Professional Documents
Culture Documents
Abstract: In this paper, a totally precast concrete counterfort retaining wall system is proposed for highway and bridge applications. This sys-
tem provides several advantages over conventional methods, such as reduced construction time, cost, and environmental impacts. The system
is composed of a precast counterfort wall that is connected to a base slab through headed anchors. The components are cast offsite and trans-
Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.
ported to the construction site for final assembly. The proposed system requires a unique method of construction. Accordingly, this paper
details the fabrication and construction procedures required for the proposed system to accelerate the on-site erection process. In the use of this
system, the general guidelines for the fabrication and construction of the totally precast counterfort retaining wall system are presented to the
contractors. The system’s components can be fully assembled and set in place in approximately 2 hours. DOI: 10.1061/(ASCE)SC.1943-
5576.0000316. © 2016 American Society of Civil Engineers.
Fig. 4. Base slab with tapered concrete cylinders used to create shear pockets: (a) base slab with cylinders used to create openings; (b) tapered
cylinders
Fig. 5. Grouting through duct opening to ensure uniform pressure distribution below base slab: (a) shear pockets created in the base slab; (b) grouting
below base slab for uniform load distribution
debonding agent to enable separation from the base slab when the the with L-bars extending vertically upward. The L-shaped bars
concrete hardens. In addition, duct openings can be created in serve as the transverse shear reinforcement for the counterforts.
separate locations in the base slab to allow grouting below the They are also used to maintain full composite action between the
slab at the construction stage to ensure uniform contact between counterfort and the face panel. The L-bars must be extended from
the base slab and the supporting soil, as shown in Fig. 5. When the face panel during the casting of the face panel, as shown in Figs.
the shear pockets are created, they must be sandblasted or water- 6 and 7.
jet blasted to remove any grease that remains from the debonding In the proposed system, the spacing between the counterforts is
agents. Special handles are inserted before casting to facilitate the optimized to equalize the bending stresses in the face panel at mid-
handling and lifting processes. span between the counterforts and above the counterforts. This con-
figuration provides a reduction in the thickness of the face panel to
15.25 cm (6 in.) compared with typical cast-in-place panels that can
Fabrication of the Wall Component
reach up to 457 mm (18 in.) and allows for the provision of only one
The fabrication of the wall component starts with the face panel. layer of steel in the middle of the section. The single steel layer is
The face panel is formed on the ground, and one steel layer is placed designed to resist both positive and negative bending stresses.
Fig. 10. Headed anchors extended from the bottom of the counterforts
Fig. 7. Casting the face panel
Fig. 8. Creating an opening at two-thirds the height of the wall for han- Fig. 11. Site preparation and soil compaction below the base slab
dling purposes
Construction Procedure
Fig. 13. Base slab during handling and erection The construction process is divided into the following four stages:
Stage 1: Site-preparation procedures. The construction site is
Downloaded from ascelibrary.org by Khemindra Narain on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.
Fig. 15. Retaining wall transportation, erection, leveling, and assembly: (a) transportation of wall face and counterforts; (b) lifting the wall compo-
nent; (c) erecting the wall component; (d) leveling the wall component over the base slab
Fig. 16. Grouting the shear pockets after wall erection and beginning of soil backfilling: (a) grouting the shear pockets; (b) 2.5-cm (1-in.) gap for
grout flow; (c) grouting the gaps between the wall and the slab; (d) soil backfilling and compaction
Fig. 17. Final assembly of the proposed system: (a) front view of the final wall assembly; (b) rear view of the final wall assembly
Fig. 19. Summary of the construction sequence for the proposed wall
erected, a 2.5-cm (1-in.) gap is kept between the base slab and the
counterfort to allow the flow of the grout into the shear pockets, as tion, modeling and experimental study of a totally precast concrete
shown in Fig. 16. The gap must also be grouted and sealed. Fast- counterfort retaining wall system for highways.” Proc., 2014 PCI
setting (15 min to set) high-performance (DOT-certified) grout should Convention and National Bridge Conf., Precast/Prestressed Concrete
Institute, Chicago.
be used to fill the shear pockets. The fast-setting grout provides quick
Goldberg, D. (1987). “Precast prestressed concrete bridge deck panels.”
initial stability and strength to the system so that the soil backfilling PCI J., 32(2), 26–45.
process can be started in a short time after erection. This process pro- Hieber, D., Wacker, J. M., Eberhard, M. O., and Stanton, J. F. (2005).
vides the advantage of fast-track construction; the estimated construc- “State-of-the-art report on precast concrete systems for rapid construc-
tion time for one unit is around 2 hours. The final assembly of the tion of bridges.” Rep. No. WA-RD 594.1, Washington DOT, Olympia,
retaining wall system is shown in Fig. 17. A general sketch showing WA.
the application of the proposed system is presented in Fig. 18. Issa, M. A., Idriss, A., Kaspar, I. I., and Khayyat, S. Y. (1995a). “Full depth
Because the site-preparation procedures are minimized, it is possi- precast and precast, prestressed concrete bridge deck panels.” PCI J.,
ble to maintain traffic flow during the construction process. The con- 40(1), 59–80.
struction sequence for the proposed wall is summarized in Fig. 19. Issa, M. A., Yousif, A. A., and Issa, M. A. (1995b) “Construction proce-
dures for rapid replacement of bridge decks.” Concr. Int., 17(2), 49–52.
Issa, M. A., Yousif, A. A., and Issa, M. A. (2000). “Experimental behavior
Conclusion of full-depth precast concrete panels for bridge rehabilitation.” ACI
Struct. J., 97(3), 397–407.
Issa, M. A., Yousif, A. A., Issa, M. A., Kaspar, I. I., and Khayyat, S. Y.
This paper provides a description of the construction procedures
(1995c). “Field performance of full depth precast concrete panels in
and practices involved in the TPCCRW system developed at the bridge deck reconstruction.” PCI J., 40(3), 82–108.
University of Illinois at Chicago. The main advantages of the pro- Issa, M. A., Yousif, A. A., Issa, M. A., Kaspar, I. I., and Khayyat, S. Y.
posed system are (1) enhanced durability compared with its cast-in- (1998). “Analysis of full depth concrete bridge deck panels.” PCI J.,
place counterpart, (2) reduced traffic interruption, and (3) fast-track 43(1), 74–85.
construction. The TPCCRW system enables offsite prefabrication PCI-NER (Precast/Prestressed Concrete Institute, New England Region
of all of the components, which are then transported to the site for Technical Committee). (2001). “Precast deck panel guidelines.”
immediate construction. The guidelines for offsite fabrication and Rep. No. PCINER-01-PDPG, Precast/Prestressed Concrete Institute,
the construction processes of the proposed retaining wall system are Chicago, 13.
presented in this paper. A crane is needed in the second and third PCI-NER (Precast/Prestressed Concrete Institute, New England Region
stages of the erection process. However, use of a crane is optional in Technical Committee). (2002). “Full depth precast concrete deck slabs.”
Rep. No. PCINER-02-FDPCDS, Precast/Prestressed Concrete Institute,
the fourth stage, depending on the wind exposure and the safety
Chicago, 18.
measures adopted by the contractor. Each phase of the erection pro- Stamnas, P. E., and Whittemore, M. D. (2005). “All-precast substructure
cess must be followed by leveling and alignment work before plac- accelerates construction of prestressed concrete bridge in New
ing the grout. The estimated construction period of the system is Hampshire.” PCI J., 50(3), 26–39.
approximately 2 h if fast-setting grout is used. The guidelines pre- Tadros, M. K., and Baishya, M. C. (1998). “Rapid replacement of bridge
sented in this paper will help accelerate the learning process for con- decks.” NCHRP Rep. 407, National Cooperative Highway Research
tractors, resulting in time savings during construction. Program, Washington, DC, 51.