You are on page 1of 8

Fabrication and Construction Procedures of a Totally Precast

Concrete Counterfort Retaining Wall System for Highways


Maen Farhat, S.M.ASCE1; and Mohsen A. Issa, Ph.D., P.E., S.E., F.ASCE2

Abstract: In this paper, a totally precast concrete counterfort retaining wall system is proposed for highway and bridge applications. This sys-
tem provides several advantages over conventional methods, such as reduced construction time, cost, and environmental impacts. The system
is composed of a precast counterfort wall that is connected to a base slab through headed anchors. The components are cast offsite and trans-
Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

ported to the construction site for final assembly. The proposed system requires a unique method of construction. Accordingly, this paper
details the fabrication and construction procedures required for the proposed system to accelerate the on-site erection process. In the use of this
system, the general guidelines for the fabrication and construction of the totally precast counterfort retaining wall system are presented to the
contractors. The system’s components can be fully assembled and set in place in approximately 2 hours. DOI: 10.1061/(ASCE)SC.1943-
5576.0000316. © 2016 American Society of Civil Engineers.

Introduction counterforts and are placed in tapered cylindrical shear pockets in


the base slab, which facilitates the on-site connection. The shear
Advances in concrete material technology and construction techni- pockets are grouted to maintain full composite action between the
ques along with increasing traffic flow and highway demand have counterforts and the base slab. The proposed system is shown in
increased the need for advanced and rapidly constructed concrete Fig. 1.
structural components, such as substructure systems, for highways This system reduces construction time, resulting in less traffic
and bridges. The combination of high-performance materials with congestion, and requires less specialized labor for construction. The
rapid fabrication methods is an advantage provided by precast con- general guidelines for the fabrication and construction of the
crete systems. This combination allows the precast manufacturer to TPCCRW system have been standardized to expedite the construc-
produce durable and uniform structural components in large quanti- tion process.
ties. Moreover, precast concrete construction techniques provide a
potential reduction in construction times and minimize waste and
Background
labor involvement in unsafe work zones compared with conven-
tional construction methods. Despite these advantages of precast
The use of fully precast concrete solutions for superstructure sys-
systems, it is essential to standardize precast construction techni-
tems has been widely studied (Issa et al. 1995a, b, c, 1998, 2000;
ques to maintain efficiency and fast track the construction process.
Goldberg 1987; PCI-NER 2001, 2002; Tadros and Baishya 1998).
This paper details the fabrication and erection processes for the
However, few attempts have been made to develop precast concrete
totally precast concrete counterfort retaining wall (TPCCRW) sys-
substructure systems (Hieber et al. 2005). Moreover, the current de-
tem developed at the University of Illinois at Chicago (Farhat et al.
velopment of the precast substructure systems is mainly focused on
2014). The proposed system consists of two precast components:
precast pier systems for bridges. For instance, a segmental substruc-
(1) the wall component, which consists of a face panel with three
ture pier system was proposed for the Texas DOT (TxDOT) in 1999
counterforts, and (2) the base-slab component. Both components
(Billington et al. 1999, 2001). The system is mainly composed of
are cast offsite and transported to the construction site for final
match cast column segments: template segments and inverted-T
assembly.
cap components. The erection procedure starts by placing a starter
Counterforts are used to strengthen the face panel of the wall.
template column segment followed by stacking the column seg-
Counterforts allow for a reduction in the thickness of the face panel
ments, which are posttensioned after erecting each segment. The
and increase the panel’s flexural capacity. Headed anchors are used
template segment is then erected and placed followed by the pre-
to connect the wall components to the base slab during on-site con-
stressed precast cap. Joints between every segment are filled with
struction. The anchors are embedded in the counterforts during the
epoxy before posttensioning.
fabrication process. They extend from the bottom of the
A fully precast cantilever retaining wall was developed by the
Michigan DOT (MDOT) (Darwish et al. 2013) to expedite the con-
1
Graduate Research Assistant, Dept. of Civil and Materials Engineering, struction schedule and improve work-zone safety. The system is
Univ. of Illinois, 950 S. Halsted, SEL 1050, Chicago, IL 60607. E-mail: composed of 34.47-MPa (5,000-psi) precast footing and stem seg-
mfarha3@uic.edu
2
ments. Mechanical splicers filled with grout were used to maintain
Professor, Dept. of Civil and Materials Engineering, Univ. of Illinois, full-moment connection. Retaining wall heights ranged from 1.21
2095 Engineering Research Facility, 842 West Taylor Street, Chicago, IL
m (3.96 ft) to 7.92 m (26 ft).
60607 (corresponding author). E-mail: missa@uic.edu
Note. This manuscript was submitted on July 21, 2016; approved on Similarly, the New Hampshire DOT (Stamnas and Whittemore
November 10, 2016; published online on December 9, 2016. Discussion 2005) developed a fully precast concrete bridge design in which the
period open until May 9, 2017; separate discussions must be submitted for speed of construction was a priority. In this project, a fully precast
individual papers. This paper is part of the Practice Periodical on abutment of 5.02 m (16.5 ft) in height on a spread footing was
Structural Design and Construction, © ASCE, ISSN 1084-0680. designed and constructed. The system consisted of precast footing

© ASCE 04016026-1 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1


Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 1. Components of the proposed TPCCRW system

and precast abutment stem. Full-moment connection was main-


tained between the base and the stem through splice-sleeve connec-
tors placed in the stem in which the extended steel rebars from the
base footing were grouted. The sleeves were grouted using high-
strength grout through splice ports.
The main advantage of using precast concrete systems for high-
way and bridge applications is the potential for reduced construc-
tion time, mass production, and a high level of quality control. This
paper presents general guidelines for the fabrication and construc-
tion of the TPCCRW system that can be used by contractors and
precast producers.

Fabrication Process of the Proposed System


Fig. 2. Fabrication of the base slab
The fabrication process of the TPCCRW system is divided into two
parts:
1. The fabrication of the base component, which is a base slab
with shear pockets.
2. The fabrication of the wall component, which comprises the
face panel and the counterforts.

Fabrication of the Base Slab


The base slab must be designed to satisfy stability requirements and
to resist the applied vertical loads resulting from soil weight and
surcharge loads that generate the soil pressure below the base foot-
ing as per the requirements of the AASHTO (2012) LRFD specifi-
cations. The location of each headed anchor in the counterforts and
the corresponding shear pocket is identified based on the structural
design. Shear pockets are created in the form of tapered cylinders
with a slope of 41.6 mm/m (0.5 in./ft) with a top diameter of Fig. 3. Casting of the base slab
127 mm (5 in.). The top diameter of the shear pocket is designed to
ease the alignment of the headed anchor as it is lowered into the
pocket, therefore facilitating the erection process. The shear pockets The shear pockets are created by using tapered concrete cylin-
are generally placed at approximately 30.5-cm (1-ft) spacing. The ders that form the desired shape and are removed after hardening of
fabrication processes for the base slab are shown in Figs. 2 and 3. the concrete, as shown in Fig. 4. The cylinders are wrapped with a

© ASCE 04016026-2 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1


Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 4. Base slab with tapered concrete cylinders used to create shear pockets: (a) base slab with cylinders used to create openings; (b) tapered
cylinders

Fig. 5. Grouting through duct opening to ensure uniform pressure distribution below base slab: (a) shear pockets created in the base slab; (b) grouting
below base slab for uniform load distribution

debonding agent to enable separation from the base slab when the the with L-bars extending vertically upward. The L-shaped bars
concrete hardens. In addition, duct openings can be created in serve as the transverse shear reinforcement for the counterforts.
separate locations in the base slab to allow grouting below the They are also used to maintain full composite action between the
slab at the construction stage to ensure uniform contact between counterfort and the face panel. The L-bars must be extended from
the base slab and the supporting soil, as shown in Fig. 5. When the face panel during the casting of the face panel, as shown in Figs.
the shear pockets are created, they must be sandblasted or water- 6 and 7.
jet blasted to remove any grease that remains from the debonding In the proposed system, the spacing between the counterforts is
agents. Special handles are inserted before casting to facilitate the optimized to equalize the bending stresses in the face panel at mid-
handling and lifting processes. span between the counterforts and above the counterforts. This con-
figuration provides a reduction in the thickness of the face panel to
15.25 cm (6 in.) compared with typical cast-in-place panels that can
Fabrication of the Wall Component
reach up to 457 mm (18 in.) and allows for the provision of only one
The fabrication of the wall component starts with the face panel. layer of steel in the middle of the section. The single steel layer is
The face panel is formed on the ground, and one steel layer is placed designed to resist both positive and negative bending stresses.

© ASCE 04016026-3 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1


Fig. 9. Reinforcement of the counterforts
Fig. 6. Fabrication of the face panel with extended L-bars
Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 10. Headed anchors extended from the bottom of the counterforts
Fig. 7. Casting the face panel

Fig. 8. Creating an opening at two-thirds the height of the wall for han- Fig. 11. Site preparation and soil compaction below the base slab
dling purposes

The main reinforcement of the counterforts is provided by


inclined steel bars along the height of the counterfort. Temperature
and shrinkage reinforcement is provided by vertical steel bars inside
the web of the counterfort. However, additional investigation using
finite-element analysis (Farhat et al. 2015) revealed that the spacing
of the vertical bars based on temperature and shrinkage require-
ments can be insufficient. As the system is loaded, the anchors are
loaded in tension, and cracks tend to generate at the anchor location.
With the increment of the load, the cracks tend to propagate toward
the web of the counterforts. As a result, the vertical steel bars in the
counterfort are used as an arrest mechanism for the crack propaga-
tion. Thus, the spacing between these bars should be reduced to Fig. 12. Site preparation and leveling before placing the base slab
15.25 cm (6 in.). The headed anchors are placed and extended from

© ASCE 04016026-4 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1


the bottom of the counterforts before casting. An opening is made
in each exterior counterfort at around two-thirds of the height of the
counterfort for erection and handling purposes, as shown in Fig. 8.
The reinforcement in the counterforts is shown in Figs. 9 and 10. It
can be seen that the L-bars that extend from the face panel serve as
the transverse shear reinforcement for the counterforts. It can also
be seen that the anchors are extended from the bottom of the
counterforts.

Construction Procedure
Fig. 13. Base slab during handling and erection The construction process is divided into the following four stages:
Stage 1: Site-preparation procedures. The construction site is
Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

prepared by performing the necessary excavation and leveling pro-


cedures. The soil below the base slab is compacted and leveled so
that the slab will be placed in horizontal position. Site-preparation
procedures are shown in Fig. 11.
Stage 2: Placement of the base slab. After fabrication and cur-
ing of the base slab are complete, the base slab is transported to the
prepared construction site. The slab is lifted by a crane using steel
cables at four points and placed at the final location. The base slab is
grouted and vibrated to ensure uniform contact with the soil
beneath. Foam sealants are used around the perimeter of the slab to
prevent grout leakage. The grout poured beneath the base slab is
used to transfer the load to the soil beneath. Any type of available
grout can be used. The placement, leveling, and grouting of the base
slab are shown in Figs. 12–14.
Fig. 14. Grouting and vibrating the base slab after placement Stage 3: Erection of the face panel and counterforts. The wall
is transported to the construction site. It is lifted with a crane using

Fig. 15. Retaining wall transportation, erection, leveling, and assembly: (a) transportation of wall face and counterforts; (b) lifting the wall compo-
nent; (c) erecting the wall component; (d) leveling the wall component over the base slab

© ASCE 04016026-5 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1


Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 16. Grouting the shear pockets after wall erection and beginning of soil backfilling: (a) grouting the shear pockets; (b) 2.5-cm (1-in.) gap for
grout flow; (c) grouting the gaps between the wall and the slab; (d) soil backfilling and compaction

Fig. 17. Final assembly of the proposed system: (a) front view of the final wall assembly; (b) rear view of the final wall assembly

© ASCE 04016026-6 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1


Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 18. General application of TPCCRW

Fig. 19. Summary of the construction sequence for the proposed wall

© ASCE 04016026-7 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1


steel cables connected to steel rods inserted in openings provided on References
the counterforts. The steel cables are used instead of fiber straps to
prevent accidental tearing of the straps when exposed to the sharp AASHTO. (2012). AASHTO LRFD bridge design specifications, Washington,
concrete edges. The wall is then positioned on the base slab such DC.
that the anchors are aligned with the shear pockets. The geometry of Billington, S. L., Barnes, R. W., and Breen, J. E. (1999). “A precast segmen-
the wall and the presence of the counterforts allow for erection of tal substructure system for standard bridges.” PCI J., 44(4), 56–73.
Billington, S. L., Barnes, R. W., and Breen, J. E. (2001). “Alternate sub-
the wall without the need for temporary bracing.
structure systems for standard highway bridges.” J. Bridge Eng., 10
The main advantage of the erection processes for the wall and
.1061/(ASCE)1084-0702(2001)6:2(87), 87–94.
the base slab is that a smaller number of skilled laborers and less Darwish, I., Kasi, M., and Alfred Benesch & Co. (2013). “Innovative pre-
equipment are required compared with conventional construction cast concrete cantilever retaining wall system.” ASPIRE, Spring, 21.
methods. The erection process of the wall is shown in Fig. 15. Farhat, M., Issa, M., and Rahman, M. (2015). “Design optimization and
Stage 4: Grouting the shear pockets. The shear pockets are modeling of totally precast concrete counterfort retaining wall system.”
grouted to maintain full composite action between the counterforts Proc., 16th European Bridge Conf., ECS Publications, Edinburgh,
and the base slab through the headed anchors. After the wall has been Scotland.
Farhat, M., Rahman, M., Ibrahim, M., and Issa, M. (2014). “Design, fabrica-
Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.

erected, a 2.5-cm (1-in.) gap is kept between the base slab and the
counterfort to allow the flow of the grout into the shear pockets, as tion, modeling and experimental study of a totally precast concrete
shown in Fig. 16. The gap must also be grouted and sealed. Fast- counterfort retaining wall system for highways.” Proc., 2014 PCI
setting (15 min to set) high-performance (DOT-certified) grout should Convention and National Bridge Conf., Precast/Prestressed Concrete
Institute, Chicago.
be used to fill the shear pockets. The fast-setting grout provides quick
Goldberg, D. (1987). “Precast prestressed concrete bridge deck panels.”
initial stability and strength to the system so that the soil backfilling PCI J., 32(2), 26–45.
process can be started in a short time after erection. This process pro- Hieber, D., Wacker, J. M., Eberhard, M. O., and Stanton, J. F. (2005).
vides the advantage of fast-track construction; the estimated construc- “State-of-the-art report on precast concrete systems for rapid construc-
tion time for one unit is around 2 hours. The final assembly of the tion of bridges.” Rep. No. WA-RD 594.1, Washington DOT, Olympia,
retaining wall system is shown in Fig. 17. A general sketch showing WA.
the application of the proposed system is presented in Fig. 18. Issa, M. A., Idriss, A., Kaspar, I. I., and Khayyat, S. Y. (1995a). “Full depth
Because the site-preparation procedures are minimized, it is possi- precast and precast, prestressed concrete bridge deck panels.” PCI J.,
ble to maintain traffic flow during the construction process. The con- 40(1), 59–80.
struction sequence for the proposed wall is summarized in Fig. 19. Issa, M. A., Yousif, A. A., and Issa, M. A. (1995b) “Construction proce-
dures for rapid replacement of bridge decks.” Concr. Int., 17(2), 49–52.
Issa, M. A., Yousif, A. A., and Issa, M. A. (2000). “Experimental behavior
Conclusion of full-depth precast concrete panels for bridge rehabilitation.” ACI
Struct. J., 97(3), 397–407.
Issa, M. A., Yousif, A. A., Issa, M. A., Kaspar, I. I., and Khayyat, S. Y.
This paper provides a description of the construction procedures
(1995c). “Field performance of full depth precast concrete panels in
and practices involved in the TPCCRW system developed at the bridge deck reconstruction.” PCI J., 40(3), 82–108.
University of Illinois at Chicago. The main advantages of the pro- Issa, M. A., Yousif, A. A., Issa, M. A., Kaspar, I. I., and Khayyat, S. Y.
posed system are (1) enhanced durability compared with its cast-in- (1998). “Analysis of full depth concrete bridge deck panels.” PCI J.,
place counterpart, (2) reduced traffic interruption, and (3) fast-track 43(1), 74–85.
construction. The TPCCRW system enables offsite prefabrication PCI-NER (Precast/Prestressed Concrete Institute, New England Region
of all of the components, which are then transported to the site for Technical Committee). (2001). “Precast deck panel guidelines.”
immediate construction. The guidelines for offsite fabrication and Rep. No. PCINER-01-PDPG, Precast/Prestressed Concrete Institute,
the construction processes of the proposed retaining wall system are Chicago, 13.
presented in this paper. A crane is needed in the second and third PCI-NER (Precast/Prestressed Concrete Institute, New England Region
stages of the erection process. However, use of a crane is optional in Technical Committee). (2002). “Full depth precast concrete deck slabs.”
Rep. No. PCINER-02-FDPCDS, Precast/Prestressed Concrete Institute,
the fourth stage, depending on the wind exposure and the safety
Chicago, 18.
measures adopted by the contractor. Each phase of the erection pro- Stamnas, P. E., and Whittemore, M. D. (2005). “All-precast substructure
cess must be followed by leveling and alignment work before plac- accelerates construction of prestressed concrete bridge in New
ing the grout. The estimated construction period of the system is Hampshire.” PCI J., 50(3), 26–39.
approximately 2 h if fast-setting grout is used. The guidelines pre- Tadros, M. K., and Baishya, M. C. (1998). “Rapid replacement of bridge
sented in this paper will help accelerate the learning process for con- decks.” NCHRP Rep. 407, National Cooperative Highway Research
tractors, resulting in time savings during construction. Program, Washington, DC, 51.

© ASCE 04016026-8 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2017, 22(2): -1--1

You might also like