Professional Documents
Culture Documents
Abstract: Accelerated bridge construction (ABC) is gaining popularity because it offers a number of advantages over conventional methods
of construction. Prefabrication of bridge components for rapid on-site assembly is a highly effective ABC approach. Bridge substructures are
traditionally cast in place with columns that form plastic hinges during earthquake events. Recent studies have explored new precast column-
Downloaded from ascelibrary.org by Ayman Shama on 10/03/18. Copyright ASCE. For personal use only; all rights reserved.
footing connections that either emulate the seismic performance of monolithic construction (emulative) or show improved seismic perform-
ance with the use of rocking connections (nonemulative). This paper presents findings from half-scale experimental testing of one emulative
and two nonemulative precast column-footing connections. The two nonemulative connections were designed and detailed to sustain limited
damage that can be rapidly and cost-effectively repaired using predefined methodologies. The tested connections showed promising results for
use in regions of moderate to high seismicity; however, further developments of the proposed construction and repair methodologies are
required for their full potential to be realized. DOI: 10.1061/(ASCE)BE.1943-5592.0000872. © 2016 American Society of Civil Engineers.
Author keywords: Precast; Concrete; Column; Footing; Nonemulative; Posttensioned.
1
Bridge Engineer, Opus International Consultants, 100 Beaumont St., Categories of Precast Column-Footing Connections
Auckland 1010, New Zealand (corresponding author). E-mail: sam
.white@opus.co.nz Columns with emulative precast connections behave in a similar
2
Associate Professor, Dept. of Civil and Natural Resources manner as traditional monolithic CIP columns that are designed to
Engineering, College of Engineering, Univ. of Canterbury, 20 Kirkwood form plastic hinges in seismic events, undergoing inelastic flexural
Ave., Upper Riccarton, Christchurch 8041, New Zealand. E-mail:
deformation to dissipate seismic energy.
alessandro.palermo@canterbury.ac.nz
Note. This manuscript was submitted on March 2, 2015; approved on
Numerous emulative connections that are potentially suitable
October 5, 2015; published online on February 3, 2016. Discussion period for column-footing connections were summarized by Marsh et al.
open until July 3, 2016; separate discussions must be submitted for indi- (2011). These include grouted (Brenes et al. 2006; Steuck et al.
vidual papers. This paper is part of the Journal of Bridge Engineering, © 2007), socket (Haraldsson et al. 2013; Osanai et al. 1996), and
ASCE, ISSN 1084-0702. coupled connections (Ameli et al. 2013; Haber et al. 2014).
connections were repaired following initial testing and retested (2013). Socket connections have also been used in actual construc-
(SC-N* and CC-N*). Each test model had a section depth of tion (Khaleghi et al. 2012).
Unbonded post-tensioned
in mm post-tensioned bar
bar
2700
Armoring Couplers
Dissipating Non-yielding
Socket longitudinal reinforcement
connection reinforcement -
500
2100
(a) (b) (c) (d)
Fig. 3. Summary of test models: (a) test model dimensions; (b) emulative socket connection (SC-E); (c) nonemulative socket connection (SC-N); (d)
nonemulative coupled connection (CC-N)
Threaded 290 20
anchorage
100
110
All dims. 80
in mm
Fig. 4. SC-N proposed and experimental repair methodologies: (a) proposed repair methodology; (b) experimental repair methodology; (c) mounting
collar
A 40-mm-diameter unbonded posttensioned bar was used in the which was expected to have increased the overall moment capacity
test model to apply an axial load of constant magnitude to the column, of the nonemulative connections by up to 6%.
simulating gravity load in the structure. Theposttensioned bar wasnot This connection is similar to nonemulative socket connections
intendedforuseinactualapplicationsofthisconnection. that are currently being investigated at the University of
In the emulative test (SC-E), the load on the posttensioned bar was Washington (Davis et al. 2012; Finnsson 2013; Schaefer 2013).
continually monitored using a load cell, and the hydraulic pressure These projects investigate a number of methods for reducing con-
was manually regulated to maintain a constant axial load of 450 kN. nection damage and maximizing recentering capabilities, with
promising results, but don’t directly address methods and effective-
ness of repair, which is a focus of the present research.
Nonemulative Socket Connection (SC-N) The test specimen was reused from a previous test, in which it
was tested to a 2% drift ratio with no supplementary connection
SC-N featured a nonemulative posttensioned variant of the socket confinement. Moderate spalling occurred in the column. Damaged
connection to improve seismic performance (Fig. 3). A natural concrete was removed and the column was repaired using structural
rocking interface occurred as a result of the formation of a single repair mortar. The column was then wrapped with fiber-reinforced
wide crack at the base of the column. The formation of a single polymer (FRP) fabric over a height of 600 mm to target a confined
crack was encouraged by the addition of connection confinement at concrete compressive strength of 1.3 times the unconfined compres-
the base of the column, which terminated above the rocking inter- sive strength. Although yielding of the longitudinal bars occurred, it
face and the debonding of the longitudinal bars at the rocking inter- was assumed that the residual strength and ductility of the bars had
face over a length of 50 mm in the half-scale test column. Regular not been significantly altered, and thus the damage was considered
reinforcement was used for energy dissipation, with no reduction in to have no significant influence on the results of subsequent tests.
bar diameter at the rocking interface, and thus strain penetration The FRP wrap provided connection confinement to the test
was expected to occur. This means that inelastic deformation was model. Alternative methods of connection confinement include
not limited to just the debonded length, but extended for some dis- FRP tube (ElGawady et al. 2010; Nelson et al. 2008) or steel pipe
tance on either side of the debonded region. The columns were (Restrepo et al. 2011).
designed with a recentering ratio of 1.6 for the SC-N test column The proposed repair methodology for this connection is illustrated
and 1.3 for the repaired SC-N* connection. in Fig. 4. A saw cut was made at the base of the column to intention-
In an actual structure using posttensioned nonemulative connec- ally sever the existing damaged reinforcement. The saw cut was filled
tions, axial load resulting from both posttensioning forces and gravity with grout or epoxy to reinstate a bearing pad for transfer of axial force
load would provide recentering capabilities to the connection. The and to prevent corrosion. A steel collar and external dissipaters were
gravity load would remain approximately constant, whereas the post- then mounted to the connection using preinstalled threaded inserts.
tensioning load would increase with column displacement as a result The anchorages, footing, and column were all designed as capacity
of elongation of the posttensioned bar or tendon. Testing limitations protected members with strength that exceeded the overstrength
meant that the constant and increasing axial loads could not be sepa- capacity of the connection. It should be noted that further research
rated, and thus a posttensioned bar of 50 mm was used to represent into the use of threaded inserts, particularly in damaged concrete, is
both the gravity and posttensioning loads in the nonemulative connec- required before this system can be considered for implementation in
tions. The load in the bar was not regulated during testing and the field (ACI 2014).
increased with column displacement. Because of space constraints during casting of the half-scale col-
The initial posttensioning force in the bar was such that at the umn and reuse of the footing from a previous test, the intended repair
method of dissipater anchorage into preinstalled threaded inserts was
design drift, the posttensioning load would approximately equal the
not used for the repair of SC-N. Chemically anchored bars were used
expected sum of the posttensioning and gravity loads, had the loads
instead (Figs. 4 and 5).
been separated. The limitation of this approach is that the axial load
in the test model is underrepresented at drifts smaller than the
Nonemulative Coupled Connection (CC-N)
design drift and overrepresented at drifts larger than the design drift.
The difference between observed and expected axial load was esti- CC-N used replaceable dissipating reinforcing bar segments (dis-
mated to be up to 11% at the maximum column displacement, sipaters) with mechanical couplers to form a connection between
80 150 80
(b)
Overlap of grooved and
threaded regions 24mm equivalent
24 diameter
Fig. 5. Energy dissipaters for SC-N*, CC-N, and CC-N*: (a) grooved dissipater for SC-N*; (b) turned dissipater for CC-N; (c) grooved dissipater for CC-N*
Downloaded from ascelibrary.org by Ayman Shama on 10/03/18. Copyright ASCE. For personal use only; all rights reserved.
Column placed
Upper couplers and aligned with Couplers attached Stirrups
wound back onto couplers to upper studs spaced
dissipater
CIP grout
cast
Stirrups Grout bed poured
Post-tensioning
Lower couplers bar connected
attached to anchorage
to footing Bar tensioned
Damage Damaged
limited to CIP Couplers
grout and wound back onto dissipaters
dissipaters Stirrups and dissipaters removed
CIP grout
removed or or
No damage to any
other conection Damaged Couplers
components dissipaters cut and ends of
dissipaters
removed
(a) (b) (c) (d)
column and footing (Figs. 3, 5, and 6). The dissipaters were enclosed residual drifts in the connection were expected to be smaller than
in CIP grout that was cast during column assembly. The connection those of an emulative connection, such as SC-E.
was designed to behave in a rocking manner during a seismic event, The connection featured a recess in which the eight replaceable
with damage limited to yielding of the dissipaters and spalling of the dissipaters were positioned around a precast core. The precast core
CIP grout. All other connection components were designed to remain was designed to resist the full axial and shear actions in the connec-
essentially elastic. The dissipaters and CIP grout are intended to be tion. The dissipaters were connected with parallel threaded couplers
removed and replaced following a seismic event to provide a rapid to studs extending from the precast column and footing. Stirrups pro-
and cost-effective method of repair. vided confinement to the CIP grout and buckling restraint to the
Similar connection types have been investigated by Haber et al. dissipaters.
(2014), who examined the use of mechanical splices in an emulative The couplers used in the test model produced a full-strength con-
column-footing connection, and Tazarv (2014), who investigated nection that exceeded the breaking strength of the Grade 500 rein-
the use of advanced shape memory alloys to form a nonemulative forcing bar. The ends of the bars to be joined were cut square and
recentering connection without the requirement for posttensioning. enlarged by cold forging to increase their core diameter and thus
In the present research, a nonemulative coupled connection using ensure that the joint was stronger than the bar.
conventional materials was targeted, which would allow for cost- The dissipaters used in the test model are shown in Fig. 5. The dis-
effective construction and repair. sipaters used for initial assembly of the test model were fabricated
A 50-mm-diameter unbonded posttensioned bar provided some from Grade 300 steel and had a diameter of 24 mm, which was
recentering capabilities to the connection; however, the connection increased to 30 mm for connection to the couplers. The strength of
had a recentering ratio of only 0.8, meaning full recentering was not the couplers allowed for reinforcing bar stresses exceeding 650 MPa.
expected to occur. Although full recentering was not expected, Under overstrength design actions of the Grade 300 dissipaters using
the construction methodology outlined in Fig. 6. To repair the con- Columns SC-N and CC-N were each tested to 3.25% biaxial drift
nection, the CIP material and stirrups were removed, allowing for and then repaired and retested (SC-N*, CC-N*).
removal and replacement of the damaged dissipaters using the
threaded couplers. Replacement stirrups were welded around the Testing Procedures
dissipaters, and CIP grout was cast to complete the repair process.
Because the stirrups were not subjected to significant inelastic de- Displacement-controlled hydraulic actuators were used to apply a
formation, welding was deemed to be an appropriate solution for biaxial lateral load to the columns in the north-south (N-S) and east-
repair of the connection. Single lap welds of 100-mm length and 4- west (E-W) directions at a height of 2.5 m above the footings (Figs.
mm throat thickness were used. The bars being welded were micro- 8 and 9). Fig. 10 illustrates the lateral loading sequence for each
alloyed and were identified by the manufacturer as being suitable drift cycle and the relationship between uniaxial and biaxial drift. In
for welding. Alternative methods of bar splicing, such as bar cou- general, the peak biaxial drift input for a given load cycle was 1.3
plers, could be used to connect the replacement stirrups if site weld- times the peak uniaxial drift input.
ing is not a desired repair solution. An axial hydraulic actuator was used to apply posttensioning
Because the precast core of the column is protected from damage force. The unbonded posttensioning bar was located in a polyvinyl
and designed to carry the full axial load in the column, vertical load- chloride (PVC) duct that ran through the full length of the column
carrying capacity would be maintained following an earthquake and footing. The bar was anchored at both ends using steel plates,
event, and the connection could be repaired without removal of washers, and nuts.
posttensioning load or raising of the column. Instrumentation on the columns included string potentiometers
to measure column displacement in the N-S and E-W directions,
load cells to measure lateral and vertical actuator loads, and an array
Connection Design of rod end potentiometers located on the north and east faces of the
column to measure column deformation (Figs. 8 and 9).
The design parameters of each half-scale test model are summarized Measured material properties for each test column are presented
in Table 1. The emulative connection (SC-E) was designed using a in Table 2.
Axial
Lateral Lateral load cell
actuator load cell Axial
actuator
String potentiometer
Reaction frame
Precast East-West
column (EW) actuator
Array of rod-end
potentiometers
North-South
N (NS) actuator
Precast
footing
Anchor
Post-tensioned
bolts
bar
(a) (b)
0.50 0.65
Bia Concrete—column 45 55 50
0.75 0.98
2 1 Grout—for construction 44 41 55a
W E 1.00 1.30
Grout—for repair N/A 55a (before test) 39
1.50 1.95 Steel tensile strength—yield/ultimate (MPa)
2.00 2.60 Column—longitudinal 516/650 350/530 520a/650a
2.50 3.25 Column—transverse 556/690 680/790 680/790
6 7 3.00 3.90 Dissipaters N/A 360/540 380/520
4 4.00 5.20 Footing 516/650 520/650 520/650
S 5.00 6.50 Posttensioned bar 835a/1,030a 835a/1,030a 835a/1,030a
East-West drift 6.00 7.80 Glass-fiber-reinforced polymer (FRP) wrap
Tensile strength (MPa) N/A 2,300a N/A
Fig. 10. Biaxial drift cycles Tensile modulus (GPa) N/A 76a N/A
Elongation at break (%) N/A 2.8a N/A
a
Column Assembly Reliable measurement was not achieved—expected value provided
instead.
SC-E and SC-N shared a similar assembly methodology, as shown
in Fig. 11. Assembly involved lifting the column into the socket and
The posttensioning bar was stressed just before commencement
propping. Once the column was aligned, grout was manually
of testing in all cases.
poured into the gap between the footing and column and agitated
with a thin rod to ensure that grout completely filled the gap. SC-N
was confined with FRP wrap following a prior column test, as previ- Initial Testing
ously discussed. Fig. 13 shows damage to each test model following biaxial testing.
The assembly of test column CC-N is shown in Fig. 12. Cracking initiated at the base of the column during the 0.2–0.35%
Grease tape was used to avoid bonding of the dissipaters with drift cycles in all tests. Distributed fine cracks formed along the col-
the surrounding concrete. After placement of the column and umn at larger levels of drift. All cracks above the joint region closed
connection of the couplers, high-flow grout was poured into the to hairline thickness upon unloading of the column.
shallow socket between the column and footing. The column Column SC-E was tested to failure and reached a biaxial drift of
was intended to remain unbonded from this grout layer to per- 7.8% (displacement ductility ratio, m = 7.8). Minor spalling
mit rocking behavior. It was discovered upon disassembly that occurred during the 3.25% biaxial drift cycle, with spalling becom-
bonding of the two elements had occurred, which altered the ing more severe in the 3.90% drift cycle. Bar fracture occurred dur-
behavior of the column and caused it to behave in a more emu- ing biaxial loading to 7.8% drift. Significant spalling was observed,
lative manner with flexure of the precast core. Bonding could extending to a height of 500 mm. Bar buckling occurred, although it
be avoided by placing a polythene sheet in the base of the shal- was difficult to confirm the level of drift at which buckling initiated.
low socket before grouting, or through the use of a match cast Column SC-N was tested to a biaxial drift of 3.25% (m = 3.6). A
joint that requires no grouting. very low level of damage was observed, with some horizontal
Fig. 11. SC-E and SC-N assembly: (a) precast column; (b) precast footing; (c) column lifted into place; (d) column in socket; (e) grout poured; (f)
connection after FRP wrap (SC-N only)
Fig. 12. CC-N assembly: (a) couplers on footing studs; (b) dissipaters attached; (c) column placed; (d) couplers attached; (e) stirrups spaced; (f) form-
work assembled; (g) grout gravity fed; (h) formwork removed; (i) construction complete
cracking of the FRP wrap that initiated during the 0.98% biaxial drift misalignment. The difficulty was overcome by swapping the loca-
cycle. The cracking was parallel to the fiber orientation of the wrap, tion of dissipaters and did not prevent the repair strategy from being
and thus no reduction in column confinement was expected to have applied, although it did slow the repair process. These difficulties
occurred. could be avoided by using an alternate bar coupling system that
The CC-N column was also tested to a biaxial drift of 3.25% (m = allows for a higher degree of rotational tolerance. An example is the
3.6). Spalling of the CIP region of the column initiated during the upset headed coupler with threaded sleeve, as tested by Haber et al.
2.6% biaxial drift cycle. Spalling extended to a height of 100 mm by (2014) and Tazarv (2014).
the end of testing. No spalling occurred outside of the CIP region. In both repairs, longitudinally grooved dissipaters were used as
an alternative to bars that were turned down to a smaller diameter
over the yielding region (Fig. 5). The longitudinally grooved dis-
Repair sipaters used in this research had a radius of gyration that was 40%
higher than that of the round dissipaters, with a circular cross sec-
Postdrilling and chemical anchorage of the dissipaters was used for tion of equal cross-sectional area, which decreased the dissipaters’
repair of SC-N (Figs. 4 and 14). Repair of CC-N involved removal susceptibility to buckling. In the repair of the SC-N connection, an
of the CIP grout material and stirrups, allowing access for replace- unbonded steel sleeve provided buckling restraint to the externally
ment of the dissipaters (Fig. 15). Minor buckling of the dissipaters mounted grooved dissipaters. The sleeve was fabricated from
had occurred, and thus the bars were cut for removal. There was no Grade 300 bar and had a wall thickness of 8 mm. The grooved dis-
apparent damage to the couplers or threads, which allowed the cou- sipaters maintained a constant outside diameter along their length
plers to be removed and reused. There was some difficulty with in- that enabled continual contact with the buckling restraint sleeve.
stallation of the replacement dissipaters because of thread This avoided the need for epoxy or grout to close the gap between
Fig. 13. Damage to test models: (a) SC-E; (b) SC-N; (c) SC-N*; (d) CC-N; (e) CC-N*
Fig. 14. SC-N repair: (a) internal reinforcing bars cut; (b) holes drilled for dissipaters; (c) mounting collar and dissipaters installed
the bar and sleeve, as is required in similar dissipater designs sliding of the mounting collar at drifts exceeding 1.5%, and pullout
(Marriott 2009; Sarti et al. 2013). In the repair of the CC-N column, of the dissipaters at drifts exceeding 2.5%.
no sleeve was used and welded stirrups provided buckling restraint. The repaired CC-N* column was tested to biaxial drifts of 3.9%
Preliminary testing of the grooved dissipaters was carried out prior (m = 4.3). Damage in the repaired column was similar to that of the
to column testing. The dissipaters were subjected to cyclic loading initial test. Spalling initiated during the 2.5% drift cycle. The testing
at increasing magnitudes of strain. Each load cycle involved exten- ended after premature failure of a dissipater. The cause of this fail-
sion of the dissipater to a certain strain limit before compressing the ure was overlap of the grooved and threaded regions of the bar, as
dissipater back to its original length. The dissipater yielded in com- shown in Fig. 5, which should be avoided in fabrication of the
pression as it returned to its original length, but was not compressed grooved dissipaters. The failure strain of the grooved dissipater was
further than its original length. Three load cycles were applied at not measured directly, but was estimated from the column drift and
each strain limit. Very good results were observed showing stable observed gap opening to be less than 6%. This was significantly
hysteresis loops and good ductility, with the dissipater reliably com- smaller than the cyclic strain of 9% achieved in preliminary testing
pleting three cycles at 9% strain (Fig. 16). of the grooved dissipater, indicating that column performance
would likely be improved with correct dissipater detailing.
Postrepair Testing No failure of transverse reinforcement or welds was observed in
any of the tests.
Fig. 13 shows damage to each test model following biaxial testing
of the repaired test models. SC-N* was tested to the limits of the
test equipment and completed the 7.8% biaxial drift cycle (m = 7.1) Results
without bar fracture. Actuator stroke limitation meant that only 4%
uniaxial drift could be applied in the south direction. Inadequate an- Fig. 16 and Table 3 summarize the experimental results for each
chorage and previous damage to the concrete footing led to some test model. SC-E showed stable hysteresis loops with good levels
Fig. 15. CC-N repair: (a) damaged CIP grout removed; (b) damaged dissipaters exposed; (c) damaged dissipaters removed; (d) replacement
dissipaters installed; (e) debonding tape applied; (f) replacement stirrups welded; (g) formwork assembled; (h) grout gravity fed
of energy dissipation, as indicated by the fatness of the hysteresis • Detailed cost-comparison and loss modeling analysis to quan-
loops. No flag shape was visible in testing of SC-N, but this shape tify the potential cost benefits of nonemulative systems, con-
developed at higher levels of drift during SC-N* testing. CC-N sidering life-cycle costs that encompass the construction,
showed no flag-shaped hysteresis loops, with a similar ratio of maintenance, repair, and deconstruction stages of the struc-
peak to residual drift as SC-E, despite having a higher recentering ture’s life (Lee and Billington 2011; Marriott et al. 2009).
ratio. Residual drifts in SC-N and SC-N* were significantly lower • Durability of the nonemulative connections, including corro-
than those of SC-E, CC-N, and CC-N*. Residual drift following sion protection of the dissipating and posttensioning compo-
loading to a 6% uniaxial drift cycle was 0.7% in the SC-N* col- nents at the jointed connection interface. Research is currently
umn, which was 78% smaller than that of the SC-E column, which under way at the University of Canterbury to address these
had residual drift of 3.2% following the same load cycle. issues (Andisheh et al. 2014).
CC-N* dissipated significantly more energy than both SC-E and • Applicability of the connection types to certain environments
SC-N* up to the failure biaxial drift of 3.9% (3% uniaxial drift that pose additional challenges for construction and repair,
cycle). Because CC-N(*) and SC-E had similar energy dissipation including in-water piers. Additionally, application of these
moment contributions to overall capacity (Table 1), and both col- connection types to other regions of the bridge substructures,
umns were subjected to the same displacement input, the amount of including column-to-cap-beam connections.
energy dissipated by both columns was expected to be similar. In • Shake table testing to investigate the dynamic behavior of the
reality, the repaired CC-N* column dissipated 50% more energy connections, including rate dependency in the connection
than SC-E on completion of the 3.9% biaxial load cycle (3% uniax- response and the potential for suboptimal coupler performance
ial drift). Bonding of the precast core (as previously discussed) is as investigated by Noureddine (1996) and Rowell et al.
believed to be the reason for the increased residual drifts and energy (2009).
dissipation of CC-N and CC-N*. • Compliance of the connections to current design standards,
Similar cumulative energy dissipation was observed in SC-E, particularly those relating to the use of mechanical splices in
SC-N, and SC-N* for biaxial drift cycles up to 3.9% (3% uniaxial plastic hinge regions.
drift). The cumulative dissipated energy of SC-N* was 61% that of
SC-E at completion of testing, with both columns achieving the
same ultimate drift. This corresponds well to the contribution of Conclusion
energy dissipation components to the overall strength of each con-
nection, as summarized in Table 2. The dissipating contribution of The experimental results of quasi-static cyclic tests of three half-
SC-N* was expected to be 180 kN·m, which is 62% that of SC-E at scale test models with emulative and nonemulative column-footing
290 kN·m. connections have been presented. The nonemulative connections
were designed to behave in a rocking manner with opening of a single
gap at the base of the column to improve seismic performance and
Further Investigations control damage. This design is aimed at facilitating rapid and cost-
effective repair using predetermined methodologies that avoids the
A number of points require further investigation before the nonemu- need for time-consuming and costly post-earthquake structural
lative connections presented in this research can be found suitable assessment and repair methodology development.
for use in regions of moderate to high seismicity. These include but The following key conclusions can be made from this paper:
are not limited to: • The emulative socket connection (SC-E) showed good seis-
• Further development of construction and repair methodolo- mic performance, with levels of energy dissipation and duc-
gies to increase connection effectiveness, robustness, and tility comparable to those of a conventional monolithic
reliability. connection. As expected, significant damage occurred,
80 150
100
-80 −100
−150
-120
0 2 4 6 8 10 12 14 −200
Strain (%) −6 −5 −4 −3 −2 −1 0 1 2 3 4 5 6
Uniaxial drift (%)
(a) (b)
Downloaded from ascelibrary.org by Ayman Shama on 10/03/18. Copyright ASCE. For personal use only; all rights reserved.
Yield Design
200 North-South actuator 200 Collar Slip
North-South actuator Yield Design/Pull-Out
East-West actuator East-West actuator
150 150
100 100
Uniaxial force (kN)
100 100
Uniaxial force (kN)
Uniaxial force (kN)
50 50
E N E N
0 0
S W S W
−50 −50
North-South North-South
actuator actuator
−100 East-West −100 East-West
actuator actuator
−150 −150
−200 −200
−6 −5 −4 −3 −2 −1 0 1 2 3 4 5 6 −6 −5 −4 −3 −2 −1 0 1 2 3 4 5 6
Uniaxial drift (%) Uniaxial drift (%)
(e) (f)
3.5 400
*Repaired *Repaired SC-E
Cumulative dissipated energy (kJ)
SC-E
3 350
Residual uniaxial dri (%)
2.5 300
250
2
CC-N* 200
1.5 CC-N*
SC-N*
150
1 CC-N SC-N* CC-N
SC-N 100
0.5
50
SC-N
0
0 1 2 3 4 5 6 0
0.5 0.75 1 1.5 2 2.5 3 4 5 6
Peak uniaxial dri (%) Drift cycle (%)
(g) (h)
Fig. 16. Experimental results: (a) force-strain behavior of grooved dissipaters; (b) SC-E uniaxial force-drift; (c) SC-N uniaxial force-drift; (d) SC-N*
uniaxial force-drift; (e) CC-N uniaxial force-drift; (f) CC-N* uniaxial force-drift; (g) residual drift following each drift cycle; (h) cumulative dissipated
energy in each test
56–73.
including spalling of concrete and yielding and buckling of Brenes, F. J., Wood, S. L., and Kreger, M. E. (2006). “Anchorage require-
longitudinal reinforcement. ments for grouted vertical-duct connectors in precast bent cap systems.”
• The nonemulative socket connection (SC-N, SC-N*) sustained FHWA/TX-06/0-4176-1, Center for Transportation Research, Univ. of
significantly less damage than SC-E. No flag-shaped hysteretic Texas at Austin, Austin, TX.
behavior was observed in the initial testing, but became appa- Christopoulos, C. (2004). “Frequency response of flag-shaped single
degree-of-freedom hysteretic systems.” J. Eng. Mech., 10.1061
rent in testing of the repaired column at larger column drifts.
/(ASCE)0733-9399(2004)130:8(894), 894–903.
The construction methodology was straightforward; however, Culmo, M. P. (2011). “Accelerated bridge construction: Experience in
the repair methodology requires further development to avoid design, fabrication, and erection of prefabricated bridge elements and
dissipater pullout and unintended slippage of the mounting systems.” Federal Highway Administration Rep. No. FHWA-HIF-12-
brackets. 013, U.S. Dept. of Transportation, Washington, DC.
• The nonemulative coupled bar connection (CC-N, CC-N*) Davis, P. M., Todd, M. J., Eberhard, M. O., and Stanton, J. F. (2012).
showed similar performance to that of SC-E up until the pre- “Unbonded pre-tensioned columns for bridges in seismic regions.”
mature failure point that occurred during the 3% drift cycle. PEER Rep. 2014/04, Pacific Earthquake Engineering Research Center,
CC-N had a higher recentering ratio than SC-E, which should Univ. of California, Berkeley, CA.
ElGawady, M., Booker, A. J., and Dawood, H. M. (2010). “Seismic behav-
have resulted in improved performance with reduced residual
ior of posttensioned concrete-filled fiber tubes.” J. Compos. Constr., 10
drift. Unintentional bonding of the column and footing is
.1061/(ASCE)CC.1943-5614.0000107, 616–628.
believed to be the reason for the higher-than-expected residual Finnsson, G. (2013). “Unbonded pre-tensioned bridge columns with hybrid
drift and energy dissipation. Difficulties were encountered fiber-reinforced concrete shells.” M.Sc. thesis, Univ. of Washington,
when aligning the replacement energy dissipaters, and prema- Seattle.
ture failure of the dissipaters occurred as a result of a detailing Haber, Z. B., Saiidi, M. S., and Sanders, D. H. (2014). “Seismic perform-
error. ance of precast columns with mechanically spliced column-footing con-
The experimental testing showed that the proposed construction nections.” ACI Struct. J., 111(3), 639–650.
and repair methodologies require further improvements to address Haraldsson, O., Janes, T., Eberhard, M. O., and Stanton, J. F. (2013).
issues relating to connection effectiveness, robustness, and reliabil- “Seismic resistance of socket connection between footing and precast
column.” J. Bridge Eng., 10.1061/(ASCE)BE.1943-5592.0000413,
ity. Nevertheless, it is believed that a controlled damage approach
910–919.
with connections that can be rapidly and cost-effectively repaired Hewes, J. T., and Priestley, M. J. N. (2002). Seismic design and perform-
will significantly reduce post-earthquake repair costs and maximize ance of precast concrete segmental bridge columns, Caltrans,
the functionality of bridge structures following severe earthquake Sacramento, CA.
events. Hieber, D. G., Wacker, J. M., Stanton, J. F., and Eberhard, M. O.
(2005). Precast concrete pier systems for rapid Construction of
bridges in seismic regions, Washington State Transportation Center
(TRAC), Seattle.
Acknowledgments Kapur, J., et al. (2012). “Best practices regarding performance of ABC
connections in bridges subjected to multihazard and extreme
The authors thank the New Zealand Ministry of Business, events.” NCHRP Project No. 20-68A, Transportation Research
Innovation and Employment—Natural Hazard Research Platform Board, Washington, DC.
Khaleghi, B., et al. (2012). “Accelerated bridge construction in Washington
for financially supporting this project as part of the research
state: From research to practice.” PCI J., 57(4), 34–49.
program Advanced Bridge Construction and Design (ABCD). The Kurama, Y. (2004). “A friction damper for post-tensioned precast concrete
authors also thank Mustafa Mashal for his assistance in design and moment frames.” PCI J., 49(4), 112–133.
testing throughout project and technicians Gavin Keats and Lee, W. K., and Billington, S. L. (2011). “Performance-based earthquake
Russell McConchie for lab assistance. engineering assessment of a self-centering, post-tensioned concrete
bridge system.” Earthquake Eng. Struct. Dyn., 40(8), 887–902.
Lehman, D. E., Gookin, S. E., Nacamuli, A. M., and Moehle, J. P. (2001).
References “Repair of earthquake-damaged bridge columns.” ACI Struct. J., 98(2),
233–242.
AASHTO. (2015). Guide specifications for LRFD seismic bridge design, Marriott, D. (2009). “The development of high - performance post - ten-
2nd edition, with 2012, 2014 and 2015 interim revisions, Washington, sioned rocking systems for the seismic design of structures.” Ph.D. the-
DC. sis, Univ. of Canterbury, Christchurch, New Zealand.