You are on page 1of 4

CONSTRUCTION OF NEW BRIDGE ACROSS THE RAJAGIRIYA - NAWALA CANAL CONNECTING

ANGAMPITIYA ROAD AT ETHULKOTTE & SCHOOL LANE AT NAWALA RAJAGIRIYA ROAD.


(Contract No- RDA/DC/WP/R/-GOSL/202/32)
State Development & Construction Corparation
MONTHLY TIME SHEET
Name : P.G.N.K.Ranasinghe
Position : Draughtsman
Month : Jan-21 Working Days : 31 M-M : 31/31 = 1

Work time For


Total Fixed Over
Date Week Leave Lunch(hrs) Working working Days Remarks
Start Finish hours hours Time
1 Fri 8:00 17:00 1:00 8:00 8:00 1.0
2 Sat 8:00 13:00 5:00 5:00 1.0
3 Sun 1.0
4 Mon 8:00 17:00 1:00 8:00 8:00 1.0
5 Tue 8:00 17:00 1:00 8:00 8:00 1.0
6 Wed 8:00 17:00 1:00 8:00 8:00 1.0
7 Thu 8:00 17:00 1:00 8:00 8:00 1.0
8 Fri 8:00 17:00 1:00 8:00 8:00 1.0
9 Sat 8:00 13:00 5:00 5:00 1.0
10 Sun 1.0
11 Mon 8:00 17:00 1:00 8:00 8:00 1.0
12 Tue 8:00 17:00 0.04 8:00 8:00 1.0
13 Wed 8:00 17:00 1:00 8:00 8:00 1.0
14 Thu 1.0 Thai Pongal day
15 Fri 1.0 Leave
16 Sat 8:00 13:00 5:00 5:00 1.0
17 Sun 1.0
18 Mon 8:00 17:00 1:00 8:00 8:00 1.0
19 Tue 8:00 17:00 0.04 8:00 8:00 1.0
20 Wed 8:00 17:00 1:00 8:00 8:00 1.0
21 Thu 8:00 17:00 1:00 8:00 8:00 1.0
22 Fri 8:00 17:00 1:00 8:00 8:00 1.0
23 Sat 8:00 13:00 5:00 5:00 1.0
24 Sun 1.0
25 Mon 8:00 17:00 1:00 8:00 8:00 1.0
26 Tue 8:00 17:00 0.04 8:00 8:00 1.0
27 Wed 8:00 17:00 1:00 8:00 8:00 1.0
28 Thu 1.0 Poya day
29 Fri 8:00 17:00 1:00 8:00 8:00 1.0
30 Sat 8:00 13:00 5:00 5:00 1.0
31 Sun 1.0
Total 31.0

Date : 01st February 2021

Signature ……………………………...…… Signature….......................................


Name of Expert : P.G.N.K.Ranasinghe Certified by : Addl. Director (Bridge Design)

Signature….......................................
Approved by Project Director
CONSTRUCTION OF NEW BRIDGE ACROSS THE RAJAGIRIYA - NAWALA CANAL CONNECTING
ANGAMPITIYA ROAD AT ETHULKOTTE & SCHOOL LANE AT NAWALA RAJAGIRIYA ROAD.
(Contract No- RDA/DC/WP/R/-GOSL/202/32)
State Development & Construction Corparation
MONTHLY TIME SHEET
Name : P.G.N.K.Ranasinghe
Position : Draughtsman
Month : Apr-21 Working Days : 30 M-M : 30/30 = 1

Work time For


Total Fixed Over
Date Week Leave Lunch(hrs) Working working Days Remarks
Start Finish hours hours Time
1 Sat 1.0 May day
2 Sun 1.0
3 Mon 8:00 17:00 1:00 8:00 8:00 1.0
4 Tue 8:00 17:00 1:00 8:00 8:00 2.0
5 Wed 8:00 17:00 1:00 8:00 8:00 1.0
6 Thu 8:00 17:00 1:00 8:00 8:00 1.0
7 Fri 8:00 17:00 1:00 8:00 8:00 1.0
8 Sat 8:00 13:00 1:00 5:00 5:00 1.0
9 Sun 1.0
10 Mon 8:00 17:00 1:00 8:00 8:00 1.0
11 Tue 8:00 17:00 1:00 8:00 8:00 1.0
12 Wed 8:00 17:00 1:00 8:00 8:00 1.0
13 Thu 8:00 17:00 1:00 8:00 8:00 1.0
14 Fri 8:00 17:00 1:00 8:00 8:00 1.0
15 Sat 8:00 13:00 1:00 5:00 5:00 1.0
16 Sun 1.0
17 Mon 8:00 17:00 1:00 8:00 8:00 1.0
18 Tue 8:00 17:00 1:00 8:00 8:00 1.0
19 Wed 8:00 17:00 1:00 8:00 8:00 1.0
20 Thu 8:00 17:00 1:00 8:00 8:00 1.0
21 Fri 8:00 17:00 1:00 8:00 8:00 1.0
22 Sat 8:00 13:00 1:00 5:00 5:00 1.0
23 Sun 1.0
24 Mon 8:00 17:00 1:00 8:00 8:00 1.0
25 Tue 8:00 17:00 1:00 8:00 8:00 1.0
26 Wed 1.0
27 Thu 1.0 VesakFull MoonPoya day
28 Fri 8:00 17:00 1:00 8:00 8:00 1.0
29 Sat 8:00 13:00 1:00 5:00 5:00 1.0
30 Sun 1.0
Total 31.0

Date : 01st june 2021

Signature ……………………………...…… Signature….......................................


Name of Expert : P.G.N.K.Ranasinghe Certified by : Addl. Director (Bridge Design)

Signature….......................................
Approved by Project Enginner