Professional Documents
Culture Documents
CONSTRUCTION
By Ismail M. Basha' and Ahmed A. Gab-Allah2
Downloaded from ascelibrary.org by KANSAS STATE UNIV LIBRARIES on 07/17/14. Copyright ASCE. For personal use only; all rights reserved.
ABSTRACT: During the past two decades, various construction systems have been
applied in building several highway bridges and elevated roads in Egypt. This
paper deals with the use of value engineering principles to evaluate the selection
of construction systems for major bridge projects in Egypt. The construction sys-
tems used in Egypt and their applicability under different site conditions were re-
viewed. The study includes eight construction systems and 14 bridge projects. The
weighted evaluation technique was used to evaluate the construction system used
for each project in comparison with other applicable alternatives. The most im-
portant criteria considered in this evaluation include construction cost, resource
availability, ease of construction durability, construction progress rate, service life,
design efficiency, and maintenance. The evaluation led to basic conclusions con-
cerning whether the system used in each case was the best choice. A call is made
for conducting value engineering studies in the early stages of major bridge proj-
ects.
INTRODUCTION
Through the position they hold in linking different parts of highway net-
works, bridges have an important impact on the capacities of such networks.
Bridges are massive structures that require large amounts of materials, skilled
labor, and heavy machinery for their construction. Therefore, the decision
regarding the most convenient construction systems to be used should be
based on many factors, including type of bridge and the site conditions,
technology and resources available, and required construction period (Bindra
1976).
The objective of this study was to evaluate the selection of construction
systems in major bridge projects in Egypt. To achieve this objective it was
necessary to conduct a value engineering (VE) study of the construction sys-
tem used for each project and compare it with other applicable systems.
393
(D (2) (3)
A Precast concrete Use of precast, prestressed I- or T-girders on top of
girders which a deck slab is cast. The girders are erected
using a launching truss.
B Incremental The superstructure segments are cast in stationary
launching formwork in an extrusion area located at one end of
, the bridge. After each segment is completed, the
superstructure is pushed forward to the other end of
the bridge.
C Prefabricated steel Steel components of transportable size and weight are
construction fabricated and transported to the construction site.
They are then preassembled and erected to their final
positions by means of cranes and auxiliary equipment.
D Cast-in-place, free The superstructure is cast in segments in traveling forms
cantilever which are supported from one end on the completed
part of superstructure, whereas the other end is a free
cantilever. After concrete reaches required strength,
forms are moved forward and prepared for casting the
next span.
E Precast segmental, The superstructure is precast and prestressed in segments
free cantilever in a fabrication area. Segments are then transported to
F Precast segmental, the job site, where they are erected into final positions
on falsework using either a launching truss or falsework supports.
G Cast-in-place, The superstructure is cast in place in formwork
reinforced supported from the ground by falsework using either
concrete on reinforced or prestressed concrete. For small bridges,
H falsework the formwork is normally constructed in traditional
Cast-in-place, form with timber supported on either lumber of steel
prestressed falsework. For larger bridges, prefabricated steel
concrete on elements may be used as formwork.
falsework
The site conditions for a job generally suggest the construction system for
that job. According to Gab-Allah (1989), most bridge projects in Egypt could
be classified according to site conditions into three major groups: (1) Con-
struction under running traffic; (2) construction across navigable waterways,
and (3) construction at accessible sites. The construction systems applicable
under each of these site conditions are given in Table 2.
including systems A-E. The substructure cost is usually smaller than that
for navigable waterways. Consequently, the economic span length, which is
proportional to the square root of substructure cost (Bindra 1976), is usually
small. Since systems D and E are most suitable for long spans (Ratay 1984),
they are dropped. Systems F, G, and H cannot be used because they include
falsework supports, which are not allowed. Therefore, systems A, B, and
C are most suitable for this site condition (see Table 2).
METHODOLOGY
The following four elements were included in the study: (1) Construction
systems; (2) bridge projects; (3) evaluation technique; and (4) evaluation
criteria.
Construction Systems
Consideration was given to the eight construction systems applied in Egypt,
given in Table 2.
395
Bridge Projects
Consideration was given to 10 bridge projects, which included 14 super-
structures.
Evaluation Technique
The VE study procedure was used to evaluate the construction systems
applicable for each project. Several techniques could be used for this pur-
pose. Three techniques, however, were suggested by Dell'Isola (1982): life
cycle costing, weighted evaluation, and idea rating. The weighted-evaluation
technique was selected for the study since it considered both economic and
engineering factors.
Weighted evaluation, as defined by Dell'Isola (1982), is a formally or-
ganized process for making decisions that require the analysis of several
criteria, including economic and noneconomic factors. It includes two pro-
cesses: (1) Criteria weighting; and (2) analysis. In the first process, the more
important criteria are selected and their relative weights or degrees of im-
portance are established. In the second process, the alternatives developed
are listed and ranked against each set of criteria. The following five ranks
were suggested by Dell'Isola: excellent, "5"; very good, "4"; good, " 3 " ;
fair, "2"; and poor, " 1 . " For each alternative, the rank and weight of each
set of criteria are then multiplied and totaled. The alternative resulting in the
highest score is recommended for implementation.
Evaluation Criteria
According to Gangarao et al. (1988), six criteria were considered to be
the most important for the selection of low-volume road bridges. They in-
cluded: construction cost, maintenance, durability, service life, resource
availability and ease of construction (Table 3). These criteria were initially
chosen for the selection of highway bridges and elevated roads included in
this study.
Through a small sample questionnaire, 10 bridge design and construction
engineers were asked to review the aforementioned six criteria for their ef-
fectiveness in evaluating the economic and engineering performance of a
bridge. Most of the engineers believed that the criteria were inadequate for
achieving that purpose. They further recommended the consideration of two
more criteria: construction progress rate and design efficiency. They were
396
Note that the maintenance criteria received very little weight. This could
be attributed to the moderate climate extending throughout almost the entire
four seasons of the year, minimizing the maintenance effort required for
most of the bridge systems involved.
397
Bridge system Construc- Mainte- Dura- Service avail- construc- tion prog- effi-
projects used tion cost nance bility life ability tion ress rate ciency
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
1 A 3.7 4.0 4.0 4.0 3.2 3.0 3.4 3.9
2(a) D 3.5 4.0 4.0 4.0 2.6 3.0 1.5 3.7
2(b) G 2.8 4.5 4.0 4.0 5.0 5.0 2.8 3.4
3 B 1.2 3.0 4.0 4.0 2.8 2.0 2.4 3.1
4 D 4.3 4.0 4.0 4.0 2.7 3.0 1.6 3.0
5 H 2.4 4.0 4.0 4.0 2.7 4.0 1.7 3.9
6 G 2.7 4.5 4.0 4.0 5.0 5.0 2.2 5.0
7(a) B 2.4 3.0 4.0 4.0 3.2 2.0 2.5 2.9
7(b) D 3.6 4.0 4.0 4.0 2.9 3.0 1.2 2.8
7(c) H 5.0 4.0 4.0 4.0 2.9 4.0 3.3 3.0
8(a) E 4.2 3.0 4.0 3.0 2.9 2.0 2.3 4.2
8(b) F 3.7 3.0 4.0 3.0 2.8 2.0 4.9 3.9
9 G 3.3 4.5 4.0 4.0 5.0 5.0 2.6 3.2
10 C 1.0 2.0 3.0 2.0 1.0 3.0 5.0 3.9
398
highest progress rate (4.8) and the highest design efficiency (4.0). Compared
to the used system, system (B) had about a 54% decrease in construction
cost performance, a 25% decrease in maintenance performance, a 33% de-
crease in ease of construction, a 24% decrease in progress rate, and a 23%
decrease in design efficiency. Therefore, it was not used. System C also was
not used, in spite of having about a 41% increase in progress rate compared
to the system used. This could be due to the high-level piers (having a max-
imum height of about 21m), for which very heavy cranes would have been
required for erecting the steel elements. Besides, it could achieve about a
62% decrease in construction cost performance, a 50% decrease in main-
tenance performance, a 25% decrease in durability, a 50% decrease in ser-
vice life, and a 69% decrease in local resources utilization.
Based upon the previous analysis, the system used (A) is considered the
best choice for this bridge. This can be concluded from its highest total score
of 358 as indicated in the analysis matrix shown in Table 6.
(H)
Downloaded from ascelibrary.org by KANSAS STATE UNIV LIBRARIES on 07/17/14. Copyright ASCE. For personal use only; all rights reserved.
number Bridge name Site condition Code Score Code Score Code Score
0) (2) (3) (4) (S) (6) (7) (8) (9)
l Extension to Sixth of October Running traffic A" 358 B 277 c 238
Bridge
2 Rod El-Farag Bridge
2(a) Spans Nile crossing Navigable waterways D' 320 E 265 — —
2(b) Approach spans Accessible G" 385 F 299 H 353
3 Zamalek Elevated Road Running traffic B 255 A" 363 C 243
4 Abu El-Ela Bridge Navigable waterways D" 337 E 265 — —
5 Cairo Airport Bridge Accessible H 313 F 299 G' 384
6 Passengers' Hall Bridge Accessible G* 387 F 299 H 353
7 Dessouk Bridge
7(a) Approach spans Running traffic B 290 A" 363 C 243
7(b) Spans Nile crossing Navigable waterways D" 317 E 265 — —
7(c) Spans over land Accessible H 377 F 299 G" 383
8 New Benha Bridge
8(a) Spans Nile crossing Navigable waterways E" 325 D 302 — —
8(b) Approach spans Accessible F 341 G" 384 H 353
9 Itay El-Baroud Bridge Accessible G" 393 F 299 H 353
10 Dr. Aly Ibrahim Steet Bridge Running traffic C 235 A' 363 B 277
fl
Optimal construction system.
SUMMARY
In six out of the 14 bridge project cases included in this study (about
43%), the construction system used was not the best alternative, based on
400
It should be noted that the best alternatives found in this study are the
result of a small sample survey of bridge projects in Egypt. If the VE prin-
ciples used are applied for other projects, they may not yield the same re-
sults. This is mainly due to the uniqueness and circumstances of each proj-
ect. It is therefore recommended that VE studies considering all potentially
feasible designs and construction options be conducted in the early stages
of major bridge projects. This should help the design engineer obtain the
optimal bridge design and construction system for any given situation. In
performing such studies, the evaluation criteria used in this paper should be
reviewed for their effectiveness and applicability to a particular situation.
New criteria with new weights should be investigated as might be appro-
priate.
APPENDIX. REFERENCES
Bindra, S. P., and Bindra, K. (1976). Elements of bridge, tunnel and railway en-
gineering. Dhanpat Ray and Sons, Delhi, India.
Bridges and tunnels. (1987). The Arab Contractors, Osman A. Osman and Co.,
Cairo, Egypt.
Cain, J. F. (1986). "Spanning urban obstacles." Civ. Engrg., ASCE, 56(1), 52-55.
Dell'Isola, A. J. (1982). Value engineering in the construction industry, 3rd Ed.,
Van Nostrand Reinhold Company, Inc., New York, N.Y.
Gab-Allah, A. A. (1989). "Special building construction systems—bridge construc-
tion," thesis presented to Zagazig University, at Zagazig, Egypt, in partial ful-
fillment of the requirements for the degree of Master of Science.
Gangarao, H. V. S., et al. (1988). "Value engineering approach to low-volume road
bridge selection." J. Struct. Engrg., ASCE, 114(9), 1962-1977.
"Prestressed concrete bridges." (1987). DYWIDAG-Reports: Issue No. 7, Dywidag-
Systems International, GmbH, Munich, Germany.
Ratay, R. T. (1984). Handbook of temporary structures in construction. McGraw-
Hill Book Co., New York, N.Y.
401