Design Approval
1. Obtaining Approval of Design of OCU System by vendor from Client
Project Schedule
3. Preparation of Schedule and updating as required
Material submittals and Method Statements for Each Material and System (Progressively)
7. Preparation of Material Submittals – Preparation of Compliance Sheet, Collection of Technical Details &
Profile, required documentation from Vendor/Supplier
8. Preparation of Method Statement for Construction, Installation, Testing and Commissioning– Execution
Method, Inspection Testing Plan and Risk Assessment
9. Submission of Material Submittals and Method Statements for Civil, Electrical and Mechanical System
10. Complying Comments on submission review to obtain Client Approval
Underground Utility laying - UPVC Electrical duct and HDPE Vent line
17. Excavation – Preparation, Safety barricade, signage, limit marking, manual excavation, preserving
existing warning tapes, Sand/aggregate bedding
18. UPVC duct – Duct laying, socket jointing, using suitable joints at bends
19. HDPE pipe – Identifying Tie-in points for existing line connection, HDPE laying by boom truck, butt-weld
jointing
20. Backfilling – Surround backfill with sand, Warning tape, 2 or 3 layers of Compaction, Field Density Test,
Backfilling and Re-instatement
Underground utility protection in Road crossing and Asphalt Re-instatement in Week duration
21. Preparation of pre-cast slab for HDPE protection – Re-bar, formworks, concrete pouring, curing and
formwork removal
22. Road cutting and Excavation – Preparation, Barricade protection, traffic diversion with proper signage,
Asphalt cutting, excavation and Sand/Aggregate Bedding
23. UPVC duct and HDPE Pipe – Placing HDPE vent line and UPVC duct with spares, No joints
24. UPVC duct Protection – SRC20 Concrete pouring around UPVC duct and curing
25. HDPE Pipe protection - Backfill around HDPE pipe, placing of pre-cast slab with boom trucks
26. Backfilling – Warning Tape, Compaction Layer, Backfilling and Re-instatement
27. Asphalt Paving – Transport of asphalt, Placing base and Wearing course, Road markings
Client Inspection
33. Inspection by HIA MPD, FM, SME, FM Contractor, for material and each work activity upon deliverables