
NOODLE BLDG (Level
7,242.00 pcs Approved SRBC Balance Stair Wall
3)
PACKAGING & Waiting for the Area to be
12,915.00 pcs Approved SRBC
SEASONING ready
13MM THK MOISTURE RESISTANT GYPSUM BOARD ON SUPPLIER: World Waiting for the Area to be
SS OIL 376.00 pcs Approved
METAL FRAMING (BORAL) Home Depot ready
WATER PROOFING
SUPPLIER:
NOODLE BLDG 26.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER:
DC WAREHOUSE 2.00 sets Pending Shop Drawing Approval
Metrotech
STEEL DOOR 2100mm x 900mm Ga. 18 45mm thk Hollow Core
SUPPLIER:
Epoxy Painted Finish, with complete necessary hardwares, all in SS OIL 3.00 sets Pending Shop Drawing Approval
Metrotech
accordance with Architect's specification with viewing glass
SUPPLIER:
CUP 11.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER:
SILO 4.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER:
STEEL DOOR2100x1800 Steel Door with 6mm Thk Wire Mesh NOODLE BLDG 3.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER:
NOODLE BLDG 1.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER:
SS OIL 3.00 sets Pending
Metrotech
SUPPLIER:
NOODLE BLDG 6.00 sets Pending Shop Drawing Approval
Metrotech
PACKAGING & SUPPLIER:
6.00 sets Pending Shop Drawing Approval
SEASONING Metrotech
MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18 45mm
OSM as per Meeting last
thk Hollow Core Epoxy Painted Finish with complete necessary DC WAREHOUSE 36.00 sets Pending
week
hardwares, all in accordance with Architect's specification
SUPPLIER:
CUP 2.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER:
SILO 1.00 sets Pending Shop Drawing Approval
Metrotech
SUPPLIER: Approved Shop Drawing
STORM LOUVER with HEPA FILTER NOODLE BLDG 4.00 sets Approved
Metrotech 02/27/2020
SUPPLIER: Approved Shop Drawing
NOODLE BLDG 14.00 sets Approved
Metrotech 02/27/2021
SUPPLIER:
STORM LOUVER with INSECT SCREEN BOILER 4.00 sets Approved On Going Fabrication
Metrotech
SUPPLIER: Approved Shop Drawing
CUP 19.00 sets Approved
Metrotech 02/27/2021
FIXED WINDOWS NOODLE BLDG 82.00 sets Approved JNSTW Date of Delivery:
AWNING WINDOWS NOODLE BLDG 3.00 sets Approved JNSTW 03/30/2021
FIXTURES
PAINTING WORKS
NOODLE BLDG 13,002.92 sq.m Approved SRBC On Going Application
Waiting for the Area to be
DC WAREHOUSE 708.14 sq.m Approved SRBC
ready
PACKAGING & Waiting for the Area to be
1,605.50 sq.m Approved SRBC
SEASONING ready
Waiting for the Area to be
SKIMCOAT SS OIL 2,025.73 sq.m Approved SRBC
ready
Waiting for the Area to be
CUP 4,305.14 sq.m Approved SRBC
ready
Waiting for the Area to be
SILO 622.00 sq.m Approved SRBC
ready
BOILER 195.00 sq.m Approved SRBC On Going Application
METAL FABRICATION
STAIR RAILINGS
STAIR 1 NOODLE BLDG 38.70 LM SRBC
STAIR 2 NOODLE BLDG 38.70 LM SRBC
STAIR 3 NOODLE BLDG 35.50 LM SRBC
STAIR 4 NOODLE BLDG 35.50 LM Approved SRBC Start of Installation
Materials By
STAIR 5 NOODLE BLDG 35.50 LM SRBC 03/22/2021
Designer
STAIR 6 NOODLE BLDG 24.40 LM SRBC
STAIR 7 NOODLE BLDG 24.40 LM SRBC
STAIR 8 NOODLE BLDG 24.40 LM SRBC
WALL FINISHES
On Going On Going On Going
CHB 6'' @ 450psi - LEVEL 2 1,421.34 sq.m Approved SRBC 20-Apr-21
Installation Installation Installation
300X600MM VITRIFIED GLAZED WALL TILES
Waiting Approved
T101/T102/T103 74.11 sq.m Approved Designer
Color
CEILING FINISHES
FIXTURES
WATER CLOSET
SPECS DIV.10 SEC10800 PART 2.01 All toilet fixtures,
sets Approved SRBC 18-Mar-21 28-Apr-21 28-Apr-21 1-May-21 For Deliver
fittings and bathroom accessories shall be as manufactured by AMERICAN
STANDARD, BRAVAT or approved equal.
LAVATORIES sets Dis Approved DESIGNER
MALE URINAL
SPECS DIV.10 SEC10800 PART 2.02 All Urinal shall be by
sets Dis Approved DESIGNER
AMERICAN STANDARD, or approved equal.
MIRROR
4100mm x 1200mm 1/4" thk. Distorition Free Mirror on
3/4" thk. Plywood Backing sets
600mm x 1200mm 1/4" thk. Distorition Free Mirror on 3/4"
thk. Plywood Backing
PAINTING WORKS
SKIMCOAT sq.m Approved SRBC 26-Feb-21 2-Mar-21 2-Mar-21 3-Apr-21 For Order
Waiting Approved
EXTERIOR AND INTERIOR WALL Designer
Color
METAL FABRICATION
STAIR RAILINGS
STAIR 1 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
For Actual
STAIR 2 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
Measurement
WINDOW STEEL RAILINGS lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21
LEGEND
Prepared By: Approved by: Submitted to: Waiting for the Approval
HOLD
ALEXANDRA JANE UY JED ELLER CIELO LINDA C. PEREZ On Going Installation
Site Architect - SRBC Project Manager. - SRBC Architect - DCCD Already Installed
Waiting for the Area to be ready
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Architectural Material's
Date : April 02. 2021
25mm thk Insulated (PIR) Roofing System (0.60mm Outer Metal Skin and SUPPLIER:
4,815.00 sq.m Approved Already Installed Already Installed 23-Jan-21 30-Jan-21 Already Installed
0.40mm Inner Metal Skin) UPR 250 by Puyat Steel (OFF WHITE) Puyat Steel
WALL PANEL
On Going On Going Inst. of
50MM THK PRE PAINTED (PIR) METAL PANEL UPW M500 By SUPPLIER:
1,087.90 sq.m Approved Installation of 17-Feb-21 18-Feb-21 5-Apr-21 Interior Sidings
Puyat Steel (Off White) - INTERIOR SIDINGS Puyat Steel
Interior Sidings 95%
FLOOR TILES
2MM THK HOMOGENEOUS VINYL SHEET, SEAMLESS Waiting for the
590.19 sq.m Approved Designer 15-Apr-21 15-Apr-21 22-Apr-21
(ARMSTRONG) Approved Color
Waiting for the
300MM X 300MM HOMOGENEOUS VINYL TILES (ARMSTRONG) 10,145.00 pcs Approved Designer 15-Apr-21 15-Apr-21 30-Apr-21
Approved Color
Pending Approved
Waiting for the Color - for Follow
600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES 305.00 pcs Pending Designer 15-Apr-21 15-Apr-21 22-Apr-21
Approved Color Up
Waiting for the
300MM X 300MM VITRIFIED UNGLAZED FLOOR TILES 86.00 pcs Pending Designer 15-Apr-21 15-Apr-21 22-Apr-21
Approved Color
Waiting for the
300MM X 600MMVITRIFIED GLAZED WALL TILES 475.00 pcs Pending Designer 15-Apr-21 15-Apr-21 22-Apr-21
Approved Color
FLOOR FINISHES
SEALED CONCRETE (ASHFORD)
SUPPLIER: Waiting for the
ENGR. MAINTENANCE TOOL ROOM (LOWER GROUND) 259.16 sq.m Approved 13-Nov-20 20-Apr-21 20-Apr-21 21-Apr-21
Tradetek Inc. Area to be ready
SUPPLIER: Waiting for the
ALKALINE TANKS 47.00 sq.m Approved 13-Nov-20 20-Apr-21 20-Apr-21 21-Apr-21
Tradetek Inc. Area to be ready
SUPPLIER:
PACKAGING AREA1 (LEVEL 1) 1,367.76 sq.m Approved DONE 8-Apr-21 8-Apr-21 10-Apr-21 DONE
IIPI Inc.
WALL FINISHES
On Going On Going On Going On Going
CHB 6'' @ 450psi - LOWER GROUND 481.81 sq.m Approved SRBC 19-Apr-21
Installation Installation Installation Installation
On Going On Going On Going On Going
CHB 6'' @ 450psi - LEVEL 2 196.50 sq.m Approved SRBC 20-Apr-21
Installation Installation Installation Installation
On Going On Going On Going On Going
CHB 6'' @ 450psi - LEVEL 3 1,585.83 sq.m Approved SRBC 20-Apr-21
Installation Installation Installation Installation
DRYWALL 1-
6mm thk Both Faced Fiber Cement Board on light gauge frame
On Going Framing
LOWER GROUND 326.99 sq.m Approved SRBC 12-Feb-21 10-Mar-21 29-Mar-21 10-Apr-21
Installation
On Going Framing
LEVEL 1 (COOLING AREA & PACKAGING 1) 239.72 sq.m Approved SRBC 12-Feb-21 10-Mar-21 22-Mar-21 14-Apr-21
Installation
LEVEL 2 (MIXER) 81.95 sq.m Approved SRBC 12-Feb-21 10-Mar-21 8-Mar-21 18-Mar-21 DONE
On Going Framing
LEVEL 2 (PACKAGING 2) 223.93 sq.m Approved SRBC 12-Feb-21 10-Mar-21 22-Mar-21 11-Apr-21
Installation
Waiting for the
LEVEL 3 (HOPPER) 289.53 sq.m Approved SRBC 12-Feb-21 10-Mar-21 7-Apr-21 17-Apr-21
Area to be ready
On Going Framing
VIEWING CORRIDOR 96.00 sq.m Approved SRBC 12-Mar-21 15-Mar-21 15-Mar-21 6-Apr-21
Installation
Waiting for the
9MM THK CEMENT BOARD COLUMN CLADDING - Exterior Wall 2,910.00 sq.m Approved SRBC 15-Mar-21 22-Mar-21 27-Mar-21 21-Apr-21
Details of Framing
DRYWALL
On Going Framing
2-16mm THK both Faced Firestop Boards on G.I studs @ Lower 124.50 sq.m Approved SRBC 12-Mar-21 15-Mar-21 5-Apr-21 14-Apr-21
Installation
Ground (Engr. Maintenance Office)
10MM THK TEMPERED GLASS ON POWDER COATED ALUMINUM Waiting for the
391.00 sq.m Approved JNSTW 15-Feb-21 24-Mar-21 26-Mar-21 27-Mar-21
FRAMING - Viewing Corridor Area to be ready
10MM THK TEMPERED GLASS ON POWDER COATED ALUMINUM Shop Drawing Shop Drawing for
53.25 sq.m JNSTW 26-Mar-21 15-Apr-21 16-Apr-21 23-Apr-21
FRAMING - @ Lower Ground Meeting Room for Approval Approval
WIREMESH WALL (50MM BI PIPE & CYCLONE WIRE)
FRONT EXTERIOR WALL 70.63 sq.m Pending SRBC 7-Apr-21 9-Apr-21 10-Apr-21 16-Apr-21 Waiting for the
REAR ELEVATION 48.56 sq.m Pending SRBC 7-Apr-21 9-Apr-21 15-Apr-21 21-Apr-21 Approval
300X600MM VITRIFIED GLAZED WALL TILES
T101/T102/T103 190.00 pcs Pending Designer Waiting Approved
WASHBAY 125.00 pcs Pending Designer Color
CEILING FINISHES
13MM THK MOISTURE RESISTANT GYPSUM BOARD ON METAL
FRAMING (BORAL)
Waiting for the
HALLWAY 158.46 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
STO/VISUALS ROOM 32.24 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
TOILET 101 7.32 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
WASHBAY 69.12 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
Waiting for the
ANTE ROOM 40.20 sq.m Approved SRBC 6-Feb-21 5-Apr-21
Area to be ready
ROLLER AREA 373.60 sq.m Approved Designer 6-Feb-21 26-Mar-21 8-Apr-21 23-Apr-21 HOLD
PACKAGING AREA1 1,369.58 sq.m Approved SRBC 6-Feb-21 26-Mar-21 29-Mar-21 13-Apr-21 HOLD - 3/22/2021
FIXTURES
WATER CLOSET
SPECS DIV.10 SEC10800 PART 2.01 All toilet fixtures,
3.00 sets Approved SRBC 18-Mar-21 28-Apr-21 28-Apr-21 1-May-21
fittings and bathroom accessories shall be as manufactured by AMERICAN
STANDARD, BRAVAT or approved equal.
LAVATORIES 1.00 sets Dis Approved DESIGNER
MALE URINAL for Approval of
SPECS DIV.10 SEC10800 PART 2.02 All Urinal shall be by Sensorized Urinal
4.00 sets Dis Approved DESIGNER and Faucet
AMERICAN STANDARD, or approved equal.
MIRROR
4100mm x 1200mm 1/4" thk. Distorition Free Mirror on
3/4" thk. Plywood Backing 5.00 sets
600mm x 1200mm 1/4" thk. Distorition Free Mirror on 3/4"
thk. Plywood Backing
PAINTING WORKS
On Going
SKIMCOAT 13,002.92 sq.m Approved SRBC 26-Feb-21 2-Mar-21 2-Mar-21 3-Apr-21
Application
Waiting Approved
EXTERIOR AND INTERIOR WALL Pending Designer
Color
METAL FABRICATION
STAIR RAILINGS
STAIR 1 38.70 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
STAIR 2 38.70 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21
On Going
STAIR 3 35.50 lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21
Installation
STAIR 4 35.50 lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21
STAIR 5 35.50 lm Approved SRBC 27-Feb-21 8-Apr-21 9-Apr-21 11-Apr-21
STAIR 6 24.40 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21 Already Installed
STAIR 7 24.40 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21 Already Installed
STAIR 8 24.40 lm Approved SRBC 27-Feb-21 22-Mar-21 22-Mar-21 24-Mar-21 Already Installed
LEGEND
Prepared By: Approved by: Submitted to: Waiting for the Approval
HOLD
ANDREW MANALO JED ELLER CIELO LINDA C. PEREZ On Going Installation
Architect - SRBC Project Manager. - SRBC Architect - DCCD Already Installed
Waiting for the Area to be ready
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Plan
Date : September 17, 2021
387.63 sq.m
6mm thk medium duty polyurethane concrete flooring system
477.42 sq.m
9mm thk Heavy duty polyurethane concrete flooring system
DRYWALL 1-
6mm thk Both Faced Fiber Cement Board on light gauge frame
Lower Ground 326.99 sq.m Framing On-Going
Level 1 (Cooling Area & Packaging 1) 239.72 sq.m Framing On-Going
Level 2 (Packaging 2) 223.93 sq.m Framing On-Going
Waiting for the Area to be
Level 3 (Hopper) 289.53 sq.m
ready
DRYWALL 2-
Waiting for the Area to be
16mm THK both Faced Firestop Boards on G.I studs @ 124.5 sq.m
ready
Lower Ground (Engr. Maintenance Office)
Wiremesh wall (50mm BI Pipe & Cyclone Wire)
Front Exterior Wall 70.63 sq.m Waiting for the Area to be
Rear Elevation 48.56 sq.m ready
WALL CLADDING Waiting for the Area to be
9mm thk cement board column - EXTERIOR WALL ready
B CEILING FINISHES
13mm thk moisture resistant gypsum board on metal framing
HALLWAY LOWER GROUND 137.65 sq.m
STO/VISUALS ROOM LOWER GROUND 31.4 sq.m
TOILET 101 (LOWER GROUND) 7.32 sq.m
WASHBAY 276.24 sq.m
ANTE ROOM LOWER GROUND 53.19 sq.m
ROLLER AREA LEVEL 1 472.32 sq.m
PACKAGING AREA1 LEVEL 1 1367.76 sq.m HOLD- as per Designer
MIXER (LEVEL 2) 472.32 sq.m
VIEWING CORRIDOR LEVEL 2 445.31 sq.m Waiting for other Trades
PACKAGING AREA 2 (LEVEL 2) 1367.74 sq.m
HOPPER LEVEL 3 472.32 sq.m
STAIR LEVEL 3 124.91 sq.m
600mm x 600mm acoustic ceiling tiles
TRAINING ROOM 261.34 sq.m
Waiting for the Area to be
ENGR. MAINTENANCE OFFICE 114.11 sq.m
ready
MTG 101 27.96 sq.m
C WATERPROOFING
Membrane
UTILITY DECK 445.3 sq.m Waiting for the Area to be
ROOF DECK (STAIR) 183.12 sq.m ready
ALKALINE TANKS (RC DECK) 45.96 sq.m
Cementitious
WASHBAY (X4) 17.25 sq.m
D FLOORING FINISHES
Sealed concrete (Ashford)
ENGR. MAINTENANCE TOOL ROOM (LOWER
259.16 sq.m
GROUND) Waiting for the Area to be
ready
ALKALINE TANKS 47 sq.m
300mm x 300mm Vitrified Unglazed Floor Tiles - TOILET Pending Approved Color By
86 pcs
101 (LOWER GROUND) the Designer
3mm Thk Medium Duty Polyurethane Concrete Flooring
System
ROLLER AREA (LEVEL 1) 472.32 sq.m
On Going Application 43%
MIXER (LEVEL 2) 472.32 sq.m
Waiting for the Area to be
HOPPER (LEVEL 3) 472.32 sq.m
ready
6mm thk medium duty polyurethane concrete flooring
system
PROCESS AREA (LEVEL 1) 1918.8 sq.m
COOLING AREA (LEVEL 1) 370.64 sq.m On Going Application 43%
PACKAGING AREA1 (LEVEL 1) 1367.76 sq.m
PROCESS AREA EQUIPMENT LINE (LEVEL 1) 934.8 sq.m On Going Application 28%
ELEVATOR WALL
G STAIR RAILINGS
Stair 3 (LG to Level 3) 344.13 sq.m
Stair 4 (LG to Level 3) 264.1 sq.m
Stair 5 (LG to Level 3) 264.1 sq.m
H FIXTURES
TOILET
URINAL - SENSORIZED
FAUCET - SENSORIZED
MIRROR
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Construction Schedule
Date : September 17, 2021
APRIL MAY
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
PACKAGING & SEASONING
A WALL FINISHINGS
150 mm thk CHB Wall including reinforcement ;in cement and sand mortar (1:3)
Exterior Wall 1,109.60 sq.m
Interior Wall 380.00 sq.m
Plastering & Skimcoat
Exterior Wall 2,219.20 sq.m
Interior Wall 760.00 sq.m
B CEILING FINISHES
13MM THK MOISTURE RESISTANT GYPSUM BOARD ON
125.00 pcs
METAL FRAMING
D FLOOR TILES
600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES 495.00 pcs
300MM X 300MM VITRIFIED UNGLAZED FLOOR TILES 440.00 pcs
300MM X 600MMVITRIFIED GLAZED WALL TILES 798.00 pcs
300MM X 300MM HOMOGENEOUS VINYL TILES 2,627.00 pcs
E FLOOR FINISHES
SEALED CONCRETE (ASHFORD) 3,646.28 sq.m
F WATER PROOFING
ROODECK (MEMBRANE) 55.68 sq.m
G DOORS & WINDOWS
2100 x 1800 Ga. 18 45mm thk Hollow Core Epoxy Painted Finish,
with complete necessary hardwares, all in accordance with Architect's 2.00 sets
specification, with viewing glass
APRIL
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
CUP BUILDING
A WALL FINISHINGS
150 mm thk CHB Wall including reinforcement ;in cement and sand mortar (1:3)
APRIL
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
BOILER
A WALL FINISHINGS
Plastering & Skimcoat
Exterior Wall 269.64 sq.m
B FLOOR FINISHES
E PAINTING WORKS
Walls
150mm thk CHB
Ext wall 269.64 sq.m
Conrete beams and columns 107.52 sq.m
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Construction Schedule
Date : September 17, 2021
Area :
B CEILING FINISHES
13mm thk moisture resistant gypsum board on metal
708.015 sq.m
framing
600mm x 600mm acoustic ceiling tiles 2583.063 sq.m
9mm THK Fiber Cement Board on Metal Framing,
66 sq.m
Painted Finish
C FLOORING FINISHES
750mm x 1500mm x 10mm THK Floor Tiles 153.3 sq.m
E PAINTING WORKS
150mm thk CHB 2,214.46 sq.m
2-16mm THK both faced firestop boards on G.I studs
2,136.00 sq.m
with rockwool insulation
Conrete beams and columns 5,106.00 sq.m
Ceiling
13mm thk moisture resistant gypsum board on metal
708.02 sq.m
framing
F FIXTURES
Water Closet 29.00 set
Lavatories 29.00 set
Male Urinal 14.00 set
Kitchen Sink 5.00 set
Prepared By: Approved by: Approved by: Submitted to: Noted By:
ANDREW MANALO JOSEPH EDGAR CAYA JED ELLER CIELO LINDA C. PEREZ LEWIS DAVE C. BURCE
Architect - SRBC PIC Engr. - SRBC Project Manager Architect - DCCD Construction Manager - DCCD
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Balance of Works - NOODLE BUILDING
Date : September 17, 2021
A.2 ROOFING
INSULATED PANEL ROOFING SYSTEM ROOFING 4,709.32 sq.m
A.3 WALL PANEL
50MM THK PRE PAINTED (PIR) METAL PANEL INTERIOR WALL 1,988.20 sq.m
EXTERIOR WALL 1,665.72 sq.m
A.9 DOORS
STEEL DOOR& WINDOWS
2100 x 1800 Ga. 18 45mm thk Hollow Core
Epoxy Painted Finish, with complete necessary hardwares, all 7.00 sets
in accordance with Architect's specification, with viewing glass
STEEL DOOR 2100mm x 900mm Ga. 18 45mm thk Hollow
Core Epoxy Painted Finish, with complete necessary
26.00 sets
hardwares, all in accordance with Architect's specification with
viewing glass
STEEL DOOR2100x1800 Steel Door with 6mm Thk Wire
3.00 sets
Mesh
TOILET DOORS 2100mm x 900mm Ga. 18 45mm thk Hollow
Core Epoxy Painted Finish with Louver, with complete
1.00 sets
necessary hardware all in accordance with Architect's
specification
GLASS DOOR 1.00
MOTORIZED ROLL UP DOOR 3000mm x 3200mm Ga. 18
45mm thk Hollow Core Epoxy Painted Finish with complete
6.00 sets
necessary hardwares, all in accordance with Architect's
specification
AWNING WINDOWS 87.00 sets
RFI
ITEM NO. DESCRIPTION PROJECT STATUS
PTMN-CSAP-AR-SRBC-MH-RFI-001 VERIFICATION OF WINDOW T102 & CALLOUTS OF 2ND FLOOR DOOR MESS HALL
PTMN-CSAP-AR-SRBC-MH-RFI-002 MESS HALL AUTOCAD FILE MESS HALL RECEIVED
PTMN-CSAP-AR-SRBC-MH-RFI-003 WALL WITH STEEL DECORATIVE RAILINGS MESS HALL
SRF
CSAP-SRF-MESS HALL-AR-001 SHOP DRAWINGS OF STEEL DOOR BY METROTECH MESS HALL
CSAP-SRF-MESS HALL-AR-002 SHOP DRAWINGS OF TOILET PARTITION BY G.S. GO BROS., INC. MESS HALL
CSAP-SRF-AR-024 SHOP DRAWINGS OF TEMPERED GLASS BY ICON RBR GLASS & MESS HALL, SB1&2
ALUMINUM SUPPLY
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : Catch Up Construction Schedule
Date : September 17, 2021
APRIL
ITEM NO. DESCRIPTION TOTAL QTY UNIT
1 2 3 4 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
DC WREHOUSE
A WALL FINISHES
Ga.24 Pre-Painted G.I Sheet on Steel Frame (Rib Type) - SIDINGS 3508.28 sq.m
150 mm thk CHB Wall including reinforcement ;in cement and sand
mortar (1:3)
Exterior Wall 339.76 sq.m
Interior Wall 14.31 sq.m
Plastering & Skimcoat sq.m
Exterior Wall 679.52 sq.m
Interior Wall 28.62 sq.m
B CEILING FINISHES
C ROOFING
25mm thk Roofing Insulated Panel
D FLOOR FINISHES
SEALED CONCRETE (ASHFORD)
600mm x 600mm Vitrified Unglazed Floor Tiles
300mm x 300mm Vitrified Unglazed Floor Tiles
E DOORS & WINDOWS
2100mm x 900mm Ga. 18 45mm thk Hollow Core Epoxy Painted
Finish, with complete necessary hardwares, all in accordance with 2 sets
Architect's specification
2100mm x 900mm Ga. 18 45mm thk Rockwool Core Epoxy
Painted Finish with complete necessary panic device and hardwares 5 sets
all in accordance with Architect's specification
2100mm x 900mm Ga. 18 45mm thk Hollow Core Epoxy Painted
Finish with Louver, with complete necessary hardware all in 36 sets
accordance with Architect's specification
Motorized Roll up Door
3000mm x 3200mm Ga. 18 45mm thk Hollow Core Epoxy Painted
Finish with complete necessary hardwares, all in accordance with 1 sets
Architect's specification
F PAINTING WORKS
Walls
150mm thk CHB 74.90 sq.m
Conrete beams and columns
Ceiling
13mm thk moisture resistant gypsum board on metal framing 30.00 sq.m
RC Canopy sq.m
Exposed Steel Structure, epoxy painted sq.m
Project : PROJECT TRANSCEND - Monde Nissin Manufacturing Plant
Location : LISP IV, Malvar, Batangas
Subject : MATERIAL DELIVERY REPORT - SILO
Date : September 17, 2021
GMQ QTY
DATE
ITEM NO. MATERIALS STATUS
NEEDED
QTY UNIT
A ARCHITECTURAL WORKS
A.1 MASONRY WORKS
CHB 6'' (EXTERIOR & INTERIOR) 3,890.00 pcs 12/7/2020
CHB 4'' (for CATCH BASIN) 290.00 pcs 12/1/2020
10 mm Ø REBARS @ 610mm Bothways 282.00 pcs 12/1/2020
CEMENT ( Filler, Mortar & Plastering) 545.00 bags 12/1/2020
SAND ( Filler, Mortar & Plastering) 44.60 cu.m 12/1/2020
A.2 ROOFING
GA 24 LONGSPAN PRE PAINTED HI-RIB G.I. ROOFING WITH
19MM THK BUBBLE WRAP INSULATION (VERBAL as per meeting 716.53 sq.m
last 10/24/2020)
A.3 WALL PANEL
GA.24 PRE-PAINTED G.I SHEET ON STEEL FRAME (RIB TYPE) 1,365.77 sq.m
A.4 FLOOR TILES
600MM X 600MM VITRIFIED UNGLAZED FLOOR TILES 50.00 pcs 12/21/2020
TILE ADHESIVE 16.61 sq.m 12/21/2020
A PLUMBING WORKS