Professional Documents
Culture Documents
To date, there has been limited research because of a lack of data or proper site
undertaken in Nepal that has attempted to explore investigation. Meanwhile, the uncertainty of
the impact of DT on projects. In particular, the operation – operating in different environmental
previous DT models cannot be applied adequately conditions – causes a greater risk of equipment
to equipment management in developing countries breakdown (Arditi et al., 1997; Edwards et al.,
where the contractors face a number of problems 1998). The location of the site, for instance, may
related to equipment management, such as a lack limit the type and size of equipment that can be
of expertise and generally poor cost accounting transported to the site (Day and Benjamin, 1991).
practices. These equipment management-related Moreover, the remoteness of a construction site
factors, coupled with the working environment, may affect the repair time of equipment by
result in expensive repair and DT costs (Kirmani, affecting communication and the prompt
1988). A more comprehensive framework is procurement of parts.
needed to address these issues in the context of a
developing economy, such as Nepal’s. Equipment-related factors
In this paper, we identify the generic factors Factors that are related to equipment are its age,
related to DT, and its dynamic consequences, type, quality, complexity of operation, and degree
using causal loop diagrams. In addition, the need of usage. A company’s procedures and policies and
for managerial efforts to minimize the impact of site management actions can have significant
DT is highlighted, demonstrating how various influence on the selection, use and operation of
factors and processes interact with each other to equipment. It has been reported that the risk of
create DT and mitigate or exacerbate its impact on equipment breakdown is related to the complexity
the performance of a project. The framework is and sophistication of the mechanical and hydraulic
presented to assess the impact of DT. Data system of a piece of equipment (Arditi et al., 1997;
collected from nine road projects in Nepal over a Elazouni and Basha, 1996). It is, therefore,
2 month period illustrate the impact of DT on important for site management to have proper
schedule and cost. We analyze the results and knowledge about equipment in terms of its
discuss the implications of the research. capacity, complexity and technical suitability for
use under the given conditions.
Crew-level factors
Impact of DT These factors are related with human aspects of
crews who are involved in the equipment
In this section, we analyze the impact of DT maintenance, operation, and production process.
qualitatively, with an emphasis on construction The factors in this category would include skill
dynamics caused by DT. Earlier research has level of operators and mechanics, fatigue, morale,
reported that factors related to plant and and motivation. An operator’s skill is one of the
equipment breakdown, particularly from a most important factors and it affects the operator’s
management perspective, must be considered in performance and the direct cost of DT through job
assessing the impact of DT (Edwards et al., 1998). efficiency (Arditi et al., 1997; Edwards et al., 2000;
Therefore, first we identify the generic factors and Elazouni and Basha, 1996). In addition, misuse of
processes related to DT (Figure 1), some of which equipment, induced by the negligence of the
are incorporated into causal loop diagrams. Then, operator and lack of proper training and know-
using the diagrams, we analyze the dynamic how on the part of equipment supervisor, may
consequences of DT that may unfold during result in increased frequency and cost of DT
construction operation. (Pathmanathan, 1980). Another important aspect
that may have impact on DT is through morale,
DT factor analysis motivation and fatigue of the crews. These
Site-related factors conditions may occur when site management
As shown in Figure 1, examples of site-related attempts to increase the work rate by extensive use
factors include poor working conditions, of overtime and placing pressure on crews to avoid
uncertainties during equipment operation, and the impact of DT. Above a certain threshold level,
location of the site. The first two factors may affect both these factors can have negative effects on
the performance of equipment. For example, productivity by affecting fatigue and morale
difficult and rugged terrain may cause equipment (Cooper, 1994; Roberts and Alfred, 1974).
to deteriorate rapidly, thereby causing sudden Furthermore, when the job context – such as
failure. Proactive action on the part of a contractor supervision, resource availability, worker
can have significant effects in dealing with such compensation and the work environment – is
factors. Contractors may not aware, however, of degraded, workers’ motivations can result in loss of
the site conditions they may encounter, either productivity (Maloney and McFillen, 1986).
200
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
parts of a country. There are instances in which the into causal loop diagrams to analyze various
specifications and contract documents may specify consequences of DT. The first and most noticeable
the types and sizes of equipment to be used. For effect of DT is resource idleness, which, if it lasts
instance, to avoid undesirable end results, the for extended periods, would slow down the
types and sizes of compacting equipment are progress of a project. Slow project progress
sometimes specified, as are the travel speeds and increases schedule pressure (Neil, 1989). When
the number of passes over embankments (Day and project managers (PMs) are under schedule
Benjamin, 1991). Additionally, the availability, pressures, they might become distracted from
location and sophistication of a workshop can have proper supervision and resort to hasty
considerable influence on DT. maintenance. This distraction tends to produce a
low quality of maintenance, which then increases
Site management actions
DT, which again increases schedule pressure,
Site management may influence DT in a number
generating the vicious reinforcing loop denoted as
of ways, such as substituting broken equipment,
R1 in Figure 2. On the other hand, DT of vital
waiting for broken equipment to be repaired,
equipment and/or on critical activities brings an
adding or changing resources, accelerating
increase in DT costs. As DT cost increases, there is
activities, transferring crews to other operations
an increased emphasis on cost, which shows up as
or sites, and changing the sequence of work.
cost pressure. A PM under high cost pressure (due
Each of these actions, when implemented
to unexpected DT costs) might pay less attention
properly, may reduce the impact of DT; if the
to maintenance work. As a result, another vicious
selected course of action is not appropriate or is
feedback loop is triggered, represented as R2 in
implemented in an improper way, however, it
Figure 2. These feedback loops cause further cost
may exacerbate the situation. For example,
extended use of overtime to accelerate work pressures and can slow down project progress
without improving the work environment may until, or unless, the root causes are identified and
erode the motivation level of crews; it may also proper action is taken.
increase fatigue and, thus, induce more errors Extended and frequent DT can also disrupt the
and rework (Eden et al., 2000; Thomas and original sequence of work. Disruption of work
Raynar, 1997). Consequently, a project may may occur in several ways. For example, PMs may
suffer loss of productivity. In addition, the decide to change the sequence of work, which
selection of interdependent equipment is also may introduce new methods or procedures, or they
important to ensure economical construction may decide to divert the resources affected by DT
operations and to minimize costly idle time to other site operations. If PMs are not fully aware
(Day and Benjamin, 1991). of the indirect consequences of their decisions, the
diverted resources could distract the original
DT and its consequences production plan by diluting the experience level of
Some of the important consequences of DT existing crews, and increasing site congestions and
include idleness of equipment and crews, work work interference (Piper and Vachon, 2001).
disruption, activity delays and loss of productivity. The frequent disruption of work can also erode
Each of these consequences may, in turn, interact crew morale (Eden et al., 2000). This effect can
with site management actions, company’s also lead to frequent stoppages and the imposition
procedure and policies, project-level factors, and of additional learning requirements for crews,
crew-level factors, as indicated by the two-way which slows down project progress (Piper and
arrows in Figure 1. The nature of construction Vachon, 2001). As a result, the feedback effects
projects is that they are primarily “solution driven” caused by two additional reinforcing loops,
and mostly focus on minimizing costs and limiting indicated as R3 and R4 in Figure 2, affect the
immediate consequences (Mitropoulos and construction process.
Tatum, 1999). Thus, it is possible that site On the other hand, a PM seeks options to relieve
management may underestimate the actual impact schedule pressure as it builds up. Schedule
of DT that may evolve from their action in due pressure can be reduced by timely maintenance of
course. Site management, therefore, should equipment by project staff, as indicated by
understand the underlying phenomenon of DT balancing loop B1. The other common managerial
and its possible impact on project performance in a actions that are often taken to avoid the impact of
systematic way, which we discuss further in the DT on project progress are the use of overtime and
following section. the placing of pressure on staff to increase the work
completion rate. Overtime can facilitate the
Dynamics of DT progress of construction by increasing working
The identified DT factors related with crews and hours, as conceptualized with balancing loop B2 in
site management actions have been incorporated Figure 2, but as it continues it also can lower
202
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
productivity through causing fatigue in workers equipment is not working because it is undergoing
(Cooper, 1994; Thomas and Raynar, 1997). As a repairs or adjustment (Peurifoy and Ledbetter,
result, an additional vicious reinforcing loop, R5 in 1985). In this paper, we use DT and equipment
Figure 2, is generated. breakdown interchangeably. Thus, DT is defined
In summary, we have discussed the impacts of as the period in which the equipment assigned to
DT and its various ramifications that could appear work is not available because of breakdown. Based
during the operation of a construction project. on this definition, the percentage of DT for
This qualitative analysis can be useful to provide equipment is calculated in terms of planned
valuable policy implications by helping managers working hours:
to understand how DTand subsequent managerial
decisions can affect on project performance. Not The DT percentage ¼ ðTotal DT hours=
ð1Þ
all the variables are quantifiable, however, and Total planned working hoursÞ £ 100
many subjective issues may arise. In the following
section, we present a framework and rationale for Secondly, DT costs are the monetary values for
evaluating the impact of DT in terms of the time idle equipment and the time when it is unavailable
and cost of a particular project. (Pathmanthan, 1980). DT costs can be
categorized into two broad categories: tangible and
intangible costs (Vorster and De La Garza, 1990).
Tangible costs include the costs of labor, materials
Quantification of DT impact and other resources accrued for repairing the
equipment, operators’ wages, and the loss of
DT impacts the performance of a project in terms production by the equipment. Intangible costs
of time and cost, but clear definitions of those include costs accrued as a result of loss of
dimensions need to be set. First, researchers have production of other resources starved of
defined DT in different ways in relation to the time production, loss of labor productivity, extended
aspect. For example, Elazouni and Basha (1996) overhead costs and, in some cases, the liquidated
have defined DT as the time during which damages and late-completion charges
equipment cannot perform its specified function. (Pathmanthan, 1980; Tsimberdonis and
DT is also defined as the time during which Murphee, 1994). By incorporating these and other
203
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
factors, the following cost categories are identified equipment either from a contractor’s own fleet or
as the most likely to render an additional cost from an outside agency. In the former case,
burden to the project and, eventually, to the management still incurs the cost from the
contracting company. Thus, the DT cost for the contractor because the contractor would have
broken equipment is the sum of the all cost deployed the equipment in other projects or given
categories. We discuss these cost categories in the it to other contractors for rent. In addition, as
following sections. argued by Tsimberdonis and Murphy (1994), if
after a particular failure the management decides
Repair cost to rent a piece of equipment that otherwise would
The cost to repair broken equipment is categorized not be rented, the associated rental costs should be
under this heading. It consists of three items: included. It was found, however, by the authors
(1) labor (mechanics/helpers), that this cost normally would occur only when the
(2) materials, and breakdowns lasted for extended period of time and
(3) spare parts needed to repair the equipment. there was fear that the DT could affect critical
activities.
As it is not appropriate to charge major repairs and
complete overhaul to the present project
(Tsimberdonis and Murphee, 1994), those items Project-associated costs
are not included under this cost category. Hence, Project-associated costs are costs related to the
this category includes the costs that are applicable contractual obligations and clauses agreed on for
to the broken equipment but not to its periodic and the particular project and deserve particular
scheduled maintenance work. importance to the extent they are valid and
enforceable (Tsimberdonis and Murphee, 1994).
Costs such as liquidated damages, additional
Idle cost for laborers, operators and
claims, and late completion penalties belong to this
supervisors
category. Sometimes, when the project is packaged
This cost includes the cost incurred for idle time of
to a number of contracts with involvement of
human resources because of DT associated with
different contractors, additional costs may be
broken as well as dependent equipment that is
incurred when DT in particular work disrupts the
forced to be idle as a result of breakdown. As
works of other entities.
equipment fails, wages will continue to be paid to
laborers, operators and supervisors who are idle.
The effect is more pronounced when equipment Loss of labor productivity
works in conjunction with large crews and the DT Loss of labor productivity caused by DT can arise
causes their idleness (Selinger, 1983). This effect because of disruption of work, crowding of
tends to continue unless substitute equipment is workers, extended overtime, accelerated working,
mobilized or the crews are transferred to other sites learning curve effects, and so on. The effects of
and/or operations. these factors is well recognized in the literature
(Construction Industry Institute, 1995; Eden et al.,
Idle cost for equipment 2000; Halligan et al., 1994; Horner and Talhouni,
This cost category includes the idle cost for broken 1995; Schwartzkopf, 1995). Thomas (2000)
and other dependent equipment, if any, that argues that the economic consequences to the
remains idle because of the breakdown. The main contractor as a result of the loss of labor
consideration in financing equipment is that it productivity are quite severe.
should be used fully and productively and should
earn adequate revenues to recover the investment Other costs
cost. Thus, some sort of penalty costs should be This category includes other indirect costs such as
levied on idle equipment because of the overtime costs, cost of accelerations, incentives
expectation that, as far as possible, resources paid to crews, and miscellaneous petty expenses
representing capital investments in productive that are attributable to the DT event.
assets should be kept in good condition (Vorster Based on the above cost categorization, the
and De La Garza, 1990). The cost, which is percentage of DT cost in any project is
calculated as an expected rent charge for the calculated in terms of the budgeted cost for the
equipment, reflects the opportunity cost that period:
would be earned if the equipment was not broken.
The percentage of DT cost for any project
Cost for substitute equipment ¼ ðTotal DT cost=Budgeted project costÞ
This category of cost occurs only when
management decides to substitute the broken £ 100 ð2Þ
204
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
The PMs generally acknowledged that DT could unaltered on sites mainly because of the cheap
cause disruption of work and job rhythms. We labor costs. The efforts taken by site management
observed that frequent stoppages caused by the on project C were noteworthy, in that the PM
breakdown of bituminous equipment often urged the equipment operators and supervisors to
hampered and disrupted the weekly work plan in submit daily equipment performance reports.
project H. In some projects, site management
could easily substitute the broken equipment, DT and cost impact by equipment type
while in others, the delivery of substitute Summary statistics for equipment DT is presented
equipment was delayed as a result of the in Table V; it illustrates that DT is chaotic. The
remoteness of the site. Even in the case of extended percentage of DT and DT cost impact for different
DT, however, the number of workers remained types of equipment are summarized in Table VI.
Table III DT for different projects Table IV DT cost against budgeted cost for different projects
Planned working Total DT DT Budgeted cost DT cost DT cost
Project (h) (h) (percent) Project (NRs) (NRs) (percent)
A 4,560 1,225 26.9 A 16,200,500 1,754,490 10.83
B 7,410 641 8.7 B 12,170,000 796,700 6.55
C 6,000 55 0.9 C 8,000,000 49,876 0.62
D 4,800 257 5.4 D 3,000,000 588,200 19.61
E 6,840 94 1.4 E 26,000,000 109,825 0.42
F 3,528 99 2.8 F 14,276,000 107,250 0.75
G 6,480 193 3.0 G 13,590,000 345,250 2.54
H 7,616 122 1.6 H 10,800,000 368,960 3.42
I 2,880 386 13.4 I 21,139,322 430,410 2.04
Total 50,114 3,072 6.1 Total 125,175,822 4,550,961 3.64
206
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
Bituminous equipment had less average DT, but been reported that because of long delivery times,
higher cost impact. This observation can be it is common for those who are in need of parts
explained by the fact that during bituminous work, to travel to Calcutta (India), or even Singapore,
many pieces of equipment worked in conjunction to pick up parts and carry them back by hand to
with each other. Major component breakdown in Nepal (N. D. Lea International Ltd, 1993).
such works caused considerable impact on project The DT cost impact on equipment that has a
costs and work accomplishment rates. Therefore, sophisticated mechanical and hydraulic system –
project staff was required to take necessary such as motor graders, bulldozers, loaders, rollers
precautions and measures to ensure that and excavators – is relatively higher when
equipment worked without major failures. It is compared to ordinary and less-sophisticated
noteworthy to mention here that, to this day, no equipment. Also, the cost impact reflects the
asphalt concrete storing system has ever been in nature and stage of the construction in which the
use in road construction works in Nepal. equipment was being used. Especially during sub-
Therefore, there is always a high risk of DT during base, base course and surfacing work, where pieces
asphalt work. of equipment work in conjunction with each other,
One of the reasons behind the highest the associated DT cost impacts are relatively high.
percentage of DT being for the stone crusher was The studied equipment had ages ranging from 1
because of the long time for delivery of a V-belt. to 26 years. We observed that equipment that was
This delay problem highlights the lack of a good older than 9 years had higher cost impacts than did
inventory system. There are reports suggesting newer ones. It is not surprising that DT tends to
that delayed project completion is attributable to increase with usage of equipment (Navon and
DT of construction equipment (Figure 3). It has Mayer, 1995). This trend is because the increased
207
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
usage of equipment causes wear, scoring and and project-related factors. The most-often-cited
overheating of the engine. As a result, the reasons for delay in maintenance are related to the
availability of the equipment decreases with its age location and facilities available in a workshop,
(Nunally, 2000). the remoteness of the site, the lack of a proper
spare parts inventory, and unskilled mechanics.
Management actions taken to reduce an impact of
Policy implications
DT can have other consequences in due course
The quantification of DT impact has important
implications for organization. DT percentages for through the ramifications of various managerial
equipment are helpful numbers for project decisions. Clearly, these observations have
participants to judge the effectiveness of their important implications for PMs and companies to
maintenance programs and operation of adopt proper policies at the project and/or
equipment. Equipment with a high DT percentage company level to minimize DT and increase
might necessitate project staff to find the root project performance.
causes and take necessary steps to reduce it. On We observed that getting genuine spare parts is
the other hand, the DT cost percentage could be still a big problem in the industry and propose that
useful for PMs and senior managers to monitor the a sufficient stock of fast-wearing and -breaking
health of the projects – whether considerable parts be kept. Further, we recommend that a
money is lost in projects as a result of DT – and certain percentage of an investment be made in
trigger their attention towards proper action to spare parts when buying new equipment. One
increase profit margins. The cost of equipment DT practical way to reduce DT is to maintain a high
could also be useful to PMs, such as for taking availability factor for the equipment by adopting
special precautions and measures during a good maintenance program. More importantly,
equipment assignment. For example, equipment greater emphasis should be given for good
with high cost impact may need special maintenance programs that maintain a high
management attention in operations that may availability of equipment. Simple proactive actions
include making contingency plans, such as the
– such as replacing worn parts prior to failure,
provision of standby equipment and assigning
preferably at the end of shift or over a weekend
more experienced operators and relatively new
when the machine is not in use – can increase the
equipment to critical activities. In other cases, the
availability of equipment substantially (Peurifoy
cost might have to be lowered to justify any prior
and immediate action. and Ledbetter, 1985). Site management should
In the earlier sections, we discussed why make contingency plans so that they can effectively
addressing the impact of DT on a construction reduce the effects of DT. The measures are
project is important and have shown various especially important in the context of Nepal. It
factors and processes related with DT. The case may seem a cost burden to keep stocks of spare
study projects highlight that DT is caused mainly parts and to conduct regular maintenance of
by site-, equipment- and crew-level-related equipment for some time, but the benefits accrued
factors, the duration and severity of which are during the execution of a project would outweigh
influenced by a company’s operating procedures the expenses.
208
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
Another way to reduce the increased cost of DT monetary value of less-tangible DT costs (Vorster
is to introduce new equipment models, and to and De La Garza, 1990).
avoid the use of old equipment because its working Special efforts at the project and/or company
efficiency is low and spare parts are not easily level are needed to bring down the impact of DT.
available in local markets. Management should at At the project level, a PM should emphasize
least replace older machines with ones having timely, but quality, maintenance. Also, a PM must
higher availability factors and assign the older understand the causes and possible ramifications
machines to operations where they can work alone of DT while taking any managerial actions in order
(Peurifoy and Ledbetter, 1985). to avoid the impact of DT. At the company level,
Training is needed for operators and supervisors senior managers should focus on proper
so that they can have full knowledge of the equipment management policies to reap greater
equipment’s capabilities, such as its capacity and benefits from their projects. Above all,
functionality. Moreover, highly skilled mechanics construction companies need to adopt proactive
are needed on sites to ensure that good-quality equipment management and maintenance
maintenance can be achieved. The industry is still programs to avoid the non-trivial impact of DT on
lacking of knowledgeable skilled mechanics, construction project performance.
however. The establishment of mechanic training The DT model introduced in this paper
centers in the private sector is essential; the contributes mainly in terms of the following
Contractors Association of Nepal should act features. First, the model identifies factors that
promptly towards their establishment. cause DT. Second, the model emphasizes the
importance of focusing on crew-level factors.
Third, the model shows how the ramifications of
DT can occur by generating a feedback structure
Conclusions and recommendations through managerial action and decisions. Fourth,
the model shows the contractor’s role in
Research on construction equipment DT is influencing the DT. Finally, the model provides a
limited. Moreover, the research conducted to date framework for tracing the causes of DT and its
is of little value in illustrating the causes and impact on project performance. In addition, the
consequences of DT. In addition, it is of limited research serves as a framework for further work.
application in determining the impact of DT for Future studies are needed to identify the most
any given project. After all, they cannot address the important factors and processes relating to DT.
issues involved with equipment management Future DT studies, preferably for project duration
aspects in the context of a developing country in each category of equipment, will be useful for
where contractors face a number of problems the reasonable assessment of the relative impacts
related to equipment. The model presented in this of DT. Research could also be expanded in future
paper has identified generic factors and processes to address the dynamics of DT using dynamic
related to DT, and portrayed graphically how they planning methodology. Moreover, more studies,
may interact to cause DTand its consequences. We particularly in the context of developing countries,
have also discussed why addressing the impact of are needed to provide insight into equipment
DT is important and how managerial actions at the management and to improve the competitiveness
company or project level can eliminate, reduce or of industries.
exacerbate the impacts of DT.
We have used data from nine road projects over
a 2 month period to explain the framework of the
model. The variation in DT and its impact on References
different projects reflect the condition of the
equipment, the quality of the equipment, the Arditi, D., Kale, S. and Tangkar, M. (1997), “Innovation in
quality of maintenance, the company’s operating construction equipment and its flow into the construction
industry”, Journal of Construction Engineering and
policies, the location of the projects, and the nature
Management, Vol. 123 No. 4, pp. 371-8.
of the work. Although the quantitative information Central Bureau of Statistics (CBS) (2000), Statistical Pocket Book,
provided in this paper is specific to the Nepalese Kathmandu.
construction industry and the project types in the Construction Industry Institute (CII) (1995), Quantitative Effects
study, the research results demonstrate that the of Project Change, Project Management Research Team,
DT model presented in this paper could assist Publication 43-2, Austin, TX.
managers in minimizing the impact of DT by Contractors’ Association of Nepal (CAN) (1998), Construction
Equipment Management Issues of Nepalese Contractors,
providing insight into equipment management. Kathmandu, Nepal.
We acknowledge, however, that quantifying the Cooper, K.G. (1994), “The $2,000 hour: How managers influence
impact of DT is inherently subjective, and any project performance through the rework cycle”, IEEE
approach does little more than assessing the Engineering Management Review, Vol. 22 No. 4, pp. 12-23.
209
Downtime model development for construction equipment management Engineering, Construction and Architectural Management
Madhav Prasad Nepal and Moonseo Park Volume 11 · Number 3 · 2004 · 199–210
Day, D.A. and Benjamin, N.B.H. (1991), Construction Equipment Nunally, S.W. (2000), Managing Construction Equipment,
Guide, 2nd ed., Wiley, New York, NY. Prentice-Hall, Upper Saddle River, NJ.
Eden, C., Williams, T. and Howick, S. (2000), “The role of Pathmanathan, V. (1980), “Construction equipment downtime
feedback dynamics in disruption and delay on the nature costs”, Journal of Construction Division, Vol. 106 No. 4,
of disruption and delay in major projects”, Journal of the pp. 604-7.
Operational Research Society, Vol. 51, pp. 291-300. Peurifoy, R.L. and Ledbetter, W.B. (1985), Construction Planning,
Edwards, D.J., Holt, G.D. and Harris, F.C. (1998), “Financial Equipment and Method, 4th ed., McGraw-Hill Book
management of construction plant: conceptualizing cost Company, New York, NY.
prediction”, Journal of Financial Management of Property Piper, C.J. and Vachon, S. (2001), “Accounting for productivity
and Construction, Vol. 3 No. 2, pp. 59-73. losses in aggregate planning”, International Journal of
Edwards, D.J., Holt, G.D. and Harris, F.C. (2000), “A model for Production Research, Vol. 39 No. 17, pp. 4001-12.
predicting plant maintenance costs”, Construction Rieger, H.C. and Bhadra, B. (1978), Comparative Evaluation of
Management and Economics, Vol. 18, pp. 68-75. Road Construction Techniques in Nepal, Center for
Edwards, D.J., Holt, G.D. and Harris, F.C. (2002), “Predicting Economic Development and Administration, Tribhuvan
downtime costs of tracked hydraulic excavators operating University, Kathmandu.
in the UK opencast mining industry”, Construction Roberts, E.B. and Alfred, P. (1974), “A simple model of R & D
Management and Economics, Vol. 20, pp. 581-91. project dynamics”, R & D Management, Vol. 5 No. 1,
Elazouni, A.M. and Basha, I.M. (1996), “Evaluating the pp. 1-15.
performance of construction equipment operations in Schaufelberger, J.E. (1999), Construction Equipment
Egypt”, Journal of Construction Engineering and Management, Prentice-Hall, Upper Saddle River, NJ.
Management, Vol. 122 No. 2, pp. 109-14. Schwartzkopf, W. (1995), Calculating Lost Labour Productivity in
Halligan, D.W., Demsetz, L.A., Brown, J.D. and Pace, C.B. (1994), Construction Claims, Wiley Law Publications, Wiley,
“Action-response model and loss of productivity in New York, NY.
construction”, Journal of Construction Engineering and Selinger, S. (1983), “Economic service life of building
Management, Vol. 120 No. 1, pp. 47-64. construction equipment”, Journal of Construction
Hanna, A.S. and Heale, D.G. (1994), “Factors affecting
Engineering and Management, Vol. 109 No. 4,
construction productivity: Newfoundland versus rest of
pp. 398-405.
Canada”, Canadian Journal of Civil Engineering, Vol. 21,
Sharma, R. (1998), Opportunities and Challenges in the Road
pp. 663-73.
Sector in Nepal, Federation of Contractors’ Association of
Horner, R.M.W. and Talhouni, B.T. (1995), Effects of Accelerated
Nepal, Kathmandu.
Working, Delays and Disruption on Labour Productivity,
Sözen, Z. and Giritli, H. (1987), “Equipment policy as one of the
The Chartered Institute of Building, Ascot.
factors affecting construction productivity: a comparative
Kirmani, S.S. (1988), “The construction industry in development
study”, in Lansley, P.R. and Harlow, P.A. (Eds), Managing
issues and options”, Policy Planning and Research Staff,
Infrastructure and Urban Development Department, Construction Worldwide: Productivity and Human Factors
Report INU 10, World Bank, Washington, DC. in Construction, 5th International Symposium, CIOB, CIB,
Maloney, W.F. and McFillen, J.M. (1986), “Motivational London, pp. 691-6.
implications of construction work”, Journal of Thomas, H.R. (2000), “Schedule acceleration, work flow, and
Construction Engineering and Management, Vol. 112 labour productivity”, Journal of Construction Engineering
No. 1, pp. 137-51. and Management, Vol. 126 No. 4, pp. 261-7.
Mitropoulos, P. and Tatum, C.B. (1999), “Technology adoption Thomas, H.R. and Raynar, K.A. (1997), “Scheduled overtime and
decisions in construction organizations”, Journal of labour productivity: quantitative analysis”, Journal of
Construction Engineering and Management, Vol. 125 Construction Engineering and Management, Vol. 123
No. 5, pp. 330-8. No. 2, pp. 181-8.
Navon, R. and Mayer, D. (1995), “Equipment replacement and Tsimberdonis, A.I. and Murphee, E.L. Jr (1994), “Equipment
optimal size of a civil engineering fleet”, Construction management through operational failure costs”, Journal
Management and Economics, Vol. 13, pp. 173-83. of Construction Engineering and Management, Vol. 120
N.D. Lea International Ltd (1993), Baseline Assessment of the No. 4, pp. 522-35.
Road Construction Industry, Ministry of Work and Vorster, M.C. and De La Garza, J.M. (1990), “Consequential
Transport, Department of Road, Kathmandu. equipment costs associated with lack of availability
Neil, J.M. (1989), “Concepts and methods of schedule and DT”, Journal of Construction Engineering and
compression”, Transactions of the American Association Management, Vol. 116 No. 4, pp. 656-69.
of Cost Engineers, pp. S971-7. Vorster, M.C. and Sears, A.S. (1987), “Model for retiring,
Nepal, M.P. (2001), “Impact of construction equipment replacing, or reassigning construction equipment”,
downtime on road projects in Nepal”, Thesis No. ST-01-38, Journal of Construction Engineering and Management,
Asian Institute of Technology, Bangkok. Vol. 113 No. 1, pp. 125-37.
210