You are on page 1of 9

Case Study

Value Engineering for Roadway Expansion


Project over Deep Thick Soft Soils
Tae-Hyung Kim 1; Hyun Woo Lee, M.ASCE 2; and Seok-Woo Hong 3

Abstract: A roadway expansion that takes place on soft ground is susceptible to differential settlement because of the high consolidation of
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

soft soils. Therefore, steps must be taken to lessen the risk of such settlement; yet, this often only results in costly drainage solutions. In that,
applying a systematic value engineering (VE) process can be beneficial to develop cost-effective design alternatives. However, VE studies
specifically targeting for this problem are absent from the field. Thus, the goal of this study is to supplement this knowledge gap by applying a
systematic VE process to an expansion project on soft ground to demonstrate the benefits of performing VE. A case study was performed on
an expansion project over a soft soil layer approximately 50 m thick. Through the VE process, the original design was reviewed, problems
were discussed, and three alternatives were proposed. Then value analysis techniques were applied to evaluate these alternatives in terms of
cost saving, function improvement, and value improvement with respect to the original design. The VE process and design alternatives as
applied in this study are expected to serve as a guideline for engineers and decision-makers in roadway expansion projects on soft ground.
DOI: 10.1061/(ASCE)CO.1943-7862.0001054. © 2015 American Society of Civil Engineers.
Author keywords: Value engineering (VE); Job plan; Roadway expansion; Deep soft ground; Differential settlement; Value improvement;
Cost saving; Project planning and design.

Introduction design solutions for a roadway expansion on soft ground. In


response, the overarching goal of this study is to supplement this
In 2011, the number of vehicles worldwide surpassed 1 billion knowledge gap by applying a systematic VE process to a case
units—an annual increase of 3.6%, 20 million vehicles, since 2009 project to exemplify the process of developing design alternatives
(WardsAuto 2011). Today, increased traffic continues to demand for a roadway expansion on soft ground. To achieve the goal, this
road expansions internationally, and these expansions require ad- study aims: (1) to analyze the original design of a roadway expan-
equate planning to minimize the chance of differential settlement sion project for brainstorming ideas for improvement; and (2) to
between new and existing sections. When an expansion project synthesize and evaluate ideas for developing alternatives as design
occurs on soft soils specifically, the embankment for new sections improvement through a systematic VE process, called the job plan.
could cause high settlement because of the high consolidation To exemplify the VE process as applied in a roadway expansion
of soft soils, which subsequently leads to differential settlement project, a highway expansion project in South Korea was selected.
between the new and existing road. Such differential settlement It is expected that the VE process as applied in this study, along
can result in a number of problems such as reduced traffic safety with the design alternatives developed as a result of the process,
and reduced structural stability, increased surface cracking, and in- will provide a guideline for engineers and decision-makers to
creased maintenance costs during construction and maintenance. perform VE when they face issues related to a roadway expansion
In recent years, ground improvement methods based on drain- project on soft ground. It is also believed that the rigor of this case
age systems have proven effective for accelerating the consolida- study will provide insight and evidence regarding the capability
tion of soft soils. Unfortunately, such drainage systems are typically and effectiveness of the VE job plan in improving the value of ex-
costly. Therefore, applying a systematic value engineering (VE) pansion projects.
process can be beneficial in developing cost-effective design alter-
natives that can improve the value of expansion projects on soft
ground, while effectively mitigating the risk of differential settle-
Literature Review
ment. However, no identified VE study has aimed at developing

Geotechnical Issues Related to Expansion Projects on


1
Soft Ground
Professor, Dept. of Civil Engineering, Korea Maritime and Ocean
Univ., Busan 606-791, Republic of Korea. E-mail: kth67399@kmou.ac.kr It is a geotechnical fact that stress can exist at a point in soils
2
Assistant Professor, Dept. of Construction Management, Univ. of not only because of a superstructure loading above the point,
Washington, 120 Architecture Hall, Campus Box 351610, Seattle, WA but also by loading on adjacent points (Bowles 1997; Clough
98195 (corresponding author). E-mail: hyunwlee@uw.edu and Woodward 1967). When applied to saturated clay, this stress
3
Assistant Professor, Dept. of Civil Engineering, Dong-Eui Univ., 176 can result in consolidation because of dissipation of excess pore
Eomhwangno, Busan-Jin-gu, Busan 614-714, Republic of Korea. E-mail:
water pressure (Bergado et al. 1990; Holtz and Kovacs 1981). This
hongswoo@deu.ac.kr
Note. This manuscript was submitted on December 29, 2014; approved
localized differential settlement can cause unevenness and cracking
on July 10, 2015; published online on August 17, 2015. Discussion period in the road, and even cracks in a superstructure itself (Ludlows et al.
open until January 17, 2016; separate discussions must be submitted for in- 1993; Varin and Saarenketo 2012). Applying uniform embankment
dividual papers. This paper is part of the Journal of Construction Engineer- preload to the entire roadway area for an extended period will
ing and Management, © ASCE, ISSN 0733-9364/05015014(9)/$25.00. create uniform settlement and thus minimize the likelihood of this

© ASCE 05015014-1 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


problem occurring (Jamiolkowski et al. 1983). However, it is chal- However, the results of VE studies (such as implemented VE
lenging to accomplish this in a road-widening project because this tools and techniques, and developed ideas and alternatives) are sel-
process leads to prolonged construction schedules, further inter- dom disseminated, hindering the knowledge transfer from project
rupting traffic and increasing construction costs (Cao and Shi 2012; to project (NCHRP 2005). An extensive literature search for VE in
Varin and Saarenketo 2012). highway construction revealed that only a few studies have reported
implemented procedures [e.g., Basha and Gab-Allah (1991) for
bridge construction] and design alternatives [e.g., Lee et al. (2010)
Value Engineering for a highway toll plaza modification]. No VE studies were iden-
VE has become an integral part of many construction projects that tified for highway expansion projects.
have sought a way to increase the value of projects (Cariaga et al.
2007; Moon et al. 2012). VE is an organized process that identifies
opportunities that can improve the value of products while remov- Original Design and Its Limitation
ing unnecessary costs (Dell’Isola 1997). The VE process generally
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

involves value analysis and function analysis to determine the cost- For the purpose of the present study, the second branch of the
effectiveness and feasibility of proposed design alternatives, while Namhae Expressway in South Korea was selected. The traffic
meeting or exceeding the required functions of a facility at a mini- on the expressway had been fast approaching the traffic capacity
mum life-cycle cost (Chun 2007; WVDOT 2004). of the roadway. Frequency of severe traffic delays had greatly in-
In the context of VE, the value improvement is achieved by in- creased. To diminish the traffic problem, the expressway would be
creasing the function or reducing the cost, or both, based on Eq. (1) expanded from four lanes to eight lanes while traffic is diverted
(Dell’Isola 1973, 1997; Lee et al. 2010): during construction.
The expansion project involves constructing a new set of four
ΔFunction lanes alongside the existing four lanes in the westbound direction
Value Improvement ¼ ð1Þ (Fig. 1). However, because the expansion would be constructed on
ΔCost
soft soils up to approximately 50 m thick, there would be a signifi-
where ΔFunction = function change relative to the original design; cant level of risk of differential settlement occurring. To meet the
and ΔCost = cost change relative to the original design (Dell’Isola project requirement of the transportation agency (hereinafter, the
1973, 1997; Lee et al. 2010). In other words, for an alternative to be agency) for any new road construction in the allowable residual
considered for implementation, ΔFunction must outweigh ΔCost settlement of 10 cm, the original design included the installation
(i.e., value improvement >1). of vertical drains, called plastic board drains (PBDs), as a way
The VE process is made possible by collaboration amongst a to accelerate the consolidation of soft soils (Rahman et al. 1990;
multidisciplinary team that carries out a rigorous, systematic effort Rixner et al. 1986).
in value and function analysis (Dell’Isola 1997). Creative work- For the existing road, PBDs were installed along 1.2 km of the
shops play a vital role in the VE process by allowing a multidis- highway, equivalent to 6% of the total length 19.6 km when the
ciplinary team to use their combined knowledge, experience, and existing road was constructed in 1978. For the sections constructed
creativity to generate ideas (Moon et al. 2012). These ideas are then without vertical drains, long-term and continuous consolidation
synthesized to develop design alternatives that aim to avoid unnec- settlement had occurred since the opening of the road because the
essary expenditures while obtaining optimum value (AASHTO embankment was built using sand, gravel, and crushed stone with-
2010; Dell’Isola 1973). The VE job plan (Dell’Isola 1973, 1997) out soft ground improvement. In that regard, the original design
provides a guideline for VE participants by describing tasks that are included the removal of the existing road and the installation of
to be performed in each phase of the VE process, including inves- new vertical drains (PBDs) for improving soft ground. The design
tigation, speculation, evaluation, development, and presentation was originally perceived to be the most economical method of en-
(FHWA 2014). The effectiveness of VE has been reported in many suring the long-term stability of the highway after the expansion.
construction project cases including a report by FHWA (2013) in It would satisfy the minimum longitudinal slope of 0.5% and the
which 1,191 approved VE recommendations were said to have re- minimum allowable residual settlement of 10 cm. However, a more
sulted in a combined cost saving of more than $1 billion in 2012 detailed investigation by the agency revealed the following the lim-
(approximately a $1 million saving per recommendation). itations of the original design.

Soft
Ground PBD

Fig. 1. Construction sequence of original design (adapted from Kim et al. 2012)

© ASCE 05015014-2 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


Low Constructability of PBD Installation on the Overall Value Engineering Process
Existing Road
The VE job plan is the systematic application of recognized VE
According to the original design, PBDs would be applied to im- techniques (Caltrans 2013; FHWA 2014), and its objective is to
prove soft soils after removing the existing road. However, as men- achieve improved value not only by a cost reduction but also by
tioned previously, only 6% of the existing road was constructed
increased function. Fig. 2 shows the main phases and associated
with vertical drains, and the remaining 94% was built using sand,
tasks of the VE job plan as applied in the project. To effectively
gravel, and crushed stone for the lower part of the roadbed without
complete the VE process according to the job plan, a group of
drains. These coarse materials would obstruct the installation of
project stakeholders gathered to form a VE team (hereinafter, the
PBDs, and would hence significantly reduce the constructability
team). The team consisted of a dozen of specialists including en-
of the PBD installation on the existing road. In addition, there
gineers from the agency, engineering consultants, and civil engi-
is a high chance of needing special drilling and excavation because
neering professors. The agency administered the process of inviting
of the low constructability, and these activities could eventually
increase the schedule and costs. What is worse, if a drilling method team members and establishing the team, and the team members
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

is applied on the slope of the existing road, construction could were selected based on diversified expertise, engineering back-
be significantly delayed because of the additional time required ground, and construction experience, to establish a multidiscipli-
for the drilling and for filling the drilled halls on the slope (Kim nary team. When the team formation was finalized, the specialties
et al. 2012). of the team members ranged from structural engineering, geotech-
nical engineering, transportation engineering, and construction
management. Performing the job plan was then centered on a series
Extended Construction Schedule for Soil Stabilization of creative workshops in which project members communicated
The agency learned from a previous project that soft ground im- their experience and expert opinions. The creative workshops were
provement using PBD installation after removing the existing road hosted by the agency at Busan, South Korea, and the team met a
is time-consuming work, because of time required for the stabili- total of nine times from March 2009 to September 2009.
zation of soft ground. In 1996, an expansion project that the agency The following sections summarize the results of each phase as
oversaw included improving soft soils in two sections of expansion performed by the team, focused on three phases, function analysis
and existing roads. Despite the original schedule to complete the and value analysis, idea creation, and development and evaluation.
entire project within 24 months, it took more than 24 months just
to improve soft soils in the expansion section. The unexpected
delay resulted in a modification of the project plan to exclude soft Function Analysis and Value Analysis
ground improvement underneath the existing road. Based on the
lessons learned from the previous project, an extensive scheduling The function analysis and value analysis phase of the job plan
analysis by the agency revealed that the soil stabilization after the started with the function analysis system technique (FAST), a func-
removal of the existing road would require more time than expected tion analysis technique that determines the basic and secondary
for construction. functions of a product or process under study (Kaufman and Wood-
head 2006). A FAST diagram has a horizontal orientation described
as the HOW-WHY dimension, because it helps “identify dependent
Increased Construction Cost for Waste Removal
functions (how) and the reason for selecting those functions (why)”
The construction costs would increase in proportion to the quantity (Kaufman and Woodhead 2006). VE participants are asked to start
of waste materials that need to be transported and disposed. On with a function on the left and ask WHY that function is performed
top of the waste materials generated by the drilling for the PBD and continue to ask why as they move across the diagram to the
installation, a large amount of asphalt concrete waste would result right. The diagram will structure the logic of the identified func-
from the removal of the existing road. A preliminary field inves- tions, and provide a basis for determining function costs (Dell’Isola
tigation revealed that the asphalt concrete at some areas (especially 1997; UDOT 2013). Fig. 3 shows the FAST diagram that the team
near bridge abutments) was up to 1.5 m deep because of repeated developed.
pavement overlays triggered by incremental settlement more than
30 years.
PHASES TASKS
Risk of Differential Settlement Review project requirements
Information Gathering Identify problems
Even after the PBD installation, the original design could still be
susceptible to additional differential settlement because of the fol- Identify functions being provided
lowing two factors. First, the soft ground below the existing road- Function Analysis and Determine costs of functions
Value Analysis Determine value of functions
way has settled for more than 30 years. The installation of PBDs Determine target functions for improvement
could disturb the settled soft soils, which in turn could lead to
unexpected, additional settlement. Second, differential settlement Identify creative ideas for target functions
Idea Creation Evaluate ideas
could occur because of different overconsolidation ratios between
the new expansion sections and existing road sections (Wang et al.
Development and Synthesize ideas into alternatives
2012). Evaluate alternatives
Evaluation
The identified issues associated with the original design trig-
gered an investigation for value improvement, and accordingly
provided a case study opportunity for this study. The following Presentation Present alternatives
sections present the VE job plan which project members followed
to develop design alternatives that would improve the value of the
Fig. 2. VE job plan phases and tasks
expansion project.

© ASCE 05015014-3 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


How? Why?
High order Ensure Minimize Reduce Minimize fill Adjust Minimize Increase Input
functions safety coupled overburden longitudinal longitudinal surface functions
settlement load alignment grade drainage
Ensure safety capacity Apply
for roadway optimum
Apply soil
expansion on Use light method
Improvement
soft ground materials
methods on
as a fill
soft ground

Control Separate new Adjust Use available


longitudinal expansion horizontal space as
cracks from the alignment green zone
existing road
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

Control
differential
settlement

Meet Simplify Stabilize Change ground


Improve
construction construction ground improvement
constructability
schedule process under the method for the
existing road existing road

Secure Reduce the Select a proper


continuity of duration of fill method
Increase the construction on soft ground considering road
use of expansion
equipment in
construction

Extend Reduce Select a proper


construction stabilization method
schedule period considering
ground property

Scope of VE Study

Fig. 3. FAST diagram

Based on the functions identified through the FAST diagram, construction and estimating knowledge of the team. Table 1
the original design was reviewed to overcome the identified limi- summarizes the results of the analysis. It was determined that
tations of the original design. The FAST diagram consists of 27 F-2 accounts for the highest function cost (38% = $4.2 million/
functions including two basic functions (“Ensure safety” and $11.2 million), followed by F-4 (30%), F-1 (18%), and F-3 (14%).
“Improve constructability”). A basic function refers to “a perfor- Following the function cost analysis, the team applied the de-
mance feature that must be attained” (WVDOT 2004). Through cision alternative ratio evaluation system (DARE) law to determine
the creative VE workshops, the team analyzed the secondary func- the value weight distribution of the four key functions. Table 2
tions as to which functions the team would need to focus on improv- presents the results of the DARE. The DARE law suggests the fol-
ing. The analysis was based on the premise that the improvement of lowing steps to determine the value weight distribution of n number
each selected function would most effectively help overcome the of functions (Sato and Kaufman 2005):
identified limitations of the original design. As a result of the analy- 1. Determine the value index of the ith function respective to that
sis, the team selected the following four key functions for further of the i þ 1th function whose value index is set at 1.0 (e.g., F-1
analysis (functions in bold in Fig. 3): received 2.0 because the team collectively decided that F-1 is
• F-1: Reduce overburden load, twice more important than F-2 that was set at 1.0). Step 2 starts
• F-2: Adjust longitudinal alignment, with F-1 in Table 2, which is i ¼ 1. The determined indices are
• F-3: Meet construction schedule, and given in the columns named “Value Index Based on Function-
• F-4: Stabilize ground under the existing road. to-Function Comparison.”
As a next step, the team analyzed the function costs of the four 2. Repeat Step 1 until the value index of the n − 1th function (F-3
key functions. Function cost is defined as “the cost of the method in Table 2) is determined.
chosen to perform the function under consideration” (WVDOT 3. Determine the relative value Ri of the ith function as a product
2004), which is prorated from the cost of an item that performs of each value index (e.g., 1.0 × 1.5 ¼ 1.5 for F-3).
the function (Park 1998). The analysis involved breaking down the 4. Determine the weight score K i of the ith function by Eq. (2):
construction costs of three main construction operations of the 
K iþ1 Ri ði ¼ 1,2; : : : ; n − 1Þ
project (earthwork, vertical drain, and horizontal drain) into rela- Ki ¼ ð2Þ
tive costs pertaining to each function to the best of the collective Ri ði ¼ nÞ

© ASCE 05015014-4 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


Table 1. Determination of Function Costs
Key function costs (in $ million)
F-1 F-2 F-3 F-4
Costs Reduce overburden Adjust longitudinal Meet construction Stabilize ground under
Type of work (in $ million) load alignment schedule the existing road
Earthwork 9.0 1.8 3.6 0.9 2.7
Vertical drain 1.3 0.1 0.4 0.4 0.4
Horizontal drain 0.9 0.1 0.2 0.3 0.3
Total 11.2 2.0 4.2 1.6 3.4
Weight (%) 100 18 38 14 30
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

Table 2. Determination of Function Value change; −1 = degradation; −2 = significant degradation). The se-
Value index based on lection of the five criteria was suggested by the agency because the
function-to-function five criteria were in alignment with not only the business missions
Item comparison R K W (%) of the agency but also the primary concerns associated with the
expansion project. The total scores were calculated for ranking the
F-1 2.0 — — 2.0 3.0 43
F-2 (1.0) 1.0 — 1.0 1.5 21 ideas based on the following five levels:
F-3 — (1.0) 1.5 1.5 1.5 21 • Rank 5: Major value improvement (total score of 7 to 10),
F-4 — — (1.0) 1.0 1.0 14 • Rank 4: Moderate value improvement (total score of 4 to 6),
Total — — — — 7.0 100 • Rank 3: Minor value improvement (total score of 0 to 3),
• Rank 2: Moderate value degradation (total score of −1
to −5), and
• Rank 1: Major value degradation, or nonconformation (total
5. Determine the value weight W i of the ith function in percent score of −6 to −10).
by Eq. (3):
X
n Development of Design Alternatives
Wi ¼ Ki Ki ð3Þ
i¼1 The development phase involved synthesizing the ideas shown in
Tables 4 and 5 to develop design alternatives, from which three
The last step in determining the target functions for improve- alternatives resulted. The alternatives share one underlying idea:
ment is to calculate the weight differential of the four key functions “2-7 Leave the existing road.” Table 6 lists the ideas synthesized
between the function cost weight in percent (C in Table 3) and the for developing the three alternatives, and the following sections
function value weight in percent (V in Table 3). The decision rule is, present each alternative in detail.
when a function cost significantly outweighs the function’s value, it
indicates that the function likely has the opportunity for improve- Alternative 1
ment. Therefore, based on the weight differentials, F-2 and F-4
were determined to present the best opportunities for improvement Alternative 1 involves lowering longitudinal grade and installing a
because their function costs outweigh the value. Subsequently they median strip along the expansion to absorb the effect of any differ-
were selected for continued analysis. ential settlement that may occur (Fig. 4).
In this alternative, based on the Ministry of Construction and
Transportation (2003), the standard for longitudinal slope was re-
Idea Creation vised from 0.5% or greater to 0.3% or greater, which results in
reducing the depth of the embankment over the existing road by
During the idea creation phase, the team carried out a series of 5 m at most. The changes were expected to eliminate a need for
brainstorming sessions to create ideas in regards to the two func- PBD installation in the existing road section and thus minimize
tions selected for improvement. Tables 4 and 5 summarize the re- the chance of additional settlement because of the disturbance
sults of the sessions. A total of 12 ideas were suggested for each of of soils. The design for the crossings with other highways was re-
the two functions (F-2 and F-4). vised from underpass to overpass so that the grade difference be-
The suggested ideas were then evaluated based on five evalu- tween the new road and the existing road could be minimized. In
ation criteria—safety, constructability, maintenance, environment, addition, the reduction of longitudinal slopes would secure enough
and cost—and subsequently rated against the criteria by using five space for installing a three to six meter-wide green zone as a
levels (2 = significant improvement; 1 = improvement; 0 = no bumper zone. The green zone would absorb the effect of differential
settlement between each direction.
Alternative 1 allows for leaving the existing road with no PBD
Table 3. Determination of Functions for Improvement installation. Alternative 1 would therefore require only typical over-
lay over the existing road and subsequently eliminate a need for
Item F-1 F-2 F-3 F-4
embankment. As a result, Alternative 1 would reduce the quantities
Function cost weight (C) in percent 18 38 14 30 of embankment and PBD, by 500,000 m3 and 1,140,000 m, respec-
Function value weight (V) in percent 43 21 21 14 tively, which leads to a significant construction cost saving. In
C−V −25 17 −7 16 addition, the original design would require the removal of the
Rank order for improvement opportunity 4 1 3 2
existing road, resulting in additional cost needed to dispose of

© ASCE 05015014-5 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


Table 4. Evaluation of Ideas Created for F-2
Evaluation criteria
Number Idea description Safety Constructability Maintenance Environment Cost Total Rank
1-1 Adjust minimum longitudinal slope from 0.5 to 0.3% based on given 0 2 0 0 2 4 4
in the manual and guideline for standards of road structures
1-2 Lower longitudinal grade to reduce an additional load on the 2 2 2 0 1 7 5
existing road
1-3 Change type of grade separation from underpass to overpass 1 1 2 1 −1 4 4
1-4 Change shape of culvert 1 0 2 1 0 4 4
1-5 Reduce inlet spacing of surface drainage facility 2 0 2 1 0 5 4
1-6 Use available space in the existing road 1 1 2 2 2 8 5
1-7 Install a green median strip as a bumper zone that observes the effect 2 1 2 2 2 9 5
of differential settlement
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

1-8 Make the most of the existing road alignment 2 1 1 1 2 7 5


1-9 Use bridge in deep thick soft ground sections rather than embankment 2 −1 −1 0 −2 −2 2
1-10 Consider the maximum flood level of the Nakdong River 2 0 2 2 0 6 4
1-11 Maintain the transverse and longitudinal profile of underpass road 1 0 1 1 0 3 3
1-12 Secure fill material for embankment and consider transport distance of 0 0 0 2 2 4 4
fill material

Table 5. Evaluation of Ideas Created for F-4


Evaluation criteria
Number Idea description Safety Constructability Mainte-nance Environment Cost Total Rank
2-1 Use expanded polystyrene (EPS) to reduce an overburden load 2 2 0 1 −1 4 4
2-2 Replace vertical drains sand compaction pile (SCP) 1 0 0 0 −1 0 3
2-3 Relax the allowable residual settlement requirement 2 1 2 0 −1 4 4
2-4 Reduce maintenance cost 1 0 2 1 0 4 4
2-5 Apply deep cement mixing method to improve soft ground 2 1 0 −1 −2 0 3
2-6 Extend the construction schedule to get enough time required to 2 1 0 1 −2 2 3
stabilization of soft ground
2-7 Leave the existing road 2 2 0 2 2 8 5
2-8 Install vertical drains by drilling hole on the existing road 2 0 1 2 −1 4 4
2-9 Minimize coupled settlement 2 1 1 0 0 4 4
2-10 Eliminate the need for ground improvement under the existing road 2 2 0 0 2 6 5
2-11 Install a differential settlement bumper zone between the new road 2 1 2 1 0 6 5
and existing road
2-12 Separate new road from the existing road 2 −1 −1 0 −2 −2 2

Table 6. List of Ideas Synthesized for Alternatives result in a significant reduction in the quantity of embankment
Alternatives Descriptions Ideas number by 500,000 m3, but because of the same longitudinal grade as
the original design, it would require additional embankment. The
Alternative 1 • Leave the existing road 1-1, 2, 3, 4, 5, 6, 7,
PBD installation on the existing road would require additional
• Lower longitudinal grade 8, 10, 12
• Eliminate PBD installation 2-3, 4, 7, 9, 10, 11
construction cost not only for the installation itself but also for
• Install a median strip the treatment of the disturbed soil during installation. For those rea-
Alternative 2 • Leave the existing road 1-10, 12 sons, the schedule reduction by Alternative 2 is not as significant as
• Install PBD installation 2-3, 4, 7, 8, 9 Alternative 1.
through the existing road
Alternative 3 • Leave the existing road 1-10, 12
• Use EPS for embankment 2-1, 3, 7, 9 Alternative 3
Alternative 3 involves using expanded polystyrene (EPS) to re-
duce the weight of embankment on the existing road, so that the
PBD installation would not be needed (Fig. 6). Like Alternative
the demolished asphalt concrete and existing base. Therefore, if 2, Alternative 3 shares the benefit of reducing the quantity of em-
Alternative 1 is applied, the need for removing the existing road bankment by 500,000 m3 but still requires additional embankment
is eliminated, and construction schedule would be reduced by at because of the same longitudinal grade as the original design. Like
least 10 months. Alternative 1, Alternative 3 would reduce the quantity of PBDs by
1,140,000 m, and subsequently eliminate a need for the treatment
of the disturbed soil during the PBD installation. However, the in-
Alternative 2
stallation of EPS would require a significant increase both in con-
Alternative 2 involves PBD installation without removing the struction cost and operation, so the benefit from schedule reduction
existing road (Fig. 5). Similar to Alternative 1, Alternative 2 would is not comparable to Alternative 1.

© ASCE 05015014-6 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


Median Strip
3~6 m
Lower Longitudinal
Grade

Median
Leave the Strip
Existing Road 3~6m

No Ground
Improvement
The Existing Road
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

(a) (b)

Fig. 4. (a) Section view; (b) plan view of Alternative 1

38.8 m

Leave the
Existing Road 38.8 m

PBD Installation through 6.0 m


the Existing Road
The Existing Road

(a) (b)

Fig. 5. (a) Section view; (b) plan view of Alternative 2

38.8 m

EPS
Installation

Leave the
Existing Road 38.8 m

No Ground
Improvement 6.0 m

The Existing Road


(a) (b)

Fig. 6. (a) Section view; (b) plan view of Alternative 3

Evaluation of Design Alternatives Comparison of Cost Savings

The evaluation phase of the job plan consisted of three steps: com- At the start of the evaluation phase, the team determined that each
parison of cost savings, analysis of function improvement, and alternative would require an equivalent level of regular mainte-
analysis of value improvement. The three steps led to a selection nance, and hence only the construction costs were considered for
of the best value alternative, and the selection process is detailed analysis. Table 7 compares construction costs of the three alterna-
in this section. Based on Eq. (1), value improvements from each tives to those of the original design, and compares the cost varia-
alternative were measured based on the level of function changes tions among the alternatives to calculate relative cost ratios (RC).
relative to the original design, and the level of cost changes relative First, Alternative 1 would lead to a cost reduction of $3 million
to the original design. The goal was to select the alternative that (26.8% less than the original design) by leaving the existing road
would offer the largest value improvement. untouched, eliminating the need for PBD installation, reducing the

© ASCE 05015014-7 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


Table 7. Cost Variations between Alternatives and Original Design
Cost (in $ million) Cost Variation (in $ million)
Type of work Original design Alternative 1 Alternative 2 Alternative 3 Alternative 1 Alternative 2 Alternative 3
Earthwork 9.0 8.2 8.2 8.2 (0.8) (0.8) (0.8)
Vertical drain 1.3 — 3.4 — (1.3) 2.1 (1.3)
Horizontal drain 0.9 — 0.9 — (0.9) — (0.9)
EPS — — — 19.5 — — 19.5
Total 11.2 8.2 12.5 27.7 (3.0) 1.3 16.5
Relative cost ratio (RC) (%) (26.8) 11.6 147.3

Table 8. Analysis of Function Improvement


Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

Items Original design Alternative 1 Alternative 2 Alternative 3


a a a
Weighting Rank Points Rank Points Rank Points Ranka Points
Performance (A) (B) (A × B) (B1) (A × B1) (B2) (A × B2) (B3) (A × B3)
Safety 7 4 28 4 28 4 28 4 28
Constructability 10 1 10 5 50 2 20 5 50
Maintenance 5 3 15 4 20 3 15 3 15
Environment 2 3 6 3 6 3 6 3 6
Cost 7 2 14 4 28 2 14 1 7
Function points 73 132 83 106
Relative function improvement — 80.8 13.7 45.2
(FI) (%)
a
Rank: 5 = very good; 4 = good; 3 = fair; 2 = poor; 1 = very poor.

longitudinal slope, and installing a bumper zone. Second, Alterna- Table 9. Analysis of Value Improvement
tive 2 would actually result in a cost increase of $1.3 million Original Alternative Alternative Alternative
(11.6% more than the original design) because of the increased Items design 1 2 3
quantity of PBD installation on the existing road. Lastly, Alterna-
Relative function 1.00 1.81 1.14 1.45
tive 3 is presumed to save $3 million in earthwork and installation
improvement ðFIÞ þ 100%
of vertical and horizontal drains; yet the installation of EPS would Relative cost ratio 1.00 0.73 1.12 2.47
completely offset the savings and eventually result in a cost in- ðRCÞ þ 100%
crease of $16.5 million (147.3% more than the original design). Value improvement — 2.48 1.02 0.59

Analysis of Function Improvement


value degradation because of a significant cost increase by the EPS
The same five evaluation criteria used in the idea creation phase installation. It is interesting to see that a value improvement from
(safety, constructability, maintenance, environment, and cost) were Alternative 2 is insignificant because its improved function is offset
used for analyzing function improvement of each alternative with by its increased construction cost.
regards to the original design. The team collectively decided on
weightings of each preformation criterion in which constructabil-
ity received the highest weighting of 10, whereas environment Conclusion and Future Study
received the lowest weighting of two. Table 8 summarizes the re-
sults of the function improvement analysis that was performed When a roadway expansion project occurs on soft ground, the high
based on five-point rating. The analysis results indicate that Alter- consolidation of soft soils can significantly increase the risk of
native 1 offers a significant function improvement from the origi- differential settlement occurring between the new and existing
nal design by 80.8%. In contrary, Alternative 2 only indicates a road. Recently, ground improvement involving drainage systems
function improvement by 13.7% with regards to the original de- have been used to mitigate the risk, yet significant cost increases
sign. A relatively significant function improvement by 45.2% was have resulted. Therefore, applying a systematic VE process can
determined for Alternative 3, primarily because of its high score in support the development of design alternatives to improve the value
constructability. of roadway expansion projects. By using the job plan, this study
aimed at achieving such value improvement for a roadway expansion
Analysis of Value Improvement project on soft ground. A case study was carried out on a highway
expansion project that would occur on soft soils up to 50 m thick.
Table 9 summarizes the results of value improvement analysis. The original design included installing PBD after removing the
The analysis involved determining the value improvement of each existing road. This design was subject to a number of issues includ-
alternative based on Eq. (4): ing low constructability, increased construction costs, difficulty in
Function ImprovementðFIÞ þ 100% PBD installation, a complicated construction process, and a pro-
Value Improvement ¼ ð4Þ longed construction schedule. The identified issues triggered an
Relative Cost RatioðRCÞ þ 100%
investigation of value improvement to be carried out by a group of
As a result, Alternative 1 indicates a significant value improve- experts acting as a VE team. By following the VE job plan, the
ment by a ratio of 2.48, whereas Alternative 3 indicates significant team hosted a series of brainstorming sessions to develop and com-

© ASCE 05015014-8 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014


pare ideas for the two key functions identified for improvement: Cao, W. P., and Shi, Q. C. (2012). “Settlements of existing and widened
adjust longitudinal alignment and stabilize the ground under the embankments over soft soils.” Adv. Mater. Res., 446–449, 1167–1171.
existing road. As a result, a total of 24 ideas were developed—12 Cariaga, I., El-Diraby, T., and Osman, H. (2007). “Integrating value analy-
for each of the two functions. The ideas included leaving the sis and quality function deployment for evaluating design alternatives.”
J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2007)133:10(761),
existing road, lowering longitudinal grade, reducing overload
761–770.
weight, and installing a green median zone. These ideas were then
Chun, K.-S. (2007). “Current status and suggestions of performance and
synthesized, resulting in three final alternatives. The alternatives value assessment in design VE.” Korean Soc. Civ. Eng. Mag., 55(2),
shared one underlying idea, “Leave the existing road.” 41–46.
Based on the detailed analyses in cost saving, function improve- Clough, R. W., and Woodward, R. J. (1967). “Analysis of embankment
ment, and value improvement, it was determined that Alternative 1 stresses and deformations.” J. Soil Mech. Found. Div., 93(4), 529–549.
provides the best value with respect to the original design. Alter- Dell’Isola, A. J. (1973). Value engineering in the construction industry,
native 1 involved lowering longitudinal grade and installing a Construction Publication, Cedar Rapids, IA.
median strip along the expansion to absorb the effect of any differ- Dell’Isola, A. J. (1997). Value engineering: Practical applications
Downloaded from ascelibrary.org by Florida Atlantic University on 10/09/15. Copyright ASCE. For personal use only; all rights reserved.

ential settlement that may occur. Alternative 1 would result in a cost for design, construction, maintenance and operations, RSMeans,
saving of $3 million—26.8% less than the original design. Based Norwell, MA.
on the five evaluation criteria (safety, constructability, maintenance, FHWA (Federal Highway Administration). (2013). “FY 2012 value engi-
environment, and cost), Alternative 1 indicated a significant function neering accomplishment report.” Washington, DC.
improvement of 80.8% (from 73 to 132), and subsequently a signifi- FHWA (Federal Highway Administration). (2014). “Job plan.” 〈http://www
.fhwa.dot.gov/ve/vejob.cfm〉 (Jan. 7, 2014).
cant value improvement (248% improvement from the original de-
Holtz, R. D., and Kovacs, W. D. (1981). An introduction to geotechnical
sign). As a result, Alternative 1 was selected for implementation. engineering, 2nd Ed., Prentice Hall, Upper Saddle River, NJ.
In conclusion, the job plan based on the team’s creative work- Jamiolkowski, M., Lancellotta, R., and Wolski, W. (1983). “Precompres-
shops allowed for the effective development of a design alternative sion and speeding up consolidation.” Proc., 8th Europe Conf. Soil Mech.
that would offer a significant value improvement over the original and Foundation Engineering, A.A. Balkema, Rotterdam, Netherlands,
design. The team believed that the selected design alternative 1201–1226.
(Alternative 1) would be effective in mitigating the risk of differ- Kaufman, J. J., and Woodhead, R. (2006). Stimulating innovation in
ential settlement while significantly reducing the complexity, cost, products and services: Function analysis and function mapping, Wiley,
and schedule of the construction. Therefore, the implementation Hoboken, NJ.
of the alternative is expected to improve the overall value of the Kim, T.-H., Park, T.-Y., Kim, S.-R., You, S.-H., Kim, K.-H., and Kim, Y.-T.
expansion project through improved function and cost saving com- (2012). “Design improvement of the road expansion on a deep thick soft
pared with the original design. ground.” J. Korean Geotech. Soc., 28(8), 89–99.
Lee, M. J., Lim, J. K., and Hunter, G. (2010). “Performance-based value
The findings and conclusions in this study require careful inter-
engineering application to public highway construction.” KSCE J. Civ.
pretation because of the uniqueness of every project and because of
Eng., 14(3), 261–271.
VE being project-specific. Thus, the authors do not claim that the Ludlows, J., Chen, W. F., Bourdeau, P. L., and Lovell, P. L. (1993).
three alternatives presented in this study are the only viable options Embankment widening and grade raising on soft foundation soils,
for roadway expansion projects on deep soft ground. However, Purdue Univ., West Lafayette, IN.
given that there is a dearth of reported VE studies on highway con- Ministry of Construction and Transportation. (2003). “Manual and guide-
struction in general, the authors expect that the rigor of this case line for standards of road’s structure and facilities.” Gwacheon, Korea.
study has provided insight on and may act as a guideline for how Moon, S., Ha, C., and Yang, J. (2012). “Structured idea creation for
a VE study can be implemented to improve the value of expansion improving the value of construction design.” J. Constr. Eng. Manage.,
projects on soft soils. The authors suggest that additional case stud- 10.1061/(ASCE)CO.1943-7862.0000491, 841–853.
ies be conducted to further capture VE practices in roadway expan- NCHRP (National Cooperative Highway Research Program). (2005).
sion projects. Such efforts are expected to further contribute to the “Value engineering applications in transportation.” Washington, DC.
overall body of knowledge in the field. Park, R. (1998). Value engineering: A plan for invention, CRC Press, Boca
Raton, FL.
Rahman, J., Suppiah, A., Yong, K. W., and Shahrizaila, Z. (1990). “Perfor-
Acknowledgments mance of stage constructed embankment on soft clay with vertical drains.”
Proc., Sem. Geotech. Aspects of N-S Expressway, Projek Lebuhraya
The authors gratefully acknowledge that this study was performed Utara-Selatan Berhad (PLUS), Kuala Lumpur, Malaysia, 245–253.
with the support and cooperation of the Naengjeong-Busan Con- Rixner, J. J., Kraemer, S. R., and Smith, A. D. (1986). Prefabricated
vertical drains, Vol. 1 (Engineering guidelines), Federal Highway
struction Agency of the Korea Expressway Corporation.
Administration (FHWA), Washington, DC.
Sato, Y., and Kaufman, J. J. (2005). Value analysis tear-down: A new pro-
References cess for product development and innovation, Industrial Press, South
Norwalk, CT.
AASHTO. (2010). Guidelines for value engineering, Washington, DC. UDOT (Utah Department of Transportation). (2013). Manual of instruc-
Basha, I., and Gab-Allah, A. (1991). “Value engineering in Egyptian bridge tion: Value engineering, UDOT, Salt Lake City, UT.
construction.” J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364 Varin, P., and Saarenketo, T. (2012). Road widening guidelines, Roadex
(1991)117:3(393), 393–401. Network, Finland.
Bergado, D. T., Ahmed, S., Sampaco, C. L., and Balasubramaniam, A. S. Wang, Y., Tan, W., Zhao, J., and Guo, H.-Y. (2012). “The analysis of
(1990). “Settlements of Bangna-Bangpakong highway on soft Bangkok the differential settlement of widened road based on ANSYS.” Proc.,
clay.” J. Geotech. Eng., 10.1061/(ASCE)0733-9410(1990)116:1(136), Civil Engineering and Urban Planning (CEUP 2012), ASCE, Reston,
136–155. VA, 699–703.
Bowles, J. E. (1997). Foundation analysis and design, 5th Ed., WardsAuto. (2011). “World vehicle population tops 1 billion units.” 〈http://
McGraw-Hill, NY. wardsauto.com/ar/world_vehicle_population_110815〉 (Jan. 17, 2014).
Caltrans (The California Department of Transportation). (2013). “Value WVDOT (West Virginia Department of Transportation). (2004). Value
analysis team leader guide.” Sacramento, CA. engineering manual, WVDOT, Charleston, WV.

© ASCE 05015014-9 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 05015014

You might also like