Professional Documents
Culture Documents
DAMREHABILITITIONANDIMPROVEMENTPROJECT (Phase-II)
REQUEST FOR BIDS NO..........2020/21
From
To
PERIOD OF SALE OF BIDDING
DOCUMENT
…2021
REQUESTFORBIDS
(RFB)
GOVERNMENT OFGUJARAT
DAMREHABILITITIONANDIMPROVEMENT PROJECT
NATIONALOPENCOMPETITIVEPROCUREMENT
NameofProject:DamRehabilitationandImprovementProject(DRIP-II)
RFBReferenceNo.: ……………………………
Date: …………………….
1. The Government of India has applied for financing from the World Bank toward the cost
of the Dam Rehabilitation and Improvement Project and intends to apply part of the
proceeds toward eligible payments under the contract for construction of works as
detailed below.
3. Bidders from India should, however, be registered with the Government of India or
other State Governments/Government of India, or State/Central Government
Undertakings.
4. The Executive Engineer, Kadana Division No.1, Diwada Colony, Kadana now invites online
Bids from eligible Bidders for the construction of works detailed below in the table. The
bidders may submit bids for any or allof the works indicated therein. Interested bidders
may obtain further information and inspect the bidding document at the address given
below during office hours.Bidders are advised to note the clauses on eligibility (Section I
Clause 4) and minimum qualification criteria (Section III – Evaluation and Qualification
Page | 2
Criteria), to qualify for the award of the contract. In addition, please refer to paragraphs
3.14 and 3.15 of the “Procurement Regulations” setting forth the World Bank’s policy on
conflict of interest.
7. Bidscomprise two Parts, namely the Technical Part and the Financial Part, andboth parts
must be submitted simultaneously online website: www.nwr.nprocure.com, on or before
16:00 hours on ……2021and the ‘Technical Part’ of the bids will be publicly opened online
on ……2021at 16:30 hours, in the presence of the bidders designated representatives
who wish to attend.The “Financial Part” shall remain unopenedin the e-procurement
system until the second public Bid opening for the financial part. Any bid or modifications
to bid (including discount) received outside e-procurement system will not be considered.
If the office happens to be closed on the date of opening of the bids as specified, the bids
will be opened on the next working day at the same time and venue. The electronic
bidding system would not allow any late submission of bids.
8. All Bids must be accompanied by a Bid Security of the amount specified for the work in
the table below, drawn in favour of The Executive Engineer, Kadana Division No.1, Diwada
Colony, Kadana Bid security will have to be in any one of the forms as specified in the
bidding document and shall have to be valid for 45 days beyond the validity of the bid.
Procedure for submission of bid security is described in Para 9.
9. The bidders are required to submit (a) original payment documents towards the cost of
bid document; and registration on e-procurement website (if applicable); (b) original bid
security; and (c) original affidavit regarding correctness of information furnished with bid
document with The Executive Engineer, Kadana Division No.1 ,Diwada Colony - 389250,
Taluka-Kadana, Dist. Panchmahal, Gujarat before the bid submission deadline, either by
registered post/speed post/courier or by hand, failing which the bids will be declared non-
responsive and will not be opened.
Page | 3
10. A pre-bid meeting will be held on……2021at 14:00 hours at the office of Office of Chief
Engineer and Additional Secretary (South Gujarat), Block No. 09, 2nd Floor, Sachiwalay,
Gandhinagar, Gujarat to clarify the issues and to answer questions on any matter that may
be raised at that stage as stated in ITB Clause 7.4 of ‘Instructions to Bidders’ of the
bidding document.Bidders are advised to download the bidding document prior to the
pre-bid meeting in order for bidders to have a good understanding of the scope of work
under this contract for discussion and clarification at the pre-bid meeting.
11. Other details can be seen in the bidding document.The Employer shall not be held liable
for any delays due to system failure beyond its control. Even though the system will
attempt to notify the bidders of any bid updates, the Employer shall not be liable for any
information not received by the bidder. It is the bidders’ responsibility to verify the
website for the latest information related to this bid.
TABLE
Executive Engineer
Kadana Division.1,
Diwada Colony
Page | 4
TableofContents
Page | 6
PART 1 – BIDDING PROCEDURES
Page | 7
Section – I – Instructions to Bidders
A. General
1. Scope of Bid 1.1 In connection with the Specific Procurement Notice - Request
for Bids (RFB), specified in the Bid Data Sheet (BDS),the
Employer, as specified in the BDS, issues this bidding
document for the provision of Works as specified in Section
VII, Works’ Requirements. The name, identification and
number of lots (contracts) of thisRFB are specified in the BDS.
1.2 Throughout this bidding document:
(a) the term “in writing” means communicated in written
form (e.g. by mail, e-mail, and fax, including if specified
in the BDS, distributed or received through the
electronic-procurement system used by the Employer)
with proof of receipt
(b) if the context so requires, “singular” means “plural” and
vice versa
(c) “Day” means calendar day, unless otherwise specified
as “Business Day”. A Business Day is any day that is
working day of the Borrower. It excludes the Borrower’s
official public holidays
(d) the term “ES” means environmental and social (including
Sexual Exploitation, and Abuse (SEA), and Sexual
Harassment (SH));
Page | 8
Section – I – Instructions to Bidders
Page | 9
Section – I – Instructions to Bidders
3. Fraud and 3.1 The Bank requires compliance with the Bank’s Anti-Corruption
Corruption Guidelines and its prevailing sanctions policies and procedures
as set forth in the WBG’s Sanctions Framework, as set forth in
Section VI.
3.2 In further pursuance of this policy, bidders shall permit and
shall cause their agents (whether declared or not),
subcontractors, sub-consultants, service providers, suppliers,
and personnel, to permit the Bank to inspect all accounts,
records and other documents relating to any initial selection
process, prequalification process, bid submission, proposal
submission, and contract performance (in the case of award),
and to have them audited by auditors appointed by the Bank.
4. Eligible Bidders 4.1 A Bidder may be a firm that is a private entity, or a state-
owned enterprise or institution subject to ITB 4.6, or any
combination of them in the form of a joint venture (JV), under
an existing agreement, or with the intent to enter into such an
agreement supported by a letter of intent, unless otherwise
specified in the BDS. In the case of a joint venture, all
members shall be jointly and severally liable for the execution
of the entire Contract in accordance with the Contract terms.
The JV shall nominate a Representative who shall have the
authority to conduct all business for and on behalf of any and
all the members of the JV during the Bidding process and, in
the event the JV is awarded the Contract, during contract
execution. This authorization shall be evidenced by submitting
a power of attorney signed by legally authorized signatories of
all members. Unless specified in the BDS, there is no limit on
the number of members in a JV. The joint venture agreement
shall be registered in the place specified in BDSsoastobe
legally valid and binding on members.
4.2 A Bidder shall not have a conflict of interest. All Bidders found
to have a conflict of interest shall be disqualified. A Bidder
may be considered to have a conflict of interest for the
purpose of this Bidding process, if the Bidder:
(a) directly or indirectly controls, is controlled by or is under
common control with another Bidder; or
(b) receives or has received any direct or indirect subsidy
Page | 10
Section – I – Instructions to Bidders
Page | 11
Section – I – Instructions to Bidders
Page | 12
Section – I – Instructions to Bidders
Page | 13
Section – I – Instructions to Bidders
Page | 14
Section – I – Instructions to Bidders
Page | 15
Section – I – Instructions to Bidders
C. Preparation of Bids
9. Cost of Bidding 9.1 The Bidder shall bear all costs associated with the preparation
and submission of its Bid, and the Employer shall in no case be
responsible or liable for those costs, regardless of the
conduct or outcome of the Bidding process.
10. Language of Bid 10.1 The Bid, as well as all correspondence and documents relating
to the Bid exchanged by the Bidder and the Employer, shall be
written in English. Supporting documents and printed
literature that are part of the Bid may be in another language
provided they are accompanied by an accurate translation of
the relevant passages in English, in which case, for purposes
of interpretation of the Bid, such translation shall govern.
11. Documents 11.1 The Bid shall comprise two Parts, namely the Technical Part
Comprising the and the Financial Part. These two Parts shall be submitted
Bid simultaneously.
11.2 The Technical Part shall contain the following:
Page | 16
Section – I – Instructions to Bidders
Page | 17
Section – I – Instructions to Bidders
Page | 18
Section – I – Instructions to Bidders
Page | 19
Section – I – Instructions to Bidders
procurement portal.
Page | 20
Section – I – Instructions to Bidders
Page | 21
Section – I – Instructions to Bidders
Page | 22
Section – I – Instructions to Bidders
Page | 23
Section – I – Instructions to Bidders
Page | 24
Section – I – Instructions to Bidders
uploaded along with the Bid. The name and position held by
each person signing the authorization must be typed or
printed below the signature.
20.4 In case the Bidder is a JV, the Bid shall be signed by an
authorized representative of the JV on behalf of the JV, and
so as to be legally binding on all the members as evidenced
by a power of attorney signed by their legally authorized
representatives. Documents establishing authority to sign the
bid on behalf of the JV shall be uploaded along with the bid.
20.5 Any interlineations, erasures, or overwriting shall be valid only
if they are signed or initialed by the person signing the Bid.
Page | 25
Section – I – Instructions to Bidders
Page | 26
Section – I – Instructions to Bidders
Page | 27
Section – I – Instructions to Bidders
Page | 28
Section – I – Instructions to Bidders
Page | 29
Section – I – Instructions to Bidders
Page | 30
Section – I – Instructions to Bidders
32.4 Only Bids that are both substantially responsive to the bidding
documentand meet all Qualification Criteria shall have the
Financial Parts of their Bids opened at the second public
opening.
33. Subcontractors 33.1 Unless otherwise stated in the BDS, the Employer does not
intend to execute any specific elements of the Works by
subcontractors selected in advance by the Employer.
33.2 The subcontractor’s qualifications shall not be used by the
Bidder to qualify for the Works unless their specialized parts of
the Works were previously designated by the Employer in the
BDS as can be met by subcontractors referred to hereafter as
‘Specialized Subcontractors’, in which case, the qualifications
of the Specialized Subcontractors proposed by the Bidder may
be added to the qualifications.
33.3 Bidders may propose subcontracting up to the percentage of
total value of contracts or the volume of works as specified in
the BDS.Subcontractors proposed by the Bidder shall be fully
qualified for their parts of the Works.
Page | 31
Section – I – Instructions to Bidders
1
Daywork is work carried out following instructions of the Project Manager and paid for on the basis of time spent by
workers, and the use of materials and the Contractor’s equipment, at the rates quoted in the Bid. For Daywork to be
Page | 32
Section – I – Instructions to Bidders
priced competitively for Bid evaluation purposes, the Employer must list tentative quantities for individual items to be
costed against Daywork (e.g., a specific number of tractor driver staff- days, or a specific tonnage of Portland cement),
to be multiplied by the Bidders’ quoted rates and included in the total Bid price.
Page | 33
Section – I – Instructions to Bidders
Page | 34
Section – I – Instructions to Bidders
appropriate:
(a) accept the Bid without any additional Performance
Security; or
(b) require that the amount of the Performance Security be
increased at the expense of the Bidder to a level not
exceeding twenty percent (20%) of the Contract Price to
protect the Employer against financial loss in the event of
default of the successful Bidder under the Contract; or
(c) reject the Bid if the risk cannot be mitigated through
additional performance security.
42. Most 42.1 Having compared the evaluated costs of Bids, the Employer
Advantageous shall determine the Most Advantageous Bid. The Most
Bid Advantageous Bid is the Bid of the Bidder that meets the
Qualification Criteria and whose Bid has been determined to
be:
(a) substantially responsive to the bidding document; and
(b) the lowest evaluated cost.
43. Employer’s Right 43.1 The Employer reserves the right to accept or reject any Bid,
to Accept Any and to annul the Bidding process and reject all Bids at any
Bid, and to time prior to Contract Award, without thereby incurring any
Reject Any or All liability to Bidders. In case of annulment, all documents
Bids submitted and specifically, Bid securities, shall be promptly
returned to the Bidders.
44. Standstill Period 44.1 Standstill Period shall not apply.
[Note 1: where it is proposed to permit Standstill Period, incorporate
all changes as indicated in Attachment 1 at the end of this document.
Note 2: Standstill period shall not apply where only one bid is
submitted or where the bidding process is in response to an
emergency situation recognized by the Bank].
45. Notice of 45.1 Not used.
Intention to
Award
J. Award of Contract
46. Award Criteria 46.1 Subject to ITB 43, the Employer shall award the Contract to
the successful Bidder. This is the Bidder whose Bid has been
Page | 35
Section – I – Instructions to Bidders
Page | 36
Section – I – Instructions to Bidders
successful Bidder.
Page | 37
Section – I – Instructions to Bidders
Page | 38
Section II – Bid Data Sheet
The following specific data for the Works to be procured shall complement, supplement,
or amend the provisions in the Instructions to Bidders (ITB). Whenever there is a conflict,
the provisions herein shall prevail over those in ITB
ITB A.General
Reference
ITB 1.1 ThenumberoftheRequestforBidsis: ……………. 2020/21 Commented [SD1]: Insert the reference number
B.Contentsof BiddingDocument
ITB 7.1 Electronic–Procurement System
TheEmployer shalluse the following electronic-procurement system to
managethis Biddingprocess:www.nwr.eprocurement.com
Page | 39
Section II – Bid Data Sheets (BDS)
The Bidder shall submit its Code of Conduct that will apply to Contractor’s
Personnel (as defined in Sub-Clause 1 (ii) of the General Conditions of
Contract), to ensure compliance with the Contractor’s Environmental and
Social (ES) obligations under the Contract. The Bidder shall use for this
purpose the Code of Conduct form provided in Section IV. No substantial
modifications shall be made to this form, except that the Bidder may
introduce additional requirements, including as necessary to take into
account specific Contract issues/risks.
Management Strategies and Implementation Plans (MSIP) to manage
the (ES) risks
The Bidder shall submit Management Strategies and Implementation
Plans (MSIPs) to manage the following key Environmental and Social (ES)
risks:
Page | 40
Section II – Bid Data Sheet
The Bidder shall furnish a Bid Security in the amount of Rs. 3,72,499/-
ITB 19.3 (d) Other types of acceptable securities are:
Fixed Deposit/Time Deposit certificate issued by a Nationalized or
Page | 41
Section II – Bid Data Sheets (BDS)
and such pledging has been noted and suitably endorsed by the bank
issuing the certificate.
Date: ……………
Time:16:30 Hours
F.Evaluation of Bids–GeneralProvisions
ITB29.3 The adjustment shall be based on the highestprice of the item or
component as quoted in other substantially responsive Bids, subject to
a maximum of the estimated price of the item. If the price of the item
or component cannot be derived from the price of other substantially
responsive Bids, the Employer shall use its best estimate.
Page | 42
Section II – Bid Data Sheet
ITB33.2 NA
ITB33.3 (a) Contractor’s proposed subcontracting: Maximum percentage of
subcontracting permitted is::25%of the total contract amount
(b) Bidders planning to subcontract more than 10% of total volume of work
shall specify, in the Letter of Bid, the activity (ies) or parts of the Works to be
subcontracted along with complete details of the subcontractors and their
qualification and experience. The qualification and experience of the sub-
contractors must meet the minimum criteria for the relevant work to be
sub-contracted failing which such sub-contractors will not be permitted to
participate.
(c) Subcontractors’ qualification and experience will not be considered for
evaluation of the Bidder. The Bidder on its own (without taking into account
the qualification and experience of the sub-contractor) should meet the
qualification criteria.
[Note-Work should not be split into small parts and sub-contracted].
H. Public OpeningofFinancialParts
ITB 34.2 (c)
Following the completion of the evaluation of the Technical Parts of the
Bids, the Employer will notify all Bidders of the date, time, and location of
the public opening of Financial Parts.
The online bid opening of Financial Parts of Bids shall take place at:
Office of Superintending Engineer,
Panam Project Circle , Panam Colony, Godhra-389001, Ta. Shahera, Dist.
Panchamahal, Gujarat-389001
Country:INDIA
Date & Time: To be Informed after evaluation of Technical bids through
www.nwr.nprocure.comportal
InadditiontotheabovetheEmployershallpublishanoticeofthepublic
openingofthe
FinancialPartsoftheBidonitswebsite:www.nwr.nprocure.com
I.Evaluation of Bids- FinancialParts
ITB40.2 Provisions related to Abnormally Low Bids do not apply
Page | 43
Section II – Bid Data Sheets (BDS)
J.Award of Contract
ITB 50.1 and The successful Bidder shall also be required to submit an Environmental
50.2
and Social (ES) Performance Security.
Page | 44
Section III – Evaluation and Qualification Criteria
This section contains all the criteria that the Employer shall use to evaluate Bids and qualify
Bidders through post-qualification.No other factors, methods or criteria shall be used other
than specified in this bidding document. The Bidder shall provide all the information
requested in the forms included in Section IV, Bidding Forms.
.
Page | 45
Section III – Evaluation and Qualification Criteria
1. Technical Part
(i) an assessment of the Bidder's technical capacity to mobilize key equipment and
personnel for the contract consistent with its proposal regarding work methods,
scheduling, material sourcing, and quality control/ assurance in sufficient detail and
fully in accordance with the requirements stipulated in Section VII, Works’
Requirements.
(iii) Bidders shall submit an undertaking from each proposed subcontractor to confirm
that they have read, understand and will comply with the ES obligations and code of
conduct for Contractor’s Personnel.
1.2 Alternative Technical Solutions for specified parts of Works(ITB13.4) – Not Applicable
[Note: provide details if the clause is relevant. Insert ‘Not Applicable’ or delete the clause,
if not relevant]
If permitted under ITB33, only the specific experience of Subcontractors for specialized
works permitted by the Employer will be considered. The general experience and
financial resources of the Specialized Subcontractors shall not be added to those of the
Bidder for purposes of qualification of the Bidder.
The specialized sub-contractors proposed shall be fully qualified for their work
proposed, and meet the following criteria:
Page | 46
Section III – Evaluation and Qualification Criteria
Pursuant to ITB 32.1, the Employer shall assess each Bid against the following
Qualification Criteria. Requirements not included in the text below shall not be
used in the evaluation of the Bidder’s qualifications.
Page | 47
Section III – Evaluation and Qualification Criteria
1. Eligibility
1.1 Nationality Nationality in accordance Must meet N/A N/A N/A Forms ELI – 1.1
with ITB 4.4 requirement and 1.2, with
attachments
1.2 Conflict of No conflicts of interest in Must meet N/A N/A N/A Letter of Bid
Interest accordance with ITB 4.2 requirement
1.3 Bank Eligibility Not having been declared Must meet N/A N/A N/A Letter of Bid
ineligible by the Bank, as requirement
described in ITB 4.5.
1.4 State- Meets conditions of ITB Must meet N/A N/A N/A Forms ELI –
owned 4.6 requirement 1.1 and 1.2,
enterprise with
or attachments
institution
of the
Borrower
country
1.5 United Nations Not having been excluded Must meet N/A N/A N/A Forms ELI –
resolution or as a result of prohibition in requirement 1.1 and 1.2,
Borrower’s the Borrower’s country with
country law laws or official regulations attachments
against commercial
relations with the Bidder’s
country, or by an act of
compliance with UN
Security Council resolution,
both in accordance with
ITB 4.8 and Section V.
Page | 48
Section III – Evaluation and Qualification Criteria
2. Historical ContractNon-Performance
2.1 History of Non- Non-performance of a contract2 did not Must meet N/A N/A N/A Form CON-2
Performing occur as a result of contractor default since requirement2&3
Contracts 1st June 2013
2.2 Suspension Not under suspension based on execution Must meet N/A N/A N/A Letter of Bid
Based on of a Bid/ Proposal Securing Declaration requirement
Execution of Bid/ pursuant to ITB 4.7 or withdrawal of the
Proposal Securing Bid pursuant ITB 19.9
Declaration by
the Employer or
withdrawal of the
Bid within Bid
validity period
2.3 Pending Bidder’s financial position and prospective Must meet N/A N/A N/A Form CON – 2
Litigation long-term profitability sound according to requirement
criteria established in 3.1 below and
assuming that all pending litigation will be
resolved against the Bidder
2.4 Litigation History No consistent history of court/arbitral Must meet N/A N/A N/A Form CON – 2
award decisions against the Bidder3 since requirement
1stApril 2013
2.5 Declaration: Declare any civil N/A N/A N/A
work contracts that have beensuspended Must make the
Environmental or declaration
and Social terminated and/or performance security
(ES)past
2Non-performance, as decided by the Employer, shall include all contracts where (a) non-performance was not challenged by
the contractor, including through referral to the dispute resolution mechanism under the respective contract, and (b)
contracts that were so challenged but fully settled against the contractor. Non-performance shall not include contracts
where Employers decision was overruled by the dispute resolution mechanism. Non-performance must be based on all
information on fully settled disputes or litigation, i.e. dispute or litigation that has been resolved in accordance with the
dispute resolution mechanism under the respective contract and where all appeal instances available to the Bidder have
been exhausted.
3The Bidder shall provide accurate information on the Letter of Bid about any litigation or arbitration resulting from contracts
completed or ongoing under its execution over the last five years. A consistent history of court/arbitral awards against the
Bidder or any member of a joint venture may result in disqualifying the Bidder.
Page | 49
Section III – Evaluation and Qualification Criteria
3. FinancialSituationandPerformance
3.1 Financial ((i) The Bidder shall demonstrate that it Mustmeet N/A N/A N/A FormFIN– 3.1,
Capabilities has access to, or has available, liquid requirement Withattachmen
assets, unencumbered real assets, lines ts
of credit5, and other financial means
(independent of any contractual
advance payment) sufficient to meet
the construction cash flow
requirements estimated as Rs.0.6
Croresfor the subject contract(s) net of
the Bidder’s other commitments
(ii) The Bidders shall also demonstrate, Mustmeet N/A N/A N/A
to the satisfaction of the Employer, that requirement
it has adequate sources of finance to
meet the cash flow requirements on
works currently in progress and for
future contract commitments.
(iii) The audited balance sheets or, if not Must meet N/A N/A N/A
required by the laws of the Bidder’s requirement
country, other financial statements
acceptable to the Employer, for the last
seven years shall be submitted and must
demonstrate the current soundness of
the Bidder’s financial position and
Page | 50
Section III – Evaluation and Qualification Criteria
6
Cost of completed works of previous years shall be given weightage @5% per year based on rupees value to
bring them to the price level of the financial year in which bids are received.
6
For contracts under which the Bidder participated as a joint venture member or sub-contractor, only the
Bidder’s share, by value, shall be considered to meet this requirement
Page | 51
Section III – Evaluation and Qualification Criteria
Page | 52
Section III – Evaluation and Qualification Criteria
Page | 53
Section III – Evaluation and Qualification Criteria
3. KeyPersonnel
The Bidder must demonstrate that it will have suitably qualified (and in adequate
numbers) minimum Key Personnel, as described in the Table below, that are required
to perform the Contract.
The Bidder shall provide details of the Key Personnel and such other Key Personnel that
the Bidder considers appropriate, together with their academic qualifications and work
experience. The Bidder shall complete the relevant Forms in Section IV, Bidding Forms.
The Contractor shall require the Employer’s consent to substitute or replace the Key
Personnel (reference the Particular Conditions of Contract 9.1).
KeyPersonnel
Position/specialization Relevant
academic Minimumyears
Item ofrelevant work
No. qualificcation
experience
4. Equipment
1 JCB/Excavator 1
2 Dumper 2
3 Generator 1
5 Compressor 2
6 Mechanical Hoist 1
8 Drilling Machines 2
Form in SectionIV.
Note:"Form for Equipment" must be prepared for each equipment. Affidavit in place of
Agreement regarding availability of equipment i.e. rented/ leased/ specially manufactured is
acceptable.
Page | 56
Section III – Evaluation and Qualification Criteria
2. Financial Part
2.1 Margin of Preference - Not Applicable
2.2 Multiple Contracts: Not Applicable
2.3 Sustainable procurement (Section VII - Specifications) – Not Applicable
2.4 Alternative Completion Times (ITB 13.2) - Not Applicable
2.5 Alternative Technical Solutions for specified parts of the Works (ITB 13.4)-
Not Applicable
2.6 Other criteria (if permitted under ITB 35.1(f)): Not Applicable
Page | 57
SECTION IV - BIDDING FORMS
Section III – Evaluation and Qualification Criteria
INSTRUCTIONS TO BIDDERS: DELETE THIS BOX ONCE YOU HAVE COMPLETED THE DOCUMENT
The Bidder must prepare this Letter of Bid on stationery with its letterhead clearly showing the
Bidder’s complete name and business address.
Date of this Bid submission: [insert date (as day, month and year) of Bid submission]
We, the undersigned, hereby submit our Bid, in two parts, namely:
(b) Eligibility: We meet the eligibility requirements and have no conflict of interest in
accordance with ITB 4;
(c) Bid-Securing Declaration: We havenot been suspended nor declared ineligible by the
Employer based on execution of a Bid-Securing Declaration or Proposal-Securing
Declaration in the Employer’s Country in accordance with ITB 4.7
(d) Conformity: We offer to execute in conformity with the bidding document the
following Works: [insert a brief description of the
Works]__________________________________
1
Delete if not applicable
Page | 59
Section III – Evaluation and Qualification Criteria
(e) Bid Validity Period: Our Bid shall be valid for a period specified in BDS ITB 18.1 (or as
amended if applicable) from the date fixed for the Bid submission deadline specified
in BDS 22.1 (or as amended if applicable), and it shall remain binding upon us and may
be accepted at any time before the expiration of that period;
(g) One Bid Per Bidder: We are not submitting any other Bid(s) as an individual Bidder or
as a subcontractor, and weare not participating in any other Bid(s) as a Joint Venture
member, and meet the requirements of ITB 4.3, other than alternative Bids
submitted in accordance with ITB 13;
(h) Suspension and Debarment: We, along with any of our subcontractors, suppliers,
consultants, manufacturers, or service providers for any part of the contract, are not
subject to, and not controlled by any entity or individual that is subject to, a
temporary suspension or a debarment imposed by the World Bank Group or a
debarment imposed by the World Bank Group in accordance with the Agreement for
Mutual Enforcement of Debarment Decisions between the World Bank and other
development banks. Further, we are not ineligible under the Employer’s Country
laws or official regulations or pursuant to a decision of the United Nations Security
Council;
(j) Binding Contract: We understand that this Bid, together with your written
acceptance thereof included in your Letter of Acceptance, shall constitute a binding
contract between us, until a formal contract is prepared and executed;
(k) Not Bound to Accept: We understand that you are not bound to accept the lowest
evaluated cost Bid, the Most Advantageous Bid or any other Bid that you may
receive; and
(l) Fraud and Corruption: We hereby certify that we have taken steps to ensure that no
person acting for us or on our behalf engages in any type of Fraud and Corruption;
and
(m) Adjudicator: We accept the appointment of [insert name proposed in Bid Data Sheet]
as the Adjudicator.
[or]
2
Use one of the two options as appropriate
Page | 60
Section III – Evaluation and Qualification Criteria
We do not accept the appointment of [insert name proposed in Bid Data Sheet] as the
Adjudicator, and propose instead that [insert name] be appointed3 as Adjudicator, whose
daily fees and biographical data are attached.
Name of the Bidder: *[insert complete name of person signing the Bid]
Name of the person duly authorized to sign the Bid on behalf of the Bidder:**[insert
complete name of person duly authorized to sign the Bid]
Title of the person signing the Bid: [insert complete title of the person signing the Bid]
Signature of the person named above: [insert signature of person whose name and
capacity are shown above]
Date signed [insert date of signing] day of [insert month], [insert year]
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture
as Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to be
attached with the Bid
3
In case appointment of Adjudicator was proposed from the list provided by an Institution in ITB 51, the
replacement should also be proposed from the list of same institution.
Page | 61
Section III – Evaluation and Qualification Criteria
Technical Proposal
- Equipment
- Site Organization
- Method Statement
- Mobilization Schedule
- Construction Schedule
Note: Work should not be split into small parts and sub-contracted; but sub-contracting
specialized elements of works is acceptable.
- Others
- Bidder’s Qualification
Bidders should provide the names and details of the suitably qualified Key Personnel to
perform the Contract. The data on their experience should be supplied using the Form
PER-2 below for each candidate.
Key Personnel
1. Title of position:
Name of candidate:
Duration of [insert the whole period (start and end dates) for which this
appointment: position will be engaged]
Expected time [insert the expected time schedule for this position (e.g. attach
schedule for this high level Gantt chart]
position:
Name of candidate:
Duration of [insert the whole period (start and end dates) for which this
appointment: position will be engaged]
Page | 63
Section III – Evaluation and Qualification Criteria
Expected time [insert the expected time schedule for this position (e.g. attach
schedule for this high level Gantt chart]
position:
Name of candidate:
Duration of [insert the whole period (start and end dates) for which this
appointment: position will be engaged]
Expected time [insert the expected time schedule for this position (e.g. attach
schedule for this high level Gantt chart]
position:
Name of candidate:
Duration of [insert the whole period (start and end dates) for which this
appointment: position will be engaged]
Expected time [insert the expected time schedule for this position (e.g. attach
schedule for this high level Gantt chart]
position:
Page | 64
Section III – Evaluation and Qualification Criteria
Name of candidate:
Duration of [insert the whole period (start and end dates) for which this
appointment: position will be engaged]
Expected time [insert the expected time schedule for this position (e.g. attach
schedule for this high level Gantt chart]
position:
6. Title of position:
Name of candidate
Duration of [insert the whole period (start and end dates) for which this
appointment: position will be engaged]
Expected time [insert the expected time schedule for this position (e.g. attach
schedule for this high level Gantt chart]
position:
Page | 65
Section III – Evaluation and Qualification Criteria
Form PER-2:
Key Personnel
Name of Bidder
Address: E-mail:
Professional qualifications:
Academic qualifications:
details
Address of employer:
Fax:
Page | 66
Section III – Evaluation and Qualification Criteria
Duration of
Project Role involvement Relevant experience
[From - To]
[main [role and
[describe the experience relevant to this
project responsibilities on the [time in role]
position]
details] project]
Declaration
I, the undersigned Key Personnel, certify that to the best of my knowledge and belief,
the information contained in this Form PER-2 correctly describes myself, my
qualifications and my experience.
I confirm that I am available as certified in the following table and throughout the
expected time schedule for this position as provided in the Bid:
Commitment Details
Commitment to duration of [insert period (start and end dates) for which this Key
contract: Personnel is available to work on this contract]
Time commitment: [insert the number of days/week/months/ that this Key
Personnel will be engaged]
Page | 67
Section III – Evaluation and Qualification Criteria
Signature: __________________________________________________________
Signature: ________________________________________________________
Page | 68
Section III – Evaluation and Qualification Criteria
The Bidder shall provide adequate information to demonstrate clearly that it has the
capability to meet the requirements for the key equipment listed in Section III (Evaluation
and Qualification Criteria). A separate Form shall be prepared for each item of equipment
listed, or for alternative equipment proposed by the Bidder. The Bidder shall provide all the
information requested below, to the extent possible. Fields with asterisk (*) shall be used
for evaluation.
Type of Equipment*
The following information shall be provided only for equipment not owned by the Bidder.
Address of owner
Fax Telex
Page | 69
Section III – Evaluation and Qualification Criteria
Site Organization
[insert Site Organization information]
Page | 70
Section III – Evaluation and Qualification Criteria
Method Statement
Page | 71
Section III – Evaluation and Qualification Criteria
Mobilization Schedule
[insert Mobilization Schedule]
In accordance with the Particular Conditions, Sub-Clause 16.2, the Contractor shall not
carry out mobilization to Site unless the Project manager gives consent that appropriate
measures are in place to address environmental and social risks and impacts, which as a
minimum shall include applying the Management Strategies and Implementation Plans
(MSIPs) and Code of Conduct for Contractor’s Personnel, submitted as part of the Bid
and agreed as part of the Contract.
Page | 72
Section III – Evaluation and Qualification Criteria
Construction Schedule
The construction schedule shall include the following key milestone - No-objection to the
Code of Conduct for Contractor’s Personnel and Contractor’s MSIPs, which collectively form
the C-ESMP, in accordance with the Particular Conditions of Contract Sub-Clause 16.2.
Page | 73
Section III – Evaluation and Qualification Criteria
(ES-MSIP)
The Bidder shall submit comprehensive and concise Environmental and Social
Management Strategies and Implementation Plans (ES-MSIP) as required by ITB 11.2
(j) of the Bid Data Sheet. These strategies and plans shall describe in detail the
actions, materials, equipment, management processes etc. that will be implemented
by the Contractor, and its subcontractors.
In developing these strategies and plans, the Bidder shall have regard to the ES
provisions of the contract including those as may be more fully described in the
Works Requirements in Section VII.
Page | 74
Section III – Evaluation and Qualification Criteria
The Bidder shall initial and submit the Code of Conduct form as part of its bid.
We are the Contractor, [enter name of Contractor]. We have signed a contract with
[enter name of Employer] for [enter description of the Works]. These Works will be carried
out at [enter the Site and other locations where the Works will be carried out]. Our
contract requires us to implement measures to address environmental and social risks
related to the Works, including the risks of sexual exploitation, sexual abuse and sexual
harassment.
This Code of Conduct is part of our measures to deal with environmental and social risks
related to the Works. It applies to all our staff, laborers and other employees at the
Works Site or other places where the Works are being carried out. It also applies to the
personnel of each subcontractor and any other personnel assisting us in the execution of
the Works. All such persons are referred to as “Contractor’s Personnel” and are subject
to this Code of Conduct.
This Code of Conduct identifies the behavior that we require from all Contractor’s
Personnel.
Page | 75
Section III – Evaluation and Qualification Criteria
REQUIRED CONDUCT
Contractor’s Personnel shall:
1. carry out his/her duties competently and diligently;
2. comply with this Code of Conduct and all applicable laws, regulations and other
requirements, including requirements to protect the health, safety and well-being of
other Contractor’s Personnel and any other person;
3. maintain a safe working environment including by:
a. ensuring that workplaces, machinery, equipment and processes under each
person’s control are safe and without risk to health;
b. wearing required personal protective equipment;
c. using appropriate measures relating to chemical, physical and biological
substances and agents; and
d. following applicable emergency operating procedures.
4. report work situations that he/she believes are not safe or healthy and remove
himself/herself from a work situation which he/she reasonably believes presents an
imminent and serious danger to his/her life or health;
5. treat other people with respect, and not discriminate against specific groups
such as women, people with disabilities, migrant workers or children;
6. not engageinSexual Harassment, which means unwelcome sexual advances,
requests for sexual favors, and other verbal or physical conduct of a sexual nature with
other Contractor’s or Employer’s Personnel;
7. not engage in Sexual Exploitation, which means any actual or attempted abuse
of position of vulnerability, differential power or trust, for sexual purposes, including, but
not limited to, profiting monetarily, socially or politically from the sexual exploitation of
another;
8. not engage in Sexual Abuse, which means the actual or threatened physical
intrusion of a sexual nature, whether by force or under unequal or coercive conditions;
9. not engage in any form of sexual activity with individuals under the age of 18,
except in case of pre-existing marriage;
10. complete relevant training courses that will be provided related to the
environmental and social aspects of the Contract, including on health and safety matters,
and Sexual Exploitation, and Abuse (SEA) and Sexual Harassment (SH);
11. report violations of this Code of Conduct; and
12. not retaliate against any person who reports violations of this Code of Conduct,
whether to us or the Employer, or who makes use of the grievance mechanism for
Contractor’s Personnel or the project’s Grievance Redress Mechanism.
Page | 76
Section III – Evaluation and Qualification Criteria
RAISING CONCERNS
If any person observes behavior that he/she believes may represent a violation of this
Code of Conduct, or that otherwise concerns him/her, he/she should raise the issue
promptly. This can be done in either of the following ways:
1. Contact [enter name of the Contractor’s Social Expert with relevant experience in
handling gender-based violence, or if such person is not required under the Contract,
another individual designated by the Contractor to handle these matters] in writing at this
address [ ] or by telephone at [ ] or in person at [ ]; or
2. Call [ ] to reach the Contractor’s hotline (if any) and leave a message.
I have received a copy of this Code of Conduct written in a language that I comprehend.
I understand that if I have any questions about this Code of Conduct, I can contact [enter
name of Contractor’s contact person with relevant experience] requesting an explanation.
Name of Contractor’s Personnel: [insert name]
Signature: __________________________________________________________
Page | 77
Section III – Evaluation and Qualification Criteria
Others
Page | 78
Section III – Evaluation and Qualification Criteria
Sub-Contracting
SCHEDULE OF SUBCONTRACTORS
The Bidder shall enter in this schedule a list of the major sections and appropriate value
of the work for which he proposed to use subcontractors [for those costing more than
10% of the bid price for each element], together with the names, addresses and experiences
of the proposed subcontractors.
The capability of the sub-contractor will also be assessed (on the same lines as for the
main Contractor) before according approval to him.
(Work should not be split into small parts and sub-contracted; but sub-contracting
specialized elements of works is acceptable).
Page | 79
Section III – Evaluation and Qualification Criteria
Page | 80
Section III – Evaluation and Qualification Criteria
Bidder’s Qualification
To establish its qualifications to perform the contract in accordance with Section III
(Evaluation and Qualification Criteria) the Bidder shall provide the information requested
in the corresponding Information Sheets included hereunder
Page | 81
Section III – Evaluation and Qualification Criteria
Date: _________________
RFB No. and title: _________________
Page__________of_______________pages
Page | 82
Section III – Evaluation and Qualification Criteria
Date: _______________
RFB No. and title: __________________
Page _______________ of ____________ pages
JV Information
Page | 83
Section III – Evaluation and Qualification Criteria
Date: _______________
RFB No. and title: __________________
Page _______________ of ____________ pages
Bidder’s legal name:
Page | 84
Section III – Evaluation and Qualification Criteria
(Lead Member)
Financial
Planning
Construction Equipment
Key Personnel
Page | 85
Section III – Evaluation and Qualification Criteria
[to be completed for the Bidder and for each member of a Joint Venture]
Non-Performed Contracts in accordance with Section III, Evaluation and Qualification Criteria
Contract non-performance did not occur since 1st January [insert year]specified in Section III,
Evaluation and Qualification Criteria, Sub-Factor 2.1.
Contract(s) not performed since 1st January [insert year] specified in Section III, Evaluation
and Qualification Criteria, requirement 2.1
Year Non- Contract Identification Total Contract
performed Amount (Rs.)
portion of
contract
[insert [insert amount Contract Identification: [indicate complete contract [insert amount]
year] and percentage] name/ number, and any other identification]
Name of Employer: [insert full name]
Address of Employer: [insert street/city/country]
Reason(s) for non-performance: [indicate main
reason(s)]
Pending Litigation, in accordance with Section III, Evaluation and Qualification Criteria
No pending litigation in accordance with Section III, Evaluation and Qualification Criteria,
Sub-Factor 2.3.
Pending litigation in accordance with Section III, Evaluation and Qualification Criteria, Sub-
Factor 2.3 as indicated below.
Page | 86
Section III – Evaluation and Qualification Criteria
Page | 87
Section III – Evaluation and Qualification Criteria
Page | 88
Section III – Evaluation and Qualification Criteria
Page | 89
Section III – Evaluation and Qualification Criteria
[The following table shall be filled in for the Bidder, each member of a Joint Venture and each
Specialized Subcontractor]
[insert [insert amount Contract Identification: [indicate complete contract [insert amount]
year] and name/ number, and any other identification]
percentage] Name of Employer: [insert full name]
Page | 90
Section III – Evaluation and Qualification Criteria
[insert [insert amount Contract Identification: [indicate complete contract [insert amount]
year] and name/ number, and any other identification]
percentage] Name of Employer: [insert full name]
[insert Contract Identification: [indicate complete contract name/ number, [insert amount]
year] and any other identification]
Name of Employer: [insert full name]
Address of Employer: [insert street/city/country]
Reason(s) for calling of performance security: [indicate main
reason(s) e.g. for gender-based violence; sexual exploitation or sexual
abuse breaches]
Page | 91
Section IV – Bidding Forms
Appendix to Technical Part
(B) Works for which bids already submitted and likely to be awarded – expected additional
commitment.
Description Place & Name and Address Estimated value Stipulated period Date when
of Work State of Employer of Works (Rs. of completion decision is Remarks,
equivalent in expected if any
million)
11
Attach certificate(s) from the Engineer(s)-in-Charge.
Page | 92
Section IV – Bidding Forms
1. Financial data
(Rs.) ____________
(amount in Rs.)
Year 1 Year 2 … … Year 7
Page | 93
Section IV – Bidding Forms
2. Sources of Finance
3. Financial documents
The Bidder and its parties shall provide copies of financial statements for
_________years pursuant Section III, Evaluation and Qualifications Criteria, Sub-factor
3.2. The financial statements shall:
(a) reflect the financial situation of the Bidder or in case of JV member, and
not an affiliated entity (such as parent company or group member).
12
If the most recent set of financial statements is for a period earlier than 12 months from the date of
bid, the reason for this should be justified.
Page | 94
Section IV – Bidding Forms
Appendix to Technical Part
Average
Annual
Construction
Turnover *
Page | 95
Section IV – Bidding Forms
Appendix to Technical Part
JOINT VENTURE
(Where permitted as per BDS ITB 4.1)
1. Member in charge
2. Member
3. Member
3. Member
TOTALS
Page | 96
Section IV – Bidding Forms
Appendix to Technical Part
2.
3.
4.
-- Sd. --
Name of Bank
Manager
* Change the text as follows for Joint venture: (Where permitted as per BDS ITB
4.1)
This is to certify that M/s. ………………………………. who has formed a JV with M/s.
………………………….. and M/s. …………………………….. for participating in this
bid, is a reputed company with a good financial standing.
Page | 98
Section IV – Bidding Forms
[The following table shall be filled in for the Bidder and for each member of a Joint
Venture]
[Identify contracts that demonstrate continuous construction work over the past [7]
years pursuant to Section III, Qualification Criteria and Requirements, Sub-Factor 4.1.
List contracts chronologically, according to their commencement (starting) dates.]
Bidder:
_____________________________
Amount of contract:
___________________
Name of Employer:
____________________
Address:
_____________________________
Contract name:
_________________________
Page | 99
Section IV – Bidding Forms
performed by the
Bidder:
_____________________________
Amount of contract:
___________________
Name of Employer:
___________________
Address: _________________________
Contract name:
________________________
Bidder: __________________________
Amount of contract:
___________________
Name of Employer:
___________________
Address: _________________________
Page | 100
Section IV – Bidding Forms
Appendix to Technical Part
Form EXP - 4.2(a): Specific Construction and Contract Management Experience
[The following table shall be filled in for contracts performed by the Bidder, each
member of a Joint Venture, and specialist sub-contractors]
Information
Similar Contract No.
Contract Identification
Award date
Completion date
Prime Member in JV Management Sub-
Role in Contract
Contractor Contractor contractor
*
If member in a JV or subcontractor,
specify participation in total
Contract amount
Employer's Name:
Address:
Telephone/fax number
E-mail:
13
Immediately preceding the financial year in which bids are received.
Page | 101
Section IV – Bidding Forms
Appendix to Technical Part
1. Amount
3. Complexity
4. Methods/Technology
6. Other Characteristics
Page | 102
Section IV – Bidding Forms
Appendix to Technical Part
All subcontractors for key activities must complete the information in this form as
per ITB 33.2 and 33.3 and Section III, Qualification Criteria and Requirements, Sub-
Factor 4.2.
1. Key Activity No One: ________________________
Information
Contract Identification
Award date
Completion date
Prime Member Management Sub-
Role in Contract
Contractor in Contractor contractor
JV
Year 1
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
14 If applicable.
Page | 103
Section IV – Bidding Forms
Information
2.Activ
ity No. Employer’s Name15:
Two
Address:
3.
…… Telephone/fax number
……
……
E-mail:
…
Information
(If applicable under 4.2 (c) of Section –III : Evaluation and Qualification Criteria)
[The following table shall be filled in for contracts performed by the Bidder,
and each member of a Joint Venture]
Contract Identification
Award date
Completion date
Role in Contract Prim Mem Manag Subcon
e ber in ement tractor
Contr JV Contrac
Total Contract Amount actor tor
Rs.
Details of relevant
experience
Page | 105
Section IV – Bidding Forms
Appendix to Technical Part
Form…..
To: …………………..
Dear Sir:
2. We are furnishing below the information required by the Employer for issue
of the necessary certificates in terms of the Government of India’s
relevant Notifications.
Goods
[a]Bitumen
[b]Cement
Page | 106
Section IV – Bidding Forms
[c]Steel
Construction Equipment
4. We agree that no modification to the above list is permitted after bids are
opened.
5. We agree that the certificate will be issued only to the extent considered
reasonable by the Employer for the work, based on the Bill of Quantities
and the construction program and methodology as furnished by us along
with the bid.
Date: ___________________
(Signature)______________________
Place:___________________ (Printed
Name)__________________
(Designation)____________________
(Common Seal)
___________________
Page | 107
Section IV – Bidding Forms
Appendix to Technical Part: Bid Security
SEALED with the Common Seal of the said Bank this _________ day of
__________ 20____.
16Insertname of the Bidder, which in the case of a joint venture shall be (a) the name of the joint venture that submits
the bid if the JV has been constituted into a legally enforceable JV, or (b) the names of all future members of the JV
as named in the letter of intent to execute the JV Agreement submitted by the bidder alongwith its bid.
17The Applicant should insert the amount of the guarantee in words and figures denominated in Indian Rupees. This
figure should be the same as shown in Clause 19.1 of the Instructions to Bidders.
Page | 108
Section IV – Bidding Forms
(1) If after Bid opening the Applicant (a) withdraws his bid during the period
of Bid validity specified in the Letter of Bid, or any extended dateprovided by the
Applicant (“the Bid Validity Period”); or (b) does not accept the correction of the
Bid Price pursuant to ITB 36;
Or
(2) If the Applicant having been notified of the acceptance of his bid by the
Employer during the period of Bid validity:
(b) fails or refuses to furnish the Performance Security and if required, the
Environmental and Social (ES) Performance Security, in accordance with the
Instruction to Bidders.
we undertake to pay to the Employer up to the above amount upon receipt of his
first written demand, without the Employer having to substantiate his demand,
provided that in his demand the Employer will note that the amount claimed by
him is due to him owing to the occurrence of one or any of the four conditions,
specifying the occurred condition or conditions.
_________________________________________________________________
1845 days after the end of the validity period of the Bid.
Page | 109
Section IV – Bidding Forms
Note: All italicized text (including footnotes) is for use in preparing this form and shall be
deleted from the final product.
Page | 110
Section IV – Bidding Forms
Appendix to Technical Part
We accept that we will automatically be suspended from being eligible for bidding
or submitting proposals in any contract with the Employer for the period of time
of [insert number of months or years] starting on [insert date], if we are in breach
of our obligation(s) under the bid conditions, because we:
(a) have not accepted the correction of the Bid Price pursuant to ITB 36; or
(b) have withdrawn our Bid during the period of Bid validity specified in the
Letter of Bid or any extended date provided by us; or
(c) having been notified of the acceptance of our Bid by the Employer during
the period of bid validity, (i) fail or refuse to execute the Contract, if required, or
(ii) fail or refuse to furnish the Performance Security and, if required, the
Environmental and Social (ES) Performance Security, in accordance with the ITB.
Name of the person duly authorized to sign the Bid on behalf of the Bidder**
[insert complete name of person duly authorized to sign the Bid]
Title of the person signing the Bid [insert complete title of the person signing the
Bid]
*: In the case of the Bid submitted by joint venture specify the name of the Joint
Venture as Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to
be attached with the Bid[Note: In case of a Joint Venture, the Bid-Securing
Declaration must be in the name of all members to the Joint Venture that submits
the Bid.]
Page | 112
Section IV – Bidding Forms
Appendix to Technical Part
Affidavit regarding correctness of information provided
(To be produced on Rs 100/- Stamp paper and duly Notarized)
To: …………………..
Dear Sir:
(1) We confirm that we are solely responsible for trueness and correctness
of the all certificates/documents and information provided by us for above
mentioned work.
Authorized Signatory……………………………
Name
……………………………………………..
For M/s
…………………………………………..
Address
…………………………………………..
Date :-
……………………………………………
[ Notary ]
Page | 113
Section IV – Bidding Forms
We hereby do solemnly affirm with oath that the all information and
certificates/documents provided by us in the above mentioned work are
absolutely true and correct to the best of our knowledge and we are wholly
responsible for all information and certificates/documents provided.
Authorized
Signatory……………………………
Name
……………………………………………..
For M/s
…………………………………………..
Address
…………………………………………..
[ Notary] Date :-
……………………………………………
Page | 114
Section IV – Bidding Forms
INSTRUCTIONS TO BIDDERS: DELETE THIS BOX ONCE YOU HAVE COMPLETED THE
DOCUMENT
The Bidder must prepare this Letter of Bid on stationery with its letterhead clearly
showing the Bidder’s complete name and business address.
Date of this Bid submission: [insert date (as day, month and year) of Bid
submission]
We, the undersigned, hereby submit the second part of our Bid, the Bid Price and
Bill of Quantities. This accompanies the Letter of Bid - Technical Part.
(a)Bid Validity Period: Our Bid shall be valid for a period specified in BDS 18.1 (or
as amended if applicable) from the date fixed for the Bid submission deadline
specified in BDS 22.1 (or as amended if applicable), and it shall remain binding
upon us and may be accepted at any time before the expiration of that period;
(b)Bid Price: The total price of our Bid, excluding any discounts offered in item (c)
below is: [Insert one of the options below as appropriate]
[Option 1, in case of one lot:] Total price is: [insert the total price of the Bid in Rs. in
words and figures];
Or
[Option 2, in case of multiple lots:] (a) Total price of each lot [insert the total price
of each lot in Rs. in words and figures]; and (b) Total price of all lots (sum of all lots)
[insert the total price of all lots in Rs. words and figures];
19
Delete if not applicable
Page | 115
Section IV – Bidding Forms
(a) Discounts: The discounts offered and the methodology for their
application are:
(i) The discounts offered are: [Specify in detail each discount offered]
(ii) The exact method of calculations to determine the net price after application
of discounts is shown below: [Specify in detail the method that shall be used to
apply the discounts];
(b) Commissions, gratuities and fees: We have paid, or will pay the following
commissions, gratuities, or fees with respect to the Bidding process or execution
of the Contract: [insert complete name of each Recipient, its full address, the reason
for which each commission or gratuity was paid and the amount and currency of
each such commission or gratuity].
Name of the person duly authorized to sign the Bid on behalf of the Bidder: **
[insert complete name of person duly authorized to sign the Bid]
Title of the person signing the Bid: [insert complete title of the person signing the
Bid]
Signature of the person named above: [insert signature of person whose name and
capacity are shown above]
Date signed [insert date of signing] day of [insert month], [insert year]
*: In the case of the Bid submitted by a Joint Venture specify the name of the
Joint Venture as Bidder.
**: Person signing the Bid shall have the power of attorney given by the Bidder.
The power of attorney shall be attached with the Bid Schedules
Page | 116
Section IV – Bidding Forms
Sub-contracting
SCHEDULE OF SUBCONTRACTORS
[Note: Entries in this Schedule shall be the same as included in the same Schedule in
the technical part of the bid, except for the column on ‘Approximate value of
subcontract’ added in the table below]
The Bidder shall enter in this schedule a list of the major sections and appropriate
value of the work for which he proposed to use subcontractors [for those costing
more than 10% of the bid price for each element], together with the names,
addresses and experiences of the proposed subcontractors.
The capability of the subcontractor will also be assessed (on the same lines as for
the main Contractor) before according approval to him.
(Work should not be split into small parts and subcontracted; but subcontracting
specialized elements of works is acceptable).
Page | 117
Section IV – Bidding Forms
APPENDIXTOFINANCIALPART: SCHEDULES
Page | 118
Section IV – Bidding Forms
Name of Work : CONSTRUCTION NEW ADMENSTRATIVE BLOCK & FLOOD CELL AT DIWADA COLONY.
Item TOTAL Amount
Description UNIT Rate
no. QTY in Rs.
In In
words figures
Excavation for foundation upto 1.5 m depth including
sorting out and stacking of useful materials and
1 disposing off the excavated stuff upto 50 Meter lead.(A)
1110 CU.MT
Loose or soft soil
Excavation for foundation for depth from 1.5 m to 3.0 m
including sorting out and stacking of useful materials and
2 960 Cu.m
disposing off the excavated stuff upto 50 Meter lead.(B)
Dense or Hard soil
Providing and laying controlled cement concrete M-150
and curing complete including the cost of form work but
3 excluding cost of reinforcement for reinforced concrete 120 Cu.m
work in : (a) Foundations, footings Bases of columns and
the like and mass concrete.
Providing and laying controlled cement concrete M 250
using B.T. stone aggregate and curing complete including
the cost of form work but excluding the cost of
4 reinforcement for reinforced concrete work in. (A)
519 CU.MT
Foundation footing, base of
columns & mass concrete.
Providing and laying controlled cement concrete M 250
using B.T. stone aggregate and curing complete including
5 the cost of form work but 14 CU.MT
excluding the cost of reinforcement for reinforced
concrete work in. For RCC Columns up to Plinth level.
Page | 119
Section IV – Bidding Forms
Page | 120
Section IV – Bidding Forms
Page | 121
Section IV – Bidding Forms
Page | 122
Section IV – Bidding Forms
Page | 123
Section IV – Bidding Forms
Page | 124
Section IV – Bidding Forms
Page | 125
Section IV – Bidding Forms
Providing and fixing eco-friendly light weight calcium silicate false ceiling tiles having
Tegular edge & 15 mm Thick Densified edges on the Tile Periphery for Extra Strength
The Light weight calcium silicate ceiling tiles shall have , light reflection 85% non
combustible as per B.S. 476 part IV, 100% humidity resistance and also havin thermal
conductivity0.043° w/m KC.for the best thermal Insulation . The Light weight calcium
Silicate tile shall be of approved texture Fine fissured/ Spintone/Cosmos having NRC
value of
0.5 & Globe having NRC value of 0.75 NRC or
equivalent of size 595 X 595 mm to be laid on true horizontal level suspended inter
locking metal grid of hot dipped galvanized steel sections (galvanizing @120 grams
per sqm including both side) consisting of main ‘T’ runner suitably spaced at joints to
get required length and size of 24X38mm made from 0.30 mm thick (minimum) sheet,
1200mm centre to centre, and cross ‘T’ of size 24X28mm made out of 0.33mm
(Minimum) sheet spaced 1200mm along spaced between main ‘T’ at 600mm centre to
centre to form agrid of 1200X600mm and secondary cross ’T’ of length 600mm
and size 24x28mm made of 0.30
mm thick (Minimum) sheet to be interlocked at middle of the 1200X600mm panel to
32 form grid of size 600X600mm resting on periphery walls/partitions on a perimeter 1267 SQ.mt
wall angle pre- coated steel of size (24X24X3000mm made of 0.40mm thick
(minimum) sheet with the help of rawl plugs at 450mm centre to centre with 25mm
long dry wall screws @ 230mm interval and laying 15mm thick Densified edges light
weight calcium silicate ceiling tiles of approved texture (Fine
Fissured/Cosmos/Spintone) in the grid including, cutting /making opening for services
like diffusers, grills, light fittings, fixtures, smoke detectors etc., wherever required,
Main ‘T’ runners to be suspended from ceiling using G.I. slotted cleats of size
25X35X1.6mm fixed to ceiling with 12.5mm dia and 50mm long dash fasteners, 4mm
G.I. adjustable rods level clips of size 85X30X0.8mm, spaced at 1200mm centre to
centre long main ‘T’ bottom exposed with 24mm of all T-sections shall be pre-baked
paint, for all heights, as per specifications, drawings and as directed by engineer-in-
charge.Note:- Only calcium silicate false ceiling area will be measured from wall to
wall. No deduction shall be made for exposed frames/opening (cut outs) having area
less than 0.30 sqm. The calcium silicate ceiling tiles shall have NRC. Value of 0.50
(Minimum) for Fine fissured/Spintone/Cosmos and 0.75 NRC for Globe, light reflection
85% non- combustible as per B.S. 476 part IV, 100% humidity resistance and also having
thermal conductivity. 0.043° w/m KC.for the best thermal Insulation
Page | 126
Section IV – Bidding Forms
Page | 127
Section IV – Bidding Forms
Page | 128
Section IV – Bidding Forms
Page | 129
Section IV – Bidding Forms
Page | 130
Section IV – Bidding Forms
Page | 131
Section IV – Bidding Forms
Page | 132
Section IV – Bidding Forms
Page | 133
Section IV – Bidding Forms
Page | 134
Section IV – Bidding Forms
Page | 135
Section IV – Bidding Forms
Page | 136
Section IV – Bidding Forms
Page | 137
Section IV – Bidding Forms
Page | 138
Section IV – Bidding Forms
Page | 139
Section IV – Bidding Forms
Page | 140
Section IV – Bidding Forms
Page | 141
Section IV – Bidding Forms
Page | 142
Section IV – Bidding Forms
Page | 143
Section IV – Bidding Forms
Page | 144
Section IV – Bidding Forms
(c)Jasud 60 60 NOS
Page | 145
Section IV – Bidding Forms
Page | 146
Section IV – Bidding Forms
SUB TOTAL =
GRAND TOTAL =
1 Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices
in the Bill of Quantities (refer:ITB Clause 14.2 and GCCClause 41.3).
2 Unit rates and prices shall be quoted by the bidder inIndianRupees(refer:ITB Clause 14.1 and ITB Clause 15.1).
3 Wherethereisadiscrepancybetweentheunitrateandthelineitemtotalresulting frommultiplyingtheunitratebyquantity,theunitratequotedshallgovern(refer:
ITBClause36).[Note:delete thispointifthee-procurementsystemautomatically calculates the total from theunitrateand quantity]
4 Wherethereisadiscrepancybetweentherateinfiguresand words,the ratesin wordswillgovern(refer:ITBClause36). [Note: delete thispointifthee-
procurementsystem automaticallypopulatestheamountinwordsfromtheamount in figures]
Page | 147
Part- 2 : Works’ Requirements
Section V - Eligible Countries
Eligibility for the Provision of Goods, Works and Non-consulting Services in Bank-
Financed Procurement
Inreference to ITB 4.8, and 5.1,for the information of the Bidders, at the present time
firms, goods and services from the following countries are excluded from this Bidding
process:
UnderITB4.8(a)and5.1:None
Under ITB4.8(b)and5.1:None
Page | 148
Part- 2 : Works’ Requirements
(Section VIshallnotbemodified)
1. Purpose
2. Requirements
a. Defines, for thepurposesof this provision, the terms set forth below as follows:
v. ―obstructivepracticeǁis:
b. RejectsaproposalforawardiftheBankdeterminesthatthefirmorindividual
recommendedforaward,any ofitspersonnel,oritsagents,oritssub-consultants, sub-
contractors,serviceproviders,suppliersand/ortheiremployees,has,directly or indirectly,
engaged in corrupt, fraudulent, collusive, coercive, or obstructive practices
incompeting for the contract inquestion;
d. PursuanttotheBank‘sAnti-CorruptionGuidelinesandinaccordancewiththe
Bank‘sprevailingsanctionspoliciesandprocedures,may sanctionafirmor
individual,eitherindefinitely orforastatedperiodoftime,includingbypublicly declaring
suchfirmorindividual ineligible(i)tobeawardedorotherwisebenefit fromaBank-
financedcontract,financiallyorinanyothermanner;10 (ii)tobea nominated11sub-
contractor, consultant,manufacturer or supplier,or serviceprovider
ofanotherwiseeligiblefirmbeing awardedaBank-financedcontract;and(iii)to receivethe
proceedsof anyloanmadebytheBank or otherwiseto participate further in
thepreparation orimplementation of anyBank-financed project;
Page | 150
Part- 2 : Works’ Requirements
information,andmakingcopies thereof as relevant;accessingand examining anyother documents,dataand
information(whether inhard copyor electronicformat)deemedrelevantfor the investigation/audit,and
makingcopies thereof as relevant; interviewing staff and other relevantindividuals;performing physical
inspections and site visits;and obtainingthirdpartyverificationofinformation.
Page | 151
Part- 2 : Works’ Requirements
SCOPE OF WORKS
S.No. SCOPEOFWORK
Page | 152
Section VII – Works’ Requirements
Page | 153
DESCRIPTION OF WORKS
S. No. DESCRIPTIONOFWORK
i
Name of Work : CONSTRUCTION NEW ADMENSTRATIVE BLOCK & FLOOD
CELL AT DIWADA COLONY.
Page | 154
GENERAL TECHNICAL SPECIFICATIONS
1. GENERAL REQUIREMENTS
The Technical Specification shall form a part of the contract and shall be read in conjunction with
other bidding documents. If required, the Project Managermay issue special specifications
modifying, amending, or supplementing the requirements spelt out in this Technical
Specification. In such a case, the provision in the Special Specification shall prevail over those in
the Technical Specification.
1.1 Acronyms
The term, Indian Standard specifications (issued by the Bureau of Indian Standards) here in
after referred as BIS used herein means the relevant Bureau of Indian Standard codes with
all amendments published up to the date of submission of tenders. A Statement of BIS as
applicable to the context of present work is listed below.
The list is not exhaustive.
Page | 2
3
LIST OF INDIAN STANDARDS
Sl.
Short title B. I. S. Number
No.
(I) CEMENT
(1) 33 Grade ordinary Portland cement 269-1989
(2) Low heat Portland Cement 12600
Portland pozzolana cement (fly ash
(3) 1489 (Part I)
based)
(4) Portland slag cement (Third Revision) 455 – 1989
Method for Physical tests for hydraulic
(5) 4031 – 1 996
cement (Reaffirmed 1980)
Method of chemical analysis of hydraulic
(6) cement (First revision) 4032 - 1985
Page | 3
Sl.
Short title B. I. S. Number
No.
Specification for cold worked steel
2 Deformed bars for concrete 1786 – 1985
reinforcement
Code of practice for Welding of M. S. Bars
3 2751 – 1966
used forReinforced Concrete Construction
Recommendations for detailing of
4 reinforcement in reinforced concreted 5525 – 1969
works
Specification of Mild Steel and Medium
5 432 - 1966
Tensile Bars for concrete reinforcement
Code for practice for safety and health
6 requirement in Electric and Gas welding 818 – 1968
and cutting operations
Code for practice for Fire precautions in
7 3016 – 1966
welding and Cutting operations
Measurement of Building and Civil
8 Engineering Works, method Part – VIII 1200 - 1974(Part – VIII)
steel work and Iron work
Code of procedure for manual or metal
9 823 – 1964
ARC welding of Mild Steel
IV CONCRETE
Method of Measurement of building and
1 Civil Engineering works Part – II cement 1200 - 1968(Part – II)
concrete works
Code of practice for plain and reinforced
2 456 – 2000
concrete
3 Methods of tests for strength of concrete 516 – 1959
5 Specification for Admixtures for concrete 9013 – 1979
Methods of Sampling and Analysis of
6 1199 – 1959
concrete
General requirements for Concrete
7 2505 – 1992
Vibrators – immersion type
General requirement for concrete vibrator
8 2506 – 1985
screed board type (first revision)
Code of practice for use of immersion
9 vibrator for consolidating concrete (first 3558 – 1983
revision)
Method for testing performance of batch
10 4634 – 1990
type concrete mixer
11 Form vibrators for concrete 4656 – 1991
12 Ready mixed concrete (First revision) 4926 – 1990
14 Vibrating plate compactor 5889 – 1994
15 Concrete Pavers 7245 – 1991
16 Concrete slump test apparatus 7320 – 1992
Method of making curing and determining
17 compressive Strength of accelerated 9013 – 1979
cured concrete test specimen
Page | 4
5
Sl.
Short title B. I. S. Number
No.
18 Guidelines for concrete mix design 10262 – 1982
V EARTH WORK
Method of Measurement of building and
1 Civil Engineering Works Part – I Earth 1200 - 1992(Part – I)
Work
Safety code for piling and other deep
2 5121 – 1994
foundations
Code of practice Design Installation,
observation and maintenance of uplift
3 6532 – 1992
pressure pipes for Hydraulic structures on
permeable foundation
4 Safety code for excavation works 3764 – 1992
Code of practice for Protection of slope
5 8237 – 1990
for reservoir embankments
8 Method of test for soils Part – II 2720 – 1973(Part – II)
Determination of water content
Method of test for soils Determination of
9 Water content Dry density relation using 2720 – 1995(Part – VII)
light compaction
Method of test for soils Determination of
2720 – 1974(Part –
10 dry density of soils in place by the sand
XXVIII)
replacement method
Method of test for soils Determination of
2720 - 1975(Part –
11 dry Density of soils in place by the core
XXIX)
cutter method
Classification & identification of soils for
12 general Engineering purpose (first 1498 – 1970
revision)
Safety code for working with construction
13 7293 – 1996,
machinery
14 Filtration media – sand & gravel 8419 – 1990 (Part – I)
2720 - 1997(Part – I to
17 Methods of tests of soils
X)
Method of load test on soils (Second
18 revision) 1888 – 1999
Any materials for which no standard is referred to or has not been fully specified in the
Specifications shall be of 1st class quality and the contractor is to carry out the necessary tests
based on International Testing Standard as per direction of Project Manager.
The temporary quarters and camp accommodation shall be run and maintained in an efficient
manner for the duration of the Contract, and shall be open to the inspection of the
Government Medical Officer of Health at all times, and any instruction given by him for the
cleaning, disinfecting, and general maintenance thereof shall be carried out by the Contractor
The above facilities shall from the time of their erection until the completion of the Works will
remain the property of the Employer and the Contractor shall not demolish or remove any
facilities or part thereof without the written permission of the Project Manager. On the
completion of the Works they shall become the property of the Contractor who shall, if so
ordered remove them and the associated services and restore the Site to the approval of the
Project Manager.
The Contractor shall submit, for the approval of the Project Manager, within fourteen (14) days
from the Commencement Date his detailed plan and/or construction drawings of his offices,
stores, and warehouse that he proposes to construct or rent, including his proposals for water
and power supply and sewage facilities. All facilities shall conform to the Employer's standards.
The Contractor shall make his own arrangements for the transport, where necessary, of his staff
and workmen to and from the site of the works at his own expenses. No payment shall be made
on this item, and such costs in this item are deemed to be covered in the unit rate.
If only deemed necessary for the Rehabilitation Works, the Contractor shall construct and
maintain temporary access roads including temporary access bridges necessary for the
construction of the Works and transportation of the materials. The access roads to the borrow
pits and for constructing the dam and roads shall be constructed by rehabilitating and
reinforcing the existing roads, where available. The access roads shall be constructed in such a
manner that all of the temporary access roads and bridges ensure the passage of heavy
equipment and trucks during the whole construction period. The Contractor shall also pay
compensation to the owner(s) if he constructs the temporary access roads on privately owned
land. To the possible extent the contractor should avoid agricultural lands and forest lands.
Not less than 14 days before he intends to start construction of any part of the temporary
access roads, the Contractor shall submit to the Project Managerhis detailed construction
program, and drawings of:
Page | 6
7
a) the temporary access roads including temporary access bridges; and
b) any other temporary works which he considers necessary for the proper execution of the
Works
The Contractor shall not start the construction of any temporary access road until the Project
Manager's approval thereto has been obtained. However, such approval shall not relieve the
Contractor of any liability or obligation under the Contract.
The Contractor shall construct the temporary access roads and bridges in accordance with the
approved drawings and construction program and shall maintain and repair such roads so as to
ensure the passage of heavy equipment and trucks throughout the construction period of the
works, giving special attention to watering the access road(s), unless otherwise specified or
directed by the Project Manager. On completion of the works, such as drain, road, bridge,
culvert, etc., he shall remove such access road and bridge from the site as directed by the
Project Manager.
The public and village roads may also be used as temporary access road. The Contractor shall
maintain and repair them to the satisfaction of the authorities concerned.
The Contractor shall facilitate the use of such roads by the public in a friendly co-operative
manner.
All costs, including cost of land compensation, therefore incurred by the Contractor in
complying with the requirements of this Sub-Clause shall be deemed to be included in the
respective item rates in the Bill of Quantities. No separate payment for these items shall be
made.
The Contractor has to arrange or procure borrow areas or procure construction materials from
certified suppliers at his own cost.
In the case of borrow area arranged by the Contractor, the Project Managershall have the
power to disallow the method of construction and/or the use of any borrow/quarry area if, in
his opinion, the stability and safety of the existing dam and appertenunt structures, all Works
or any adjacent structure is endangered, or there is undue interference with the natural or
artificial drainage, or the method or use of the area will promote undue erosion.
All areas susceptible to erosion shall be protected as soon as possible either by temporary or
permanent drainage works. All necessary measures shall be taken to prevent concentration of
surface water and to avoid erosion and scouring of slopes and other areas. Any newly formed
channels shall be backfilled.
Borrow/quarries shall be located away from the population centers, drinking water intakes and
drainage systems. The cutting of trees shall be minimized. Temporary ditches and/or settling
Page | 7
basins shall be dug to prevent erosion. The undesirable ponding of water shall be prevented
through temporary drains discharging into natural drainage channels.
Borrow pits shall not be more than 1m in depth and 25 m in length. A clear distance of 1m shall
be left between the pits. The bed of borrow pits shall be left reasonably smooth and even.
Borrow pits shall be drained to avoid stagnation of water and the bottom level of borrow pits
should be fixed with reference to the prevailing ground slope towards the nearest natural
drainage course.
Borrow pits should be avoided within the forest areas. Earthwork operations shall be strictly
limited to the areas to be occupied by the permanent Works and approved borrow areas and
quarries, unless otherwise permitted by the Project Manager. Due provision shall be made for
temporary drainage. Erosion and/or instability and/or sediment deposition arising from
earthwork operations not in accordance with the Specifications shall be made good
immediately.
The Contractor shall obtain the permission of the Project Managerbefore opening up any
borrows or quarries. Such borrow pits and quarries may be prohibited or restricted in
dimensions and depth by the Project Managerwhere:
(i) they might affect the stability or safety of the existing dam and appurtenant structures, all
Works or adjacent property;
(iv) the contractor should enter into an equitable agreement with landowner for borrow area
redevelopment if any landowner requires and after completion of the borrow area the
contractor obtains a “Satisfaction Letter “ or “No – objection Letter” from the land owner
on a stamp paper
At least 14 days before he intends to commence opening up any approved borrow pit or
quarry, the Contractor shall submit to the Project Managerhis intended method of working
and restoration. These shall include but not be limited to:
(i) the location, design and method of construction of any access track;
(iv) measures for controlling runoff and sediment from the site during operations; and
(v) proposals for site restoration including approximate finished levels, drainage, erosion and
sediment control, slope stabilization and re-vegetation, including reinstatement of any
access track.
Page | 8
9
The operation of borrow pits or borrow areas shall not be permitted until the method of
working for that particular pit or area has been approved by the Project Managerin writing.
Restoration shall be to the satisfaction of the Project Manager.
Materials in excess of the requirements for permanent works and unsuitable materials shall be
disposed of in locations and in the manner as agreed with the Project Manager. The locations
of disposal sites shall be such as not to promote instability, destruction of properties and water
supply systems. Exposed areas of such disposal sites shall be suitably dressed and be planted
with suitable vegetation.
The Contractor shall plan his works in such a way that there is no spillage or seepage of
petroleum products to the surface or sub-surface water.
Withinten (10) days from the Commencement Date the Contractor shall submit to the Project
Managerfor approval a complete and practicable construction program showing the orderly
performance of the Works. The Construction Program shall show in detail the proposed
method of operations, including purchase and delivery of materials and equipment, as well as
the construction. The Construction Program shall show in a bar chart each major item of the
Works and the Temporary Works on separate horizontal lines, sequence of operation and the
period required for the completion of each activity and preferably using Microsoft Project 2007
software. The Construction Program shall, when approved by the Project Manager, become a
part of the Contract.
In amplification, the particulars supplied by the Contractor with the program shall include the
following details:
(a) a statement giving the numbers and categories of supervisory and technical staff and
skilled/unskilled labor to be employed on the Works;
(b) a list and type/details of the Contractor's Equipment (including vehicles) which the
Contractor proposes to employ on the Works, stating whether they are to be acquired
from inside or outside India, including program dates for order and delivery;
(c) a list detailing the purchase and delivery of materials and Plant from both inside and
outside India;
(d) details of the Contractor's methods of working for all operations including construction by
sequence. The program shall also indicate the proposed temporary flow diversions and
arrangements for de-watering illustrating the sequence of various critical stages of
construction;
(e) a statement and outline layout giving the proposals for location of offices and stores at the
Site; and
Page | 9
(f) details of the program for the construction of the works from the Commencement Date,
including a complete resource allocation showing the number of units and allotted times
for each unit of the Contractor's Equipment, Plant, materials and labor allocated for each
part of the works.
(g) The program shall show the start and completion dates of the various activities, in order to
complete the entire project by the Intended Completion Date.
(h) No separate payment shall be made to the Contractor for complying with this Sub-Clause.
Monthly Report
The Contractor shall furnish to the Project Manager, at the Contractor's own cost, at regular
one (1) month intervals and in a form and number of copies determined by the Project
Manager, the following:
(i) physical and financial progress for the preceding months and estimated progress for the
report month.
(ii) completion schedules (target and actual) based on the approved Construction Program.
(iv) a tabulation of construction equipment, listing the major items and pieces of equipment
which were utilized for performance of the Works during the preceding month.
(v) a tabulation of employees, showing the supervisory staff and the numbers of several
classes of laborers employed by the Contractor in the preceding month.
(vi) purchase and expenditure report covering the Plant and materials furnished by the
Contractor for the Works.
(viii) the environmental and social measures carried out by the contractor; and
(xi) any report which may be specifically requested by the Employer and/or the Project
Manager
Within 30 days from the Provisional Acceptance Date, the Contractor shall submit to the Project
Manager Completion Report in 30 copies. The Report should include :
b) Financial statement.
Page | 10
1
c) Main issues encountered. 1
e) Recommendations
The report should also include: as-built drawings of the various structures.
Site/Works Meetings
The Contractor shall attend all the Site/Work Meetings (periodical or exceptional) called by the
Project Manager. A Minutes of Meeting should be prepared and jointly signed by the Contractor
(or its representative) and the Project Manager.
The Contractor shall maintain a site diary book in which all the main activities in the site should
be daily recorded including inventory of existing staff and equipment, works progress, incidents,
executed tests and samples collection, visits and particular or exceptional events. The diary
should be jointly signed by the Contractor's representative and the Project Manager.
The Contractor shall note that the Employer shall be entitled, at its discretion, to conduct audits
in respect to:
(b) any other costs that the Contractor claims from the Employer which are not specifically
covered by the terms of the Contract.
(c) The Contractor shall be obliged to keep accurate up-to-date accounts with records
concerning the above items.
Progress Photographs:
The Contractor shall make all arrangements to provide a minimum of 20 daily geo tagged
progress photographs by a digital camera in albums, but not pasted, showing the work
progress and shall promptly supply four copies of such photographs, larger than 10 cm x 15 cm
in size, of such portions of the works in progress and/or completed as may be directed by the
Project Manager. Each print shall contain on its back the date and title of the view taken. The
digital files of the photographs shall be the property of the Employer and no prints from those
shall be supplied to any persons without the approval of the Project Manager. No payment on
the account shall be made to the contractor.
1.7 Quality Control andField-Testing Laboratory
The Contractor shall be responsible for the quality of the work and shall conduct all quality
Page | 11
control tests required for the work and arrange for the testing of all materials in accordance
with Indian standard.
The Contractor will establish and maintain field laboratory for basic and routine tests (including
suitable building, furniture and equipment) at his own cost to conduct different field tests and
arrange on site or NABL accredited third-party laboratory for adavanced testing. Equipments
and materials as necessary to conduct the tests shall be procured by the Contractor and
brought to site or arranged at NABL accredited third-party laboratory by the contractor. A list
indicating some of the required tests but not limited to and main equipment/materials are
given below for reference of the Contractors. The Contractor shall also procure other
equipments or arrange at NABL accredited third-party, if necessary, to conduct tests specified
for different items of work to the satisfaction of the Project Manager. All necessary testing
arrangement will be subject to verification and approval by the EngineerIn Charge and the
Contractor should follow instructions to be given by the Project Manager.
The Contractor shall, within fourteen (14) days from the Commencement Date, submit a Quality
Assurance Plan. The plan shall include testing schedules, list of material sources, quality control
procedures to ensure the provision of adequate materials and the execution of the works
according to the technical specifications, the Contractor's internal organization ensuring good
Page | 12
1
quality of constructions works, procedures3for supplying of suitable materials, procedures for
verification of drawings and other items as required by the Project Manager. The Contractor
shall implement the quality control procedures in compliance with the approved Quality
Assurance Plan
Three tier system is proposed to be implemented for CS and QA activities. The first level CS&QA
is the responsibility of contractor, second level with the dam owner and third level called Third
Party CS & QA is entrusted with CPMU, Central Water Commission through Engineering and
Management Consultant. Supervision of construction work will be done by the Project
Managerand his site staff on a day-to-day basis and periodically by the concerned
Superintending Engineer and Chief Project Managerof the Project or any authorized
agency/officials by the engineer-in charge.
Regarding the material sampling and testings, by the second party and third party, it is the sole
responsibility of the dam owner and the CPMU, CWC without any financial implications to the
contractor. The representatives of the second and third party are authorized to inspect any time
the ongoing rehabilitation works even at a short notice, can take the samples of construction
materials for appropriate testing. The construction material samplings and testing shall be done
at independent material testing laboratories by each agency.
All materials and works rejected by the Project Manager's representative shall be promptly
Page | 13
removed from the site.
All materials and goods furnished and works performed under these specifications shall be
subject to the inspection of the Project Manageror his authorized representative to determine
that they meet the requirements of these specifications. The Contractor shall notify the Project
Manager, not less than 15 days in advance of the date and place that the materials will be
available for inspection. Acceptance of materials or the waiving of inspection, thereof, shall not
relieve the Contractor of the responsibility for furnishing materials and goods or performing
works in accordance with the requirements of the Contract Documents.
The Contractor shall provide all labor, and equipment necessary for the performance of all tests
required, or he may employ an approved independent testing laboratory to carry out all or part
of the testing. The contractor shall obtain approval of his proposed testing arrangement and
shall submit all results without delay.
The Contractor shall be responsible for delivering all samples to the laboratory and for collecting
the results. The original test certificates shall be presented to the Project Managerfor his review
and approval.
The Project Managershall have easy access to the laboratory/ies at all reasonable times.
The Contractor shall not interfere in any way with any existing works whether they are the
property of the Employer or of a third party and whether the position of such works is indicated
to the Contractor by the Project Manageror not, except where such interference is specifically
described as part of the Works either in the Contract or in the Project Manager's instructions.
The Contractor shall at his own expense provide and erect, to the approval of the Project
Manager, such supports as may be required to protect efficiently all structures or works which
may be endangered by the execution of the Works and he shall remove such supports on
completion of the Works or otherwise take such permanent measures as may be required by the
Project Managerto protect the structures or works.
The Contractor is to execute the Works in such a manner that he does not damage or interfere
with existing services which are located in proximity to the Site. The Contractor shall be
responsible for any damage or interference which may be caused to these services due to the
execution of the Works and shall carry out all necessary repairs at his own expense and to the
satisfaction of the Project Manager.
During the progress of the work, the Contractor shall maintain a continuous up-to-date copy and
Page | 14
1
record in softcopy and hard copy ( in PDF, 5 DOC,DWX OR DWG format) of all drawings,
specifications, supplementary data, latest revisions and field deviations from the drawings, if
any, approved by the Project Manager.
As soon as any section of the Works has been completed the Contractor shall bring the
construction drawings up to “As-Built” status incorporating all modifications, additions,
alterations etc., which may have been made during the construction period. All “As-Built”
drawings shall be subject to verification and approval by the Project Manager. Within the
contractually stated period following the date of the issue of the Certificate of Completion for
the Works or parts of the Works, the Contractor shall complete and submit one full set of such
approved drawings together with one set of auto-positives to the Project Manager.
The Contractor shall protect completed Works from damage from subsequent operations, from
the weather or any other cause, including the naturally aggressive nature of the environment in
which the works are to be constructed and make good any damage so arising until the work is
fully completed and handed over to the Project Manager.
1.13 Signboards
Notice boards shall be in Hindi and English and shall be displayed in suitable position on the Sites
to show the Employers name together with the name of the Project and the names of the co-
financer, Consultant and Contractor. The boards shall have a minimum overall size of 1.5m x 1m
and shall be in a format to be provided by the Project Manager.
The contractor shall be responsible for ensuring throughout the contract period all the safety
measures at site of work so as to prevent loss of life, property and damage of partially or
completed works.
The Contractor shall comply with any safety instruction given by the Project Manager. In the
performance of the Works, the Contractor shall exercise every reasonable precaution to protect
persons or property from injury. The Contractor shall erect and maintain all necessary temporary
fencing, barricades, barriers, signs and lights and provide fire alarm, fire extinguishing and fire-
fighting services at strategic points on the Site. The Contractor shall adopt and enforce such
rules and regulations as may be necessary, desirable or proper to safeguard the public and all
persons engaged in the work and its supervision.
The safety measures taken by Contractor shall include but shall not be limited to the following:
Page | 15
(a) Temporary Fencing – The Contractor shall erect, maintain and remove suitable and
approved temporary fencing to enclose such areas of the Permanent Works and areas of
land occupied by the Contractor within the Site as may be necessary to implement his
obligations under theContract, to the satisfaction of the Project Manager. Where any
temporary fence has to be erectedalongside a public road, footpath, etc., it shall be of the
type required by and shall beerected to the satisfaction of the Government authority
concerned.
(b) Lighting –The Contractor shall provide sufficient lighting in all places where work is in
progress, such that:
(i) Safe working conditions are provided both for the Contractor's personnel, sub-
contractor's personnel and for personnel of the Project Manager;
(ii) The Works can be constructed in complete compliance with the Contract; and
(iii) A complete inspection of all Works in progress can be made by the Project Manager.
(c) The minimum service luminance on ground or working surfaces to be provided for the
various operations or work areas shall be as directed by the Project Manager.
(d) The Contractor shall supply a suitable instrument to the Project Managerfor measuring the
intensity of illumination
(e) All mobile equipment or plant used during night operations, as and when approved by the
Project Manager, shall be equipped with sufficient lights and reflectors to ensure safe
working conditions
(f) Not less than fourteen (14) days before the start of night operations, the Contractor shall
submit his proposals for lighting in the areas in which he proposes to work at night to the
Project Manager. The Contractor shall modify the proposals if required by the Project
Manager, and shall not begin operations at night until the proposals for lighting (in an
amended form if required) have been approved
(g) Approval of the Contractor's proposals for lighting shall not relieve the Contractor of any of
his liabilities or obligations under the Contract.
(h) Work in the vicinity of electrical equipment – in the interest of safety and security, the
Contractor shall complete the erection of any safety fencing around electrical and
mechanical apparatus by the time that the said apparatus is connected to any electricity
supply.
(i) Explosives – in the use, handling and storage of explosives, the Contractor shall comply with
the guidelines given in Section 3.4, under Earthworks of this Specification and with all
statutory regulations of law. The Contractor's attention is drawn to the fact that, depending
Page | 16
1
on the nature of work in progress, the7 Project Managermay require the Contractor to
discontinue the handlingoruseofexplosivesduring the approach and progress of severe
thunderstorms in which case all persons shall be removed from danger areas to a place of
safety during such periods.
(j) Safety Instructions – the Contractor shall at his own cost supply and issue to his employees
and those of his subcontractors and the staff of the Project Managerprinted booklets, of
pocket- size, on the scale of one per person, in English and in other languages used by his
employees at Site, instructions based on good practice. Within sixty (60) days of the Project
Manager's written order to commence the Works at Site, proof copies of the booklet shall
be submitted for approval before printing and amendments shall be made to the booklet to
his entire satisfaction. The Contractor shall issue the booklet immediately after printing as
required by this Clause and ensure that all employees are fully conversant with the
instructions. Safetyinstructions shall deal with all safety including:
(vii) Welding;
(k) The Contractor shall allow for 20 booklets for the use of the Project Manager. The
Contractor shall provide for the Project ManagerandProject Manager's supervisory staff the
protective clothing, headgear and footwear necessary for the proper discharge of their
duties on Site.
(l) Accident Reports – the Contractor shall promptly report to the Project Manager, all
accidents involving death or serious injury to staff or workmen, and furnish monthly reports
of all accidents to staff or workmen involving loss of time, giving such information as may
be prescribed by the Project Manager.
(m) The Contractor shall provide all necessary signs for the works.
Page | 17
• standard road signs;
• warning signs;
• danger signs;
• control signs;
• safety signs; and
• direction signs
(ii) Wording on all signs shall be in English and Hindi and other approved languages. The
size, color, lettering and location of all signs will be subject to approval and attention
shall be paid to international signs.
(iii) The Contractor shall maintain all signs placed by him as well as those placed by the
Employer.
(iv) If the Project Managerconsiders that the system of signs provided by the Contractor is
inadequate to ensure safety, or unsatisfactory in other respects, the Contractor shall
add to, amend, or otherwise change the system to the satisfaction of the Project
Manager.
(v) The Contractor shall at his own cost make suitable replacement as directed by the
Project Managerin case of loss or damage to any signs provided by the Contractor
under this Sub-Clause.
(vi) The Contractor shall at his own cost adopt such measures as the Project Managermay
consider reasonable and necessary to minimize nuisance from dust, noise or other
disturbance created while or in carrying out the Works.
(vii) The Contractor shall at his own cost adopt such measures as the Project Managermay
consider reasonable and necessary to minimize nuisance from dust, noise or other
disturbance created while or in carrying out the Works.
Separate payment will not be made for complying with the provisions of this Clause and all
costs shall be deemed to be included in the various rates in the priced Bill of Quantities.
The Contractor shall provide and maintain adequate fire-fighting equipment and take adequate
fire precaution measures for the safety of all personnel, temporary and permanent works, and
shall take action to prevent damage to or destruction by fire of trees, shrubs or grasses.The
Contractor shall ensure that fire extinguishers of needed types are duly installed in all sensitive
places, such as, stores containing electrical material and those containing inflammable items
and, that his personnel are given regular training to operate these devices.
Separate payment will not be made for the provision of fire prevention measures.
Page | 18
1
General 9
The Contractor shall in all respects be fully responsible for ensuring necessary first-aid services
to his employees and employees of his subcontractors, including transport for injured personnel
to hospital or other appropriate accommodation as and when required.
Staff
To enable the fulfillment of his obligations under this Clause, the Contractor shall engage
qualified resident first-aid staff and shall arrange for the treatment of casualties on the Site in
first-aid units and for removal.
Separate payment will not be made for first aid and medical facilities provided by the Contractor
for his employees and the employees of his subcontractors. The facility shall be also available for
the use of staff of Project Manager.
Contractor with the help of local medical department should conduct AIDS awareness Campaign
for every six months to bring awareness to the labor employed by him.
The Contractor shall control the movement of his crews and equipment on any right-of- way,
including access routes approved by the Project Managerso as to minimize damage to crops and
property and shall Endeavour to avoid marring the lands. Ruts and scars shall be obliterated,
damage to land shall be corrected and the land shall be restored as neatly as practicable to its
original condition.
The Contractor shall be responsible directly to the Employer for any excessive or unnecessary
damage to crops or lands resulting from the Contractor's operations whether on lands adjacent
to a right-of-way or on approved access roads, and deductions shall be made from payments
due to the Contractor to cover the amount of such excessive or unnecessary damage as
determined by the Project Manager.
No separate payment shall be made to the Contractor for complying with the stipulations of
this Sub-Clause.
The Environment is defined as meaning the surrounding area, including human and natural
resources, to be affected by the execution and completion of the Works.
Page | 19
The Contractor shall take all precautions for safeguarding the environment during the
construction of the Works. He shall abide by all prevailing laws, rules and regulations governing
pollution and environmental protection.
The Contractor shall prohibit employees from unauthorized use of explosives, poaching wildlife
and cutting trees. The Contractor shall be responsible for the action of his employees.
a) Hazardous Materials
The Contractor shall not store hazardous materials near water surfaces. The Contractor shall
provide protective clothing or appliances when it is necessary to use hazardous substances.
High concentration of airborne dust resulting in deposition and damage to crops and water
resources shall be avoided. The Contractor shall take every precaution to control excessive noise
resulting in disruption to wildlife and human populations.
Space allocated for storage of materials such as cement, gabion wire, reinforcing wire etc. shall
in general be damp-free, rainproof and away from petroleum products storage.
Written information must be given to, and approval be taken from, the Project
Managerregarding the proper establishment and maintenance of such stores. Failure to comply
with the Project Manager's instruction in respect of overall standards will lead to the reduction
or withholding of payment.
c) Sanitation
The Contractor is to arrange for a high standard of sanitation to be maintained throughout his
offices, stores, and warehouse, and the Works. Sanitary conveniences for the use of persons
employed in the works shall be provided and maintained by the Contractor in accordance with
the appropriate laws and regulations in force in India to the extent and in such a manner and at
such places as may be approved by the Project Manager, and all persons connected with the
works shall be obliged to use them
d) Reinstatement of Environment
The Contractor shall arrange and execute works as well as related activities in such a way that
environmental conditions are reinstated. He may be required to carry out filling, removal and
disposal works, along with planting of grass and trees at identified locations to reinstate
environment as directed by the Project Manager.
Page | 20
2
1.19 ENVIRONMENT-General 1
The role of Contractor is very important to ensure that the environmental and social risks and
impacts for implementation of the construction works are minimized, and that all aspects of the
Environmental and Social Management Plan (ESMP) are implemented as published on
borrower’s website. The activities would be carried out in Consultation with Project Manager
under the guidance of Environmental and Social Experts to look after the implementation of
ESMP in all the Packages.
The following environmental related activities are to be implemented during the pre-
construction/construction (early part) periods:
1. Contractor, in consultation with Project Manager, shall identify the resource requirement
including water and power for work items as per the guidelines provided in Resources
Conservation Plan.
2. Contractor shall submit the required documents confirming compliance to Labour
Management Procedure.
3. Contractor, in consultation with Project Manager, shall identify the location of labour
camp and make adequate arrangement of water and power supply, waste collection and
disposal from the camp.
4. Contractor shall make adequate security arrangement at Labour camp to ensure
compliance with GBV/SEAH risks mitigation plan.
5. Contractor shall identify the suitable government approved borrow area(s) with valid
environment clearance and submit the details to Project Manager.
6. Contractor shall identify the muck/debris disposal area as per the guidelines provided in
ESMP and get approval of Project Manager.
7. Contractor, in consultation with Project Manager, shall identify the quantum and type of
waste generation from other activities such as electromechanical work, paint work, etc.
and categorize them as hazardous and non-hazardous waste and shall identify authorized
waste collectors accordingly.
8. Contractor shall train, all the staff and labour, for their code of conduct, environment and
safety procedures to be followed and other compliance requirements and submit the
record to Project Manager.
9. Contractor shall make aware, all the staff and labour, about the presence of Grievance
Redressal Mechanism (GRM) and procedure to be followed and submit the record to
Project Manager.
10. Contractor shall ensure that all the vehicles used for the project have valid fitness
certificates and valid PUC (Pollution UnderControl) certificates.
11. Contract shall create a “sense” of environmental/safety awareness within all
construction activities for all personnel to be employed by constant referral to
environmental requirements, implications, and responsibilities.
12. Contractor shall ensure compliance with all the requirement as per ESMP and submit its
compliance strategy in the form of C-ESMP.
Page | 21
a) Environmental Safety
As mentioned in the specification in Section under safety
All issues related to negative environmental impacts of the Contractor's Facilities, Plant and
equipment are to be controlled through:
• The Contractor's self-imposed Quality Assurance Plan
• Regular/periodicinspection of the Contractors Plant and Equipment and producing
Fitness and Pollution Under Control certificates time to time.
1.20 Construction Materials
The standard and specification of different construction Materials are given in detail in
respective Sections of this specification. The contractor shall procure construction materials in
confirmation to the required specification.
i. Before starting any work and during execution (if required), the contractor shall erect
reference Benchmarks, reference lines and check profiles at convenient locations as per the
direction of the Project Manager. The centreline of the dam and the reference line for all
alignments for demarcation purpose shall be laid by dug belling on the ground. The reference
line shall comprise the base line properly dug belled on the ground with the numbered
concrete / masonry R. D. pillars suitably spaced.
ii. The zones of full cutting section, full filling section, partial cutting and filling sections shall be
separated by conspicuous demarcation in the field
The curves stipulated in construction drawings shall be carefully laid in the field by adopting
approved method of curve layout. The curve shall be marked on the ground by fixing pegs at
very close intervals and joining the peg-point by dug-belling to a suitable depth.
The locations of different structures indicated in construction drawing shall also be clearly
marked on the ground along the alignment of the dam. The control structure locations of off-
taking dams shall also be clearly demarcated, so that unnecessary excavation or filling at
these locations can be avoided.
The spoil dumping zones shall clearly be demarcated in the field. These zones should be at
least 2 m. beyond the location of catch water drains.
Page | 22
2
iii. To ensure accuracy in execution of cutting, 3 the dam embankment, spoil banks and the
structures, their layout shall be given in an appropriate manner with pegs and pillars, suitably
placed in relation to outer dimensions of these elements.
iv. All materials and labor for setting out works mentioned in paragraph (i) to paragraph (iii),
as may be required at the various stages of the construction, shall be supplied by the
Contractor at his own cost. The cost of such works shall be deemed to have been included in
the cost of the items in BOQ.
The actual frequencies shall be determined by the Project Managerto suit the nature and variability
of material placed and the rate of fill placement with the objective of ensuring best quality control
and quality construction.
A Central Quality Control Laboratory and field labs with requisite equipments as per requirement
satisfactory to the Project Manager, to be established by the contractor at convenient location
as per direction of Engineer-in charge, along with the required number of mobile testing units
with requisite testing equipment relevant to the tests required to be performed in the Package.
vehicles and personnel regarding testing of material and other test concerning with
Page | 23
specification of work, shall be arranged by the bidder. Tests which cannot be conducted at
central laboratory will have to be got done at ID&R Raipur or at such other laboratory of repute
as directed by Project Manager by the bidder at his own cost. No separate payment will be made
to the bidder on this account by the Department.
O.K. cards shall have to be maintained by contractor for each major activity specified in bid
document, bidder shall get it issued from Project Manager. The O.K. cards contain important
entries/ information during execution of work at all stages and liable to be referred/ perused at a
later stage also.
The O.K. card is condensed form of specifications and essential requirement for achieving
specified workmanship and quality level of output. Each work is sub divided into various
construction activities in proper sequence/order methodology for construction of work.
Besides the location and type of work, the first column of O.K. card is to be filled by the
construction agency (Contractor) by preparing each feature and making it ready for inspection
by project construction engineer who okay through his signatures and then puts up to Q.C.
engineer for his final O.K. If. Q.C. Engineer is not available at site then O.K. given by construction
engineer will be treated as final if anything otherwise is not observed. If anything, otherwise be
found, the O.K. card shall not be signed by him and ask the construction engineer/Agency for
necessary rectification before starting the work.
Subsequently, O.K. card should refer to defects removed, if pointed out previously in O.K. card
and counter reference to the previous check and should be singed of Okayed.
The O.K. cards shall be maintained in triplicate in three colors. After processing through various
levels and entering observations and rectification. O.K. card will be closed at the time of taking
measurement for releasing payment to the contractor. Confirmation regarding rectification of
defects be obtained from Q.C. unit before making payment once in three bills and final bill of
contractor.
Specimen of O.K. cards for various work such as embankment, concrete masonry etc. have been
enclosed herewith. However, O.K. cards other then above if found necessary during course of
execution will be prescribe in consultation with Q.C. unit of W.R. Department. Shall have to be
maintained by the contractor.
Note: All expenditure towards testing before commencement of work, doing work and after
completion to test finished section shall have to be borne by bidder. The expenditure towards
laboratory testing, transportation of samples, vehicles requires for supervision of work etc. shall
have to be borne by bidder. The bidder should quote his rate accordingly. Separate payment for
their activity shall not be payable.
Page | 24
2
5
Page | 25
2.3. O.K.Card for Quality Control of Works
Page | 27
LOAD REGISTER
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Date:
Location:
Page | 28
2
SIEVE ANALYSIS9 COARSE AGGREGATE
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Date:
Location:
Note: Specimen of course aggregate form query & form site shall be preserved as per instruction
of site in charge/ Project Manager.
Page | 29
F.M. TESTING FINE AGGREGATE
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Date:
Location:
S.No. Sieve Size 4.75 2.36 1.18 600 300 150 75 Pan Total
1. Weight
Retained
2. Cumulative Wt.
Retained
3. Cumulative %
Retained
4. Cumulative %
weight Passing
100
Note: Specimen of fine aggregate form query & form site shall be preserved as per instruction of
site in charge/ Project Manager.
Page | 30
3
1 Density by Core Cutter Method
Observation Sheet for Dry Bulk
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Site Description---------------------------------------------------------------.--------------------
Sample No.----------------------------------------------------------------------------------------
Date of Receipt-----------------------------------------------------------------------------------
Date of Testing-----------------------------------------------------------------------------------
1. Container No.
2. Wt. of Container +Moist Soil (gm) W1
3. Wt. of Container +Dry Soil (gm) W2
4. Wt. of Container (gm) W3
5. Wt. of Water (W1- W2) = W4
6. Wt. of Dry Soil (W2- W3) = W5
7. Water Content W = W4 / W5 ratio
1+W
Results:
Comments if any:
Test Performed by:
Checked By: Assistant Engineer
Page | 31
CEMENT REGISTER
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Date -----------------
Location : ---------------------------------------------------------------------
Signat
Ope Bill No. Vehicl Closin
S. Sig. of ure of Signatur
ning R.R.No. e No. g Rema
N Date Receipt Issue Agenc Project e of
Bala Batch & Balan rks
o. y Manag officer
nce No. Type ce
er
Page | 32
3
CUBE CASTING & 3TESTING REGISTER
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Da Location Compressive
te of Sample Strength Dated
S. Speci Mark W/C Sig. of
of Proporti Slu initial
No men Bloc RL on the Rati 7 28 Site in-
cas on mp of QC
. no. k RD Cube o days days charge
tin unit
g
1 2 3 4 5 6 7 8 9 10 11 12 13
Note:
1. Three specimens shall be tested after 7 days and three after 28 days as per frequency
specified in specification.
2. One specimen from each sample shall be preserved duly signed by bidder for his
authorized representative &Project Manageror his authorized representative duly
marked with date.
Page | 33
Page | 34
3
5 REGISTER
INSPECTION
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Page | 35
INSTRUCTION/INSPECTION REGISTER
(for Contractor)
Name of Division: -
Name of work:
Agreement No.
Name of Agency:
Dated initial
Name and
of bidder of is Signature
S. Remark of Designation Compliance Dated
authorize of
No Department of Date made by initial of
representativ accepting
. Officers Department bidder bidder
e as a token officers
Officer
of acceptance
Page | 36
3
7
GENERAL:
1. In the specifications, “as directed” / “Approved” shall be taken to mean “as directed” /
“approved” by the Engineer-in- charge.
2. Wherever a reference to any Indian Standard appears in the specifications, it shall be taken to
mean as a reference to the latest edition of the same in force on the date of agreement.
3. In “Mode of Measurement” in the specifications wherever a dispute arises in the absence
of specific mention of a particular point or aspect, the provisions on these particular points,
or aspects in the relevant Indian Standards shall be referred to.
4. All measurements and computations, unless otherwise specified, shall be carried out
nearest to the following limits : (i) Length, width and depth (height) 0.01 Metre.
(ii) Areas .......................................................................................... 0.01 Sq. Mt.
(iii) Cubic Contents........................................................................... 0.01Cu.Mt.
In recording dimensions of work, the squence of length, width and height (depth) or thickness shall be
followed.
5. The distance which constitutes lead shall be determined along the shortest practical route
arid not necessarily the route actually taken. The decision of the Engineer-in-charge in this
regard shall be taken as final.
6. Where no lead is specified, it shall mean “all leads”.
7. Lift shal1 be measured from plinth level.
8. Upto “floor two level” means actual height of floor (Maxi. 4 M.) upto 3 Mt. above plinth level.
9. Definite particulars covered in the items of work, though not mentioned or elucidated in
it, specifications shall he deemed to be included therein.
10. Reference to specifications of materials as made in the detailed specification of the items
of work is in the form of a designation containing the number of the specification of the
material and prefix ‘M’ e.g. ‘M-5’.
11. Approval to the samples of various materials given by the Engineer-in-charge shall not absolve
the contractor from the responsibility of replacing defective material brought on site or
materials used in the work found defective at a later date. The contractor shall have no claim
to any payment or compensation whatsoever on account of any such materials being rejected
by the Engineer-in-charge.
12. The contract’ rate of the item of work shall be for the work completed in all respects.
13. No collection of materials shall be made before it is got approved from the Engineer-in-charge.
14. Collection of approved materials shall be done at site of work in a systematic manner.
Materials shall be stored in such a manner as to prevent damage, deterioration or
intrusion of foreign matter and to ensure the preservation of their quality and fitness for
the work.
Page | 37
15. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed from
the site of work.
16. No materials shall be stored prior to, during and after execution of a structure in such a way
as to cause or lead to damage or overloading of the various components of the structure.
17. All works shall be carried out in a workmanlike manner as per the best techniques for the
particular item.
18. All tools, templates, machinery and equipment for correct execution of the work as well as for
checking lines, levels, alignment of the works during execution shall be kept in sufficient
numbers and in good working condition on the site of the work.
19. The mode, procedure and manner of execution shall be such that it does not Cause damage or
over loading of me various components of the structure during execution or after completion
of the structure.
20. Special modes of construction not adopted in general Engineering practice, if proposed to be
adopted by the Contractor, shall be considered only if the contractor provides satisfactory
evidence that such special mode of construction is safe, sound and helps in speedy
construction and completion of work to the required strength and quality. Acceptance of
the same by the Engineer-in-charge shall not, however, absolve the contractor of the
responsibility of any adverse effects and consequences of adopting the same in the course of
execution of completion of the work.
21. All installations pertaining to water supply and fixtures thereof as well as drainage lines
and sanitary fittings shall he deemed to be completed only after giving satisfactory tests by
the Contractor.
Page | 38
22. The contractor shall be responsible for observing the rules and regulations imposed under
“Minor Minerals Act”, and such other law’s and rules prescribed by Government from time
to time.
23. All necessary safety measures and precaution (including those laid down in the various
relevnt Indian Standards) shall be taken to ensure the safety of men, materials and
machinery on the works as also of the work itself.
24. The testing charges of all materials shall be borne by the Contractor unless recovery a£ one
percent towards usting charges is separately made.
25. Approval to any of the executed items for the work does not in any way relieve the
contractor of his responsibility for the correctness, soundness and strength of the structure
as per the drawings and specification.
SPECIFICATIONS OF MATERIALS
M-l Water
1.1 Water shall not be salty or brackish and shall be clean, reasonably clear and free from
objectionable quantities of silt and traces of oil and injurious alkalies, salts, organic matter and other
deleterious material which will either weaken the mortar or concrete or cause efflosrescence or
attack the steel in R.C.C: Container for transport, storage and .handling of water shall be clean.
Water shall conform to the standards specified in I.S. 456-1978.
1.2 If required by Engineer-in-charge it shall be tested by comparison with distilled water.
Comparision shall be made by means of standard cement tests for soundness, time of setting and
mortar strength as specified in I.S. 269-1976. Any indication of unsoundness, change in time of
setting by 30 minutes or more or decrease of more than 10 percent in strength of mortar
prepared with water sample when compared with the results obtained with mortar prepared
with distilled water shall be sufficient cause for rejection of water under test.
1.3 Water for curing mortar, concrete or masonary should not he too acidic or too alkaline. It shall
.he free of elements which significantly affect the hydration relation or otherwise interfere with
the hardening of concrete during curing or those which produce, objectionable stains or other
unsightly deposits on concrete or mortar surfaces.
1.4 Hard and bitter water shall not be used for curing.
1.5 Potable water will be generally found suitable for curing mortar or concrete.
M-2. Lime
2.1 Lime shall be hydraulic lime as per I.S. 712-1973. Necessary test shall be carried out as per I.S.
6,932 (Parts I to X) 1973.
2.2 The following field tests for limes are-to be carried out:
(1) A very rough idea can be formed about the type of lime by its visual examination i.e. fat lime
bears pure white colour, lime in form of porous lumps of dirty while colour indicates quick lime, and
solid lumps are the unburnt lime stone.
(2) Acid tests for determining the carbonate content in lime. Excessive amount of impurities and
rough determination of class of lime.
2.3 Storage shall comply with I.S. 712-1973. The slaked lime, if stored, shall be kept in a weather proof
Page | 4
5
and damp-proof shed with impervious-floor and sides to protect it against rain, moisture, weather
and extraneous materials mixing with it. All lime that has been damaged in any way shall be
rejected and all rejected materials shall be removed from site of work.
2.4 Field testing shall be done according to I.S. 1624- 1974 to show the acceptability of materials.
M-3. Cement
3.1 Cement shall be ordinary portland slag cement as per I.S. 269-1976 or Portland slag cement as per
I.S. 455-1976.
M-4. .White Cement
4.1 The white cement shall conform to I.S.,80412”-E 1978.
M-5. Coloured Cement
5.1 Coloured cement shall be with white or gray portland cement as specified in the item of the work.
5.2 The pigments used for coloured cement shall be of approved quality-and shall not exceed 10% of
cement used in the Mix, The mixture of pigment shall be properly grounded to have a uniform
colour and shade. The pigments shall have such properties to provide-for dutability under
exposure to sunlight and weather.
5.3 The pigment shall have the property such that it is neither affected by the cement nor detrimental
to it.
MS. Sand
6.1 . Sand shall be natural sand, clean, well graded, hard strong durable and gritty particle free from
injurious-amounts of dust clay, kankar nodules, soft or flaky particles Shale, alkali, salts-organic
matter, loam, mica or other deleterious sunstance and shall be got approved, from the Engineer-in-
charge. The sand shall not contain more than 8 percent of silt as determined by field test. If
necessary the sand shall be washed to make it clean.
6.2 Coarse Sand :
The fineness, modulus of coarse sand shall not be less than 2.5 and shall not exceed 3.00. The
sieve analysis of coarse shall be as under:
Page | 5
M-7. Stone Dust
7.1. This shall be obtained from crushing hard black trap or equivalent.. It shall not contain- more
than 8% of silt as, determined by field test with measuring cylinder. The method of determining silt
contents by field test is given as under:
7.2. A sample of stone dust to be tested shall be placed without drying in 200mm. measuring
cylinder. The quantity of . the sample shall be such that it fills the cylinder upto 100 mm. mark. The
clean water shall be added upto 150 mm. mark. The mixture shall be stirred vigorously and the
content allowed to settle for 3 hours.
7.3 The height of sill visible as settled layer above the stone dust shall be expressed as percentage
of the height of the stone dust below. The stone dust containing more than 8% silt shall be washed
so as to bring the silt content within the allowable limit.
7.4 The fineness modulus of stone dust shall not be less than 1.80.
M-8 Stone Grit
8.1 Grit shall consist of crushed or broken stone and be hard strong, dense, durable, clean, of proper
gradation and free from skin or coating likely to prevent adhesion of mortar Grit shall generally be
cubical in shape and as far as possible flaky elongated pieces shall be avoided. It shall generality
comply with the provisions of I.S. 383-1970. Unless special stone of particular quarries is
mentioned, grit shall be obtained from the best black trap or equivalent hard stone as approved
by the Engineer-in-charge. The grit shall have no deleterious reaction with cement.
8.2 The grit shall conform to the following gradation as per sieve analysis :
Page | 6
7
used for preparation of lime mortar. The slaked lime shall be placed in the mill in an-even layer .and
ground for .the 180 revolution’s with a sufficient water. Water shall be added as required during
grinding (care being taken not to add more water) that will bring the mixed material to-a
consistency-of stiff paste. Thoroughly wetted sand shall then be added evenly and the mixture
ground for another 180 revolutions.
10.4 Storage:
10.4.1. Mortar shall always be kept damp, protected from san and rain till used up, covering it
by tarpaulin or open sheds.
10.5. Use :
10.5.1. All mortar shall be used as soon as possible after grinding. It should be used oft the day en
which it is prepared. But in no case mortar made earlier than 36 hours shall be permitted for use.
M-11 Cement Mortar :
11.1. Water shall conform to specification M-l. Cement shall conform to specification M-3. Sand shall
conform to M-6.
11.2. Proportion of Mix :
1-1.2.1. Cement and sand shall be mixed to specified proportion, sand being measured by measuring
boxes. The proportion of cement will be by volume on the basis of 50 Kg./Bag of cement being equal
to 0.0342 Cu.m. The mortar may be hand mixed or machine mixed as directed.
11.3. Preparation of mortar:
11.3.1 In hand mixed mortar cement and sand in the specified proportions shall be thoroughly mixed
dry on a clean Impervious platform by turning over at least 6 times or more till a homogenous
mixture of uniform colour is obtained. Mixing platform shall be so arranged that no deleterious
extraneous material shall get mixed with mortar-or mortar shall flow out. While mixing, the water
shall be gradually added and thoroughly-mixed to form a stiff plastic mass of uniform colour so that
each particle of sand shall be completely covered with a film of wet cement. The water cement
ratio shall be adopted as directed.
11.3.2 The mortar so prepared shall be used within 30 minutes of adding water. .Only such quantity
Page | 7
of mortar shall be prepared as can be used within 30 minutes.
M-12. Stone Coares Aggregate for Nominal Mix Concrete
12.1 Coarse aggregate shall be machine crushed stone of black trap or equivalent and be hard,
strong, dense, durable, clean and free from skin and coating likely to prevent proper adhesion of
mortar.
12.2 The aggregate shall generally the cubical in .shape. Unless special stones of particular quarries
arc mentioned aggregates shall be machine crushed from the best black trap or equivalent hard
stone as approved. Aggregate shall have
no deleterious reaction with cement. The size of the coarse aggregate for plain-cement concrete and
ordinary reinforced cement concrete shall generally be as per the table given below. “However in
case of reinforced cement concrete the maximum limit may be restricted to 6 mm. less than the
minimum lateral clear distance between bars or 6 mm. less than the cover, whichever is smaller.
Page | 8
TABLE
I.S. Sieve Percentage passing for I.S. Sieve Percentage passing for
Designati
Designatio single sized aggregates single sized aggregates
on
n of Nominalsize. of Nominalsize.
40 20mm 16 40m 20m 16m
mm mm m m m
80 — — — 12.5 mm. — — —
mm.
63 100 — 10 0.5 0.02 0.30
mm. mm.
40 85- 100 — 4.75 mm. — 0.5 0.5
mm. 100
20 0-20 85-100 100 2.35m — — —
mm. m
16 — — 85-
mm. 100
Note : This percentage may be varied .some what by Engineer- in-charge when considered necessary
for obtaining better density and strength of concrete.
12.3 The grading test shall be taken in the beginning and at the change of source of materials. The
necessary test indicated in
I.S. 383-1970 and I.S, 456-1978 shall have to be carried out to ensure the acceptability. The aggregates
shall be stored separately and handled in such a manner as to prevent the intermixing of different
aggregates, If the aggregates are covered will dust they shall be washed with water to make them
clean.
M-13. Blak Trap or Equivalent Hard Stone Coares.
13.1. Aggregate For Design Mix Concrete : Coarse aggregate shall be of machine crushed stone of
black trap or equivalent hard stone and be hard strong dense, durable clean and free from skin
and coating likely to prevent proper adhesion of mortar.
13.2. The aggregates shall generally be cubical in shape. Unless special stones of particular quarries
are mentioned, aggregate shall be machine crushed from4he best, black trap or equivalent hard
stones as approved. Aggregate shall have no deleterious reaction with cement.
13.3. The necessary tests indicated in I.S. 383-1970 and I.S. 456-1978 shall have to the carried oat
to. ensure the acceptability of the material.
13.4. If aggregate is covered with dust it shall be washed with water to make it clean..
M-14. Brick Bats Aggregate
14.1. Brick bat aggregate shall be broken from well burnt or slightly over burnt and dense brick. It
shall be homogeneous in texture roughtly cubical in shape, clean and free from dirt of any other
foreign material. The brick bats shall be of 40 mm. to 50 mm. size unless otherwise specified in
the item. The under burnt of over burnt brick bats shall not be allowed.
14.2. The brick’ bats shall be measured by volume by suitable boxes or as directed.
Page | 6
7
M-15. Brick
15.1. The bricks shall be hand or machine moulded and made from suitable soils and klin-burnt.
They shall be free Iron crack and nodules of free lime. They shall have smooth rectangular faces
with sharp corners and shall be of uniform colour.
The bricks shall be moulded with a frog of 100mm. x 40 mm. and 10mm. to 20 mm. deep on one of its
flat sides. The bricks shall not break when thrown oft the ground from a height of 600 mm.
15.2. The size of modular bricks shall be 190 mm. x 90 mm. x 90 mm.
15.3. The size of the conventional bricks shall be as under :
Page | 7
The stones shall be obtained only from the approved quarry and shall be hard, sound, durable and
free from defects like cavities, cracks, sand holes, flaws, injurious veins, patches of loose or soft
materials etc. and weathered portions and other structural defects or imperfections tending to affect
their soundness and strength. The stone with round surface shall not be used. The percentage of
water absorption shall not be more than 5% of dry weight, when tested in accordance , with I.S. 1134-
1974. The minimum crushing strength of the stone shall be 200 Kg./Sq.Cm. unless otherwise specified.
16.2. The samples of the stone to be used shall be got approved before the work is started.
16.3. The Khanki facing stone shall be dressed by chisel as specified in the item for khanki facing in
required shape and size. The face of stone shall be so dressed that the bushing on the exposed
face shall not project by more than 40 mm. from the general wall surface and on face to be
plastered it shall not project by more than 19 mm. nor shall it have depressions more than 10 mm.
from the average wall surface.
M-17. Laterite stone
17.1 Laterite stone shall be obtained from the approved quarry. It shall be compacted in texture,
sound, durable and free from soft patchs. It shall have a minimum crushing strength of 100
Kg./Sq.Cm. in its dry condition. It shall not absorb water more than 20% of its own weight, when
immersed for 24 hours in water. After quarrying the stone shall be allowed to weather f6r some time
before using in work.
17.2. The stone shall be dressed into regular rectangular blocks so that all faces are free from -
waviness and uneveness, edges true and square.
17.3 Those types of stone in which white clay occure, should not be used.
17.4 Special corner stones shall be provided where so directed.
M-18. Mild Steel Bars
18.1 Mild steel bars reinforcement for R.C.C. work shall conform to I.S, 432 (Part-II) 1966 and §hail be
of tested quality. It shall also comply with relevant part of I.S. 456- 1978.
18.2 All the reinforcement shall be clean and free from dirt, paint, grease, mill scale or loose or thick
rust at the time of placing.
18.3 For the purpose of payment, the bar shall be measured correct upto 100 mm. length and
weight payable worked out at the rate specified below :
Page | 9
21.2. The use of black wire will be permitted for binding reinforcement bars, ft shall be free from
rust, ojl paint, grease, loose mill scale or any other undesirable coating which may prevent adhesion
of cement mortar.
M-22. Structural Steel
22.1. All structural steel shall conform to I.S. 226-1965. The steel shall be free from the defects
mentioned in I.S. 226- 1975 and shall have a smooth finish. The material shall be free from loose mill
scale, rust pits or other defects affecting the strength and durability. Rivet bars shall conform to
I.S. 1148-1973.
22.2, When the steel is supplied by the Contractor test certificates of the manufacturers shall be
obtained according to I.S. 226-1975 and other relevant Indian Standards.
M-23. Galvanised Iron Sheets
23.1 The galvanised iron sheets shall be plain or corrugated .sheets of specified in item. The G.I.
Sheets all conform to I.S 277-1977. The sheets shall be undamaged in carriage and handling either by
rubbing off of zinc coating or otherwise they shall have clean and bright surface and shall be free
from dents, holes, rust or white powdery deposit.
23.2. The length and width Of G.I. sheet shall be as directed as per site condition.
M-23-A; G.I. Valleys gutter ridges
23.A.1. The G.I. ridges and hips shall be of plain galvanised sheets class-3 of the thickness as specified
item. These shall be 600 mm. in width and properly bent up to shape without damage to the sheets
in process of bending.
23.A.2. Valleys gutters and flashings shall also be galvanised sheet of thickness as specific in item,
Vallev’s shall be 900 mm. wide overall and fishing shall be 380 mm. wide overall. They shall be bent
(o the required shape without damage to the sheet in (he process of bending.
M-24. Asbestos Cement Sheets
24.1. Asbestos cement sheets plain, corrugated or semi corrugated shall conform to I.S. 459-1970.
The thickness of fee sheets shall be as specified in the item. The shells shall be free front all defects
such as cracks, holes deformities, chipped edges or otherwise damaged.
24.2. Ridged-& Hips
24.2.1. Ridges and hips shall be of same thickness at that of A.C. sheets. The types of ridges suitable
for the type of sheets and location’s.
24.2.2. Other accessories to be used in roof such as flashing pieces, caves filler pieces, valley gutters,
north light and ventilator curves, barge boards etc. shall be standard manufacture and shall be
suitable for the type of sheets and location. M-25. Mangalore Pattern Roof Tiles
25.1. The Mangalore pattern tiles shall conform to I.S. 654-1972 for Class AA or Class ‘A’ type as
specified in item. Samples of the tiles to be provided shall be got approved from the engineer in
charge. Necessary tests shall be carried out as directed.
M-26. Shuttering
26.1. The shuttering shall be either of Wooden planking of 30 mm. minimum thickness with or
without steel lining or of steel plates stiffened by steel angles. The shuttering shall be supported on
battens and beams and props of vertical ballies properly cross braced together so as to make the
Page | 8
9
centering rigid. In places of bullie props, brick pillar of adequate section built in mud mortar may 6e
used.
26.2. The form work shall be sufficiently strong and shall have camber, so that it assumes correct
shape after deposition of the concrete and shall be able to resist forces caused by vibration of live
load of men working over it and other incidental loads associated with it. The shuttering snail
have smooth and even surface and its joints shall not permit leakage of cement grout.
26.3. If at any stage of work during or after placing concrete in the structure, the form work sags or
bulges out beyond the required shape of the structure, the concrete shall be removed and work
redone with fresh concrete and adequately rigid form work. The complete form work shall be got
inspected by and got approved from the Engineer-in-charge, before the reinforcement bars are
placed in position.
26.4. The props shall consist of bullies having 100 mm. minimum diameter measured, at mix length
and 80 mm, at thin end and shall be placed as per design requirement. These shall rest squarely on
wooden sole plates 40 mm; thick and minimum bearing are if 0.10 sq. m. laid on sufficiently hard
base.
26.5. Double wedges shall further be provided between the sole plate and the wooden props so as
to facilitate tightening and easing of shuttering” without jerking thei concrete.
Page | 9
26.6 The. timber used in shuttering shall not be so dry as to absorb water from concrete and swell or
bulge nor so green or wet as to shrink after erection. The timber shall be properly sawn and planed
on the sides and surface coming in contact with concrete. Wooden form work with metal sheet
lining or steel plates stiffened by steel angles shall be permitted.
26.7 As far as practicable, clamps shall be used to hold the forms together and use of nails and spikes
avoided.
26.8 The surface of timber shuttering that would come in contact with concrete shall be well wetted
and coated with soap solution before the concreting is done. Alternatively coat of raw linseed oil or
oil of approved manufacturer may be applied in place of soap solution. In case of steel shuttering
either soap solution or raw linseed oil shall be applied after thoroughly cleaning the surface. Under
no circumstances black or burnt oil shall be permitted.
26.9 The shuttering for beams and slab’s shall have camber of 4 mm. per metre (1 in 250) or as
directed by the Engineer-in- charge so as to offset the subsequent deflection. For cantilevers, the
camber at free end shall be 1/50 of the projected length or as directed by the Engineer-in-Charge.
M-27. Expansion joints- Premoulded filter:
27.1 .The item provides for expansion joints in R.C.C. frame structures for internal joints, as well as
exposed pints, with the use of premoulded bituminious joint filler.
27.2. Premoulded bituminous joint filler, i.e. performed strip of expansion joint filler shall not get
deformed or broken by twisting, bending or other handling when exposed to atmospheric condition.
Pieces of joint filler that have been damaged shall be rejected.
27.3 Thickness of the pro-moulded joint filler shall be 25 mm. unless otherwise specified.
27.4 Premoulded bituminuous joint filler shall conform to I.S. 1838-1961
M-28. Expansion joints-Copper strips & hold fasts:
28.1 The item provide for expansion joints in R.C.C. frame structure for internal joint as well as for
exposed joints with the use of necessary copper strip and holdfasts.
28.2 Copper sheet shall be of 1.25 mm. thick and of 1.25 mm. width with the ‘U’ shape in the middle.
Copper strip shall have holdfast of 3 mm. diameter copper rod fixed to the plate soldered on strip at
intervals of about 30 cm. or as shown in the drawing or as directed. The width” of each flange
(horizontal side) of the copper plate to be embedded in the concrete work shall be 25 mm. Depth of
‘U’ to be provied in the expasion joint, in the copper plate shall be of 25 mm.
M-29. Teak wood:
29.1 The leak wood shall be of good quality as required for the item to be executed. When the kind
of wood is not specifically mentioned, good Indian teak wood as approved shall be used.
29.2 Teak wood shall generally be free from large, loose, dead or cluster knots, flaws, shakes, warps,
twists bends, or any other-defects. H shall generally be uniform in substance and of stright fibres as
far as possible. It shall be free from rot, decay, harmful fungi and other defects of harmful nature
which will affect the strength durability of its usefulness for the purpose for which it is required.
The colour shall be uniform as far as possible. Any effort like painting, using any adhesive or resins
materials made to hide the defects shall render the pieces liable to rejection by the Engineer in-
charge.
Page | 10
1
1
293. All scantlings; planks etc. shall be sawn in straight lines and planes in the direction of grains and of
uniform thickness.
29.4. The tolerances in the dimensions shall be allowed at the rate of 1.5 mm. per face to be planed.
29.5. First class teak wood : 29.5.1. First clalss teak wood shall have no individual hard and sound
knots, more than 6 sq. cm. size and the aggregate area of such knots shall not be more than 1% of
area of piece. The timber shall be closed grained.
29.6 Second Class Teak wood: 29.6.1. No individual hard and sound knots shall be more than 15 sq.
cms. in size and aggregate area of such knots shall not exceed 2% of the area of piece.
M-29. A. Non-teak wood:
The non teak wood shall be chemically treated, seasoned as per IS Specifications and of good quality.
The type of wood shall be got approved Before collecting the same on site. Fabrication of wooden
members shall be started only after approval.
For this purpose wood of Bio, Kalali, Siras, Bchda, Jamun, Sisoo will be used for door frames where as
only Kalali, Siras, Halda, Kalam etc, will be permitted for shutters after proper seasoning and chemical
treatment.
The non-teak wood shall be-free from large, loose, dead of cluster knots, flows shakes, warps, bends
or any other defect. It Pigtail-be uniform in substance and of straight fibers as far as possible. It shall
be free from rots, decay harmful fungi and other
Page | 11
10
defects of nature which effect the strength, durability or it usefulness for the purpose for which it is
required. The colour of wood shall be uniform as far as possible. The scantlings planks etc. shall be
sawn in straight lines and planes in the direction of grain and uniform thickness.
The department will use the Agency to produce certificate from Forest Department in event of
Dispute and the decision of the Department shall be final and binding to me contractor.
The tolerance in the dimension shall be allowed as 1.5 mm. per face to be planed.
M-30. Wooden flush door shutters (solid core):
30.1. The solid core type flush door shutters shall be decorative or non-decorative type as specified in
the drawing. The-size and thickness of the shutter shall be as specified in drawings or as directed.
The limber, species for core shall be used as per
I.S. 2202 - (Part-I) 1980. The timber shall be free from decay and insect attack. Knots and knot holes
less than half the width of cross-section of the members in which they occur may be permitted. Pitch
pockets, pitch streaks and harmless pin holes shall be permissible except in the exposed edges of the
core members. The commercial plywood, cross-bands shall conform to I.S. 303-1275.
30.2. The face panel of the shutters shall be formed by gluing by the hot press process on both face
of the core with either ply wood or cross-bands and face veneers. The hopping rebating opening of
glazing Venetian etc. shall be provided if specified in the drawing.
30.3. All edges of the door shutters shall be square. The shutters shall be free from twist or warp in
its plane. Both faces of the shutters shall be sand papered to smooth even texture.
30.4. The shutters shall be tested for
(1) End immersion test.: The test shall be carried out as per l.S. 2202 (part-I) 1980. There shall be no
delamination at the end of the test.
(2) Knife Test: The face panel when tested in accordance with l.S. 1659-1979 shall pass the test.
(3) Glue adhesion test :The flush door shall be tested for glue adhesive test in .accordance with
KS..2202 (Pan 4) 1930, The shutters shall be considered to have passed the test if no delamination
occurs in the-glue lines in the plywood and if no single delamination more than 80 mm. in length
and more than 3 mm. in depth has occnred in the assembly glue lines between the . plywood face
and the style and rail. Delamination at the comer shall be measured continuously around the comer.
Delamination at the knots, knot holes and other permissible wood defects shall not be considered
in assessing the sample.
30.5. The tolerance in size of solid core type flush door
shall be as under. In Normal thickness ±1.2 mm. In
Normal height ± 3 mm.
30.6. The thick of the shutters .shall be uniform throughout with a permissible variation of not more
than 0.8 mm. when
measured at any two points.
Page | 12
M-31. Aluminium doors, windows, ventilators
31.1 Aluminium alloy used in the manufacture of extruded window sections shall conform to I.S.
designation HEA-WP of I.S.: 733-3975 and also to I.S. Designation WVG-WP of I.S. 1285-1975. The
Section shall be as specified in the drawing and design. The fabrication shall be done as directed.
31.2. The hinges shall be cast or extruded aluminium hinge of same type as in window but of large size.
313. The hinges shall normally be of 50 mm. projecting type. Non-projecting type of hinges may also
be used if directed. The handles of door shall be of specified design. A suitable lock for the door
operatable either from outside or inside shall be provided. In double shutter door, the first closing
shutter shall have concealed aluminium alloy bolt at top and bottom.
M-32. Rolling Shutters:
32.1. The rolling shutters shall conform to 1 .S. 6248-1979. Rolling shutters shall be supplied of
specified type with accessories. The size of the rolling shutters shall be specified in the drawings.
The shutters shall be constructed with interlocking lath sections formed from cold rolled steel strips
not less than 0.9 mm. thick and 80 mm: wide for shutters upto 3.5mm., width not less than L25 mm.
thick and 80 mm; wide for shutters 3.5 mm in width and at above unless otherwise specified.
32.2. Guide channels shall be of mild steel deep channel section and of rolled pressed or built up
(fabricated) joint construction. The thickness of sheet used shall not be less than 3.15mm.
32.3. Hood covers shall be made of M.S. Sheets not less than 0 92 mm. thickness. For shutters having
width 3.5 Meter and
Page | 13
11
above, the thickness of M.S. Sheet for the hood cover shall be not less than 1.25 mm.
32.4. The spring shall be of best quality and shall be manufactured from tested high tensile spring
steel wire or strip of adequate strength to balance the shutters in all position. The spring pipe shaft
etc. shall be supported on strong M.S. or malleable C.I. brackets. The brackets shall be fixed on or
under the lintel as specified with raw plugs and screws bolts etc.
32.5. The roiling shutters shall be of self rolling type up to 8 Sq. in. clear area without ball bearing
and up to 12 sq. m. clear area with ball bearing. If the rolling shutters are larger, then gear
operated type shutters shall be used.
32.6. The locking arrangement shall be provided at the bottom of shutter at both ends. The
shutters shall be opened from outside.
32.7. The shutters shall be completed with door suspention shafts, locking arrangements, pulling
hooks, handles and other accessories.
M-33. Collapsible. Steel-Gate:
33.1. The collapsible steel gate shall be in one or two leaves and size as per approved drawings or as
specified. The gate shall be fabricated from best quality mild steel channels, flats etc. Either steel
pulleys or ball bearings shall be provided in every double channel. Unless otherwise specified the
particulars of collapsible gate shall be as under :
(a) Pickets: These shall be of 20 mm. M.S., channels of heavy sections unless otherwise shown on
drawings. The distance centre to centre of pickets shall be 12 cms. with an opening of 10 cms.
(b).Pivoted M.S. flats shall be 20 mm x 6 mm.
(c) Top and bottom guides shall be from tee or flat iron of approved size.
(d) The fittings like stoppers, fixing hold fasts, locking cleats, brass handles and cast iron rollers
shall be of approved design and size.
M-34. Welded Steel Wire Fabric :
34.1. Welded steel wire fabric for general purpose shall be manufactured from cold drawn steel wire
“as drawn” or galvanised steel conforming to I.S. 226-1975 with longitudinal and transverse wire
securely connected at every intersection by a process of electrical resistance welding and conforming
to I.S. 4948-1974. It shall be fabricated and finished in workmanlike manner and shall be free from
injurious detects and shall be rustproof. The type of mesh shall be oblong or square as directed. The
mesh sizes and size of wire for square as well as oblong welded steel wire fabric shall be as directed
The steel wire fabric in panels shall be in one whole piece in each panel as far as stock size permit.
M-35. Expanded Metal Sheets :
35.1. The expanded metal sheets shall be free from flaws, joints, broken strands, laminations and
other harmful surface. Expanded metal steel sheet shall conform to I.S. 412-1975, except that blank
sheets need not be with guaranteed mechanical properties. The size of the diamond mesh of
expended metal and dimensions of strands (width and thickness) shall be as specified. The tolerance
in nominal weight of expanded metal sheets shall be of + 10 percent.
35.2 Expanded metal in pannels shall be in one whole piece panel each as far as stock size permit. The
expanded metal sheets shall be coated with suitable protective coating to prevent corrosion.
M-36. Mild Steel Wire (Wire Gauze Jali) :
36.1 Mild steel wire, may be galvanised, as indicated. All finished steel wire shall be well cleanly drawn
to !he dimensions and-size of wire as specified in item. The wire shall be sound, free from splits,
Page | 11
surface flaws, rough jagfied and imperfect edges and other harmful surface defects and shall
conform to I.S. 280-1978.
M-37. Plywood :
37.1. The plywood for general purpose shall conform I:S. 303- 1975.
Plywood is made by cementing together thin boards or sheets of wood into panels. There are always
an odd number of layers 3, 5,7, 9 ply etc. The plies are placed so that grain of each layer is right angle
to the grain in the adjacent layer.
37.2. The chief advantages of plywood over a signal board of the same thickness is the more uniform
strength of the plywood, along the length and width of the plywood and greater resistance to
cracking and splitting with change in moisture content,
37.3. Usually synthetic resins are used for gluing, pherolic resins are usually cured in a hot press
which compresses and simultaneously heats the plies between hot plates which maintain a
temperature of 90 degree. C. to 140 degree C. and a pressure of 11 to 14 Kg/Sq. Cm. on the wood.
The times of healing may be anything from 2 to 60 minutes depending upon thickness.
Page | 12
13
37.4. When water glue are used, the wood absorbs so much water that the finished plywood must
be dried carefully. When synthetic resins are use as adhesive finished plywood must be exposed to
an atmosphere of controlled humidity until the proper amount of moisture, has been absorbed.
37.5. According to I.S. 303-1975 the plywood for general purpose shall be of three grades namely
BWR, WWR and CWR, depending upon the adhesives used for bonding and veneers, and it will be
farther classified into six types namely AA. AB. AC, BB, BC and C,C based on the quality of the two
faces, each face being of three finds namely, A, B. and C. After pressing, the finished ply wood
should be reconditioned to a moisture content not less than 8 percent and not more than 16
percent.
37.6. Thickness of ply wood Boards :
TABLE
M.38. Glass:
38.1 All glass shall be of the best quality, free from specks, bubbles, smokes, veins, air holes blisters
and other defects. The kind of glass to be used shall be mentioned in the item or specification or in
the special provisions or as shown in detailed drawings. Thickness of glass panes shall be uniform.
The specifications of different kinds of glass shall be as under: 38.2.Sheet Glass:
38.2.1. In absence of any specified thickness or weight in the item or detailed specifications of the
item of work, sheet glass shall be weighing 73 Kg/Sq.m. for panes upto 600 mm x 600 mm.
38.2.2. For panes larger than 600 mm. x 600 mm. and upto 800 mm. x 800 mm. the glass weighing not
less than 8.75 Kg/Sq
m. shall be used. For bigger panes upto 900 mm. x 900 mm. glass weighing not less than 11.25 Kg/Sq. m.
shall be used.
38.2.3. Sheet glass shall be paten, flattened glass of best quality and for glazing and framing
purposes shall conform to I.S.: 1761 -1960. Sheet glass of the specified colours shall be used, if so
shown on detailed drawings or so specified. For important buildings and for panes with any
dimension over 900 mm. plate glass of specified thickness shall be used.
38.3. Plate Glass. 38.3.1. When plat, glass is specified, it shall be ‘Polished patent plate glass’ of best
quality. It shall have both the surface ground flat and parallel and polished to obtain clear
undistrubed vision and reflection. The plate glass shall be of the thickness mentioned in the item or
as shown in the detailed drawing or as specified. In absence of any specified thickness the thickness
Page | 13
of plate glass to be supplied shall be 6mm and a tolerance of 0.20 mm. shall be admissible.
38.4. Obscured Glass : 38.4.1. This type of glass transmits light so that vision is partially or almost
completely obscured. Glass shall be plain rolled, figured, ribbed or fluted or frosted glass as may be
specified as required. The thickness and type of glass shall be as per details on drawings or at
specified or as directed.
38.5. Wired Glass: 38.5.1. Glass shall be with wire netting embedded in a sheet of plate glass
electrically welded 13 mm. Georgian square mesh may be used. Thickness of glass shah riot be less
than 6 mm. Wired glass shall be of type and thickness as specified.
M-39. Acrylic Sheets:
39.1. Acrylic sheet shall be of thickness as specified in the item and of an specified shape and size as
the case may be. Panels may be flat or curved. It should be light in weight. It shall be colourless or
coloured or opaque as specified in the item. Colourless sheet shall be as transparent as the finest
optical glass, its light transmission rate shall be about 95%. Transparency shall not bef affected for the
sheets of larger thickness. It shall be extremely .resistant to sunlight, weather and low temperatures.
It shall not show any significant yellowing or change in physical properties or loss of light
transmission over a longer period of use. The sheet Shall be impact resistant also. Sheets should be
available in complete range of standard transparent, translucent and opaque colours. Sheets shall be
of such quality that they can be cut bent and jointed as desired. Solution for the joints shall be used as
per the requirement of manufacturer.
Page | 14
15
M-40. Particle board : 40.1. The particle boards used for face panels shall be of best quality free
from any defects. The particle boards shall be made with phenoimaldehyde adhesive. The particle
boards shall conform to I.S. : 3087-1965. “Specification for wood particle board for general
purpose”. The size and the thickness shall be as indicated.
M-41. Expanded polystyrene of framed styroper slabs :41.1. The expanded polystytrene ceiling
boards and files shall be of approved make and shall be of size, thickness, finish and colour as
indicated. It shall be of high density and suitable for use as insulating material. The insulating material
shall be like slab of Thermocole etc.
M-42. Resin bonded fibre glass : 42.1 The resin bonded fibre glass tiles, or rolls shall be of approved
make and shall be of sizes, thickness and finish as indicated.
42.2. For test of Minerral wool thermal insulation Blanket I.S.: 3144/1965 shall be followed.
42.3. Insulation wool blanket shall be with following coverings on one or both sides as indicated.
(1) Bituminised hessain Kraft paper suitable for use in position where moisture has to be excluded.
(2) Hessian cloth or Kraft paper for keeping out dust.
(3) G.I. wire netting, suitable for surfaces to be plastered over.
M-43. Fixtures and fastenings :
43.1. General:
43.1.1. The fixtures and fastenings, that is, butt, hinges, tee and strap hinges, sliding door bolts,
tower bolts, door latch, bath room latch, handles, door stoppers, casement window fasteners,
casement stays and ventilators catch shall be made of the metal as specified in the item or its
specifications.
43.1.2. They shall be of iron, brags, aluminium, chromium plated iron, chromium plated brass, copper
oxidised iron, copper oxidised brass or anodised aluminium as specified.
43.1.3. The fixtures shall be heavy, medium or light type. The fixtures and fastenings shall be smooth
finished and shall be such as will ensure ease of operation.
43.1.4. The samples of fixtures and fastenings shall be got approved as regards quality and shape
before providing them in position.
43.1.5. Brass and anodised aluminium fixtures and fastenings shall be bright finished.
43.2. Holdfasts: 43.2.1. Holdfasts shall be made from mild steel flat 30 cm. length and one of the
holdfasts shall be bent at right angle and two nos. of 6 mm. diameter holes shall be made in it for
fixing it to the Farme with screws. At the other end, the holdfast shall be forked and bent at right
angles in opposite directions.
43.2. Butt hinges:
43.3.1. Railway standard heavy type butt hinges shall be used when so specified. 43.3.2. Tee and strap
hinges shall be manufactured from M.S. Sheet.
43.4. Siding door bolts (Aldrops): 43.4.1. The aldrops as specified in the item shall be used and shall be
got approved.
43.5. Tower bolts (Barrel Type): 43.5.1. Tower bolts as specified in the item shall be used and shall be
Page | 15
got approved.
43.6. Door latch : 43.6.1. The size of door latch shall be taken as the length of latch.
43.7. Bathroom Latch : 43.7.1. Bathroom latch shall be similar to tower bolt.
43.8. Handle: The size of the handles shall be determined by the inside grip length of the handles.
Handles shall have a base plate of length 50 mm. more than the size of the handle.
43.9. Door Stoppers: 43.9.1. Door stoppers shall be either floor door stopper type or door catch type.
Floor stopper shall be of overall size as specified and shall have a rubber cushion.
43.10. Door Catch : 43.10.1. Door catch shall be fixed at a height of about 900 mm. from the floor
level so that one part of the catch is fitted on the inside of the shutter and the other part is fixed in
the wall with necessary wooden plug arrangements for appropriate fixity. The catch shall be fixed
20 mm. inside the face of the door for easy operation of catch.
43.11. Wooden Door Stop with hinges : 43.11.1. Wooden door stop of size 100 mm x 60 mm x 40 mm
shall be fixed on the door frame with a hinge of 75 mm size and at a height of 900 mm. from the
floor level. The wooden door stop shall be provided with 3 coats of approved oil paint.
43.12. Casement window Fastener: Casement window fastener for single leaf window shutter shall
be left or right handled
Page | 16
17
as directed.
43.13. Casement stays (Straight Peg Stay) :43.13.1. The stays shall be made from a channel section
having three holes at appropriate position so that the window can be opened either fully or
partically as directed. Size of the stay shall be 250 mm. to 300 mm. as directed.
43.14. Ventilator Catch: 43.14.1. The pattern and shape of the catch shall be as approved.
43.15. Pivot: 43.15.1. The base and socket plate shall be made from minimum 3 mm. thick plate and
projected pivot shall not be less than 12 mm. diameter and 12 mm. length and shall be firmly riveted
to the base plate in case of iron pivot and in single piece base plate in the case of brass pivot.
M-44.
Paints: 44.1 (A) Oil paints :
44.1.1. Oil paints shall be of the specified colour and shade, and as approved. The ready mixed paints
shall only be used. However, if ready mixed paint or specific shade or tint is not available, white
ready mixed paint with approved stainer will be allowed. In such a ease, the contractor shall ensure
that the shade of the paint so allowed shall be uniform.
44.1.2. All the paints shall meet with following general requirements :
(i) Paint shall not show excessive setting in a freshly opened full can and shall easily be redispressed
with a paddle to a smooth homogeneous state. The paint shall show no curdling, livering, caking or
colour separation and shall be free from lumps and skins.
(ii) The paint as received shall brush easily, possess good leverling properties and show no running or
sagging tendencies.
(iii) The paint shall not skin within 48 hours in a three quarters filled closed container.
(iv) The paint shall dry to a smooth uniform finish free from roughness, grit, unevenness and other
imperfections.
44.1.3. Ready mixed paint shall be used exactly as received from the manufacturers and generally
according to their instructions and without any admixtures whatsoever.
44.2. (B) Enamel Paints:
44.2.1. The enamel paint shall satisfy in general requirements as mentioned in specification of oil
paints. Enamel paint shall conform to I.S. 2933-1975.
M-45 French polish :
45.1. The french polish of required tint and shape shall be prepared with the below mentioned
ingredients and other necessary materials:
(i) Denatured spirit of approved quality (ii) Chandras (iii) Shellac (iv) Pigment.
45.2. The french polish so prepared shall conform to I.S.: 348-1968.
M-46 Marble chips for marble mosaic terrazzo:
46.1. The marble chips shall be of approved quality and shades. It shall be hard, sound, dense and
homogeneous in texture with crystalline and coarse grains. It shall be uniform in colour and free
from stains, cracks decay and weathering.
46.2. The size of various colours of marble chips ranging from the smallest upto 20 mm. shall be used
where the thickness of top wearing layer is 6 mm. size. The marble chips of approved quality and
Page | 17
colours only as per grading as decided by the Engineer-in- charge shall be used for marble mosic
tiles or works.
46.3 The marble chips shall be machine crushed. They shall be free from foreign matter, dust etc.
Except as above, the chips shall conform to I. S.: 2114-1962.
M-47. Flooring Tiles: 47.1. (A) Plain Cement tiles :
47.1.1. The plain cement tiles shall be general purpose type. These are the tiles in the manufacturer of
which no pigments are used. Cement used in the manufacture of tiles shall be as per Indian
Standards.
47.1.2. The tiles shall be manufactured from a mixture of cement and natural aggregates by pressure
process. During
Page | 18
19
manufacture, the tiles shall be subjected to a pressure of not less than 140 Kg/Sq. Cm. The proportion
of cement to aggregate in the backing of the tiles shall be not less than 1:3 by weight. The wearing
face through the tiles are of plain cement, shall be proviedd with stone chips of 1 to 2 mrn. size. The
proportions of cement to the rnarble chips aggregate in the wearing layer of the tiles shall be three
parts of cement to one part chips by weight. The minimum thickness of wearing layer shall be 3 mm.
The colour and texture of wearing layer shall be uniform throughout its face and thickness. On
removal from mould, the tiles shall be kept in moist conditions continuously at least for seven days
and subsequently, if necessary, for such long period as would ensure their conformity to
requirements of I.S.: 1237-1980 regarding strength resistance to wear and water absorption.
47.1.3. The wearing face of the tiles shall be plain, free from projections, depressions and crackes and
shall be reasonably parallel to the back face of the tile. All angles shall be right and all edges shall be
sharp and true.
47.1.4. The size of tiles shall generally be square shape 24.85 Cm. x 24.85 Cm. or 25 Cm. x 25 Cm. The
thickness of tiles shall be 20 mm.
47.1.5. Tolerance of length and breadth shall be plus or minus one millimeter. Tolefance on thickness
shall be plus 5 mm.
47.1.6. The tiles shall satisfy the tests as regards transverse strength resistance to wear and water
absorption as per I.S
: 1237-1980.
47.2. (B) Plain Coloured Tiles :
47.2.1. These tiles shall have the same specification as per plain cement tiles as per (A) above except
that they shall have a plain wearing surface wherein pigments are used. They shall conform to I.S.
1237-1980.
47.2.2. The pigment used for colouring cement shall not exceed 10 percent by weight of cement used
in the mix. The pigments synthetic or otherwise, used for colouring tiles shall have permanent
colour and shall not contain materials detrimental to concrete.
47.2.3. The colour of the tiles shall be specified in the item or as directed.
47.3. (C) Marble mosaic tiles :
47.3.1. These tiles have, the same specifications as per plain cement tiles except the requirements as
stated below:
47.3.2. The marble mosaic tiles shall conform to I. S. 1237-1980. The wearing face of the tiles shall be
mechanically ground and filled. The wearing face of tiles shall be free from projections, depressions
and cracks and shall be reasonably parallel to the back face of the tiles. All angles shall be right
angles and all edges shall be sharp and true.
47.3.3. Chips used in the tiles be from smallest upto 20 mm. size. The minimum thickness of wearing
layer of tiles shall of 6 mm. For pattern of chips to be used on the wearing face, a few samples with
or without their full size photographs as directed shall be presented to the Engineer-in-charge for
approval.
47.3.4. Any particular samples, if found suitable shall be approved by the Engineer-in-charge, or he
may ask for a few more samples to be prepared indicating roughly the particular sized chips to be
Page | 19
more-or less in the samples presented. The samples have to be made by the contractor till a suitable
sample is finally approved for use in the work.
The Contractor shall ensure that the tiles supplied for the work shall be in conformity with the
approved sample only, in terms of its dimensions, thickness of backing layer and wearing surface,
materials, ingredients, colour shade, Chips, distribution etc. required.
47.3.5. The tiles shall be prepared from cement conforming to Indian Standards or coloured
portland cement generally depending upon the colour of tiles to be used or as directed.
47.4. (D) Chequered Tiles :
47.4.1. Chequered tiles shall be plain cement tiles or marble mosaic tiles. The former shall have the
same specification as per
(A) above and the latter as per marble mosaic tiles as per (C) except as mentioned below :
47.4.2. The tiles shall be of nominal size of 250 mm. x 250 mm. or as specified. The centre to centre
distance of chequer shall not be less than 25 mm. and not more than 50 mm. The overall thickness
of the tile shall be 22 mm.
47.4.3. The grooves in the chequers shall be uniform and straight. The depth of the grooves shall not
be less than 3 mm. The chequered shall be plain, coloured or mosaic as specified. The thickness of
the upper layer measured from the top of the chequers shall not be less than 6 mm. The tiles shall
be given the first grinding with machine before delivery to site.
47.4.4. Tiles shall conform to relevant I.S. 1237-1930.
Page | 20
21
Page | 22
23
51.4. The slab shall not be thinner than the specified thickness at its thinnest part. A few specimen of
finished slab to be used shall be deposited by the Contractor in the office for reference.
51.5. Except as above, the marble slabs shall,conform to I.S. 1130-1969.
M-52. Granite Stone Slab :
52.1. Granite shall be of approved colour and quality. The stone shall be hard, even, sound regular in
shape and generally uniform in colour. It shall be without any soft veins, cracks of flows.
52.2. The thickness of the stone shall be as specified in the items.
52.3. All exposed face shall be double polished to tender truly smooth and the even reflecting
surface. The exposed edges and corners shall be rounded off as directed. The exposed edges shall
be machine cut and shall have uniform thickness.
M-53 P.V.C Flooring:
53.1. P. V.C sheets for P.V.C. floor covering shall be of homogeneous flexible type, conforming to I.S.
3452-1966. The
P.V.C. covering shall neither develop any toxic effect while put to use nor shall give off any disagreeable
odour.
53.2 Thickness of flexible type covering tiles shall be as specified in the description of the item.
53.3. The flexible type shall be backed with hessain or other woven fabric. The following tolerances
shall be applicable on the nominal dimension of the sheet rolls or tiles :
(a) Thicknesst 0.15 mm
(b) Length or Width :
1. 300 mm. square tiles ± 0.20 mm. 39.00 mm. square tiles ±0.30 mm.
2. 600mm. “ “ ± 0.40mm. 4. Sheets and rolls + 0.10
53.4. Adhesive: percent
53.4.1. The adhesive for PVC flooring shall be of the type and make recommended by the manufacturers
of PVC sheets/tiles.
M-54. Facing tifes :
54.1. The facing tiles (burnt clay facing bricks) shall be free from craks, flaws and nodules of free
lime. They shall be thoroughly burnt and shall have plane rectangular faces with parallel sides and
sharp straight right edgled faces. The texture of the finished surface that will be exposed when in
place, shall conform to an approved sample consisting not less than four stretcher bricks each
representing the texture desired. The facing tiles shall have a pleasing appearance, sufficient
resistance to penetration by rain and greater durability than common bricks. The tiles shall conform
to I.S. 2691-1972.
54.2. The standard size effacing brick tiles shall be 19 x 9 x 4 cms. The facing brick tiles shall be
provided with frog which shall conform to I.S. 1077-1976.
54.0. The permissible tolerance in dimensions specified above shall be as follows :
Page | 23
1st class Brick 2nd class
Brick
19 Cm. ± 6mm. ±10 mm.
9cm. ± 3mm. ± 7mm.
4cm. ±1.5 mm ±3 mm.
54.4. The tolerance for distoration or warpage of face or edges of individual brick from a plane
surface and from a straight line respectively shall be as follows:
Facing dimensions Permissible
tolerance Max. below 19
cms.Max. 2.5mm.
-do- above 19 cm.Max. 3.0 mm.
54.5. The average compressive strength obtained as a sample of five dies when tested in accordance
with the procedure laid as per I.S. 1077-1976 shall be not less than 175 Kg/Sq. Cm. The average
compressive strength of any individual bricks shall be not less than 160 Kg/Sq.Cm.
54.5. The average water absorption for five bricks files shall not exceed 12 percent of average weight of
brick before testing.
Page | 24
25
The absorption for each individual bricks snail not exceed 25 percent.
54.7. The brick tiles when tested in accordance with I.S. 1077-1976, the rate of efflorescence shall not
be more than ‘Slightly effloresced.’
M-55. White glazed tiles :
55.1. The tiles shall be of best quality as approved by the Engineer-in-charge. They shall be flat and
true to shape. They shall be free from craks, crazing, spots, chipped edges and corners. The glazing
shall be of uniform shade.
55.2. The tiles shall be nominal size of 150 mm. x 150 mm. unless otherwise specified. The maximum
variation from the stated sizes, other than me thickness of tile, shall be plus or minus 1.5 mm. The
thickness of tile shall be 6 mm. Except as above the dies shall conform to I.S. 777 1970.
M-56. Galvanised iron pipes and fittings : 56.1. Galvanised iron pipe shall be of the medium type and
of required diameter and shall comply with I.S.I 239-1979. The specified diameter of the pipes shall
refer to the inside diameter of the bore. Clamps, screw and all galvanised iron fittings shall he of the
standard ‘R’ or equivalent make.
M-57. Bib cock and stop cock :
57.1. A bib cock is a draw off tap with a horizontal inlet and free outlet. A stop cock is a valve with a
suitable means of connection for insertion in a pipe line for controlling or stopping the flow.
57.2. They shall be of screw down type and of brass chromium plated and of diameter as specified in
the description of the item. They shall conform to I.S. 781-1977 and they shall be of best Indian
make. They shall be polished bright.
57.3. The minimum finished weight of bib cock and stop cock shall be as given below :
59.1. Wash basin shall be of white porcelain first quality best Indian make and it shall conform to I.S.
2556 (Part-IV) 1972 and I.S. 771-1979.
The size of the wash basin shall be as specified in the item, Wash basin shall be of one piece
construction with continued over-flow arrangements. All internal angles shall be designed so as to
facilitate cleaning. Wash basin shall have single tap hole or two holes as specified. Each basin shall
have a ciruclar waste hole which is either rabaled or bevelled internally with 65 mm. diameter at top
and 10 mm. depth to suit the waste fining. The necessary stud slot to receive the bracket on the
under side of (he basin shall be provided. Basin shall have an internal soap holder recess which shall
fully drain into the bowl.
59.2 White glazed pedestal of the quality and colour as that of the basin shall be provided where
specified in the item. It shall be completely recessed at the back for reception of supply and wash
Page | 25
pipe. It shall be capable of supporting the basin rigidly and adequately and shall be so designed as to
make the height from floor to lop of the rim of basin 750 mm. to 800 mm. as directed.
M-60. European type water closet/with low level flushing :
60.1. The European type water closet shall be white glazed porcelain first quality and shall be of
wash down type conforming to I.S. 2556-1973 and I.S. 771-1979.
60.2. ‘S’ trap shall be provided as required with water seal not less than 50 mm. The solid plastic seat
and cover shall be of the best Indian make conforming to I.S. 2548-1980. They shall be made of
moulded syntactic materials which shall be tough and hard with high resistance to solvents and
shall be free from blisters and other surface defects and shall have chromium plated brass hinges
and rubber buffer of suitable size.
M-61. Orissa type water closet: 61.1. The specification of Orissa type white glazed water closet of first
quality shall conform to I.S. 2556 (Pan-Ill) 1981 and relevant specification of Indian type water closet
except that pan will be with the integral squatting pan of size 580 mm. x 440 mm. with raised
footrest.
M-62. Indian type water cioset:
62.1. The Indian lype white glazed water clcset of first duality shall be of size as specified in (he item and
conforming to I.S.
Page | 26
19
771-1979 and I.S. 2556 (Part-II) 1981. Each pan shall have integral flushing ring of suitable type with
adequate number of holes alround as directed to have satisfactory flushing. It shall also have an inlet
at back or front for connecting flush pipe as directed. The inside of the bottom of the pan shall have
sufficient slope from the front towards the outlet and surface shall be uniform and smooth.
Pan shall be provided with l00 mm. diameter ‘P’ or’S’ trap with approximately 50 mm. water seal and 50
mm. diameter vent horn.
M-62.A Foot Rests : 62-A-l. A pair of white glazed-earthen ware rectangular foot rests of minimum
size 250 mm. x 130 mm. 20 mm. shall be provided with water closet.
M-63. Glazed Earthen Ware Sink :
63.1. The glazed earthen-ware sink shall be specified size, colour and quality. The sink shall conform
to I.S. 771 Part-II-1979. The brackets for sinks shall conform to I.S. 775-1970.
63.2. The pipes shall conform to I.S. 1239-Part-11973 and I.S. 404-1962 for steel and lead pipes
respectively 32 mm. brass waste coupling of standard pattern with brass chain and rubber plug shall
be provided with sink.
M-64. Glazed earthen ware Lipped type flat back urinal/corner type urinal: 64.1 The lipped type
urinal shall be flat back or corner type as specified in the item and shall conform to I.S. 771-1979. It
shall be of best Indian make and size as specified and approved by the Engineer-in-charge. The flat
back or corner type urinal must be of 1st quality free from any defects, cracks, etc.
M-65. Low level enamel flushing tank : 65.1. The low level enamel flushing tank shall be of 15 litres
capacity. It shall conform to I.S. 774-197 It the flushing cistern shall be of best quality and free from
any defects. The flushing tank shall have outlet 32 mm. diameter. The outlet shall be connected with
W.C. Pan by lead pipe or P.V.C. pipe as specified. The flushing tank shall be provided with inlet and
outlet for fixing G.I. inlet pipes and over-flow pipes. The flushing cistern shall be provided with
chromium plated handle for flushing. The fluushing tank shall be provided with bracket of cast iron so
that it can be fixed on wall at specified height. The brackets shall conform to I.S. 775-1970.
M-66. Cast iron flushing cistern: 66.1. The cast iron flushing cistern shall be of 15 litres capacity. It shall
conform to I.S. 774-1971. The flushing cistern shall be of best quality free from any defects. The
flushing cistern shall have outlet of 32 mm. diameter. The outlet shall be connected to lead pipe of 32
mm. diameter. The lead pipe shall conform to I.S. 404 (Part-I) 1962. For fixing G.I. inlet pipes and
overflow pipe 20 mm. dia. inlet and outlet shall be provided. The flushing cistern shall be provided
with galvanised iron chain and pull of sufficient length and shall be got approved from the Engineer-
in-charge. The cast iron flushing cistern shall be painted with one coat of anticorrosive paint and two
coats of paints. The flushing cistern shall be fixed on two C.I. brackets. The C.I. brackets shall conform
to I.S. 775-1970.
M-67. Flush cock: 67.1. Half turn flush cosfc (Heavy weight) shall be of gun metal chromium plated of
diameter as specified in the description of the item. The flush cock shall conform to relevant Indian
Standard.
M-68. Cast iron pipes and fittings :
68.1 All soil, waster, vent and antisyphonage pipes and fittings shall conform to I.S. 1729-1964. The
pipe shall have spigot and socket ends with head on spigot end. The pipes and fittings shall be true to
Page | 19
shape, smooth, cylindrical, their inner and outlet surfaces being as nearly as practicable concentric.
They shall be sound and nicely cast and shall be free from cracks, laps, pinholes or other imperfection
and shall be neatly dressed and carefully fettled. 68.2. The end of pipes and fittings shall be
reasonable square to their axis.
68.3.The sand cast iron pipes shall be of the diameter as specified in the description and shall be in
lengths of 1.5 M. 1.8 M. and 2 M. including socket ends of the pipe unless shorter lengths are either
specified or required at junctions etc. The pipes and fittings shall be supplied without ears unless
specified or directed otherwise.
Toferances:
68.4.1. The Standard weights and thickness of pipes shall be as shown in the following table : A
tolerance upto minus 10 per cent may however be allowed against these standard weights.
Page | 20
2. 100 mm 5.0mm 18.14 Kg. 21.67 Kg. 24.15 Kg.
68.4.2. A tolerance upto minus 15 pescent in thickness and 20 mm. in length will be allowed.
For fittings tolerance in lengths shall be plus 15 mm. and minus 10 mm.
68.4.3. The thickness of fittings and their socket and spigot dimensions shall conform to the
thickness and dimensions specified for the corresponding sizes of straight pipes. The
tolerances in weights and thickness shall be the same as for straight pipes.
M-69. Nahni Trap:
69.1. Nahni trap shall be of cast iron and shall be sound and free from porosity or other
defects which affect serviceability. The thickness of the base metal shall not be less than
6.5 mm. The surface shall be smooth and free from craze, ships and other flaws or any
other kind of defects which affect serviceability. The size of nahni trap shall be as specified
and shall be of self cleansing design.
69.2. The nahni trap shall be of quality approved by the Engineer-in-charge and shall
generally conform to the relevant Indian Standards.
69.3. The Nahni trap provided shall be with deep seal, minimum 50 mm, except at places
where trap with deep seal can not be accommodated. The cover shall be cast iron.
Perforated cover shall be provided on the trap of appropriate size.
M-70. Gully Trap:
70.1 Gully trap shall conform to I.S. 651-1980. It shall be sound, free from defects such as fire
cracks. The glaze of the traps shall be free from crazing. They shall give a shart clear note
when struck with light hammer. There shall be no broken blisters.
70.2. The size of the gully trap shall be as specified in the item.
70.3. Each gully trap shall have one C.I. grating of square size corresponding to the
dimensions of inlet of gully trap. It will also have a water tight C.I. cover with frame inside
dimensions 300 mm; x 300 mm., the cover with frame inside dimension, 300 mm. x 300
mm., the cover weighing not less than 4.53 Kg. and the frame not less than 2.72 Kg. The
grating cover and frame shall be of sound and good casting and shall have truly square
machined seating faces.
M-71. Glaze Stone Ware Pipe And Fitting :
71.1. The pipes and fittings shall be of best quality as approved by the Engineer-in-charge.
The pipe shall be of best quality manufactured from stone-ware of fire clay, salt glazed
thoroughly burnt through the whole thickness, of a close even texture, free from air
blows, fire blisters, crack and other imperfactions, which effect the serviceability. The inner
and outer surfaces shall be smooth and perfectly glazed. The pipe shall be capable to-
withstand pressure of 1.5 m. lead without showing sign of leakage. The thickness of the
wall shall not be less than l/12th of the internal dia. The depth of socket shall not be less
than 38 mm. The socket shall be sufficiently large to allow a joint of 1 mm. around the pipe.
71.2. The pipes shall generally conform to relevant I.S. 651 -1980.
Page | 21
Part 3 : Conditions of Contract & Contract Forms
Page | 22
M-7.7 Select Earth :
77.1. The selected earth shall be that obtained from excavated material or shall have to brought from
outside as indicated in the item. If item does not indicate anything, the selected earth shall have to be
brought from outside.
The selected earth shall be good yellow soil and shall be got approved from the Engineer-in-charge.
la no case black cotton soil or similar expansive and shrikable soil shall be used. It shall be clean and
free from all rubish and perishable materials, stones or brick bats. The clods shall be broken to a
size of 50. mm or less, Contractor shall make his own arrangement at his own cost for land for
borrowing selected earth. The stacking of material shall be done as directed by the Engineer-in-
charge in such a way as not to interfere with any constructional activities and in proper stacks.
When excavated material is to be used, only selected stuff got approved from the Engineer-in-
charge shall be used. It shall be stacked separately and shall comply with all the requirements of
selected earth mentioned above :
The barbed wire shall be of galvanised steel and it shall generally conform to I.S. 278-1978. The
barbed wire shall be of type-I whose nominal diameter for line wire shall be 2.5 mm. and point wire
2.24 mm. The nominal distance between two bars shall be 75 mm. unless otherwise specified in the
item. The barbed wire shall be formed by twisting together two line wires, one containing the barbs.
The size of the line and point wires and barb spacings shall be as specified above. The permissible
deviation from the nominal diameter of the line wire and point wire shall not exceed
±0.08 mm.
The barbs shall carry four points shall be formed by twisting two point wires, each two turns,
lightly round one line wire, making altogether four complete turns. The barbs shall be so finished that
the four points are -set and loked at right angles to each other. The barbs shall have a length of not
less than 13 mm. and not more than 18 mm. The point, shall be sharp and cut at an angle not
greater than 35 degree of the axis of the wire forming the barbs.
The line and point wire shall be circular section free from scale and other defects and shall be uniformly
galvanised. The line wire shall be in continuous length and shall not contain any weld
other than those in the rod before it is drawn. The distance between two successive splices shall
not be less than 15 meters.
The lengths per 100 Kg. of barbed wire I.S. type I shall be as under Nominal 1000 metre Minimum 834
Metre Maximum 1066 Metre.
Page | 23
Part 3 : Conditions of Contract & Contract Forms
ITEM NO. 1 :-
Excavation for foundation upto 1.50 mt depth including sorting out and stacking of useful materials and
disposing off the excavated stuff upto 50 Meter lead.(A) Loose or soft soil
Any soil which generally require close application of picks or jumpers or scarifies to loosen it stiff
clay, gravel and stone etc. fall under this category.
1.0. General
Any soil which generally yields to the application of pickaxes and shovels, phawaras rakes or any
such ordinary excavating implement or organic soil, gravel silt, sand turf loam, clay, peat etc., fail under
this category
The site on which the structure is to be built shall be cleared, and all obstructions loose stone,
materials and rubbish of all kind bush wood and trees shall be removal as directed The materials so
obtained shall be property of the Government and shall be conveyed und stacked as directed with all
lead. The roots of the trees coming in the sides shall be cut and coated with a hot asphalt
The rate of side clearance is deemed to be included in the rate of earth work for which no extra
will be paid.
After clearing the site the centre lines will be given by the Engineer-in-charge. The contractor
shall assume full responsibility for alignment, elevation and dimension of each and all 'parts of the
work. Contractor shall supply labours materials, etc. required for setting out the reference marks and
bench 'marks and shall maintain them as long as required and directed.
1.3 Excavation
The excavation in foundation shall be carried out in true line and level and shall have the width
and depth as shown in the drawings or as directed. The contractor shall do the necessary shoring and
shutting or providing necessary slopes to a safe angle, at his own cost. The payment for such
precautionary measures shall be paid separately it not specified. The bottom of the excavated area shall
Page | 24
be leveled both longitudinally and transversely as directed by removing and watering as required no.
earth filling will be allowed for brining it to level, if by mistake or any excavation is made deeper or
wider than, that shown on the plan or directed. The extra depth or width shall be made up with
concrete of same proportion as specified for the foundation concrete at the cost of the contractor. The
excavation upto 1.5 mt. depth shall be measured under this item.
The excavated stuff of the selected type shall be used in filling the trenches and plinth or
leveling the ground in layers including ramming and watering etc.
The balance of the excavated quantity shall be removed by the contractor from the site of work to a
place as directed with lead up to 50 Meter for loose or soft soil.
The measurement of excavation in trenches for foundation shall be made according to the
sections of trenches shown on the drawing or as per sections given by the Engineer-in-charge. No
payment shall be made for surplus excavation made in excess of above requirements or due to
stopping and sloping back as found necessary on account of conditions of soil and requirements of
safety.
ITEM NO. 2 :-
Excavation for foundation depth from 1.5 mt. to 3.00 mt. including sorting out and stacking of useful
materials and disposing of the excavated stuff up to 50 Meter lead.(B) Dense or Hard soil
Any soil which generally require close application of picks or jumpers or scarifies to loosen it stiff
clay, gravel and stone etc. fall under this category.
2.2. Workmanship
The relevant specifications of Item No. 1 shall be followed except that the excavation work shall
be carried out to dense or hard soil with lift from 1.50 M. to 3.0 mt. depth.
Page | 25
Part 3 : Conditions of Contract & Contract Forms
The excavation work of depth from 1.50 M. to 3.0 M. shall be measured under this item
ITEM NO. 3 :-
Providing and laying controlled cement concrete M-150 and curing complete including the cost of form
work but excluding cost of reinforcement for reinforced concrete work in Foundations, footings base
of column and the like and mass concrete.
1. Materials
Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6. Grit shall
conform to M-8. Coarse aggregate shall conform M-12.
The shuttering to be provided shall be of ordinary timber plank and shall conform to M-26.
The dimensions of scantlings and battens shall conform to the design. The strength of the wood
shall not be less than that assumed in the design.
2. General
The concrete mix shall be designed from preliminary tests. The proportion of the concrete mix
shall be 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm. nominal size) by volume
concrete work shall have exposed concrete surface or as specified in the item.
The proportioning of cement and aggregates shall be done by weight and necessary precautions
shall be taken in the production to ensure that the required work cube strength is attained and
maintained. The controlled concrete shall be in grades of M-100, M-150, M-200, M-250, M-300, M-350 &
M-400 with prefix controlled added to it. The letter M refers to mix and the numbers specify 28 days
works cube compressive strength of 150 mm. cubes of the mix expressed in Kg./cm.
The proportion of cement, sand and coarse aggregate shall be determined of weight. The weigh
batch machine shall be used for maintaining proper control over the proportion of aggregates as per
mix design. The strength requirements of different grades of concrete shall be as under:
Page | 26
M 150 200 150
M 200 260 200
M 250 320 250
M 300 380 300
M 350 440 350
M 400 500 400
In all cases, the 28 days compressive strength specified in above be the criteria for acceptance or
rejection of the concrete. Where the strength of a concrete mix as indicated by tests, lies in between
the strength of any two grades specified in the above table, such concrete shall be classified in for
purpose as concrete belonging to the lower of the grades between which its strength lies.
3. Workmanship
The proportions for ingredients chosen shall be such that concrete has adequate workability for
conditions prevailing on the work question and can be property compacted with means available
except where it can be shown to the satisfaction of the Engineer-in-charge, that supply of properly
graded aggregate of uniform quality can be maintained till the completion of work, grading of
aggregate shall be controlled by obtaining the coarse aggregates in different sizes and bending them in
the right proportions as required. Aggregates of different sizes shall be stocked in separate stock piles.
The required quantity of material shall be stock piled several hours, preferably a day before use. The
grading of coarse and fine aggregate shall be checked as frequently as possible, the frequency for a
given job being determined by Engineer-in-charge to ensure that the suppliers are maintaining the
uniform grading as approved for samples used in the preliminary tests.
In proportioning concrete, the quantity of both cement and aggregate shall be determined by
weight. Where the weight of cement is determined by accepting the maker's weight per bag, a
reasonable number of bags shall be weighted separately to check the net weight. Where cement is
weighted form bulk stocks at site and not by bags, it shall be weighed separately from the aggregate.
Water, shall either be measured by volume in calibrated tanks or weighed. All measuring equipment
shall be maintained in clean and serviceable condition. Their accuracy shall be periodically checked.
It is most important to keep the specified water cement ratio constant and at its correct value.
To this end, moisture content in both fine and coarse aggregates shall be determined by the Engineer-
in-charge according to the weather conditions. The amount of mixing water shall then be adjusted to
compensate for variations in the moisture content. For the determination of moisture content in the
aggregates I.S. 2386 (Part-Ill) shall be referred to. Suitable adjustments shall also be made in the
weights of aggregates due to variation in their moisture content. Minimum quantity of cement to be
Page | 27
Part 3 : Conditions of Contract & Contract Forms
used in controlled concrete shall not be less than 220 kg./m3 in plain concrete and not less than 250
kg/m3 in reinforced concrete.
The form work shall conform to the shape lines and dimensions as shown on the plans and be
constructed as to remain sufficiently rigid during the placing and compacting of the concrete. Adequate
arrangements shall be made by the contractor toe safe-guard against any settlement of the form-work
during the course of concreting and after concreting. The form work of shuttering, centering,
scaffolding, bracing etc. shall be as per design.
All rubbish, particularly chipping shaving and saw dust shall be removed from the interior of the
form before the concrete work is placed and the-form in contact with concrete shall be cleaned and
thoroughly wetted or treated. The surface shall be then coated with soap solution applied before
concreting is done. Soap solution for the purpose shaft prepared by dissolving yellow soap in water to
get consistency of paint. Alternatively a coat of raw linseed oil shall be applied after thoroughly
cleaning the surface. Care shall be taken that the coating does not get on construction joint surface and
reinforced bars..
5. Stripping time:
In normal circumstances and where ordinary cement is used forms may be struck after expire of
following periods.
6.1 All form work shall be removed without such shock or vibrations as would damage the
reinforced concrete surface. Before the soffits form work and struts are removed, the soffits and the
Page | 28
concrete surface shall be exposed where necessary in order to ascertain that the concrete has
sufficiently hardened.
7. Centering:
7.1 The centering to be provided shall be got approved. It shall be sufficiently strong to ensure
absolute safety of the form work and concrete work before, during and after pouring concrete. Watch
should be kept to see that behavior or centering and form work is satisfactory during concreting.
Erection should also he such that it would allow removal of forms in proper sequence without
damaging either the concrete or the forms to be removed.
7.2 The props of centering shall be provided on firm foundation or base of sufficient strength to
carry the loads without any settlement.
7.3 The centering and form work shall, be inspected and approved by the Engineer-in-charge before
concreting. But this will not relieve the contractor of his responsibility for strength, adequacy and
safety of form work and centering. If there is a failure of form work or centering, contractor shall be
responsible for the damages to property.
8. Scaffolding:
8.1 All scaffolding, hoisting arrangements and ladders etc. required for the facilitating of conceding
shall be provided and removed on completion of work by contractor at his own expense. The
scaffolding, hoisting arrangements and ladders etc. shall be strong enough to with sand all live, dead
and impact loads expected to act and shall be subject to the approval of the Engineer-in-charge.
However contractor shall be solely responsible for the safety of the scaffolding, hoisting arrangement,
ladders, work and workman etc.
8.2 The scaffolding, hoisting arrangements and ladder shall allow easy approach to the work spot
and afford easy inspection.
8.3 The rate is applicable to all condition of working and height up to 4 mts. The rate shall include
the cost of materials and labour for various operations involved such as :
(a) Splayed edges, notching, allowance for overlaps and passing at angles, battens centering,
shuttering propping, bolting, wedging easing, striking and removal.
(b) Filleting to form stop chamfered edges or splayed external angles not exceeding 20 mm: width
to beams, columns and the like.
(c) Temporary openings in the forms for pouring concrete, if required removing rubbish etc.
(d) Dressing with oil to prevent adhesion of concrete with shuttering and.
Page | 29
Part 3 : Conditions of Contract & Contract Forms
9.0. Re-Use:
Before re-use, all from shall be inspected by Engineer-in-charge and their suitability ascertained.
The forms shall be scarred, cleaned and joints are gone over, repaired where required. Inside surface
shall be retreated to prevent adhesion of concrete.
10.1 The consolidated cubical contents of concrete work as specified in item shall be measured. No
deduction shall be made for
(a) Ends of dissimilar materials such as joints, beams, posts, girders, falters, purling trusses, corbels
and steps etc. up to 500 Sq, Cm. in section.
10.2 Form work shall be measured as the area in square meters to shuttering in contract with
concrete except in the case of inclined member and portion of curved profile and upper side in which
case on area of underside shall be measured for payment.
10.3 Form work to secondary beams shall be measured up to the sides of main beams but no
deduction shall be made form the form work of the main beam at the inter section point. No deduction
shall be made form the form work of a column at inter section of beams.
10.4 The rate includes cost of all materials labour, tools and plant required for mixing, placing in
position, vibrating and compacting, finishing, as directed, curing and all other incidental expenses for
producing concrete of specified strength. The rate includes the cost of form work.
ITEM 4:
Providing and laying controlled cement concrete M 250 using B.T. stone aggregate and curing complete
including the cost of form work but excluding the cost of reinforcement for reinforced concrete work
in. (A) Foundation footing, base of
columns & mass concrete.
Page | 30
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M 250 using B.T. stone aggregate and curing complete including the cost of
form work but excluding the cost of reinforcement for reinforced concrete work in. (A) Foundation
footing, base of
columns & mass concrete.
ITEM 5:
Providing and laying controlled cement concrete M 250 using B.T. stone aggregate and curing complete
including the cost of form work but excluding the cost of reinforcement for reinforced concrete
work for RCC Columns up to Plinth level.
The work shall be executed as per specification of Item No.3 except the work is for Providing and laying
controlled cement concrete M 250 using B.T. stone aggregate and curing complete including the cost
of form work but excluding the cost of reinforcement for reinforced concrete work for RCC Columns
up to Plinth level.
ITEM 6:
Providing and laying cement concrete 1:4:8 (1- Cement : 4- coarse sand : 8- hand broken stone
aggregates 40 mm nominal size) and curing complete including cost of formwork in (A) Foundation and
Plinth.
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
cement concrete 1:4:8 (1- Cement : 4- coarse sand : 8- hand broken stone aggregates 40 mm nominal
size) and curing complete including cost of formwork in (A) Foundation and Plinth.
ITEM 7:
Page | 31
Part 3 : Conditions of Contract & Contract Forms
Provinding and Laying controlled cement concrete M-250 & including finishing smooth with curing
complete including the cost of form work but excluding cost of reinforcement concrete for RCC PLINTH
BEAM for any cross sectional area of
Beam.
The work shall be executed as per specification of Item No.3 except the work is for providing and
Laying controlled cement concrete M-250 & including finishing smooth with curing complete including
the cost of form work but excluding cost of reinforcement concrete for RCC PLINTH BEAM for any
cross sectional area of
Beam.
ITEM 8:
Brick work using common Brunt clay building bricks having crushing strength not less than 35
Kg./Sq.cm.. in cement mortar 1:6 (1cement : 6 fine sand) (b) Conventional In Foundation and Plinth.
1.0. Materials
Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6. Bricks
shall conform to M-15. Cement mortar shall conform to M-11.
2.0. Workmanship
2.1. Proportion:
2.1.1. The proportion of the cement mortar shall be 1:6 (1 cement : 6 fine sand) by volume.
2.2.1. The bricks required for masonry shall be thoroughly wetted with clean water for about two
hours before use or as directed. The cessation of bubbles, when the bricks are wetted with water is as
indication of through wetting of bricks.
2.3. Laying:
2.3.1. Bricks shall be laid in English bond unless directed otherwise. Half or cut bricks shall not be used
except when necessary to complete to bond; closures in such case shall be cut to required size and
used near the ends of walls.
Page | 32
2.3.2. A layer of mortar shall be spread on full width for suitable length of the lower course. Each brick
shall first be property bedded and set home by gently tapping with handle of trowel or wooden mallet.
Its inside face shall be flushed with mortar before the next brick is laid and pressed against it. On
completion of course, the vertical joints shall be fully filled from the top with mortar.
2.3.3. The walls shall be taken up truly in plumb. All courses shall be laid truly horizontal and all vertical
joint shall be truly vertical. Vertical joints in alternate course shall generally be directly one over the
other. The thickness of brick course shall be kept uniform.
2.3.4. The brick shall be laid with frog up wards. A set of tools comprising of wooden straight edges,
man son's spirit level, square half meter rub, and pins, string and plumb shall be kept on the site of
work for frequent checking during the progress of work.
2.3.5. Both the faces of walls of thickness greater than 23 cms. shall be kept in proper place. All the
connected brick work shall be kept not more than one meter over the rest of the work. Where this is
not possible, the work shall be raked back according to bond (and not left toothed) at an angle not
steeper than 45 degrees.
2.3.6. All fixtures, pipes, outlets of water, hold fasts of doors and windows etc. which are required to
be built in wall shall be embedded in cement mortar.
2.4. Joints:
2.4.1. Bricks shall be so laid that all joints are quite flush with mortar. Thickness of joints shall not
exposed 12 mm. The face joints shall be raked out as directed by raking tools daily during the progress
of work, when the mortar is still green so as to provide key for plaster or pointing to done.
2.4.2. The face of brick shall be cleaned the very day on which the work is laid and all mortar dropping
removed.
2.5. Curing:
2.5.1. Green work shall be protected from rain suitably. Masonry work shall be kept moist on all the
faces for a period of seven days. The top of masonry work shall be kept well wetted at the close of the
day.
2.6.1. If the foundation is to be laid directly on the excavated bed, the shall be leveled, cleared of all
loose materials, cleaned and wetted before stating masonry, If masonry is to be laid on concrete
footing, the top of concrete shall be cleaned and moistened. The contractor shall obtain the engineer's
approval for the foundation bed before foundation masonry is started. When pucca flooring is to be
Page | 33
Part 3 : Conditions of Contract & Contract Forms
provided flush with the top to plinth, the inside plinth offset shall be kept lower than the outside plinth
top by the thickness of the flooring.
3.1. The measurements of this item shall be taken for the brick masonry fully completed in
foundation up to plinth. The limiting dimensions not exceeding those shown on the plinths or as
directed shall be final. Battered tapered and curved portions shall be measured net.
3.2. No deduction shall be made from quantity of brick work nor any extra payment made for
embedding in masonry of marking holes in respect of following item.
(1) Ends of joints, beams, posts, girders, rafters, purlins trusses corbel, steps, etc. where cross
sectional area does not exceed 500 sq.cm.
(3) Wall plate sand bed plates bearing of slab, chhajjas and like whose thickness does not exceed
10 cms. and the bearing does not extend the full thickness of wall.
(4) Drainage holes and recesses for cement concrete blocks to embed hold fasts for doors,
window etc.
(5) Iron fixtures, pipes up to 300 mm. dia. hold fasts of doors, and window built into masonry
and pipes etc. for concealed wiring.
3.3 Apparatuses for fire places shall not be deducted nor shall extra labour required to make
splaying of jumps, throating and making trenches over the aperture be paid for separately.
ITEM 9:
Filling in foundation and plinth with murrum or selected soil in layers of 20cm thickness including
watering, ramming and consolidating
etc. completed.
1.0 MATERIALS
Page | 34
1.1. Murrum or selected soil shall be clean, of good binding quality and of approved quality obtained
from approved pots / quarries of disintegrated rocks which contain silicon's material and natural
mixture of clay of clarions origin. The P.I. value of selected soil used shall not be more than 6.0.
2.0 WORKMANSHIP
2.1 The murrum or selected soil to be used for filling shall be free from salts, organic or other
foreign matter all colds of murrum or selected soil shall be broken.
2.2 As soon as the work in foundation has been completed and measured the site of foundation
shall be cleared of all debris brick bats mortar dropping etc. and filled with murrum or selected soil in
layers not exceeding 20 cms. Each layer shall be adequately watered, rammed and consolidated before
the succeeding layer is laid. The murrum shall be rammed with iron rammers where feasible and with
the but ends of crow bars. Where rammer cannot be used.
2.3 The plinth shall be similarly tilled with murrum or selected soil in layers not exceeding 20 cms
adequately watered and consolidated by ramming with iron or wooden rammers. When filling reaches
finished level the surface shall be flooded with water for at least 24 hours and allowed to dry and then
rammed and consolidated.
2.4 The finished level of filling shall be kept to shape intended to be given to floor.
2.5 In case of large heavy duty flooring like factory flooring, the consolidation may be done by
power rollers, where so specified. The extent of consolidation required shall also be as specified.
3.1 The payment shall be made for filling in plinth and foundation no deduction shall be made for
shrinkage or voids, if consolidated as instructed above.
3.2 The rate includes cost of collecting and carting murrum / or selected earth of approved quality
with all lead and labour required for filling in trenches and plinth.
ITEM 10:
Applying general insecticide pest control treatment to floors, cupboards etc including labour material
etc. complete. Using Heptachloride 20 EC. As Per 6113_pests Consentration Weight 0.50 percent is
recommended one litre chemical emulsion dillute with 39 liter of water will give. Total dillute
Page | 35
Part 3 : Conditions of Contract & Contract Forms
concrentration will be 40 litre inclusive of one litre chemical emulsion appication 0.5 Litre chemical /
Sqm of surface is recommended as per
I.S
MATERIALS
The chemicals used for the soil treatment shall be only one of the following with concentration shown
against each in aqueous emulsion.
Chemicals Concentration
WORKMANSHIP
2.1 The chemicals barrier shall be complete and continuous under whole of the structure to be
protected.
2.2 The bottom and the sides of foundations up to a height of 30 cms from the bottom of
excavation made for masonry foundation and for basement column pits shall be treated with the
chemical emulsion at the rate 5 liters/sq.meters of the surface area.
2.3 The chemical treatment shall be carried out when the surface is quite dry. Chemical treatment
shall not be carried out when it is raining or when the soil wet with rain or sub soil water.
2.4 Once formed, treated soil berries shall be not disturbed. If by chance, treated soil barriers and
disturbed, immediately steps shall be taken to restore the continuation and compactness of the barrier
system.
2.5 The treatment against termite infection shall remain fully effective for a period not less than 10
years from date of issue of the final certificate to completion of work. If at any time during this period,
any defects in treatment are revealed or any evidence of infection in any part of the building or
structure is noticed, the contractor shall be rectify the concerned failure to do so, the Engineer–in–
charge any get the same rectified through any other agency at Contractor’s risk and cost, any decision
of Engineer–in–charge as to the cost payable by contractor for the same shall be binding to the
contractor.
2.6 A Guarantee bond on appropriately stamped paper shall be given by the contractor to the
Department in the manner and form prescribed below.
Page | 36
FORM OF GUARANTEE BOND
2.7 This guarantee shall remain in force for the period of 10 years from the completion of the work
under the contract and lit shall remain binding to the contractor for period of 10 years.
2.8 The deposit at the rate of 50% of the cost of this item from the running and final bills shall be
recovered and remained for the first one year after completion of the work or at least on monsoon
season passed which ever is later and 10% shall be retained for the balance of the guarantee period land
shall be refunded only after completion of the guarantee period.
3.1. The length and breadth shall be measured correct to a cm. as per the dimensions of sanctioned
plans. No deduction shall be made nor extra paid for any opening for pipes etc. up to 0.1 sq. mt. The
rate shall include the cost of all labour and materials required for the operation involved for satisfactory
completion of this item. The sides of the trenches 30 cms, each side and bottom shall be measured
under this item.
ITEM 11:
Providing and laying controlled cement concrete M-200 and curing comp. including the cost of form
work but excluding the cost of reinforcement for reinforced concrete work for
Columns AT GROUND FLOOR
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M-200 and curing comp. including the cost of form work but excluding the
cost of reinforcement for reinforced concrete work for
Columns AT GROUND FLOOR
Page | 37
Part 3 : Conditions of Contract & Contract Forms
ITEM 12:
Providing and Laying controlled cement concrete M-200 and with curing etc. complete. Including the
cost of formwork but excluding the cost of reinforcement for R.C.C work in beam having any cross
section area of BEAM. for
Ground floor.
The work shall be executed as per specification of Item No.3 except the work is for providing and
Laying controlled cement concrete M-200 and with curing etc. complete. Including the cost of
formwork but excluding the cost of reinforcement for R.C.C work in beam having any cross section area
of BEAM. for
Ground floor.
ITEM 13:
Providing and laying controlled cement concrete M-200 and curing complete including the cost of form
work but excluding the cost of reinforcement for reinforced concrete work in SLABS for GROUND
FLOOR.
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M-200 and curing complete including the cost of form work but excluding
the cost of reinforcement for reinforced concrete work in SLABS for GROUND FLOOR.
Item 14:
Providing and laying controlled cement concrete M-200 and curing complete including the cost of form
work but excluding the cost of reinforcement for reinforced concrete work in Lintels Ground Floor.
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M-200 and curing complete including the cost of form work but excluding
the cost of reinforcement for reinforced concrete work in Lintels Ground Floor.
ITEM 15:
Providing I.S.I. mark Fe-415 T.M.T. bar reinforcement for R.C.C. work including bending, binding and
placing in position upto floor two
level for all floor.
1.0. GENERAL
This work shall consist of furnishing and placing coated, or uncoated or high strength deformed
reinforcement, bars (intentioned) of the shape and dimensions shown on the drawings and conforming
to these specifications or as approved by the Engineer in charge.
Page | 38
2.0. MATERIAL
Reinforcements may be either T.M.T. tensile steel, confirms to IS 1786-2008 bars. They may be
uncoated or coated with epoxy or with approved protective coatings.
2.2. T.M.T. bars reinforcement for R.C.C. work shall conform IS 432 (Part II) 1982 (Reaffirmed 1995)
and shall be of tested quality. It shall also comply with relevant part of IS 456-2000.
2.3. All reinforcement shall be clean and free from dirt, paint, grease or oil, all scale or loose or thick
rust at the time of placing.
2.4. All steel shall be procured form original producers no re-rolled steel shall be incorporated in the
work.
2.5. Only new steel shall be delivered to the site every bar shall be inspected before placing to its
position and defective brittle or burnt bar shall be discarded cracked ends of bars shall be discarded.
3.0. Pitch
3.1. Distance between bars shall be as specified in drawings and as directed by the Engineer in
charge all bars shall be placed at an accurate distance from each other and shall be bind tightly to
maintain the desired pitch Suitable means shall be provided for holding bars securely in position.
4.1. Mild steel binding wire shall be of 1.63 mm or 1.22 mm (16 to 18 gauge) diameter and shall
conform IS 280-2006.
Page | 39
Part 3 : Conditions of Contract & Contract Forms
4.2. The use of black wire will be permitted for binding reinforcement bars. It shall be free form free
from dirt, paint, grease or oil, oil scale or loose or thick rust and any other undesirable coating which
may prevent adhesion of cement mortar at the time of binding.
4.3. Only new binding wire shall be delivered to the site all binding wire shall be inspected before
binding to its position and defective brittle, rusted, used wire, shall be discarded.
5.1. Uncoated reinforcing steel shall be protected from rusting or chloride contamination.
Reinforcements shall be free from rust, mortar, loose mill scale, grease, oil or paints. This may be
ensured either by using reinforcement fresh from the factory or thoroughly cleaning all reinforcement
to remove rust using any suitable method such as sand blasting, mechanical wire brushing, etc. as
directed by the Engineer. Reinforcements shall be stored on bricks, racks or platforms and above the
ground in a clean and dry condition and shall be suitably marked to facilitate inspection and
identification.
5.2. Portions of uncoated reinforcing steel and dowels projecting from concrete shall be protected
within one week after initial placing of concrete with a brush coat of neat cement mixed with water to
a consistency, of thick paint. This coating shall be removed by lightly tapping with a hammer or other
tool not more than one week before placing of the adjacent pour of concrete. Coated reinforcing steel
shall be protected against damage to the coating. If the coating on the bars is damaged during
transportation or handling and cannot be repaired, the same shall be rejected.
6.0. Workmanship
6.1. The work shall consist of furnishing and placing reinforcement to the shape and dimensions
shown as on the drawings or as directed by The Engineer in charge.
6.2. Reinforcing steel shall conform accurate to the dimensions given in the bar bending schedules
shown on relevant drawing
Page | 40
7.1. Bar bend g schedule shall be furnished by the Contractor and got approved by the Engineer
before start of work.
7.2. Reinforcing steel shall conform to the dimensions and shapes given in the approved bar bending
Schedules.
7.3. Bars shall be bent cold to the specified shape and dimensions or directed by the Engineer using a
proper bar bender operated by hand power to obtain the correct radius of bends and shape.
Bars shall not be bent or straightened in a manner that will damage parent material or the coating bars
bent during transport or handling shall, be straightened before being used on work and shall not be
heated to facilitate straightening.
8.1. The reinforcement cage should generally be fabricated in the yard at ground level, and then
shifted and placed in position. The reinforcement shall be placed strictly, in accordance with the
drawings and shall be assembled in position, only when structure is otherwise ready for placing of
concrete. Prolonged time gap, between assembling of reinforcements and casting of concrete, which
may result in rust formation on the surface, shall not be permitted.
8.2. Reinforcement bars shall be placed accurately in position as shown on the drawings. The bars,
crossing one another shall be tied together at every intersection with binding wire (annealed),
conforming to IS:280 to make the skeleton of the reinforcement rigid such that the reinforcement does
not get displaced during placing of concrete, or any other operation. The diameter of binding wire shall
not be less than 1 mm.
In case of beam an slab construction, industrially produced polymer cover blocks of thickness equal to
the specified cover shall be placed between the bars and formwork subject to Satisfactory evidence
that the polymer composition is not harmful to concrete and reinforcement. Cover blocks made of
concrete may be permitted by the Engineer, provided they have the same strength and specification as
those of the member.
8.4. In case of dowels for Columns and walls the vertical reinforcement shall be kept in position by
means of timber templates with slots in them accurately, or with cover blocks tied to the reinforcement
timber templates shall be removed after the concreting has progressed up to a level just below their
location.
Page | 41
Part 3 : Conditions of Contract & Contract Forms
8.5. Layers of reinforcements shall be separated by spacer bars at approximately One meter
intervals. The minimum diameter of spacer bars shall be 12 mm or: equal to maximum size of main
reinforcement or maximum size of coarse aggregate, whichever is greater. Horizontal reinforcement
shall not be, allowed to sag between supports.
8.6. Necessary stays, blocks, metal chairs, spacers, metal hangers supporting wires etc, or other
subsidiary, reinforcement shall be provided to fix the reinforcements firmly in its correct position.
8.7. Use of pebbles, broken stone, metal pipe, brick, mortar or wooden blocks etc as devices for
positioning reinforcement shall not be permitted.
8.8. Bars coated with epoxy or any other approved protective coating shall be placed on supports
that do not damage the coating. Supports shall be installed in a manner such that planes of weakness
are not created in hardened concrete. The coated reinforcing steel shall be held in place by use of
plastic or plastic coated binding wires especially manufactured for the purpose.
8.9. Placing and fixing of reinforcement shall be inspected and approved by the Engineer before
concrete is deposited.
9.0. Lapping
9.1. All reinforcement shall be furnished in full lengths as indicated on the drawing. No splicing of
bars, except where shown on the drawing; will be permitted without approval of the Engineer. The
lengths of the splice shall be as indicated on drawing or as approved by the Engineer. Where
practicable, overlapping bars shall not touch each other, and shall be kept apart by 25 mm or 1 1 1/4
times the maximum size of coarse aggregate, whichever is greater, If this is not feasible, overlapping
bars shall be bound with annealed steel binding wire, not less than 1 mm diameter and twisted tight in
such a manner as to maintain minimum clear cover to the reinforcement from the concrete surface.
Lapped splices shall be staggered or located at points, along the span where stresses are low.
10.0. Welding
10.1 Splicing by welding of reinforcement will be permitted only if detailed on the drawing or
approved by the Engineer. Weld shall develop an ultimate strength equal to or greater than that of the
bars connected.
Page | 42
10.2. While welding may be permitted for T.M.T. reinforcing bars conforming to IS:432, welding of
deformed bars conforming to IS: 1786 shall in general be prohibited. Welding may be permitted in case
of bars of other than S 240 grade including special. Welding grade of S 415 grade bars conforming to
IS:1786, for which necessary chemical analysis has been secured and the carbon equivalent (CE)
calculated from the chemical composition using the formula:
CE = C + Mn + Cr + Mg + V + Ni + Cu
6 5 15
is 0.4 or less.
10.3. The method of welding shall conform to IS:2751 and IS:9417 and to any supplemental specifications
to the satisfaction of the Engineer
10.4. Bars shall be bent cold to the specified shape and dimensions or as directed by Engineer in charge
using the proper bender tool, operated by hand or power to attain proper radius of bends. Bars shall
not be bend or straightened in a manner that will injure the material. Bars bent during transport or
handling shall be straightened before being used in the work. Bars shall not be heated to facilate
bending
10.5. Unless otherwise specified a 'U' type hook at the end of each bar shall invariably be provided to
main reinforcement. The radius of the bane shall not be less then twice the diameter of the round bar
and the length of the straight part of the bar beyond the end of the curve shall be at least four times of
the diameter of the round bar. In case of bars which are not round and in case of deformed bars, the
diameter shall be taken as the diameter of circle having an equivalent effective area. The hooks shall be
suitably encased to prevent any spiting of the concrete
10.6. All reinforcement bars shall be accurately placed in exact position shown on the drawings and
shall be securely held in position during placing of concrete by annealed binding wire not less than 1 mm
in size and by using say blocks or metal chairs spacers, metal hangers, supporting wires or other
approved devices at sufficiently close intervals, Bars shall not be allowed to sag between supports not
displaced during concreting or any other operations of the work All devices used for positioning shall
Page | 43
Part 3 : Conditions of Contract & Contract Forms
be of not corrodible material wooden and metal supports shall not extended to the surface of the
concrete, except where shown in drawings. Placing bars on layers of freshly laid concrete as the work
progresses for adjusting bar spacing shall not be allowed. Pieces of broken stone or brick and wooden
blocs shall not be used Layers of bars shall be separated by spacer bars pre-cast mortar blocks or other
approved devices. Reinforcement after bending placed in position shall be maintained in a clean
condition until completely embedded in concrete, Special care shall be exercised to prevent any
displacement of reinforcement in concrete already placed. To prevent reinforcement form corrosion,
concrete cover shall be provided as indicated on drawings. All bars protruding from concrete and to
which other bars are to be sliced and which are likely to be exposed for a period exceeding 10 days shall
be protected by a thick coat of neat cement grout
10.7. Bars crossing each other where required shall be secured by binding wire (annealed) of size not
less than 1 mm in such a manner that they do not slip over at the time of fixing and concreting
As far possible bars of full length shall be used in case this is not possible, overlapping of bars
shall be done as directed by the Engineer in charge When practicable overlapping bars shall not touch
each other, but be kept apart by 25 mm Where no feasible overlapping bars shall be bound with
annealed wires not less than 1 mm thick twisted tight The overlaps shall be staggered for different bars
and located at points along the span where neither sheer not bending moments is maximum.
10.8. Whenever indicated on drawing or desired the Engineer in charge bars shall be jointed by
coupling which shall have a cross section sufficient to transmit the full stresses of bars The end of the
bars that are jointed by coupling shall be upset for sufficient length so that the effective cross section
at the base of threads is not less than the normal cross section of the bar. Threads shall be standards
threads Steel for coupling shall conform to IS 226
10.9. When permitted or specified on the drawings joints of reinforcement bars shall butt-welded so
as to transmit their full stresses Welded joints shall preferably be located at points when steel will not
be subject to more than 75 percent of the maximum permissible stresses and welds so staggered that
at any one section not more than 20 percent of the rods are welded Only electric are welding using a
process which excludes air form the molten metal and conforms to any or other special provisions for
the work shall be accepted Suitable means shall be provided for holding bars securely in position during
welding It shall be ensured that no voids are left in welding and when welding is done in two or three
stages previous surface shall be cleaned properly Ends of bars shall be cleaned of all loose scale rust
stages paint and other foreign matter before welding Only competent welders shall be employed on
Page | 44
the work. The M S electrodes used for welding shall conform IS 814 Welded pieces of reinforcement
shall be tested. Specimen shall be taken form the actual site and their number shall frequency to test
shall be as directed by the Engineer in charge
11.1. For the purpose of payment the bar shall be measured correct up to 10 mm length and weight
payable works out at the rate specified below
11.2. Reinforcement shall be measured in length including hooks, if any, separately for different
diameters as actually used in work, excluding overlaps. From the length so measured, the weight of
reinforcement shall be calculated in tonnes on the basis of IS: 1732. Wastage, overlaps, couplings,
welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods for binding
and placing shall not be measured and cost of these items shall be deemed to be included in the rates
for reinforcement..
Page | 45
Part 3 : Conditions of Contract & Contract Forms
11.3. The contract unit rate for coated/uncoated reinforcement shall cover the cost of material,
fabricating, transporting, storing, bending, placing, binding and fixing in position as shown on the
drawings as per these specifications and as directed by the Engineer, including all labour, equipment,
supplies, incidentals, sampling, testing and supervision.
The unit Rate for coated reinforcement shall be deemed to also include cost of all material,
labour, tools and plant, royalty, transportation and expertise required to carry out the work. The rate
shall also cover sampling, testing and supervision required for the work.
Item 16: Providing and laying brick work using common burnt clay building conventional type bricks
having crushing strength not less than 35 Kg./Sqcm. in super structure in cement mortar 1:6 (1
cement : 6 fine sand) for Ground floor
1.0. Materials
2.0. Workmanship
2.1. Proportion:
2.1.1. The proportion of the cement mortar shall be 1:6 (1 cement : 6 fine sand) by volume.
2.2.1. The bricks required for masonry shall be thoroughly wetted with clean water for about two
hours before use or as directed. The cessation of bubbles, when the bricks are wetted with water is as
indication of through wetting of bricks.
2.3. Laying:
2.3.1. Bricks shall be laid in English bond unless directed otherwise. Half or cut bricks shall not be used
except when necessary to complete to bond, closures in such case shall be cut to required size and
used near the ends of walls.
Page | 46
2.3.2. A layer of mortar shall be spread on full width for suitable length of the lower course. Each brick
shall first be property bedded and set home by gently tapping with handle of trowel or wooden mallet.
Its inside face shall be flushed with mortar before the next brick is laid and pressed against it. On
completion of course, the vertical joints shall be fully filled from the top with mortar.
2.3.3. The walls shall be taken up truly in plumb. All courses shall be laid truly horizontal and all vertical
joint shall be truly vertical. Vertical joints in alternate course shall generally be directly one over the
other. The thickness of brick course shall be kept uniform.
2.3.4. The brick shall be laid with frog up wards. A set of tools comprising of wooden straight edges,
mason's spirit level, square half meter rub, and pins, string and plumb shall be kept on the site of work
for frequent checking during the progress of work.
2.3.5. Both the faces of walls of thickness greater than 23 cms. shall be kept in proper place. All the
connected brick work shall be kept not more than one meter over the rest of the work. Where this is
not possible, the work shall be raked back according to bond (and not left toothed) at an angle not
steeper than 45 degrees.
2.3.6. All futures, pipes, outlets of water, hold fasts of doors and windows etc. which are required to
be built in wall shall be embedded in cement mortar.
2.4. Joints:
2.4.1. Bricks shall be so laid that all joints are quite flush with mortar. Thickness of joints shall not
exposed 12 mm. The face joints shall be raked out as directed by raking tools daily during the progress
of work, when the mortar is still green so as to provide key for plaster or pointing to done.
2.4.2. The face of brick shall be cleaned the very day on which the work is laid and all mortar dropping
removed.
2.5. Curing:
2.5.1. Green work shall be protected from rain suitably. Masonry work shall be kept moist on all the
faces for a period of seven days. The top of masonry work shall be kept well wetted at the close of the
day.
2.6.1. If the foundation is to be laid directly on the excavated bed, it shall be leveled, cleared of all
loose materials, cleaned and wetted before stating masonry, If masonry is to be laid on concrete
footing, the top of concrete shall be cleaned and moistened. The contractor shall obtain the engineer's
approval for the foundation bed before foundation masonry is started. When pucca flooring is to be
Page | 47
Part 3 : Conditions of Contract & Contract Forms
provided flush with the top to plinth, the inside plinth offset shall be kept lower than the outside plinth
top by the thickness of the flooring.
2.7. The frames of doors, windows, cupboards etc. shall be housed into the brick work at the correct
location and level as directed. The heavy steel doors, window frames etc. shall be built in with work, but
for ordinary steel doors and windows required opening for frames, hold-fasts etc. shall be in the wall
and frame embedded later on in order to avoid damage to the frames.
2.8. Necessary scaffolding shall be provided. The supports of the scaffolding shall be sound and
strong tied, together with horizontal pieces over which the scaffolding plunks shall be fixed. Simple
scaffolding shall be allowed normally. In this case scaffolding hole shall rest in hole header horizontal
coarse only. Minimum number of holes be left in brick work for supporting horizontal scaffolding poles.
The contractor is responsible for providing and maintaining sufficiently strong scaffolding so as to
withstand all loads likely to come upon it.
2.9. For the face of brick work, where plastering is to be done, joints shall be racked out to a depth
not less than thickness of joints. The face of brick work shall be cleaned and mortar dropping removed
on very same day that brick work is laid.
3.1. The masonry work of G.F. & First floor shall be measured and paid under this item rate includes
cost of all materials & labour.
3.2. Brick work in parapet shall be included in the corresponding masonry item of floor immediately
below the floor above which the parapet is built.
3.3. No deduction shall be made from quantity of brick work nor any extra payment made for
embedding in masonry of marking holes in respect of following item.
(1) Ends of joints, beams, posts, girders, rafters, purlins trusses corbel, steps, etc. where cross
sectional area does not exceed 500 sq.cm.
(3) Wall plate sand bed plates bearing of slab, chhajjas, and like whose thickness does not
exceed 10 cms. and the bearing does not extend the full thickness of wall.
(4) Drainage holes and recesses for cement concrete blocks to embed hold fasts for doors,
window etc.
(5) Iron fixtures, pipes up to 300 mm. dia. hold fasts of doors, and window built into masonry
and pipes etc. for concealed wiring.
Page | 48
(6) Forming charges of section not exceeding 350 sq.cm. in masonry.
(7) Apparatuses for fire places shall not be deducted nor shall extra labour required to make
splaying of jumps, throating and making trenches over the aperture be paid for separately.
Item 17: Providing 10 mm thick cement plaster in single coat on fair side brick/concrete walls for interior
plastering upto floor two level and finished even and smooth in cement mortar 1:3 (1 cement : 3 sand)
including finishing with a floating coat of neat cement slurry etc. complete for Ceiling Ground floor.
1.0. Materials
1.1. Water shall conform to M-1. The cement mortar of proportion 1:6 shall conform to M-13.
2.0. Workmanship
2.1. Scaffolding:
Wooden bullies, bamboos, planks, trestles and other scaffolding shall be sound. These shall be
properly examined before erection and use. Stage scaffolding shall be provided for ceiling plaster which
shall be independent of the walls.
2.2.1. The surface shall be cleaned of all dust, loose mortar droppings, traces of algae, efflorescence
and other foreign matter by water or by brushing. Smooth surface shall be toughened by wire brushing
if it is not hard and by hacking if it is hard. In case of concrete surface, if a chemical retarded has been
applied to the form work, the surface shall be roughened by wire brushing and all the resulting dust and
loose particles cleaned off and care shall be taken that none of the readers if left on the surface.
Trimming of projections on brick/concrete surfaces where necessary shall be carried out to get an even
surface.
2.2.2. Raking of joints in case of masonry where necessary shall be allowed to dry out for sufficient
period before carrying out the plaster work.
2.2.3. The work shall not be soaked but only damped evenly before applying the plaster. If the surface
becomes dry, such area shall be moistened again.
2.2.4. For external plaster, the pestering operation shall be started from top floor and carried
downwards. For internal plaster, the plastering operations may be started wherever the building frame
and cladding work are ready and the temporary supports of the ceiling resting on the wall of the floor
have been removed. Ceiling plaster shall be completed before starting plaster to walls.
Page | 49
Part 3 : Conditions of Contract & Contract Forms
2.3.1. The plaster about 15x15 cms. shall be first applied horizontally and vertically at not more than 2
meters intervals over the entire surface to serve as gauge. The surfaces of these gauges shall be truly in
plane of the finished plastered surface. The mortar shall then be applied in uniform surface slightly
more than the specified thickness, then brought to a true surface by working a wooden straight edge
reaching across the gauges with small upward and sideways movements at a time. Finally, the surface
shall be finished off true with a trowel or wooden float according as a smooth or a smooth or a sandy
granular texture is required Excessive troweling or overworking the float shall be avoided. All corners,
arises, angles and junctions shall be truly vertical or horizontal as the case may be and shall be carefully
finished. Hounding or chamfering, corners, arises junctions etc. shall be carried out with proper
templates to be size required.
2.3.2. Cement plaster shall be used within half an hour after addition of water and mortar or plaster
which is partially set shall be rejected and removed forthwith from the site.
2.3.3. In suspending the work at the end of the day, the plaster shall be left out clean to the line both
horizontally and vertically, when recommencing the plaster, the edges of the old work shall be scraped
clean and wetted with cement putty before plaster is applied to the adjacent areas to enable the two to
properly join together. Plastering work shall be closed at the end of the day on the body of the wall and
nearer than 15 cm. to any corners or arises. It shall not be closed on the body of features such as plaster
bands and cornices not at the corners or arises. Horizontal joints in plaster work shall not also occur on
parapet tops and copings as these invariably lead to leakage. No portion of the surface shall be left out
initially to be packed up later on.
2.3.4. Each coat shall be kept damp continuously till the next coat is applied or for a minimum period
of 7 days. Moistening shall commence as soon as plaster is hardened sufficiently. Soaking of walls shall
be avoided and only as much water as can be readily absorbed shall be used, excessive evaporation on
the sunny or windward side of building in hot air or dry weather shall be prevented by hanging matting
or gunny bags oh the outside of the plaster and keeping them wet.
2.3.5. The plastering work shall be in single coat on brick / concrete wall for interior plastering up to
floor two level, finished even and smooth in C.M. 1:6.
2.3.6 The coat of cement and fine sand mortar of proportion 1:1 (1.5 mm thick about) shall be applied
to the plastered surface with a trowel to provide uniform texture while the base coat is still plastic.
2.3.7. In any continuous face of wall the finishing treatment should be carried out continuously and
day lo day breaks made to coincide with architectural breaks in order to avoid unsightly Junctions
The smooth concrete shall be suitably say read to provide necessary bond before plastering.
Page | 50
2.3.8. Curing : All the plaster work shall be kept damp continuously for a period 7 days.
3.1. The rate shall include the cost of all materials, labour and scaffolding etc. involved in the
operations described under workmanship.
3.2. All plastering shall be measured in square meters unless otherwise specified. Length breadth or
height shall be measured correct to a centimeter.
3.3. Thickness of the plaster shall be exclusive of he thickness of the key i.e. grooves or open joints in
brick work, stone work etc. or space between laths. Thickness of plaster shall be average thickness with
minimum 10 mm at any point on this surface.
3.5. The measurement of wall plastering shall be taken between the walls or partition (dimensions
before plastering being taken) for length and from the top of floor or skirting to ceiling for height.
Depth of cover of cornices if any shall be deducted.
3.6. Soffits of stairs shall be measured as plastering on ceilings, following soffits shall be measured
separately.
3.7. For jambs, soffits, sills etc. for openings not exceeding 0.5 sq. met each in area for ends of joints
beams, posts, girders, steps etc. not exceeding 0.5 sq.mt each in area and for openings exceeding 0.5.
sq.mt and not exceeding 3.00 sq.mt. in each area deductions and additions shall be made in the
following manners.
(a) No deductions shall be made for ends of joints, beams, posts etc. and openings not
exceeding 0.5 sq.mt each and no addition shall be made for reveals, jambs, soffits, sils etc. of these
openings, for finish to plaster around ends of joints, beams posts etc.
(b) Deduction for openings exceeding 0.5 sq.mt but not exceeding 3 sq.mt. each shall be made
as follows and no addition shall be made for ravels, jambs, soffits, sills etc. of these openings, (i) When
both faces of all wall are plastered with same plaster, deduction shall be made for one face only, (ii)
When two faces of wall are plastered with different types of plasters or if one face is plastered and the
other pointed, deductions shall be made from the plaster or pointing on the side of frame for door,
window etc. on which width of reveals is less than that on the other side but no deductions shall be
made on the other side. Where width of reveals on both faces of all are equal, deductions of 50% of area
of opening on each face shall be made from areas of plaster and / or pointing as the case may be.
3.8. For openings having door frames equal to or projecting beyond the thickness of wall, full
deduction for opening shall be made from each plastered face of the wall.
Page | 51
Part 3 : Conditions of Contract & Contract Forms
3.9. In case of openings of area above 3 sq.mt. each, deduction shall be made for openings but
jambs, soffits sand sills shall be measured.
3.10. The payment shall he made extra for this work over and above the plaster work
3.11. The rate shall he for a unit or 1 Kg of water proofing materials used in 1 bag of weighing 50 Kg.
cement used extra over the rate of plastering work.
Item 18: Providing 15mm thick MALA Trowel Finished cement plaster in single coat on brick/concrete
walls for interior plastering upto floor two level and finished even and smooth in (i) Cement mortar 1:4
(1-cement:4-sand) including Curing etc. complete. for Ground Floor
1.0. Materials
1.1. Water shall conform to M-1. The cement mortar of proportion 1:4 shall conform to M-13.
2.0. Workmanship
2.1. Scaffolding:
Wooden bullies, bamboos, planks, trestles and other scaffolding shall be sound. These shall be
properly examined before erection and use. Stage scaffolding shall be provided for ceiling plaster which
shall be independent of the walls.
2.2.1. The surface shall be cleaned of all dust, loose mortar droppings, traces of algae, efflorescence
and other foreign matter by water or by brushing. Smooth surface shall be toughened by wire brushing
if it is not hard and by hacking if it is hard. In case of concrete surface, if a chemical retarded has been
applied to the form work, the surface shall be roughened by wire brushing and all the resulting dust and
loose particles cleaned off and care shall be taken that none of the readers if left on the surface.
Trimming of projections on brick/concrete surfaces where necessary shall be carried out to get an even
surface.
2.2.2. Raking of joints in case of masonry where necessary shall be allowed to dry out for sufficient
period before carrying out the plaster work.
2.2.3. The work shall not be soaked but only damped evenly before applying the plaster. If the surface
becomes dry, such area shall be moistened again.
Page | 52
2.2.4. For external plaster, the pestering operation shall be started from top floor and carried
downwards. For internal plaster, the plastering operations may be-started wherever the building frame
and cladding work are ready and the temporary supports of the ceiling resting on the wall of the floor
have been removed. Ceiling plaster shall be completed before starting plaster to walls.
2.3.1. The plaster about 15x15 cms. shall be first applied horizontally and vertically at not more than 2
meters intervals over the entire surface to serve as gauge. The surfaces of these gauges shall be truly in
plane of the finished plastered surface. The mortar shall then be applied in uniform surface slightly
more than the specified thickness, then brought to a true surface by working a wooden straight edge
reaching across the gauges with small upward and sideways movements at a time. Finally, the surface
shall be finished off true with a trowel or wooden float according as a smooth or a smooth or a sandy
granular texture is required Excessive troweling or overworking the float shall be avoided. All corners,
arises, angles and junctions shall be truly vertical or horizontal as the case may be and shall be carefully
finished. Hounding or chamfering, corners, arises junctions etc. shall be carried out with proper
templates to be size required.
2.3.2. Cement plaster shall be used within half an hour after addition of water and mortar or plaster
which is partially set shall be rejected and removed forthwith from the site.
2.3.3. In suspending the work at the end of the day, the plaster shall be left out clean to the line both
horizontally and vertically, when recommencing the plaster, the edges of the old work shall be scraped
clean and wetted with cement putty before plaster is applied to the adjacent areas to enable the two to
properly join together. Plastering work shall be closed at the end of the day on the body of the wall and
nearer than 15 cm. to any corners or arises. It shall not be closed on the body of features such as plaster
bands and cornices not at the corners or arises. Horizontal joints in plaster work shall not also occur on
parapet tops and copings as these invariably lead to leakage. No portion of the surface shall be left out
initially to be packed up later on.
2.3.4. Each coat shall be kept damp continuously till the next coat is applied or for a minimum period
of 7 days. Moistening shall commence as soon as plaster is hardened sufficiently. Soaking of walls shall
be avoided and only as much water as can be readily absorbed shall be used, excessive evaporation on
the sunny or windward side of building in hot air or dry weather shall be prevented by hanging matting
or gunny bags oh the outside of the plaster and keeping them wet.
2.3.5. The plastering work shall be in single coat on rough (similar) side of single or half brick walls for
interior plastering up to floor two level, finished even and smooth in C.M. 1:4.
2.3.6 The coat of cement and fine sand mortar of proportion 1:1 (15 mm thick about) shall be applied
to the plastered surface with a trowel to provide uniform texture while the base coat is still plastic.
Page | 53
Part 3 : Conditions of Contract & Contract Forms
2.3.7. In any continuous face of wall the finishing treatment should be carried out continuously and
day lo day breaks made to coincide with architectural breaks in order to avoid unsightly Junctions
2.3.8. Curing : All the plaster work shall be kept damp continuously for a period 7 days.
2.3.9. Providing necessary grooves between structural members as directed by Engineer in charge.
3.1. The rate shall include the cost of all materials, labour and scaffolding etc. involved in the
operations described under workmanship.
3.2. All plastering shall be measured in square meters unless otherwise specified. Length breadth or
height shall be measured correct to a centimeter.
3.3. Thickness of the plaster shall be exclusive of he thickness of the key i.e. grooves or open joints in
brick work, stone work etc. or space between laths. Thickness of plaster shall be average thickness with
minimum 15 mm at any point on this surface.
3.5. The measurement of wall plastering shall be taken between the walls or partition (dimensions
before plastering being taken) for length and from the top of floor or skirting to ceiling for height.
Depth of cover of cornices if any shall be deducted.
3.6. Soffits of stairs shall be measured as plastering on ceilings, following soffits shall be measured
separately.
3.7. For jambs, soffits, sills etc. for openings not exceeding 0.5 sq. met each in area for ends of joints
beams, posts, girders, steps etc. not exceeding 0.5 sq.mt each in area and for openings exceeding 0.5.
sq.mt and not exceeding 3.00 sq.mt. in each area deductions and additions shall be made in the
following manners.
(a) No deductions shall be made for ends of joints, beams, posts etc. and openings not
exceeding 0.5 sq. mt each and no addition shall be made for reveals, jambs, soffits, sils etc. of these
openings, for finish to plaster around ends of joints, beams posts etc.
(b) Deduction for openings exceeding 0.5 sq. mt but not exceeding 3 sq.mt. each shall be made
as follows and no addition shall be made for ravels, jambs, soffits, sills etc. of these openings, (i) When
both faces of all wall are plastered with same plaster, deduction shall be made for one face only, (ii)
When two faces of wall are plastered with different types of plasters or if one face is plastered and the
other pointed, deductions shall be made from the plaster or pointing on the side of frame for door,
window etc. on which width of reveals is less than that on the other side but no deductions shall be
Page | 54
made on the other side. Where width of reveals on both faces of all are equal, deductions of 50% of area
of opening on each face shall be made from areas of plaster and / or pointing as the case may be.
3.8. For openings having door frames equal to or projecting beyond the thickness of wall, full
deduction for opening shall be made from each plastered face of the wall.
3.9. In case of openings of area above 3 sq.mt. each, deduction shall be made for openings but
jambs, soffits sand sills shall be measured.
3.10 The payment shall be made for a unit of 1.0 sq.mt of work done over an above the finishing of
work of base coat.
Item 19: Applying two coats of Birla (white cement based) or Asian (acrylic lapy- putty) or equivalent &
two coats of primer of approved brand and manufacture on new wall surface to give an even shade
including thoroughly brushing the surface free from mortar dropping and otherforeign matter and sand
papered smooth.
1.0. Materials
Water shall be conform M-1. The acrylic emulsion paint shall conform to I.S.: 5411-1969 (Part-l).
2.0. Workmanship
The painting work shall be of Birla (white cement based) or Asian acrylic lappy (putty) and two
coats of primer of approved brand & manufactures on new wall surface to give an even shade.
2.1. Scaffolding : Wherever scaffolding is necessary it shall be erected in such a way that as far as
possible on part of scaffolding shall rest against the surface to be white or colour washed A properly
secured strong and well tied suspended platform (Zoola) may be used for white washing. Where
ladders are used pieces of old gunny bags shall be tied at top and bottom to prevent scratches to the
floors and walls. For white washing of ceilings, proper stage scaffolding shall be erected where
necessary.
2.2. Preparation of surface : The undecorated surface to be distempered shall be thoroughly brushed
from dust, dirt, grease, mortar dropping and other foreign matter and sand papered smooth. New
plaster surface shall be allowed to dry for at least 2 months before applications of distemper.
2.2.1. All unnecessary nails shall be removed. Pitting in plaster shall be made good with plaster again
with a fine grade sand paper and made smooth. A coat of distemper shall be applied over the patches.
The surface shall be allowed to dry thoroughly before the regular coat of distemper is allowed. The
surface affected by moulds, moss, fungi, algae lichens, efflorescence etc. shall be treated in accordance
Page | 55
Part 3 : Conditions of Contract & Contract Forms
with I.S; 2395 (Part 01) 1966. Before applying distempering, any unevenness shall be made good by
applying putty made of plaster of pairs mixed with water on entire surface including filling up the
undulation and then sand papering the same after it is dry.
This shall be done as per manufacture's instructions. The thinning of emulsion is to be done with
water and not with turpentine. The quantity of thinner to be added shall be as per manufacturer
instructions.
2.4. Application :
2.4.1. Before pouring into small containers for use, the paint shall be stirred thoroughly in item
container. When applying also, the paint shall be continuously stirred in the smaller container, so that
its consistency is kept uniform.
2.4.2. The paint shall be laid on evenly and smoothly by means of crossing and laying off the crossing
and consist of covering the area over with paint, brushing the surface hard for the first time over and
then, brushing alternately in opposite direction two or three times and then finally brushing lightly in
direction at right angles to the same. In this process, no brush Marks shall be left after the laying off is
finished. No hair marks from the brush or clogging of paint puddles in the corners of panels, angles of
moldings, etc. shall be left on the work. The full process of crossing and laying off will constitute one
coat.
2.4.3. The paint shall be applied with brush or rollers. For undecorated surfaces, the surface shall be
treated with minimum two coats of cement water proofing paint. The second or subsequent coat shall
not be started until the proceeding coat as become sufficiently hard to resist marking by brushing being
used.
2.4.4. The surface on finishing shall present a flat velvety smooth finish. It shall be even and uniform in
shade without patches, brush marks, paint drops etc.
2.5. Precautions :
(a) Old brushes if they are to be used with emulsion paints shall be completely dried of
turpentine or oil paint by washing in warm soap water. Brushes shall be quickly washed in water
immediately after use and kept immersed in water fusing break periods to prevent the paint from
hardening on the brush.
(b) In the preparation of wall for plastic emulsion painting, no oil base petals shall be sued in
filling cracks, holes etc.
Page | 56
(c) Splashes on floors etc. shall be cleaned out without delay as they will be difficult to remove
after hardening.
(d) Washing or surfaces treated with emulsion paint shall not be done within 3 to 4 weeks of
application.
2.6. Protective measures : The surface of doors, windows, floors, articles, of furniture etc. and such
other parts of the building not to be white washed shall be protected from being splashed upon. Such
surfaces shall be cleaned of white wash splashed if any.
3.1. All the work shall be measured in the decimal system as under:
(b) Area in individual item shall be worked out to the nearest 0.01 sq.m.
All the work shall be measured in sq.mt. Deductions for jambs, soffits, sills etc. for openings not
exceeding 0.5 sq.mt. each in area, for ends of joists, posts, beams, girders, steps etc. not exceeding 0.5
sq.mt. each in area and for openings exceeding 0.5 sq.mt. and not exceeding 3.0. sq.mt. each in area,
deductions and additions shall be made as under.
3.2. No deductions shall be made for ends of joists, beams, posts, etc. and openings not exceeding
0.5 sq mt. each. No addition shall be made for reveals, jambs, soffits, sills etc. of these openings not for
finish around ends of joints, beams, posts etc.
3.3. No deductions for openings exceeding 0.5 sq.mt. but not exceeding 3 sq.mt. each shall be made
as follows and no addition will be made for reveals, jambs, soffits etc. of these openings :
(a) When both the faces of walls are provided with finish, deduction shall be made for one face
only.
(b) When each face of wall is provided with different finish, deduction shall be made for that
side of frame for door, windows, etc. on which width of reveals is less than that of the other side.
Where width of reveals on both faces of wall are equal, deduction of .50% of area of opening on each
face shall be made from total area of finish.
(c) When only one face of wall is treated and the other face is not treated, full deduction shall be
made if the width of reveal on the treated side is less than that on the untreated side, but if the width
of the reveal is equal or more than on the untreated side neither deductions nor additions to be made
for reveals, jambs, soffits, sills etc.
Page | 57
Part 3 : Conditions of Contract & Contract Forms
3..4 In case of area of openings exceeding 3 sq. mt. each, deductions shall be made for openings but
jambs, soffits, sills shall be measured.
3.5. No deductions shall be made for attachment such as casing, conducts, pipe, electric wiring and
the like.
3.6. Corrugated surfaces shall be measured flat as fixed and not girth. The quantities so measured
shall be increased by the following percentage and the resultant shall be included with the general
areas:
3.7. Cornices and other wall features, when they are not picked out in a different finish/colour shall
be girthed and included in the general area.
3.9. The rate shall include the cost of ail materials, labour, scaffolding, protective measures etc.
involved in all the operations described above.
Item 20: Wall painting (two coats) with plastic emulsion paint of approved brand and manufacture on
undecorated wall surface to give an even shade including throughly brushing the surface free from
mortar droppings and other foreign matter and sand papered smooth.
1.0. Materials
Water shall be conform M-1. The plastic emulsion paint shall conform to I.S.: 5411-1969 (Part-l).
2.0. Workmanship
The painting work shall be for subsequent coat of plastic emulsion paint of approved brand &
manufactures on undecorated wall surfaces and ceiling to give an even shade as directed.
2.1. Scaffolding : Wherever scaffolding is necessary it shall be erected in such a way that as far as
possible on part of scaffolding shall rest against the surface to be white or colour washed A properly
Page | 58
secured strong and well tied suspended platform (Zoola) may be used for white washing. Where
ladders are used pieces of old gunny bags shall be tied at top and bottom to prevent scratches to the
floors and walls. For white washing of ceilings, proper stage scaffolding shall be erected where
necessary.
2.2. Preparation of surface : The undecorated surface to be distempered shall be thoroughly brushed
from dust, dirt, grease, mortar dropping and other foreign matter and sand papered smooth. New
plaster surface shall be allowed to dry for at least 2 months before applications of distemper.
2.2.1. All unnecessary nails shall be removed. Pitting in plaster shall be made good with plaster again
with a fine grade sand paper and made smooth. A coat of distemper shall be applied over the patches.
The surface shall be allowed to dry thoroughly before the regular coat of distemper is allowed. The
surface affected by moulds, moss, fungi, algae lichens, efflorescence etc. shall be treated in accordance
with I.S; 2395 (Part 01) 1966. Before applying distempering, any unevenness shall be made good by
applying putty made of plaster of pairs mixed with water on entire surface including filling up the
undulation and then sand papering the same after it is dry.
This shall be done as per manufacture's instructions. The thinning of emulsion is to be done with
water and not with turpentine. The quantity of thinner to be added shall be as per manufacturer
instructions.
2.4. Application :
2.4.1. Before pouring into small containers for use, the paint shall be stirred thoroughly in item
container. When applying also, the paint shall be continuously stirred in the smaller container, so that
its consistency is kept uniform.
2.4.2. The paint shall be laid on evenly and smoothly by means of crossing and laying off the crossing
and consist of covering the area over with paint, brushing the surface hard for the first time over and
then, brushing alternately in opposite direction two or three times and then finally brushing lightly in
direction at right angles to the same. In this process, no brush Marks shall be left after the laying off is
finished. No hair marks from the brush or clogging of paint puddles in the corners of panels, angles of
moldings, etc. shall be left on the work. The full process of crossing and laying off will constitute one
coat.
2.4.3. The paint shall be applied with brush or rollers. For undecorated surfaces, the surface shall be
treated with minimum two coats of cement water proofing paint. The second or subsequent coat shall
not be started until the proceeding coat as become sufficiently hard to resist marking by brushing being
used.
Page | 59
Part 3 : Conditions of Contract & Contract Forms
2.4.4. The surface on finishing shall present a flat velvety smooth finish. It shall be even and uniform in
shade without patches, brush marks, paint drops etc.
2.5. Precautions :
(a) Old brushes if they are to be used with emulsion paints shall be completely dried of
turpentine or oil paint by washing in warm soap water. Brushes shall be quickly washed in water
immediately after use and kept immersed in water fusing break periods to prevent the paint from
hardening on the brush.
(b) In the preparation of wall for plastic emulsion painting, no oil base petals shall be sued in
filling cracks, holes etc.
(c) Splashes on floors etc. shall be cleaned out without delay as they will be difficult to remove
after hardening.
(d) Washing or surfaces treated with emulsion paint shall not be done within 3 to 4 weeks of
application.
2.6. Protective measures : The surface of doors, windows, floors, articles, of furniture etc. and such
other parts of the building not to be white washed shall be protected from being splashed upon. Such
surfaces shall be cleaned of white wash splashed if any.
3.1. All the work shall be measured in the decimal system as under:
(b) Area in individual item shall be worked out to the nearest 0.01 sq.m.
All the work shall be measured in sq.mt. Deductions for jambs, soffits, sills etc. for openings not
exceeding 0.5 sq.mt. each in area, for ends of joists, posts, beams, girders, steps etc. not exceeding 0.5
sq.mt. each in area and for openings exceeding 0.5 sq.mt. and not exceeding 3.0. sq.mt. each in area,
deductions and additions shall be made as under.
3.2. No deductions shall be made for ends of joists, beams, posts, etc. and openings not exceeding
0.5 sq mt. each. No addition shall be made for reveals, jambs, soffits, sills etc. of these openings not for
finish around ends of joints, beams, posts etc.
3.3. No deductions for openings exceeding 0.5 sq.mt. but not exceeding 3 sq.mt. each shall be made
as follows and no addition will be made for reveals, jambs, soffits etc. of these openings :
Page | 60
(a) When both the faces of walls are provided with finish, deduction shall be made for one face
only.
(b) When each face of wall is provided with different finish, deduction shall be made for that
side of frame for door, windows, etc. on which width of reveals is less than that of the other side.
Where width of reveals on both faces of wall are equal, deduction of .50% of area of opening on each
face shall be made from total area of finish.
(c) When only one face of wall is treated and the other face is not treated, full deduction shall be
made if the width of reveal on the treated side is less than that on the untreated side, but if the width
of the reveal is equal or more than on the untreated side neither deductions nor additions to be made
for reveals, jambs, soffits, sills etc.
3..4 In case of area of openings exceeding 3 sq. mt. each, deductions shall be made for openings but
jambs, soffits, sills shall be measured.
3.5. No deductions shall be made for attachment such as casing, conducts, pipe, electric wiring and
the like.
3.6. Corrugated surfaces shall be measured flat as fixed and not girth. The quantities so measured
shall be increased by the following percentage and the resultant shall be included with the general
areas:
3.7. Cornices and other wall features, when they are not picked out in a different finish/colour shall
be girthed and included in the general area.
3.9. The rate shall include the cost of ail materials, labour, scaffolding, protective measures etc.
involved in all the operations described above.
Page | 61
Part 3 : Conditions of Contract & Contract Forms
General
MATERIALS
2.1 Scaffolding :
Where scaffolding is required, it shall be erected in such a way that as far as possible no part of
scaffolding shall rest against the surface to be finished. A properly secured strong and well tied
suspended platform (joola) may be used for finishing of exterior wall. Where ladders are used, pieces of
old gunny bags shall be placed.
Workmanship:
The surface shall be cleaned of all dust, loose mortar droppings, traces of algae, efflorescence and
other foreign matter by water or by brushing. Smooth surface shall be toughened by wire brushing if it
is not hard and by hacking if it is hard. In case of concrete surface, if a chemical retarded has been
applied to the form work, the surface shall be roughened by wire brushing and all the resulting dust and
loose particles cleaned off and care shall be taken that none of the readers if left on the surface.
Trimming of projections on brick/concrete surfaces where necessary shall be carried out to get an even
surface.
Page | 62
3.0 MODE OF MEASUREMENT & PAYMENT :
3.4. The payment will be made on square meter basis of the finished work.
Item 22: Providing and fixing Green / Black granite in window jams of 16 mm to 18 mm thickness with
inside & out side Edge Half Round moulding and polishing of the stone, fixing with cement mortar and
filling the joints with necessary materials like araldite, with necessary fixtures and fastening etc.
complete or as directed By Engineer in Charge.
General
This work shall consist of providing and fixing machine cut free edges, pre mirror polished
Granite stone slab 16 to18 mm thick in single piece for windows jambs as per design of the shape and
dimensions and conforming to these specifications or as approved by the Engineer in charge.
1.0 MATERIAL
Water shall confirm to M-1. Cement Mortar shall confirm to M-11. Granite slab shall confirm to M-
52. Sand shall conform to M-6.
1.1. Granite slab shall be hard even sound, and regular in shape and generally uniform in colour. The
colour of the stone shall generally be green. Only approved coloured shall not be allowed for use. They
shall be without any soft veins cranks of flaws Granite slab shall be hard, even, and regular in shape and
it should without fault.
1.2. The size of the Granite slab to be used for flooring shall be of as approved by Engineer in charge
or Architect. However smaller sizes will be allowed to be used to the extent of maintaining required
pattern. Thickness shall be as specified. For windows jams the granite marble slab shall be in single
piece.
1.3. Tolerance of minus 30 mm. on accounts of chisel dressing of edges shall be permitted for length
as well as breadth. Tolerance in thickness shall be ±1 mm.
Page | 63
Part 3 : Conditions of Contract & Contract Forms
1.4. The edges of Granite slab shall be truly chiseled and table rubbed with coarse sand before
paving. All angles and edges of the stones of shall be true, square and free chipping and surface shall be
true and plain.
1.5. The Granite slab shall have machine cut free edges with half round pipe moulding mirror
polished surface. When brought on site. The stones to be used for flooring dedo, skirting, sink,
veneering, sills, steps, etc.
2.0 WORKMANSHIP
2.1 Granite slab shall be of approved quality shall be laid evenly to level and slope as directed by
Engineer in charge over a bed of a base layer consisting of cement mortar 1:6 (1 cement: 6 coarse sand
by volume).
2.2 Granite slab shall be laid evenly as per detailed drawing or as directed by Engineer in charge.
Width, length and shape of stone shall be as per pattern shown in detailed drawing.
2.3. Cement and sand for base layer shall be mixed in proportions of 1:6 (1 cement : 6 coarse sand by
volume). Cement and sand shall be proportioned by volume after making due allowance for bulking.
The require quantity of water shall then be added and the mortar mixed to produce workable
consistency before mixing platform shall be thoroughly cleaned before changing from one type of
cement to another.
2.4. The mixing for base layer shall be done intimately. The operation shall be carried out on clean
water tight platform, and cement sand shall be first mixed dry in the required proportion to obtain
uniform colour and then the mortar shall be mixed for at least two minutes after addition of water. In
case of cement mortar, that has suffered because of evaporation of water the same shall be re-
tempered by adding water as frequently as needed to restore the requisite consistency but its re-
tempering shall be permitted only within thirty minute from the time of addition to water at the time of
initial mixing.
Page | 64
2.5. Cement and sand for base layer shall be mixed in proportion as specified in the item, Cement
and sand shall be proportioned by volume after making due allowance for bulking. The required
quantity of water shall then be added and the mortar mixed to produce workable consistency.
2.6. Curing shall be started as soon as the mortar used for finished has hardened sufficiently no to be
damaged when watered. It shall be kept wet for a period of at least 7 days. During this period, it shall be
suitably protected from all damages.
2.7. During hot weather, all finished or partly finished work shall be covered or wetted in such
manner as will prevent rapid drying of the flooring work.
2.8. Joints of Granite slab flooring shall be through and continuous throughout the building as
directed by Engineer in charge.
2.9. Joints shall be filled with a stiff mixture of gray cement slurry.
2.10. The Granite slab flooring work shall be finished by rubbing and mirror polishing after the work of
flooring is set properly.
3.1. The unit rate of Granite stone flooring shall include the cost of all materials, tools and plant
required for mixing, laying of base layer in true level and slope as required applying & placing stones in
position, finishing, curing etc all over the length of windows jams etc. and all other incidental expenses
to complete the structure or its components according to these specifications. They shall also include
the cost of making, fixing and removing of all scaffolding and forms required for the work. The rate
includes cost of filling the joints with necessary materials like araldite, with necessary fixtures and
fastening etc. complete or as directed By Engineer in Charge including mirror polishing of flooring and
dado work.
3.2 The rate shall include the cost of all materials and labours involved in all the operations
described above. The granite stone slab shall be measured in square meter correct to 2 places of
Page | 65
Part 3 : Conditions of Contract & Contract Forms
decimal. Length and breadth shall be measured to correct to a centimeter and between the finished the
finished face of the skirting, dado or wall plaster and no deduction shall be made nor extra paid for any
opening in floors or areas up to 0.1 square meter.
Item 23: Steel Work,Providing M S Grill for Window, Ventilators, Wethershed , & Iron Double shutter
door With frame & Window Gril, using Riveted in buildt up sections framed work, chanels, Washers,
angles, flats, hollow section, Square Bar, Round bar, iron plates, including cutting,hoisting welding,
bending ,fixtures & fasting, fixing in position and applying a priming coat of lead paint… etc complated
as per Drawing & as directed by Engineer in charge
Materials
The structured steel work shall conform to M-22. Red lead paint shall conform to I.S : 102-1962.
2.0. Workmanship
2.1. Welding shall generally be done by electric process. Gas welding shall be resorted to, using
oxyacetylene flame with specific prior approval. Gas welding shall not be permitted for structural steel
work.
2.2. The work shall be done as shown in the shop drawings which should clearly indicate various
details of the joints to he welded, shop and site welded as well as type of electrodes to be used, symbol
for welding on plans and shop drawings shall be according to I.S. 813-1961. As far as possible every
effort shall be made to limit the welding that must be done after improper welding that is likely to be
done due to heights and difficult positions on scaffoldings etc. The welding work shall conform to I.S.
816-1969.
2.3. Preparation of surfaces : Surfaces which are to be welled together shall be free from loose mill
scale, rust, paint, grease or other foreign matter. A coating of boiled linseed oil shall be permitted.
2.4. Assembly for welding : Before welding is commenced, the plates shall first be brought together
and firmly clamped or spot welded at specified distance. This temporary connection has to be strong
enough to hold the plates accurately in place without displacement.
2.5. Precautions : All operations connected with welding and cutting equipment shall conform to
safety requirement given in I.S. 818-1968.
The following paints shall be borne in mind during the process of welding:
Page | 66
(b) Are length voltage and amperage shall be suited to the thickness of material type of groove and
other circumstances of the work.
(c) The segments of welding shall be such that where possible the members which offer the
greatest resistance to compression are welded first.
2.6. The defective welds which shall be considered harmful to the structural strength shall cut out
and rewarded.
2.7. Finished welds and adjacent parts shall be protected with clean boiled linseed oil and after all
stag has been removed. Welds and adjacent parts shall be painted after the same are approved.
2.8. All the members shall be thoroughly cleaned of rust-scales, dust etc. and given a priming coat of
red lead paint before fixing them in position.
(a) All work shall be measured on the basis of finished dimensions as fixed at site and measured
net unless specified otherwise.
(b) The weight of steel sections, steel rods, and steel strips in finished work shall be calculated
Hum standard weight on the same basis on which steel is supplied to Contractor by department or
those given in relevant I.S. if steel is arranged by the contractor.
(c) The weight of steel plates and strips shall be taken from relevant I.S. based on 7.35 kg./ sq.
meter for every millimeter sheet thickness if steel is supplied to the contractor by department.
(d) Unless otherwise specified, weight of cleats, brackets, packing pieces, bolts, nuts, washer,
distance pieces, separators, diaphragm gusset (taking overall square dimensions) fish plates etc. shall
be added to the weight of respective items.
(e) In riveted work allowance is to be made for weight of rivet hands. No deductions shall be
made for rivet or bolts holes excluding holes for anchor or holding down bolts.
(f) For forged steel and steel castings, weight shall be calculated on the basis of 7850 kg./cum.
(g) Unless otherwise specified, no allowance shall be made for the weld metal in case of welded
steel structure.
Page | 67
Part 3 : Conditions of Contract & Contract Forms
(h) Dimensions other than cross sections and thickness of plates shall be measured to nearest
0.001m
3.2. The rate includes cost of all material, labour, erection, hoisting scaffolding, protective measures,
required for proper completion of the item of work. This shall also include conveyance and delivery
handling, loading, unloading and storing etc. required for completing the item described above
including necessary wastage involved.
Item 24: Painting two coats (excluding priming coat) on new steel and other metal surface with enamel
paint, brushing, interior to give an even shade including cleaning the surface an even shade including
cleanicn the surface of all dirt, dust and other foreign matter.
1.0. Materials
2.0. Workmanship
2.1. General : The materials required for work of painting work shall be obtained directly from
approved manufactures or approved dealer and brought to the site in maker's drums; kegs etc. with
seal unbroken.
2.1.2. All materials not in actual use shall be kept properly protected, lids of containers shall be kept
closed and surface of paint in open or partially open containers covered with a thin layer of turpentine
to prevent formation of skin. The materials which have become state or flat due to improper and long
storage shall not be used. The paint shall be stirred thoroughly in its container before pouring into small
containers. While applying also, the paint shall be continuously stirred in smaller container. No left over
paint shall be put back into stock tins. When not in use the containers shall be kept properly closed.
Page | 68
2.1.3. If for any reasons, things is necessary, the brand of thinner recommended by the manufacturer
shall be used.
2.1.4. The surface to be painted shall be thoroughly cleaned and dusted. All rust, dirt and grease shall
be thoroughly removed before painting is started. No painting on exterior or other exposed part o the
work shall be carried out in wet, damp or otherwise unfavorable weather and all the surfaces shall be
thoroughly dry before painting work is started.
2.2.1. Brushing operations are to be adjusted to the spreading capacity advised by the manufacture of
particular paint. The paint shall be applied evenly and smoothly by means of crossing and laying off. The
crossing and laying off consists of covering the area over with paint, brushing the surface hard for the
first time over and then brushing alternately in opposite directions two or three times and then finally
brushing lightly in a direction at right angles to the same. In this process, no brush marks shall be left
after the -laying off is finished. The full process of crossing and laying off will constitute one coat.
2.2.2. Each coat shall be allowed to dry completely and lightly rubbed with very fine grade of sand-
paper and loose particles brushed off before next coat is applied. Each coat shall vary slightly in shade
and shall be got approved from Engineer-in-charge before next coat is started.
2.2.3. Each coat the last shall be lightly rubbed down with sand paper of fine pumice stone and
cleaned of dust before the next coat is applied. No hair marks from the brush of clogging of paint
puddles in the corners of panels, angles of moldings etc. shall be left on the work.
2.2.4. Special care shall be taken while painting over bolts, nuts, rivets, overlaps etc. Approved best
quality brushes shall be used.
3.1.The new steel and other metal surface shall be measured under this item.
3.2.All the work shall be measured net in the decimal system, as executed subject to the following limits
unless otherwise stated hereinafter.
(b) Areas shall be worked out to the nearest 0.01 sq. meter.
3.3. No deductions shall be made for openings not exceeding 0.5 sq. mt. each and no addition shall
be made for painting to beddings, moldings, edges, jambs, soffits, sills etc. of such opening.
3.4. In case of fabricated structural steel and iron work, priming coat of paint shall be included with
frabation. In case of trusses if measured in sq. m. compound girders, stanchions, lattices, grader and
Page | 69
Part 3 : Conditions of Contract & Contract Forms
similar work, actual area shall be measured in sq. m. and no extra shall be paid for painting on bolts
heads, nuts, washers etc. No addition shall be made to the weight calculated for the purpose of
measurements of steel and iron works for paint applied on shop or at site.
3.5 The rate is excluding priming coat.The rate shall be for a unit of One sq. meter.
Item 25: Providing and fixing window having extruded aluminum Colour anodized section frame main
outer size 95mm x 24mm x 1.17mm (of Jindal Section no:2459 @ wt.of 0.738 Kg/mt), horizontal Three
track member size 92mm x 31.75mm x 1.30mm (of Jindal Section no:8688,@ Wt.1.07 Kg/mt), vertical
member of size 92mm x31.75mm x 1.50mm (of Jindal Section no:8933,@ Wt. 1.06 Kg/mt) with
sliding shutters of horizontal member size 40 mmx18mm x1.29mm (of Jindal Section no:8947@ wt.of
0.456 Kg/mt), vertical member of size 40mm x 18mm x 1.29 mm (of Jindal Section no:8949 @ wt.of
0.456Kg/mt/ with 5 mm thick transparent bronze colour tinted float glass with powder coated
aluminum fittings and fixtures and transparent silicon sealant glass fixing to frame as per details etc
1.0 MATERIALS
1.1 Standard extruded anodized Alluminium section allows used in the manufacture of extruded
section shall confirm to I.S. designation HEA - WP of IS 733 - 1975 and also designation WVG - WP of IS
1285 - 1975 section shall be as specified in the drawing a design or as directed by Engineer-in-charge. All
section shall be free from scratches holes or any damages on surface. All section shall have finished
plaster surface on all sides.
1.1.1. The work includes standard extruded of Aluminium section of size 95mm x 24mm x 1.17mm (of
Jindal Section no:2459 @ wt.of 0.738 Kg/mt), horizontal Three track member size 92mm x 31.75mm x
1.30mm (of Jindal Section no:8688,@ Wt.1.07 Kg/mt), vertical member of size 92mm
x31.75mm x 1.50mm (of Jindal Section no:8933,@ Wt. 1.06 Kg/mt) with sliding shutters of horizontal
member size 40 mmx18mm x1.29mm (of Jindal Section no:8947@ wt.of 0.456 Kg/mt), vertical member
of size 40mm x 18mm x 1.29 mm (of Jindal Section no:8949 @ wt.of 0.456Kg/mt/ with 5 mm thick
transparent bronze colour tinted float glass with powder coated aluminum fittings and fixtures and
transparent silicon sealant glass fixing to frame as per details etc as directed by Engineer in charge.
1.2 Glass : The transparent bronze colour tinted float glass of louvers fixed to alluminium strip blade
shall be of approved make having thickness of 5mm. The glass shall be clear and free from scratches
and cracks. The glass shall be provided on wall panel and fixed with tinted silicon gasket.
1.2.1 The glass shall be of the brief quality, free from specks, bubbles, smoken veins, air holes distress
and other defects. The kind of glass to be used shall be as mentioned in the item or as shown in detailed
drawing or as directed by Engineer-in-charge.
Page | 70
1.3. Glazing clips: Glazing clips shall be colour marble jambs all around the ventilator shall be free
from any scratches or holes or any damage of on surface all section shall have finished luster surface on
all sides.
1.4 Rubber Gasket : Rubber gasket shall be approved make shall be free from any scratches or holes
or any damage on surface and shall have finished luster surface on all sides.
1.5. Fixtures
1.5.1. Hinges shall be of approved make shall be free from any scratches or holes or any damage on
surface and shall have finished luster surface on all sides.
WORKMANSHIP
The work of standard extruded of Aluminium section for window shall be done with extreme
finishing. The inclined blades shall be fixed as directed by Engineer-in-charge. 5 mm thick transparent
bronze colour tinted float glass shall be fixed on blades.
The unit rate of standard extruded of Aluminium section for window shall include the cost of all
labours, materials, anodizing charges, tools, plants, cost of necessary fixtures & fastenings.
Item 26: Providing Curtain of Vertical blinds with runners, blind ferbic, rollar thread, manual powder
coated channel with necessaray fiiitings, fixtures & fastening for moving of blinds etc completed as
directed by Engineer in charge.
It shall be provided with Curtain of Vertical blinds with runners, blind ferbic, rollar thread, manual
powder coated channel with necessaray fiiitings, fixtures & fastening for moving of blinds etc
completed as directed by Engineer in charge.
The Measurement and payment shall be made on sq.mt. basis of completed finished work.
Item 27: Providing and fixing black / Green granite two frame for door Jems of 16mm to 18 mm
thickness with outside & inside Half Round moulding and polishing both sides of the stone, fixing with
Page | 71
Part 3 : Conditions of Contract & Contract Forms
cement mortar and filling the joints with necessary materials like araldite, with necessary fixtures and
fastening etc. complete or as directed by Engineer in Charge.
The work shall be executed as per specification of Item No.22 except the work is for providing and
fixing black / Green granite two frame for door Jems of 16mm to 18 mm thickness with outside & inside
Half Round moulding and polishing both sides of the stone, fixing with cement mortar and filling the
joints with necessary materials like araldite, with necessary fixtures and fastening etc. complete or as
directed by Engineer in Charge.
Item 28: Providing and fixing 35 mm thick shutters for Doors, windows and clerestory windows
including Indian teak wood frames 12 cm x 7 cm size including anodized aluminum fixtures and
fastenings including primer coat of approved quality and two coats of oil painting etc complete. (ii)
Fully paneled
1.0. Materials
Flush door shall conform to M-30. Plywood shall conform to M-37. Anodised aluminum butt hinges shall
conform to M-43.
2.0. Workmanship
The item covers the requirement of preparation of shutters for doors, windows, clerestory windows,
their supply and fixing.
2.1.1. Indian teak wood frames 12 cm x 7 cm size including paneled shutters shall be constructed in the
form of timber frame work of styles and rails with panel inserted of type as specified in the detailed
drawings. Panel shall be fixed by providing grooves in the style and rails. The styles and rails shall be
joined to each other by mortise and tenon joints at right angles. The shutters be non decorative type
and block board core with face veneer or plywood with 35 mm. thickness.
2.1.2. All members of the shutters shall be straight without any warp or bow and shall have smooth,
well planed faces at right angles to each other.
2.1.3. The size of styles and rails shall be as per drawings or as directed. Styles and rails of shutters
shall be made of one piece only.
Page | 72
2.2.1. Thickness of the panel shall be as specified in the item as shown in the drawing or as directed. If
the panel is made from more than one piece the pieces shall be finished as shown in the detailed
drawings and shall be joined with continuous groove with specified size. The end pieces of the panel
and the top and bottom of the panel shall be provided with continuous tongue to frame into groove of
the frame shutter. An air space of 1.5 mm. shall be left in the groove of frame of shutter while framing
the panels in it.
2.2.2. The faces of the panel as well as various pieces of the panel shall be- closely fitted to the sizes of
the grooves.
2.2.3. Finishing of the corners of raised panel edges shall be done as shown in drawings or as directed.
2.2.4. The thickness specified shall be finished thickness and no tolerance will be permitted.
2.3.1. The rate shall include anodized aluminum fixtures, fastenings and butt hinges including fixing
with iron screws. The size and number of hinges shall be as per standard. Door lock & stainless steel
handles are to be provided as directed.
2.3.2 The rate shall include primer coat of approved quality and two coats of oil painting etc complete
for Fully paneled
3.1. The rate for shutter includes cost of providing block and cleat for keeping the shutter in open
position if directed.
3.2. The dimension of the shutter shall be measured clear size of the shutter in close position
between the grooves of the frame.
Marbo Grenite Tiles captures the charm and character of natural marble and granite. Marble and
Granite being natural stone, variation to shade & pigmentation with in a batch is a natural occurrence
and accepted by the industry as normal. This variation adds unique beauty to the finished surface.
Page | 73
Part 3 : Conditions of Contract & Contract Forms
It should be confirmed to Indian or International standard shall be of specified size and make or
equivalent. Tiles shall be free from cracks, grazes, spots, chipped edges and corners. Variation in size
shall belimited to + 1.5 mm. Thickness shall be 8 to 10 mm thick.
Bed of tiles
This shall be 12mm thick cement mortar 1:3 (1-cement: 3-coarse sand). Water, cement and sand shall be
as per item no. 2. Mortar of proportion 1:3 shall be laid over wire brushed cleaned, wetted and mopped
prepared back-ground.
Workmanship
Tiles shall be laid in accordance to IS specifications and instructions of Engineer-in-charge. Tiles shall be
fixed by using tile adhesive (cement based) as specified about 3-6 mm on floor. Adhesive well combed
and tile fixed with twist method to correct position. Tiles shall be positioned by tapping with wooden
hammer and level checked with straight edge 2-3 metre long. Joints shall be as as thin as possible.
Joints shall be cleaned thoroughly and grouted with site made white cement grout or as directed by the
Engineer. Joints shall be cleaned thoroughly and grouted with site made grout. White or colour grout
shall be prepared by mixing quartz powder with colour pigments added to cement as per colour of tiles
or as directed by the Engineer. Grout shall be a thick paste and tooled into joints and area of the tile
cleaned with a damp cloth. Grouting shall be cured by wet curing for 7 days.
Mode of Payment
he Unit rate flooring shall include the cost of all material,tool and plant required for mixing, laying of
base layer in true level and slope as required applying & placing tiles in position, compacting, curing
mirror polishing.
Page | 74
Payment shall be made on the basis of Sqm of work done.
Item 30: Providing and laying Ceramic tiles 6mm thick in skirting risers of steps and dado on 10mm thick
cement plaster 1:3 (1-cement : 3-coarse sand) and jointed with white cement slurry (upto 10 Ton)
1.0. Materials
Water shall conform to M-1. Cement mortar shall conform to M-11. Ceramic tiles 6mm thick in
skirting risers of steps and dado on 10mm thick cement plaster 1:3 (1-cement : 3-coarse sand) and
jointed with white cement slurry as approved by Engineer in charge and shall conform to relevant
Indian standard.
2.0. Workmanship
In case of brick masonry wall, the joints shall be raked out to a depth of least 10 mm. while the
masonry is being laid. In case of concrete wall the surface shall be chiseled and roughed with wire
brushes. The surface shall be cleaned and wetted thoroughly before commencing the laying work.
2.2. Laying ;
2.2.1. The wall surface shall be covered with 10 mm. thick plaster of cement plaster 1:3 mix and allowed
to harden. The plaster shall be roughened with wire brushes both way. The back of tiles shall be floated
with grey cement slurry set and edges with white cement slurry in bedding mortar. The tiles shall be
gently tapped in position on after the other keeping the joints as thin as possible. Top of skirting or
dedo shall be truly horizontal and the joints vertical or as per required pattern.
2.2.2. Risers of steps, skirting and dedo shall rest on top of treads or flooring where full size tiles
cannot be fixed. They shall be cut to the required size and the edges be smoothened.
2.2.3. The joints shall be cleaned and flush pointed with white cement. The surface shall be kept wet
for seven days. After curing the surface shall be washed clean.
3.1. The rate shall include the cost of all materials and labour required for various operations
described above.
Page | 75
Part 3 : Conditions of Contract & Contract Forms
Risers of steps : skirting and dedo shall be measured in square meters, length and height shall be
measured along the finished face of the skirting or dedo including curves, where special such as covers
internal and external angles, etc. used. The length and height shall be measured correct lo the
centimeter except in case of risers and skirting where height shall be measured correct to 3 mm.
Item 31: Providing and laying Ceramic tiles 6mm thick in flooring treads of steps and landing laid on a
bed of 12mm thick cement mortar 1:3 (1- cement : 3- coarse sand ) finishing with flush pointing in white
cement. (upto 10 ton)
The work shall be executed as per specification of Item No.22 except the work is for Providing and
laying Ceramic tiles 6mm thick in flooring treads of steps and landing laid on a bed of 12mm thick
cement mortar 1:3 (1- cement : 3- coarse sand ) finishing with flush pointing in white cement.
Item 32: Providing and fixing eco-friendly light weight calcium silicate false ceiling tiles having regular
edge & 15 mm Thick Densified edges on the Tile Periphery for Extra Strength The Light weight calcium
silicate ceiling tiles shall have , light reflection 85% non combustible as per B.S. 476 part IV, 100%
humidity resistance and also having thermal conductivity0.043° w/m KC.for the best thermal Insulation .
The Light weight calcium Silicate tile shall be of approved texture Fine fissured/ Spintone/Cosmos
having NRC value of
0.5 & Globe having NRC value of 0.75 NRC or
equivalent of size 595 X 595 mm to be laid on true horizontal level suspended inter locking metal grid of
hot dipped galvanized steel sections (galvanizing @120 grams per sqm including both side) consisting
of main ‘T’ runner suitably spaced at joints to get required length and size of 24X38mm made from 0.30
mm thick (minimum) sheet, 1200mm centre to centre, and cross ‘T’ of size 24X28mm made out of
0.33mm (Minimum) sheet spaced 1200mm along spaced between main ‘T’ at 600mm centre to centre
to form agrid of 1200X600mm and secondary cross ’T’ of length 600mm and size 24x28mm made
of 0.30 mm thick (Minimum) sheet to be interlocked at middle of the 1200X600mm panel to form grid
of size 600X600mm resting on periphery walls/partitions on a perimeter wall angle pre- coated steel of
size (24X24X3000mm made of 0.40mm thick (minimum) sheet with the help of rawl plugs at 450mm
centre to centre with 25mm long dry wall screws @ 230mm interval and laying 15mm thick Densified
edges light weight calcium silicate ceiling tiles of approved texture (Fine Fissured/Cosmos/Spintone) in
Page | 76
the grid including, cutting /making opening for services like diffusers, grills, light fittings, fixtures,
smoke detectors etc., wherever required, Main ‘T’ runners to be suspended from ceiling using G.I.
slotted cleats of size 25X35X1.6mm fixed to ceiling with 12.5mm dia and 50mm long dash fasteners,
4mm G.I. adjustable rods level clips of size 85X30X0.8mm, spaced at 1200mm centre to centre long
main ‘T’ bottom exposed with 24mm of all T-sections shall be pre-baked paint, for all heights, as per
specifications, drawings and as directed by engineer-in-charge.Note:- Only calcium silicate false ceiling
area will be measured from wall to wall. No deduction shall be made for exposed frames/opening (cut
outs) having area less than 0.30 sqm. The calcium silicate ceiling tiles shall have NRC. Value of 0.50
(Minimum) for Fine fissured/Spintone/Cosmos and 0.75 NRC for Globe, light reflection 85% non-
combustible as per B.S. 476 part IV, 100% humidity resistance and also having thermal conductivity.
0.043° w/m KC.for the best thermal Insulation.
Providing and fixing eco-friendly light weight calcium silicate false ceiling tiles having regular edge & 15
mm Thick Densified edges on the Tile Periphery for Extra Strength The Light weight calcium silicate
ceiling tiles shall have , light reflection 85% non combustible as per B.S. 476 part IV, 100% humidity
resistance and also having thermal conductivity0.043° w/m KC.for the best thermal Insulation .
The Light weight calcium Silicate tile shall be of approved texture Fine fissured/ Spintone/Cosmos
having NRC value of
0.5 & Globe having NRC value of 0.75 NRC or
equivalent of size 595 X 595 mm to be laid on true horizontal level suspended inter locking metal grid of
hot dipped galvanized steel sections (galvanizing @120 grams per sqm including both side) consisting
of main ‘T’ runner suitably spaced at joints to get required length and size of 24X38mm made from 0.30
mm thick (minimum) sheet, 1200mm centre to centre, and cross ‘T’ of size 24X28mm made out of
0.33mm (Minimum) sheet spaced 1200mm along spaced between main ‘T’ at 600mm centre to centre
to form agrid of 1200X600mm and secondary cross ’T’ of length 600mm and size 24x28mm made
of 0.30 mm thick (Minimum) sheet to be interlocked at middle of the 1200X600mm panel to form grid
of size 600X600mm resting on periphery walls/partitions on a perimeter wall angle pre- coated steel of
size (24X24X3000mm made of 0.40mm thick (minimum) sheet with the help of rawl plugs at 450mm
centre to centre with 25mm long dry wall screws @ 230mm interval and laying 15mm thick Densified
edges light weight calcium silicate ceiling tiles of approved texture (Fine Fissured/Cosmos/Spintone) in
the grid including, cutting /making opening for services like diffusers, grills, light fittings, fixtures,
smoke detectors etc., wherever required, Main ‘T’ runners to be suspended from ceiling using G.I.
slotted cleats of size 25X35X1.6mm fixed to ceiling with 12.5mm dia and 50mm long dash fasteners,
4mm G.I. adjustable rods level clips of size 85X30X0.8mm, spaced at 1200mm centre to centre long
Page | 77
Part 3 : Conditions of Contract & Contract Forms
main ‘T’ bottom exposed with 24mm of all T-sections shall be pre-baked paint, for all heights, as per
specifications, drawings and as directed by engineer-in-charge.
Note:- Only calcium silicate false ceiling area will be measured from wall to wall. No deduction shall be
made for exposed frames/opening (cut outs) having area less than 0.30 sqm. The calcium silicate ceiling
tiles shall have NRC. Value of 0.50 (Minimum) for Fine fissured/Spintone/Cosmos and 0.75 NRC for
Globe, light reflection 85% non- combustible as per B.S. 476 part IV, 100% humidity resistance and also
having thermal conductivity. 0.043° w/m KC. for the best thermal Insulation.
The payment shall be made for a unit of one square meter including materials & labour used for
the same work.
Item 33: Constructing Sandwitch Platform of 18 to 25 mm thick Polished Black Granite at top and 25
mm thick Kota stone slab using cement mortar 1:3 for sandwich and fitting at bottom & edges with
waterproof rigid adhesives including
macking necessary grooves in walls with Vertical Kotastone 30 mm x 2 No sandwitch thick every 60
cm centre to cenre including all labour material of approved quality incl. full moulded round front edge
fixed in wall for partition and jointed with grey cement slurry including rubbing and polishing etc.
complete
Materials :
Water shall confirm to M-1. Cement shall confirm to M-3. Sand shall confirm to M-6, burnt brick
shall confirm to M-15. Rough kota stone shall confirm to M-48. Granite shall to M-52.
Workmanship :
Item No. 96 comprises of 18 mm thick polished granite stone at top and 25mm thick Kota stone slab of
approved quality.
The sand witch type platform shall be erected with 2 Nos. on three places of 18mm thick polished
granite stone with a height of 75 cm. and 0.75 width and with horizontal shelves of 60 cm x 75 cm.
making groove of at least 50 mm in existing wall and vertical granite stone shall be inserted on to the
groove and 60 cm. shall be clear from the wall surface shall be visible. The height of granite stone shall
be 80 cm. from the floor surface. Each stone shall be erected at a distance of at least 25 mm. and shall
be filled it with cement mortar of 1:3 (1: cement, 3 : coarse sand). The rough Kotah stone shall be laid
Page | 78
horizontally over the vertical post. The bedding of cement mortar of 1:3 (1 cement, 3 coarse sand) shall
be laid on top of at least 20 mm in thickness. After laying of bedding the 18 mm thick granite stone shall
be laid in line and level so as to drain of the water easily on to the kitchen sink. The space for the sink
shall be cut to the size of sink with the help of cutting machine. The edges of the Kitchen platform shall
be covered with 10 cm. thick strip and shall be fixed with glue i.e. by epoxy type materials i.e. resin and
hardener (Araldite type materials) and kept the same for curing up to 12 hours. The edges of the vertical
strip shall be made half round by grinding machine and the grinded surface shall be polished as good as
top surface. The granite stone shall be of approved quality as per the instruction of Engineer-in-charge.
Item 34: Providing and fixing chromium plated brass half trun flush cock of approved quality including
fixing in pipe line etc. complete ( ii ) 25 mm dia.
General
This work shall consist of providing and fixing chromium plated brass half trun flush cock of approved
quality including fixing in pipe line etc. complete 25 mm dia. as approved by the Engineer in charge.
1.0 MATERIAL
Flush Cock
1.1. Half turn flush cosfc (Heavy weight) shall be of gun metal chromium plated of diameter as
specified in the description of the item. The flush cock shall conform to relevant Indian Standard.
2.0. WORKMANSHIP
2.1. When the Flush cock is to be fitted, the ends shall be carefully filed out so that no obstruction to
bore in offered. The Bib cock shall be fitted with pipes carefully in such a manner as will not result in
slackness of joints when the two pieces are screwed together
Page | 79
Part 3 : Conditions of Contract & Contract Forms
2.2 In jointing the Flush cock the inside of the socket and the screwed end of the Flush cock shall be
oiled and smeared with the white or red lead and wrapping around with a few turns of fine spun yarn
round the screwed end of the Flush cock. The end shall then be tightly screwed in the socket, Tees etc
with a pipe wrench Care shall be taken that all items are free from dust, dirt and rust during fixing Burr
from the joints shall be removed after screwing After laying the open ends of the Flush cock shall be
temporarily plugged to prevent excess of water soil or any other foreign matter.
2.3. Any threads exposed after jointing shall be painted or in the case of underground piping thickly
coated with approved anti corrosive paint to prevent corrosion.
TESTING OF JOINTS
After fitting, the Flush cock shall be inspected under working conditions of pressure and flow. Any
joints found liken shall be redone, and all leaking Flush cock shall be removed and replaced without
extra cost.
The Flush cock after they are fitted shall be tested to hydraulic pressure of 6 kg / sq. cm. The Flush cock
shall be slowly and carefully charged with water allowing all air to escape and avoiding all shock and
water hammer. The draw off takes and stop cock shall then be closed and specified hydraulic pressure
shall be applied gradually. The Flush cock shall be tested in sections as the work laying proceeds,
veeping the joints exposed for inspection during the testing.
3.1. The unit rate of full turn brass flush tap shall include the cost of all materials, tools and plant
required for fitting, the same to specified position as per drawings, and as directed by Engineer in
charge finishing structure, etc. and all other incidental expenses for producing Flush cock work to
complete the structure or its components as shown on the drawings, and as directed by Engineer in
charge and according to these specifications. They shall also include the cost of making, fixing and
removing of all scaffolding and forms required for the work.
Page | 80
The rate of chromium plated brass half trun flush cock shall include the cost of all labour,
materials, G. I. fittings as required, tools and plant scaffolding and all incidental expenses as described
herein above including testing.
3.2. The chromium plated brass half trun flush cock shall be measured for its Number, limiting
dimensions to those specified on plan or as directed. The rate shall be for a unit of one number.
3.3. The payment will be made on number basis of the finished work.
Item 35: Providing and laying Urinal Flow Sensor Urinal( Star White Color) Make by Hindware including
installing and fitting as per manufacturers standards by skilled trained plumber including testing etc
complete quality and brand as approved by Engineer in charge.
MATERIAL
This work shall consist of providing and fixing Urinal Flow Sensor Urinal (Star White Color) make by
Hindware as approved by the Engineer in charge.
WORKMANSHIP:
This work shall be performed by installing and fitting as per manufacturers standards by skilled trained
plumber including testing etc complete quality and brand as approved by Engineer in charge.
Item 36:Providing laying and jointing in true line and level, Consil 25mm dia. U.P.V.C. Pipe
(SCH- 40) for cold water including fittings make PRINCE / SUPREME / ASTRAL / FINOLEX or equivalent
as approved by Engineer In Charge. Pipe shall be fixed on the wall with the help of clamp at every two
metre C/C or shall be concelled as directed including necessary 25mm tube MT fittings, such as such
ruducing coupler, union, band plug, endcap, pipe clip, Tee, hex nipple, elbow, cuopler,..etc complete As
directed By Engineer in Charge & using bonding materials.fittings etc. including testing of pipe and
joints and fixing the same with adhesive solvent, including cost of all materials, Labours. Etc.
1.0 Materials
1.1. The specified dia. U.P.V.C. pipes of ISI mark of approved quality shall be used.
Page | 81
Part 3 : Conditions of Contract & Contract Forms
2. Workmanship
U.P.V.C. pipes and fittings shall be of the diameter, size and type specified in the item. The pipe shall be
full lengths of 2 meter as far as possible. All the pipes shall be fixed on wall face at locations indicated
on drawings or as ordered by the Engineer-in-charge. Pipe shall be secured to face of wall below all
joints by M.S. clamps with wooden gut ties. The spigot of the upper pipe shall be properly fitted into
the socket of the lower pipe such that there is uniform annular space for fitting with the jointing
materials. One third depth of annular space between the item. The pipe shall be full lengths of 2 meter
as far as possible. All the pipes shall be fixed on wall face at locations indicated on drawings or as
ordered by the Engineer-in-charge. Pipe shall be secured to face of wall below all joints by M.S. clamps
with wooden gut ties.The spigot of the upper pipe shall be properly fitted into the socket of the lower
pipe such that there is uniform annular space for fitting with the jointing materials. One third depth of
annular space between the socket and the spigot shall be filled with spun-yarn soaked in bitumatic
jointing compound and shall be pressed home by means of caulking tool. The remaining 2/3 depth of
the joints shall be filled in with stiff cement mortar 1:2 and shall be pressed with caulking tool and
finished smooth at top at an angle of 45 sloping up. The joints shall be filled with cement mortar 1:2 (1
cement : 2 sand) span spun yarn. The joints shall be filled with cement mortar 1.2 (1 cement : 2 sand) and
spurn yarn. The pipes without care shall be fixed to wall with M.S. clamps The pipes will earns shall be
secured with 100 mm before steel or iron barrel distance pieces or boils and stout galvanised iron nails
10 cms long into hand wool plug fixed in walls. Access doors to fittings shall be provided with 3 mm.
rubber insertion packing and secured without screws to made air and water tight.All soil pipes shall be
earned up above the roof and shall have a wire ball on guarded or a cowl.The ventilating pipe or shaft
shall be carried out to a height of at least one meter above the outer covering of the roof of the
building or in the case of windows in a gable wall or a dormer windows, it shall carried up to a ridge of
the roof or at least tow meters above the top of the windows. In case of flat roof to which access for
use is provided, it shall be carried out up to a height of at least on meter above the parapet or two
meters measured vertically from the top of any windows or opening which any exist up to a horizontal
distance of five meters from the vent pipe into such building and in no case shall be carried out to a
height less then three meters.Where ventilating pipes are carried in pipe shafts, the shaft shall be of a
minimum size of one meter. If !he shells are also used to give fight and air to rooms, the ventilating
pipes must be carried out to a horizontal distance at root level not loss than five meter from the site of
the shaft. The sand cast iron pipes above parapet shall be fixed with M.S. clamps and stays. The clamps
shall be made from 1.5 mm. thick MS flat or 3 mm. width band to the required shape and size to fit
tightly one the sockets when tightened with screw bolts. It shall be formed of two semi circular pieces
with flanged ends on both sides, with holes to fit in the screw bolts and nuts 100 mm. dia. M.S. Bars,
One end of the stay shall be bent to form a hook to be fixed with clamps by means of bolts and the
other end shall be bent for embedding in wall in cement concrete block of size 200 mm. x 100 mm. x
100 mm. in 1:2:4 mix. The concrete shall be finished to match the surrounding surfaces.
Page | 82
The connection between the main pipe and branch pipes shall be made by using branches and bends
with access doors for cleaningThe waste from lavatories, kitchens basins, sinks, baths and other floor
traps shall be separately connected to respective stacks of upper floor. The waste stack of lavatories
shall be connected directly to main hole while the waste stack of other shall be separately discharged
over gulley trap.
3.0. Measurements
The length of pipe shall be measured including all fittings along its length in running meters correct to a
centimeter. No allowance shall be made for the portion of pipe length entered in the sockets of the
adjacent pipe of fittings.
The rate includes all labour, and materials, tools and plant etc. required for satisfactory completion of
this item.
Item 37: Providing laying and jointing in true line and level, Consil 50mm dia. U.P.V.C. Pipe (SCH- 40) for
cold water including fittings make PRINCE /
SUPREME / ASTRAL / FINOLEX or equivalent asapproved by Engineer In Charge. Pipe shall be fixed
on the wall with the help of clamp at every two metre C/C or shall be concelled as directed including
necessary 50 mm tube MT fittings, such as such ruducing coupler, union, band plug, endcap, pipe clip,
Tee, hex nipple, elbow, cuopler,..etc complete As directed By Engineer in Charge & using bonding
materials.fittings etc. including testing of pipe and joints and fixing the same with adhesive solvent,
including cost of all materials, labours etc.
The work shall be executed as per specification of Item No.36 except the work is for providing laying
and jointing in true line and level, Consil 50mm dia. U.P.V.C. Pipe (SCH- 40) for cold water including
fittings make PRINCE /
SUPREME / ASTRAL / FINOLEX or equivalent asapproved by Engineer In Charge. Pipe shall be fixed
on the wall with the help of clamp at every two metre C/C or shall be concelled as directed including
necessary 50 mm tube MT fittings, such as such ruducing coupler, union, band plug, endcap, pipe clip,
Tee, hex nipple, elbow, cuopler,..etc complete As directed By Engineer in Charge & using bonding
materials.fittings etc. including testing of pipe and joints and fixing the same with adhesive solvent,
including cost of all materials, labours etc.
Item 38: Providing and fixing 600mm x 450mm bevelled edge mirrror of superior glass mounted on
6mm thick A.C. sheet or plywood sheet and fixing to wooden pluge with C.P. brass screws and washers.
Page | 83
Part 3 : Conditions of Contract & Contract Forms
The item shall be providing and fixing 600mm x 450mm bevelled edge mirrror of superior glass
mounted on 6mm thick A.C. sheet or plywood sheet and fixing to wooden plugs with C.P. brass screws
and washers.
All necessary fittings and laborers cost include in this items. The payment shall be made on Number
basis
Item 39: Providing & fixing fiber / PVC Netlon Jali I Mosquate of Best Quaility approved by Engineer
including necessarty fittings, 35mm vide velcrow, 40mm vide X 12mm thick Teak Wood Patti, stric etc
completed as directed by Engineer in charge.
Providing & fixing fiber / PVC Netlon Jali I Mosquate of Best Quaility approved by Engineer
It inciudes necessarty fittings, 35mm vide velcrow, 40mm vide X 12mm thick Teak Wood Patti, stric etc
completed as directed by Engineer in charge.
The measurement and payment shall made on the sqmt basis of completed work.
Item 40: Providing and fixing Granite of 18 to 20mm thick having minimum single plece length of 210mm
to be fixed on Walls to act as Study Table/ Wash Basin, including fixing the same using cement mortar in
proportion 1:1 etc. comp, Necessary Grove in Walls By Machine, Front Side Round the edge and cutting
hole in granite stone for wash basin, Computer Wire, including rubbing and polishing finishing jointed
with grey cement slurry including rubbing and polishing finishing etc complete. etc complete.. with all
labour & material & equipment.....etc. Completed as directed by Engineer-in-charge (A) Granite slab
18mm thick
The work shall be executed as per specification of Item No.22 except the work is for providing and
fixing Granite of 18 to 20mm thick having minimum single plece length of 210mm to be fixed on Walls to
act as Study Table/ Wash Basin, including fixing the same using cement mortar in proportion 1:1 etc.
Page | 84
comp, Necessary Grove in Walls By Machine, Front Side Round the edge and cutting hole in granite
stone for wash basin, Computer Wire, including rubbing and polishing finishing jointed with grey
cement slurry including rubbing and polishing finishing etc complete. etc complete.. with all labour &
material & equipment.....etc. Completed as directed by Engineer-in-charge (A) Granite slab 18mm thick
Item 41: Providing and fixing Table Top wash basin Jaguar Continental series CNS-WHT-WB03 with pillar
cock (LYR-3805B ), waste coupling, fisher union, bottle trap, angular stop cock, etc complete unit of
jaguar Brand (or equivalent) including installing and fitting as per manufacturers standards by skilled
trained plumber including testing etc complete - quality and brand as approved by engineer in charge.
(Providing and fixing granite table top is to be paid separately)
1.0. Materials
1.1. The white vitreous china Table Top basin (Jaguar Continental series CNS-WHT-WB03 shall be first
quality and make as approved by the Engineer-in-charge. The wash basin shall conform to M-59.
2.0. Workmanship
2.1. The first quality white vitreous china Table Top basin shall be fixed on the wall as and where
directed. The wash basin shall be supported on a pair of M.S. or C.I. brackets fixed in C.M. 1:3 (1 cement :
3 sand). The bracket shall conform to I.S. : 775-1962. The wall plaster on the rear shall be cut to rest the
top edge of the washbasin. After fixing the basing, plaster shall be made good and surface finished to
match the existing one.
2.2. The brackets shall be painted white with ready mixed paint.
2.3. The Bottle trap and union shall be connected to suitable dia. waste pipe which shall be suitably
bent towards the wall and which shall discharge into an open drain leading to a gully trap or direct in to
gully trap on the ground floor and shall be connected to a waste pipe through a floor trap on the upper
floors. Bottle trap and union may not be provided where the surface drain or a floor trap is placed
directly under the basin and the waste is discharged in to vertically.
2.4. The height of the front edge to the wash basin from the floor level shall be 80 cms.
2.5. The necessary inlet, outlet connections and fittings such as pillar cocks (LYR-3805B ),, bottle trap
waste pipe, chain wish rubber plug , waste coupeling, fisher union, bottle trap, angular stop cock, etc
Page | 85
Part 3 : Conditions of Contract & Contract Forms
complete unit of jaquar Brand (or equvalant) including installing and fitting as per manufacturers
standards by skilled trained plumber including testing etc complete etc. shall be fixed.
2.6. The payment of providing and fixing granite table top shall be paid separately.
Page | 86
Item 42: Providing and fixing Bib taps of 15 mm dia size of Jaquar Branch (Or equivalent) Quality and
brand as Approved by Engineer in charge. Including fitting the same by skilled trained plumber as per
manufacturers standard as directed
General
This work shall consist of providing and fixing Bib taps of 15 mm dia size of Jaquar Branch (Or
equivalent) Quality and brand as Approved by Engineer in charge.
1.0 MATERIAL
Bib Cock
1.1. Bib cock of specified 15 mm diameter nominal bore shall conform to I.S. 781-1977. The Bib Cock
shall be best Indian make and quality .
1.3 A Bib cock is a draw off tap with a horizontal inlet and free outlet. A stop cock is a valve with a
suitable means of connection of insertion in a pipe line for controlling or stopping the flow.
1.4 They shall be screw down type and or polished chrome and of diameter as specified in the
description of the item. They shall conform to I.S 781-1977 and they shall be of best Indian make. They
shall be polished chrome.
1.5 The minimum finished weight of bib cock and stop cock shall be as given below
Diameter Bib cock Stop Cock Diameter Bib cock Stop cock
Page | 87
Part 3 : Conditions of Contract & Contract Forms
1.6. The necessary galvanized fittings like Nipple, casing etc. of best quality and makes as approved
by the Engineer-in-charge required for specified dia. bore bib cock shall be used for fitting Bib cock as
necessary.
2.0. WORKMANSHIP
2.1. When the Bib cock is to be fitted, the ends shall be carefully filed out so that no obstruction to
bore in offered. The Bib cock shall be fitted with pipes carefully in such a manner as will not result in
slackness of joints when the two pieces are screwed together
2.2 In jointing the Bib cock the inside of the socket and the screwed end of the Bib cock shall be
oiled and smeared with the white or red lead and wrapping around with a few turns of fine spun yarn
round the screwed end of the Bib cock. The end shall then be tightly screwed in the socket, Tees etc
with a pipe wrench Care shall be taken that all items are free from dust, dirt and rust during fixing Burr
from the joints shall be removed after screwing After laying the open ends of the Bib cock shall be
temporarily plugged to prevent excess of water soil or any other foreign matter.
2.3. Any threads exposed after jointing shall be painted or in the case of underground piping thickly
coated with approved anti corrosive paint to prevent corrosion
TESTING OF JOINTS
Page | 88
After fitting, the Bib cocks shall be inspected under working conditions of pressure and flow. Any joints
found liken shall be redone, and all leaking Bib cocks shall be removed and replaced without extra cost.
The Bib cocks after they are fitted shall be tested to hydraulic pressure of 6 kg / sq. cm. The Bib cock
shall be slowly and carefully charged with water allowing all air to escape and avoiding all shock and
water hammer. The draw off takes and stop cock shall then be closed and specified hydraulic pressure
shall be applied gradually. The Bib cocks shall be tested in sections as the work laying proceeds, veeping
the joints exposed for inspection during the testing.
3.1. The unit rate of full turn brass bib tap shall include the cost of all materials, tools and plant
required for fitting, the same to specified position as per drawings, and as directed by Engineer in
charge finishing structure, etc. and all other incidental expenses for producing Bib cock work to
complete the structure or its components as shown on the drawings, and as directed by Engineer in
charge and according to these specifications. They shall also include the cost of making, fixing and
removing of all scaffolding and forms required for the work.
The rate of full turn brass bib tap shall include the cost of all labour, materials, G. I. fittings as
required, tools and plant scaffolding and all incidental expenses as described herein above including
testing.
3.2. The full turn brass bib tap shall be measured for its Number, limiting dimensions to those
specified on plan or as directed. The rate shall be for a unit of one number.
3.3. The payment will be made on number basis of the finished work.
Item 43: Providing and fixing Toilet paper holder with flap of Jaquar Brand (Or equivalent) Quality and
brand as Approved by Engineer in Charge. Including fitting the same by skilled trained plumber as per
manufacturers standard as
Directed
All necessary fittings and labored cost include in this items. the payment shall be made on number
basis.
Page | 89
Part 3 : Conditions of Contract & Contract Forms
Item 44: Providing and fixing shop dish of jaquar Branch (Or Equivalent) Quality and brand as Approved
by Engineer in charge. Including fitting the same by skilled trained plumber as per manufacturers
standard as directed.
All necessary fittings and labored cost include in this items. the payment shall be made on number
basis.
Item 45: Providing and laying wash down water closet (european type WallHung WC pan) Florentine
series FLS-WHT 0111B including providing and fixing metropole Flush cock seat cover, jet wash etc
complete unit of jaquar Branch (or equvalant)
including installing and fitting as per manufacturers standards by skilled trained plumber
including testing etc complete quality and brand as approved by Engineer in charge.
Materials
Wash down water closet (European type W.C. Pan) shall conform to M-60. Cement mortar shah
conform to M-11.
2.0. Workmanship
2.1. The closet shall be fixed to the floor by means of 75 mm. long 6.5 mm. diameter counter sunk
bolts and nuts embedded in the floor concrete using rubber or before washers so as not to allow any
lateral displacement The joint between the trap of W.C. and soil pipe shall ho made with C M. 1:1 (1
cement : 1 fine sand).
3.1. The rate shall includes the cost of all materials and labour involved in all the operations
described under workmanship.
3.2. The rate includes cost of all labour for fixing pans and sent and cover, inlet, connections etc.
complete including testing the same. The payment of seat and cover shall be made separately.
Page | 90
Item 46: Providing and fixing Towel ring of Jaquar Brand (or equivalent) Quality and brand as Approved
by Engineer in Charge. Including fitting the same by skilled trained plumber as per manufacturers
standard as directed
1.0. Materials :
Premium quality Towel Ring of Jaquar ACN-1121N or equivalent make shall conform to I.S. 781-
1977. The square Towel Ring shall be of Jaquar or equivalent make and as approved by the Engineer in
charge.
2.0. Workmanship
2.1. The Premium quality Towel Ring in polished chrome as specified above shall be fixed as directed
by Engineer in charge. The bracket to hold the towel ring should be fixed on the wall in proper position
or as directed by engineer in charge consisting of operating lever, wall flange (with seab) & button only.
The Premium quality Towel Ring in polished chrome shall be fixed as per the approved design and
drawings supplied by the Engineer in charge.
3.1. The rate includes cost of all labour, materials, tools and plant etc. required for satisfactory
completion of this item.
Item 47: Providing and fixing PVC SWR Nahni trap IS 14735 for drain - 100 mm diameter with jali of the
following nominal diameter of self cleansing design with C.I scread down or hinged grating including
the cost of cutting and making good the
Walls.
1.0. Materials
1.1. The PVC SWR Nahni Trap IS 14735 for drain with jali shall conform to M-69. The C.I. hinged or
screwed down cover shall be of best quality and approved by Engineer in charge.
2.0. Workmanship
Page | 91
Part 3 : Conditions of Contract & Contract Forms
2.1. The PVC SWR Nahni Trap with 100 mm. dia inlet and 50 mm. dia. outlet shall be fixed as per
drawing or as directed.
2.2. The PVC SWR Nahni Trap shall be jointed with C.I. pipe, 100 mm. dia. with lead joints. The lead
joints shall be done in conformation with I.S. 782-1976.
3.1. The rate includes cost of RCC slab hole, all labour, materials, tools and plants etc. required for
satisfactory completion of this item including lead, jointing and testing.
Item 48: Providing erecting and fixing double coated Syntex PVC. (ISI) water tank of required capacity
each with all necessary fittings and connection
etc. complete on terrace.
The double coated Syntex PVC. (ISI) water tank of required capacity as directed by engineer - in-
charge. It shall conform to relevant I.S. specification. The tank shall be of best quality and free from any
defects. The tank shall have outlet required diameter. The outlet shall be connected as specified by
Engineer - in- Charge. The flushing tank shall be provided with inlet - outlet and over-flow pipes. The
inlet & outlet pipes to water tank shall be fitted with necessary valves to control water supply. the
water tank shall also be provided with necessary fittings as directed by Engineer in charge.
It shall be made on the litre capacity basis of water tank including material, all fittings & labour charge
to complete the work as specified.
Item 49: Supply, fixing and commissioning of 1x36 W tubelight fitting with lamp (Philips make Batten
TMS21/136 HPF series (Box Type with reflector) or equivalent from Crompton, Bajaj GE). Rate to include
all accessories, interconnection of wires from ceiling rose to the fittings and fluorescent tube /GLS/PL
lamps, copper choke etc.
The work shall be performed by supply, fixing and commissioning of 1x36 W tubelight fitting with lamp
(Philips make Batten TMS21/136 HPF series (Box Type with reflector) or equivalent from Crompton,
Bajaj GE). Rate to include all accessories, interconnection of wires from ceiling rose to the fittings and
fluorescent tube /GLS/PL lamps, copper choke etc.
Page | 92
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item50: Providing & fixing MS fan hooks with 16 mm dia MS bar bent to shape with hooked ends in RCC
Slab during laying including painting the exposed
Portion.
The work shall be performed by providing & fixing MS fan hooks with 16 mm dia MS bar bent to shape
with hooked ends in RCC Slab during laying including painting the exposed
Portion.
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
The work shall be performed by Supplying and fixing of the ceiling fans of
approved make with detail as below : Sweep :1400/ 1200 mm (as per HPCL requirement)
Colour: White Bearing type : Double ball bearing Down Rod : Clear 300 mm long
Regulator : Electronic type ANCHOR/MK make
Accessories : Screws, wall nuts etc.
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item52: Providing and laying point wiring in concealed conduits for the required points as per drawing/
Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded 3 x 1.5 sqmm copper conductor
wires. Rate to include supplying, laying and securing in position in roof slabs and brick walls or concrete
columns 25mm dia rigid PVC conduits of approved make with necessary accessories, junction boxes,
pull boxes etc. Rate includes wall chasing and rough plastering. Rate to include providing and fixing in
the brick wall flush type metal switch boxes of approved make, shade and sufficient size to accomodate
all 6A Modular switches/3 pin socket, screws, holders, ceiling roses and fan regulator wherever
required. Rate to include providing and fixing single pole 5A modular plate switches of MK or ANCHOR
Page | 93
Part 3 : Conditions of Contract & Contract Forms
make of approved colour. One switch shall be provided for each light and fan point. Rate to also
include providing main circuit wiring from DB to switch boards with 2.5 sqmm copper wire.
The work shall be performed by Providing and laying point wiring in concealed conduits for the required
points as per drawing/ Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded 3 x 1.5
sqmm copper conductor wires. Rate to include supplying, laying and securing in position in roof slabs
and brick walls or concrete columns 25mm dia rigid PVC conduits of approved make with necessary
accessories, junction boxes, pull boxes etc. Rate includes wall chasing and rough plastering. Rate to
include providing and fixing in the brick wall flush type metal switch boxes of approved make, shade
and sufficient size to accomodate all 6A Modular switches/3 pin socket, screws, holders, ceiling roses
and fan regulator wherever required. Rate to include providing and fixing single pole 5A modular plate
switches of MK or ANCHOR make of approved colour. One switch shall be provided for each light and
fan point. Rate to also include providing main circuit wiring from DB to switch boards with 2.5 sqmm
copper wire.
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item53: Providing and laying point wiring in concealed conduits for the required points as per drawing/
Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded 3 x 1.5 sqmm copper conductor
wires. Rate to include supplying, laying and securing in position in roof slabs and brick walls or concrete
columns 25mm dia rigid PVC conduits of approved make with necessary accessories, junction boxes,
pull boxes etc. Rate includes wall chasing and rough plastering. Rate to include providing and fixing in
the brick wall flush type metal switch boxes of approved make, shade and sufficient size to
accomodate all 6A Modular switches/3 pin socket, screws, holders, ceiling roses and fan regulator
wherever required. Rate to include providing and fixing single pole 5A modular plate switches of MK or
ANCHOR make of approved colour. One switch shall be provided for each light and fan point. Rate to
also include providing main circuit wiring from DB to switch boards with
2.5 sqmm copper wire. ( Two Way Switch)
The work shall be performed by : Providing and laying point wiring in concealed conduits for the
required points as per drawing/ Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded
3 x 1.5 sqmm copper conductor wires. Rate to include supplying, laying and securing in position in roof
slabs and brick walls or concrete columns 25mm dia rigid PVC conduits of approved make with
necessary accessories, junction boxes, pull boxes etc. Rate includes wall chasing and rough plastering.
Rate to include providing and fixing in the brick wall flush type metal switch boxes of approved make,
shade and sufficient size to
accomodate all 6A Modular switches/3 pin socket, screws, holders, ceiling roses and fan regulator
Page | 94
wherever required. Rate to include providing and fixing single pole 5A modular plate switches of MK or
ANCHOR make of approved colour. One switch shall be provided for each light and fan point. Rate to
also include providing main circuit wiring from DB to switch boards with
2.5 sqmm copper wire. ( Two Way Switch)
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item54: Providing and laying point wiring in concealed conduits for the required points as per drawing/
Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded 3 x 1.5 sqmm copper conductor
wires. Rate to include supplying, laying and securing in position in roof slabs and brick walls or concrete
columns 25mm dia rigid PVC conduits of approved make with necessary accessories, junction boxes,
pull boxes etc. Rate includes wall chasing and rough plastering. Rate to include providing and fixing in
the brick wall flush type metal switch boxes of approved make, shade and sufficient size to accomodate
all 6A Modular switches/3 pin socket, screws, holders, ceiling roses and fan regulator wherever
required. Rate to include providing and fixing single pole 5A modular plate switches of MK or ANCHOR
make of approved colour. One switch shall be provided for each light and fan point. Rate to also
include providing main circuit wiring from DB to switch boards with
2.5 sqmm copper wire. but for 5A socket
controlled by one 5A switch independently mounted including wiring through PVC conduit & providing
and fixing 5A socket (5A SOCKET ON NEW BOARD)
The work shall be performed by Providing and laying point wiring in concealed conduits for the required
points as per drawing/ Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded 3 x 1.5
sqmm copper conductor wires. Rate to include supplying, laying and securing in position in roof slabs
and brick walls or concrete columns 25mm dia rigid PVC conduits of approved make with necessary
accessories, junction boxes, pull boxes etc. Rate includes wall chasing and rough plastering. Rate to
include providing and fixing in the brick wall flush type metal switch boxes of approved make, shade
and sufficient size to accomodate all 6A Modular switches/3 pin socket, screws, holders, ceiling roses
and fan regulator wherever required. Rate to include providing and fixing single pole 5A modular plate
switches of MK or ANCHOR make of approved colour. One switch shall be provided for each light and
fan point. Rate to also include providing main circuit wiring from DB to switch boards with
2.5 sqmm copper wire. but for 5A socket
controlled by one 5A switch independently mounted including wiring through PVC conduit & providing
and fixing 5A socket (5A SOCKET ON NEW BOARD)
Page | 95
Part 3 : Conditions of Contract & Contract Forms
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item55: Providing and laying point wiring in concealed conduits for the required points as per drawing/
Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded 3 x 1.5 sqmm copper conductor
wires. Rate to include supplying, laying and securing in position in roof slabs and brick walls or concrete
columns 25mm dia rigid PVC conduits of approved make with necessary accessories, junction boxes,
pull boxes etc. Rate includes wall chasing and rough plastering. Rate to include providing and fixing in
the brick wall flush type metal switch boxes of approved make, shade and sufficient size to accomodate
all 6A Modular switches/3 pin socket, screws, holders, ceiling roses and fan regulator wherever
required. Rate to include providing and fixing single pole 5A modular plate switches of MK or ANCHOR
make of approved colour. One switch shall be provided for each light and fan point. Rate to also
include providing main circuit wiring from DB to switch boards with
2.5 sqmm copper wire. but for AC point with 2
runs of 4 sqmm (P&N) and 1 run of 2.5 sqmm PVC insulated, FRLS multistrand copper cable in PVC
conduit from MCB DB to 20A power-socket. Rate includes supply and fixing of 20A industrial socket
controlled by 20A SP MCB.
The work shall be performed by Providing and laying point wiring in concealed conduits for the required
points as per drawing/ Engineer-in-charge using 1100V grade PVC insulated, FRLS multistranded 3 x 1.5
sqmm copper conductor wires. Rate to include supplying, laying and securing in position in roof slabs
and brick walls or concrete columns 25mm dia rigid PVC conduits of approved make with necessary
accessories, junction boxes, pull boxes etc. Rate includes wall chasing and rough plastering. Rate to
include providing and fixing in the brick wall flush type metal switch boxes of approved make, shade
and sufficient size to accomodate all 6A Modular switches/3 pin socket, screws, holders, ceiling roses
and fan regulator wherever required. Rate to include providing and fixing single pole 5A modular plate
switches of MK or ANCHOR make of approved colour. One switch shall be provided for each light and
fan point. Rate to also include providing main circuit wiring from DB to switch boards with
2.5 sqmm copper wire. but for AC point with 2
runs of 4 sqmm (P&N) and 1 run of 2.5 sqmm PVC insulated, FRLS multistrand copper cable in PVC
conduit from MCB DB to 20A power-socket. Rate includes supply and fixing of 20A industrial socket
controlled by 20A SP MCB.
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Page | 96
Item56: Supply, fixing and commissioning of 1x60 W Bulkhead luminaire & lamp (Phillps catno. NX C
101 or equivalent) - Outside building. Rate to
include all accessories, interconnection of wires from ceiling rose to the fittings.
The work shall be performed by Supply, fixing and commissioning of 1x60 W Bulkhead luminaire &
lamp (Phillps catno. NX C 101 or equivalent) - Outside building. Rate to
include all accessories, interconnection of wires from ceiling rose to the fittings.
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item57: PLATE EARTHING Construction of Earth Pit as per IS 3043 at various Retail Outlets under Rajkot
Retail Region. Job includes
Excavation to minimum 3.0m depth. (Soil, rock, RCC etc.).
Providing 600X600X6mm GI Plate.
Providing two 50X6mm GI Stripes from Plate to the top.
Providing 40mm dia medium duty GI Pipe with
8mm holes from Plate to the top. Providing GI Funnel with Wire-mesh on top of GI
Pipe.
Connecting all the above parts with necessary nuts, bolts & washers.
Filling the pit in Alternate layers of 300mm thick Charcoal & Salt.
Constructing 400 X 400 X 400 mm Plastered Brick Chamber with ISA 25X25X3 Frame, necessary hold
fasts & CI/ 12mm thick MS Cover.
Providing & Fixing 250X150X3mm Painted MS Sheet indicating Earthing Details.
Carrying out & Submitting Test Report.
The work shall be performed by PLATE EARTHING Construction of Earth Pit as per IS 3043 at various
Retail Outlets under Rajkot Retail Region. Job includes
Excavation to minimum 3.0m depth. (Soil, rock, RCC etc.).
Providing 600X600X6mm GI Plate.
Providing two 50X6mm GI Stripes from Plate to the top.
Providing 40mm dia medium duty GI Pipe with
8mm holes from Plate to the top. Providing GI Funnel with Wire-mesh on top of GI
Pipe.
Connecting all the above parts with necessary nuts, bolts & washers.
Filling the pit in Alternate layers of 300mm thick Charcoal & Salt.
Constructing 400 X 400 X 400 mm Plastered Brick Chamber with ISA 25X25X3 Frame, necessary hold
Page | 97
Part 3 : Conditions of Contract & Contract Forms
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item58: Supply and fixing of wall mounting type meter board (Electricity Board approved) made out of
16 SWG CRCA sheet steel and single iron with 3 nos 200A Fuse cutouts N.L ,1 no. earth link, 1 no neutral
link and space for accommodating 1 no. 3 ph, 4 wire KWH meter complete with adequate size of copper
wire interconnections, powder
coating etc. complete.
The work shall be performed by Supply and fixing of wall mounting type meter board (Electricity Board
approved) made out of 16 SWG CRCA sheet steel and single iron with 3 nos 200A Fuse cutouts N.L ,1 no.
earth link, 1 no neutral link and space for accommodating 1 no. 3 ph, 4 wire KWH meter complete with
adequate size of copper wire interconnections, powder
coating etc. complete.
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Item59: Supply, fixing and commissioning of 230mm dia Exhaust fans including bird louvers, frame
works and other civil works like chipping and making the surface good etc.
The work shall be performed by Supply, fixing and commissioning of 230mm dia Exhaust fans including
bird louvers, frame works and other civil works like chipping and making the surface good etc.
All necessary fittings and labored cost include in this items. The payment shall be made on number
basis.
Page | 98
Item60: Supply and installation of 1HP Kirloskar make submersible water motor pumpset, including
fitting of switch/ starter/ cable/ panel at electrical room within 25 RMT distance.
1.1 Providing Submerged pumpsets (water immersed, dry air filled, class "F" insulated TEWC motor
integrally mounted on volute casing pumpsets for water duty, 3-phase, 50Hz±3%,415V±10% along with
suitable foundation/ installation device with cable length from pumps to panels & of following Material
of Construction:
Impeller-CF8M, Casing-C.I. FG 260, Wearing Ring -SS, TC mechanical seal, CS/S.S.bearing, S.S shaft with
sleeve, SS strainer & MS motor body. (A) Rating + (B) Erection Charges for Pumpsets
1.2 The standard company same for pump with motor with all accessories shall be selected with
prior approval of Engineer-in -change. It is a responsibility of agency to make the pump and pipeline
system working at site and keeps working up to defect liability period and /or guarantee period of
Company.
The rate shall be for a unit of one number basis of complete work done.
Item61: Providing water proofing agent for RCC (Perma- Plast SL for M-25 Concrete) as per approved
quality of ASTMC 494 conforming IS 9103-2007
& 2645-2003.
The work shall be executed as per specification of item no 17 except the work is for providing water
proofing agent for RCC (Perma- Plast SL for M-25 Concrete) as per approved quality of ASTMC 494
conforming IS 9103-2007
& 2645-2003.
The work shall be executed as per specification of item no 17 except the work is for providing water
proofing agent for plastering
(Perma Grout -500).
Page | 99
Part 3 : Conditions of Contract & Contract Forms
The work shall be executed as per specification of item no 17 except the work is for Providing Perma
bitu coat for Foundation.
(Waterproofing agent as well as anti terminite treatment for footing and Column.
Item64: Providing and laying controlled cement concrete M-200 and curing comp. including the cost of
form work but excluding the cost of reinforcement for reinforced concrete work for Columns AT FIRST
FLOOR
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M-200 and curing comp. including the cost of form work but excluding the
cost of reinforcement for reinforced concrete work for Columns AT FIRST FLOOR
Item65: Providing and Laying controlled cement concrete M-200 and with curing etc.complete.
Including the cost of formwork but excluding the cost of reinforcement for R.C.C work in beam heving
any cross section area of BEAM ( For First floor).
The work shall be executed as per specification of Item No.3 except the work is for providing and
Laying controlled cement concrete M-200 and with curing etc.complete. Including the cost of
formwork but excluding the cost of reinforcement for R.C.C work in beam heving any cross section area
of BEAM ( For First floor).
Item66: Providing and laying controlled cement concrete M-200 and curing complete including the cost
of form work but excluding the cost of reinforcement for reinforced concrete work in SLABS for FIRST
FLOOR
The work shall be executed as per specification of Item No.3 except the work is for Providing and laying
controlled cement concrete M-200 and curing complete including the cost of form work but excluding
the cost of reinforcement for reinforced concrete work in SLABS for FIRST FLOOR
Page | 100
Item67: Providing and laying controlled cement concrete M-200 and curing complete including the cost
of form work but excluding the cost of reinforcement for reinforced concrete work in Lintels FIRST
Floor
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M-200 and curing complete including the cost of form work but excluding
the cost of reinforcement for reinforced concrete work in Lintels FIRST Floor
Item68: Providing and laying brick work using common burnt clay building conventional type bricks
having crushing strength not less than 35 Kg./Sqcm. in super structure in cement mortar 1:6 (1
cement : 6 fine sand) for First floor including the cost of all materials and labour charges etc.
complete.
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
brick work using common burnt clay building conventional type bricks having crushing strength not less
than 35 Kg./Sqcm. in super structure in cement mortar 1:6 (1 cement : 6 fine sand) for First floor
including the cost of all materials and labour charges etc. complete.
Page | 101
Part 3 : Conditions of Contract & Contract Forms
Item69: Providing 10 mm thick cement plaster in single coat on fair side brick/concrete walls for interior
plastering upto floor two level and finished even and smooth in cement mortar 1:3 (1 cement : 3 sand)
including finishing with a floating coat of neat cement slurry etc. complete for Ceiling First floor.
The work shall be executed as per specification of Item No.17 except the work is for providing 10 mm
thick cement plaster in single coat on fair side brick/concrete walls for interior plastering upto floor two
level and finished even and smooth in cement mortar 1:3 (1 cement : 3 sand) including finishing with a
floating coat of neat cement slurry etc. complete for Ceiling First floor.
Item70: Providing 15mm thick MALA Trowel Finished cement plaster in single coat on brick/concrete
walls for interior plastering upto floor two level and finished even and smooth in (i) Cement mortar 1:4
(1-cement:4-sand) including Curing etc. complete. for First floor
The work shall be executed as per specification of Item No.18 except the work is for providing 15mm
thick MALA Trowel Finished cement plaster in single coat on brick/concrete walls for interior plastering
upto floor two level and finished even and smooth in (i) Cement mortar 1:4 (1-cement:4-sand) including
Curing etc. complete. for First floor
Page | 102
The work shall be executed as per specification of Item No.29 except the work is for providing and
laying Marbo Granite tiles 8 to 10
mm thick , 24'' x 24'' in flooring treads of steps and landing laid on a bed of 12mm thick cement mortar
1:3 (1-cement : 3-coarse sand ) finishing with flush pointing in white cement.
Item72: Providing & fixing fiber / PVC Netlon Jali I Mosquate of Best Quaility approved by Engineer
including necessarty fittings, 35mm vide velcrow, 40mm vide X 12mm thick Teak Wood Patti, stric etc
completed as directed by Engineer in charge.
Providing & fixing fiber / PVC Netlon Jali I Mosquate of Best Quaility approved by Engineer
It inciudes necessarty fittings, 35mm vide velcrow, 40mm vide X 12mm thick Teak Wood Patti, stric etc
completed as directed by Engineer in charge.
The measurement and payment shall made on the sqmt basis of completed work.
Item73: Providing and laying point wiring in concealed conduits for the required points as per drawing/
Engineer-in-charge using 1100V grade PVC insulated, FRLS multi stranded 3 x 1.5 sq mm copper
conductor wires. Rate to include supplying, laying and securing in position in roof slabs and brick walls
or concrete columns 25mm dia rigid PVC conduits of approved make with necessary accessories,
junction boxes, pull boxes etc. Rate includes wall chasing and rough plastering. Rate to include
providing and fixing in the brick wall flush type metal switch boxes of approved make, shade and
sufficient size to accomodate all 6A Modular switches/3 pin socket, screws, holders, ceiling roses
and fan regulator wherever required. Rate to include providing and fixing single pole 5A modular plate
switches of MK or ANCHOR make of approved colour. One switch shall be provided for each light and
fan point. Rate to also include providing main circuit wiring from DB to switch boards with 2.5 sq mm
copper wire. (Two Way Switch)
Page | 103
Part 3 : Conditions of Contract & Contract Forms
Providing and laying point wiring in concealed conduits for the required points as per drawing/
Engineer-in-charge.
It shall be used 1100V grade PVC insulated, FRLS multi stranded 3 x 1.5 sq mm copper conductor wires.
It shall be supplied and laying, securing in position in roof slabs and brick walls or concrete columns
25mm dia rigid PVC conduits of approved make.
It shall be supplied with necessary accessories, junction boxes, pull boxes etc.
It shall include providing and fixing in the brick wall flush type metal switch boxes of approved make,
shade and sufficient size to accommodate all 6A Modular switches/3 pin socket, screws,
holders, ceiling roses and fan regulator wherever required.
It shall include providing and fixing single pole 5A modular plate switches of MK or ANCHOR make of
approved colour.
One switch shall be provided for each light and fan point.
It shall include providing main circuit wiring from DB to switch boards with 2.5 sqmm copper wire (Two
Way Switch).
Page | 104
It shall made on number basis of complete finished work including all materials and equipment, labour
charges.
Item74: Providing and laying controlled cement concrete M-200 and curing comp. including the cost of
form work but including the cost of reinforcement for reinforced concrete work for Columns AT AT
SECOND FLOOR. & MISC. WORK
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M-200 and curing comp. including the cost of form work but including the
cost of reinforcement for reinforced concrete work for Columns AT AT SECOND FLOOR. & MISC. WORK
Item75: Provinding and Laying controlled cement concrete M-200 and with curing etc.complete.
Including the cost of formwork but excluding the cost of reinforcement for R.C.C work in beam heving
any cross section area of BEAM AT SECOND FLOOR. & MISC. WORK
The work shall be executed as per specification of Item No.3 except the work is for provinding and
Laying controlled cement concrete M-200 and with curing etc.complete. Including the cost of
formwork but excluding the cost of reinforcement for R.C.C work in beam heving any cross section area
of BEAM AT SECOND FLOOR. & MISC. WORK
Item76: Providing and laying controlled cement concrete M-200 and curing complete including the cost
of form work but excluding the cost of reinforcement for reinforced concrete work in SLABS for AT
SECOND FLOOR. & MISC. WORK
Page | 105
Part 3 : Conditions of Contract & Contract Forms
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
controlled cement concrete M-200 and curing complete including the cost of form work but excluding
the cost of reinforcement for reinforced concrete work in SLABS for AT SECOND FLOOR. & MISC.
WORK
Item77: Providing and laying brick work using common burnt clay building conventional type bricks
having crushing strength not less than 35 Kg./Sqcm. in super structure in cement mortar 1:6 (1
cement : 6 fine sand) for First floor including the cost of all materials and labour charges etc.
complete. AT SECOND FLOOR. & MISC. WORK
The work shall be executed as per specification of item no 8 except the work is for providing and laying
brick work using common burnt clay building conventional type bricks having crushing strength not less
than 35 Kg./Sqcm. in super structure in cement mortar 1:6 (1 cement : 6 fine sand) for First floor
including the cost of all materials and labour charges etc. complete. AT SECOND FLOOR. & MISC. WORK
Item78: Providing 10 mm thick cement plaster in single coat on fair side brick/concrete walls for interior
plastering upto floor two level and finished even and smooth in cement mortar 1:3 (1 cement : 3 sand)
including finishing with a floating coat of neat cement slurry etc. complete for Ceiling AT SECOND
FLOOR. & MISC. WORK
The work shall be executed as per specification of item no 17 except the work is for Providing 10 mm
thick cement plaster in single coat on fair side brick/concrete walls for interior plastering upto floor two
level and finished even and smooth in cement mortar 1:3 (1 cement : 3 sand) including finishing with a
floating coat of neat cement slurry etc. complete for Ceiling AT SECOND FLOOR. & MISC. WORK
Page | 106
Item79: Providing 15mm thick MALA Trowel Finished cement plaster in single coat on brick/concrete
walls for interior plastering upto floor two level and finished even and smooth in (i) Cement mortar 1:4
(1-cement:4-sand) including Curing etc. complete. for AT SECOND FLOOR. & MISC. WORK
The work shall be executed as per specification of item no 18 except the work is for Providing 15mm
thick MALA Trowel Finished cement plaster in single coat on brick/concrete walls for interior plastering
upto floor two level and finished even and smooth in (i) Cement mortar 1:4 (1-cement:4-sand) including
Curing etc. complete. for AT SECOND FLOOR. & MISC. WORK
Item80: Providing & Fixing a Solar Street Light as per aproved brand by Engineer In Charge
1、Material:Sheet metal bending + paint
2、Solar panel:Solar cell (monocrystalline
silicon) 6V/11W 3、Battery:High temperature
rechargeable lithium battery 3.7V/24.2A
4、Working time: plenty of sun charge 8 hours
can work 24hours.
5、LED:42pcs (Tai Wan's Epistar,2835 pure
white, 5700- 6500MCD )
6、Rainy days: full of electricity for 3 days
7、Work mode: always bright at night
8、Lighting condition:Start light intensity:
Page | 107
Part 3 : Conditions of Contract & Contract Forms
11、Waterproof:IP65
13、Product size:385*252*42MM
2.54KG/set
The In and out gate shall be fabricated of M S Sliding Gate including Bottom Railing Track mounted with
25mm round bright bar, Gate Holding Structure, Gate Stoppers and relevant accessories for Width : 4.55
+ 1.0 = 5.55mtr (incl. overlap) Height: 2.0mtr from finish floor level. It shall include:
M.S. Bottom Roller – Large shall be 120 X 25mm bearing controlled rollers.
Side Roller shall be 75 X 50mm Nylon Rollers with bearing support inside.
Installation of Entrance Automation Product: Installation of Gates and Automation of Main Sliding Gate
with configuration shall be done.
The gate shall be fabricated from best quality mild steel channels, flats etc. Either steel pulleys or ball
bearings shall be provided in every double channel.
The measurement & payment shall be made on number basis of completed finished work of the gate.
Page | 109
Part 3 : Conditions of Contract & Contract Forms
It shall be provided a complete range of up-lights in terms of wattage, beam angle and colour
temperature, etc. It shall make space distinctive with more safety and convenience. It shall be compact
and robust design with a diecast aluminium housing and stainless trim, IP68 waterproof connectors
ensure long-lasting operation without maintenance after installation. The waterproof connector shall
be provided to make installation easy and saves installation costs. Also, high-quality white light, RGB
(and mono RGB) shall be available with a DMX512 decoder built inside. The lighting LED board can be
adjusted to deliver light at precise angles to make the inspirations of lighting designers come true. The
detail specification shall be as under:
Product data:
General Information
Control interface -
Flammability mark NO [ -]
CE mark -
Page | 110
Serviceability class Class C, luminaire without serviceable parts, not serviceable
Light Technical
Input frequency 50 or 60 Hz
Dimmable No
Colour Steel
Page | 111
Part 3 : Conditions of Contract & Contract Forms
People want to create a pleasant atmosphere around their property – something that will catch visitors’
attention, make them feel good and want to come back again. They would like to be able to create an
appealing ambience at minimum cost, though without compromising on the quality of the lighting.
Combining a simple round design with reliable lighting performance, this low-cost white-light LED wall
fixture with opal diffuser delivers a soft light effect with attractive uniformity.
Product data
Control interface -
Page | 112
Connection Screw connection block
CE mark CE mark
Input Frequency 50 to 60 Hz
Dimmable No
Overall height 62 mm
Page | 113
Part 3 : Conditions of Contract & Contract Forms
Item84: Excavation for foundation upto 1.5 m depth including sorting out and stacking of useful
materials and disposing off the excavated stuff upto 50 Meter lead.(A) dense or hard soil
The work shall be executed as per specification of item no 2 except the work is for excavation for
foundation upto 1.5 m depth including sorting out and stacking of useful materials and disposing off the
excavated stuff upto 50 Meter lead.(A) dense or hard soil
Item85: Excavation for foundation for depth from 1.5 m to 3.0 m including sorting out and stacking of
useful materials and disposing off the excavated stuff upto 50 Meter lead.(B) Dense or Hard soil
The work shall be executed as per specification of item no 2 except the work is for excavation for
foundation for depth from 1.5 m to 3.0 m including sorting out and stacking of useful materials and
disposing off the excavated stuff upto 50 Meter lead.(B) Dense or Hard soil
Page | 114
Item86: Providing and laying cement concrete work 1:2:4 (1- Cement : 2- Coarse sand : 4- graded stone
aggregates 20 mm nominal size) and curing
complete excluding cost of formwork and reinforcement for reinforced concrete work in Foundation &
Plinth
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
cement concrete work 1:2:4 (1-
Cement : 2- Coarse sand : 4- graded stone
aggregates 20 mm nominal size) and curing
complete excluding cost of formwork and
reinforcement for reinforced concrete work in
Foundation & Plinth.
Item87: Providing 15mm thick WATER PROOF cement plaster in single coat on fair side brick work or
concrete wall for interior plastering up to floor to level and finishing even smooth in cement mortar 1:3
(1
cement: 3 sand) finished with floating coat of neat cement slurry including providing and mixing water
proofing materials in proportion recommended by the manufacturers for all floor.
The work shall be executed as per specification of item no 17 except the work is for providing 15mm
thick WATER PROOF cement
plaster in single coat on fair side brick work or
concrete wall for interior plastering up to floor to level
and finishing even smooth in cement mortar 1:3 (1
cement :3 sand) finished with floating coat of neat
cement slurry including providing and mixing water
proofing materials in proportion recommended by the
manufacturers for all floor.
Page | 115
Part 3 : Conditions of Contract & Contract Forms
1.0. Materials
1.1. Water shall conform to M-1. Cement mortar shall conform to M-11.
2.0. Workmanship
2.1. The work of cement vata of 10 cms x 10 cms. size shall be earned out at Functions of parapets
and terraces as directed. The vata shall he finished in quarter round shape. The work shall be earned out
in the best workman like manner. The inter portion of rain water pipe shall be rounded off properly
during constructing the vata. The work shall be cured for 7 days.
3.1. The work shall be measured for finished item in running meter.
The work shall be executed as per specification of Item No.15 except the work is for providing I.S.I.
mark Fe-415 T.M.T. bar
reinforcement for R.C.C. work including bending,
binding and placing in position upto floor two level
for Any floor.
Page | 116
Item90: Excavation for foundation ABOVE 3.0mt depth
including sorting out and stacking of useful materials
and disposing the excavated stuff upto any. lead
(D)In Dense or Hard Soil
The work shall be executed as per specification of item no 2 except the work is for excavation for
foundation ABOVE 3.0mt depth
including sorting out and stacking of useful materials
and disposing the excavated stuff upto any. lead
(D)In Dense or Hard Soil.
Item91: Brick Bat filling 40mm thick at requred depth as per Drawing and specification and direction of
Engg- in -charge.
The Brick Bat filling 40mm thick at requred depth, clean, free from dust and deleterious matters
obtained from a source as approved by the Engineer-in-charge.
After brick bat shall be filled in suitable layers not exceeding 30 cm. at a time and each layer well
compacted by rodding to maximum density or as directed by the Engineer-in-charge.
Mode of measurement shall be the total cubical content (in cum.) of the area covered by brick bat.
Unit rate includes the cost of materials, labour and tools and plant to complete the work.
Item92: Providing 15mm thick MALA Trowelled Finished cement plaster in single coat on brick/concrete
walls for interior plastering upto floor two level and finished even and smooth in (i) Cement mortar 1:3
(1-cement: 3-sand) etc. complete. for Ground Floor
Page | 117
Part 3 : Conditions of Contract & Contract Forms
The work shall be executed as per specification of item no 18 except the work is for providing 15mm
thick MALA Trowelled Finished cement plaster in single coat on brick/concrete walls for interior
plastering upto floor two level and finished even and smooth in (i) Cement mortar 1:3 (1-cement: 3-
sand) etc. complete. for Ground Floor
Item93: Box cutting the road surface to proper slope and camber for making a base for road work
including removing the excavated stuff and depositing on the road side slope as directed upto any.lead.
This work shall consist of excavation, removal and satisfactory disposal of all materials necessary for
the construction of new/widening carriageway in accordance with requirements of these specifications
and the lines, grades and cross sections shown in the drawings or as indicated by the Engineer.
After the site has been cleared the limits of excavation/ box cutting the road surface shall be set out
true to lines, curves, slopes, grades and sections as shown on the drawings or as directed by the
Engineer.
Box cutting shall be carried out in conformity with the directions laid here in under and in a manner
approved by the Engineer. The work shall be so done that the suitable materials available from box
cutting/ excavation are satisfactorily utilized as directed.
The contractor shall not excavate outside the limits of box cutting. Subject to the permitted tolerances,
any excess depth/ width excavated beyond the specified levels/ dimensions on the drawings shall be
made good at the cost of the contractor with suitable material of characteristics like that removed and
compacted as directed.
Cutting shall be done in proper grade & camber as per measurements given. Care must be taken that all
slopes are evenly and truly dressed. Cutting shall be done to the exact depth required and shall be as
per formation level in proper grade and the camber. If extra depth of cutting is done due to negligence
of contractor, the same shall be refilled with approved quality of materials duly consolidated to the
satisfaction of the Engineer-in-charge (without extra cost).
The bottom level of box cutting i.e. sub grade shall be watered and well compacted with vibratory
roller at OMC to the desired density as directed by the Engineer in charge. Rolling and compaction shall
Page | 118
be deemed to be incidental to the work and no extra cost shall be paid for compaction of box cutting
base surface.
The stuff received from the cutting shall be used for filling and correcting side slopes of bank and
earthwork for embankment as directed by the Engineer in charge with all lead and lift.
The measurement of box cutting shall be taken on level basis & level shall be taken at 30 mt. interval.
Volume shall be computed in cubic meters by average area method.
The rate includes cost of all labour, machineries required, cost of carting and spreading the cutting stuff
with all lead and lift and leveling the dumping ground/ embankment, rolling and consolidation of
subgrade level etc. complete.
Item94: Providing and laying Compacted WBM 125 mm thickness of Grading I,using BTMC metal of size
22.3mm to 53mm size including using 13% stone Screening 13.2mm size and 8% stone dust as filler
including spreading watering and Consolidation by Vibratory Rolleretc.complete. GradeI
SCOPE
This work shall consist of clean, machine crushed B.T. stone aggregates
mechanically interlocked by rolling and bonding together with screening, binding material where
necessary and water laid on a properly prepared sub grade/ sub bases base or existing pavement, as the
case may be and finished in accordance with the requirements of these specifications and in close
conformity with the lines, grades, cross-sections and thickness as per approved plans or as directed by
the Engineer.
Materials
Coarse aggregates
Coarse aggregates shall be either crushed stone of Black trap type only. The aggregates shall conform
to the physical requirements set forth in Table below. The type and size range of the aggregate shall be
specified in the Contract or shall be as specified by the Engineer. If the water absorption value of the
coarse aggregate is greater than 2 percent, the soundness test shall be carried out on the material
delivered to site as per IS : 2386 (Part 5).
Page | 119
Part 3 : Conditions of Contract & Contract Forms
The crushed or broken stone shall be hard, durable and free from excess flat, elongated, soft and
disintegrated particles, dirt and other deleterious material.
TABLE : PHYSICAL REQUIREMENTS OF COARSE AGGREGATES FOR WATER BOUND MACADAM FOR
SUB BASE COURSES
(Part-4) or
IS:5640**
2. Combined
Elongation - (Part- 1)
Indices (Total)
Aggregates like brick metal, kankar, laterite etc. which get softened in presence of water shall be tested
for Impact value under wet conditions in accordance with IS : 5640.
The requirement of flakiness index and elongation index shall be enforced only when the case of
Crushed broken stone and crushed slag.
The Coarse aggregates shall conform to one of the Grading given in Table as specified, provided,
however, the use of Grading No. 1 shall be restricted to sub-base course only.
Page | 120
TABLE
1. 90 mm to 45 mm 125 mm 100
90 mm 90-100
63 mm 25-60
45 mm 0-15
22.4 mm 0-5
2. 63 mm to 45 mm 90 mm 100
63 mm 90-100
53 mm 25-75
45 mm 0-15
22.4 mm 0-5
3. 53 mm to 22.4 mm 63 mm 100
53 mm 95-100
45 mm 65-90
22.4 mm 0-10
11.2 mm 0-5
The coarse aggregates shall be spread uniformly and evenly upon the prepared sub grade/sub-base/
base to profile by using templates placed across the road about. 6 m apart, in such quantities that the
Page | 121
Part 3 : Conditions of Contract & Contract Forms
thickness of each compacted layer is not more than 100 mm for Grading I and 75 mm for Grading 2 and
3 as specified. Wherever possible, approved mechanical devices such as aggregate spreader shall be
used to spread the aggregates uniformly so as to minimize the need for manual rectification
afterwards. Aggregates placed at locations which are inaccessible to the spreading equipment may be
spread in one or more layers by any approved means so as to achieve the specified results.
The spreading shall be done from stockpiles-along, the side of the roadway or directly from vehicles. No
segregation of large or fine aggregate shall be allowed and the coarse aggregate as spread shall be of
uniform with no pockets of fine material.
The surface of the aggregate spread shall be carefully checked with templates and all high or low spots
remedied by removing or adding aggregates as may be required. The surface shall be checked
frequently with a straight edge while spreading and rolling so as to (ensure a finished surface as par
drawings.
The coarse aggregate shall not normally be spread more than 3 days in advance of the subsequent
construction operations.
The surface finish of construction shall conform to the requirements of . Control on the quality of
materials and works shall be exercised by the Engineer
RATE
The Contract unit rate for this item of sub base/base course shall be payable in full for carrying out the
required operations including full compensation for all components listed below.
Making arrangements for traffic to except verges, shoulders and construction of diversions;
Furnishing all materials to be incorporated in the work including all royalties, fees, rents where
necessary and all leads and lifts,
Page | 122
Carrying out the work in part widths of the road where required
Item95: Providing and laying cement concrete 1:4:8 (1- Cement : 4- coarse sand : 8- B T stone aggregates
40 mm nominal size) and curing complete excluding cost of formwork in (A) Foundation and Plinth
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
cement concrete 1:4:8 (1- Cement : 4- coarse sand : 8- B T stone aggregates 40 mm nominal size) and
curing complete excluding cost of formwork in (A) Foundation and Plinth
Item96: Providing and laying cement concrete work 1:2:4 (1- Cement : 2- Coarse sand : 4- graded stone
aggregates 20 mm nominal size) and curing complete excluding cost of formwork and reinforcement
for reinforced concrete work in Foundation & Plinth
The work shall be executed as per specification of Item No.3 except the work is for providing and laying
cement concrete work 1:2:4 (1- Cement : 2- Coarse sand : 4- graded stone aggregates 20 mm nominal
size) and curing complete excluding cost of formwork and reinforcement for reinforced concrete work
in Foundation & Plinth
Item97: Providing and fixing pre cast Rubber Dye inter locking concrete block 60mm thick with grade of
concrete M200 pnumatic compresed by mechanically pressed and as per approved design including
75mm Sandlayer for levelling and filling the joint with sand in proper line and level etc.complete.
Constructing
General
Page | 123
Part 3 : Conditions of Contract & Contract Forms
This work shall consist of providing and laying precast Rubber Dye inter locking concrete block
60mm thick with grade of concrete M-200 pneumatic compressed by mechanically pressed and as per
approved design over a base layer of 75 mm thick layer of sand of the shape and dimensions shown on
the drawings and conforming to these specifications or as approved by the Engineer in charge.
1.0 MATERIAL
Rubber Dyed interlocking concrete block shall be of approved size brand and make as approved
by Engineer in charge.
1.1 The size shape and design of rubber Dyed interlocking concrete block shall generally be as per
manufacturers product or as directed by the Engineer in charge and Architect.
1.2 The rubber Dyed interlocking concrete block shall satisfy the tests as regards compress strength
transverse strength resistance to wear and water absorption.
1.3 The colour size shape and design of the rubber Dyed interlocking concrete block shall be
directed by Engineer or Architect.
1.4 The rubber Dyed interlocking concrete block shall be of best quality as approved by the Engineer
In charge. They shall be flat and true to shape. They shall be free form cracks, crazing spots, chipped
edges and corners. The glazing shall be of uniform shade.
2.0 SAND
2.1 Sand shall be natural sand, clean well graded, hard strong durable and gritty particular free from
immures amounts of dust, clay, kankar modules.
2.2. For masonry works sand shall confirm to the requirements of IS: 2116.
2.3. For plain and reinforced cement concrete (PCC and RCC) or pre stressed concrete (PSC) works
fine aggregates shall consist of clean, hard strong and durable prices of crushed stone, crushed gravel
or suitable combination of natural sand crushed stone or gravel, They shall not contain dust lumps soft
or flaky materials mica or other deleterious materials in such quantities as to reduce the strength and
durability of concrete, or to attack the embedded steel. Motorized sand washing machines should be
Page | 124
used to remove impurities from sand. Fine aggregate having positive alkali-silica reaction shall not be
used. All fine aggregates shall conform to IS L 383 and tests for conformity shall be carried out as per IS
: 2386 (Part I to VIII) The contractor shall submit to the Engineer in charge the entire information
indicated in Appendix A of IS : 383. The fineness modulus of fine aggregate shall neither be less than
2.00 nor greater than 3.5.
2.4. Sand fine aggregates for structural concrete shall conform to the following grading
requirements as shown in the table below.
2.5 Fine Sand: The fineness module shall not exceed 1.0 the sieve analysis of fine sand be as under:
Coarse Sand: The fineness modules of coarse sand shall not be less than 2.5 and shall not exceed 3.0.
The sieve analysis of coarse sand be as under:
4.75 mm 100
2.36mm 90 to 100
1.18 mm 70 to 100
Page | 125
Part 3 : Conditions of Contract & Contract Forms
600 MC 30 to 100
300 MC 85 to 70
150 MC 00 to 50
3.0 WORKMANSHIP
3.1 The rubber Dyed interlocking concrete block shall be laid on a layer 7.5 cm thick layer of coarse
sand. The slope in the floors shall be provided in the sub grade. The base layer shall be properly
watered, rammed and consolidated. Before laying the pavers blocks, it shall be moisture. Plinth
masonry offset shall be depressed so as to allow the sub grade concrete to rest on it.
3.2 Rubber Dyed interlocking concrete block of approved quality shape and design and shall be laid
evenly to level and slope as directed by Engineer in charge over a bed of a base layer consisting of
75mm thick sand layer.
3.3 Laying: The rubber Dyed interlocking concrete block tiles shall be laid in plain, diagonal or other
pattern as directed. The cement concrete blocks shall be laid properly and set home by gentle taping.
3.4 End portion of pavement shall be finished with C.M. 1:3 as per detailed drawing etc. complete.
4.1 The unit rate rubber Dyed interlocking concrete block flooring shall include the cost of all
materials, tools and plant required for supplying and laying material like brick bats sand pavers blocks,
laying of base layer in true level and slope as required applying & placing pavers blocks in position,
compacting, finishing, curing.
4.2 The length and breadth shall be measured correct to a Square meter correct to 2 places of
decimal. Length and breadth shall be measured to correct to a centimeter and between the finished the
finished face of the skirting, dedo or wall plaster and no deduction shall be made nor extra paid for any
opening in floors or areas up to 0.1 square meter.
Page | 126
4.3 The rate shall be for a unit of one Square meter.
Item98: Steel work, riveted in built up sections framed work including cutting, hoisting, fixing in
position and applying a priming coat of read lead paint. (A) In beams and joists, channels angles Tees,
flats, with connecting plates or angle cleats as in main and cross beams. Hip and jack rafters, purlins
conneted to common rafters and the like.
Materials
The structured steel work shall conform to M-22. Red lead paint shall conform to I.S : 102-1962.
2.0. Workmanship
2.1. The steel sections as specified or required, shall be cut, square and to correct lengths, as per
drawings and design. The cut ends exposed to view shall be finished smooth. No two pieces shall be
welded or otherwise jointed to make up the required length of member, except as indicated in the
drawing or as directed. All straightening and shaping to form shall be done by application of pressure
and not by hammering. Any bending or cutting shall be carried out in suet a manner as not to impair the
strength of the metal. All operations shall be done in cold state unless otherwise directed/permitted.
2.2.1. The steel structure as shown in the drawings or as per direction of the Engineer-in-charge shall
be laid out on a level platform to full scale and to full size in parts. A steel tape shall be used for
measurements to ensure maximum accuracy.
2.2.2. Wooden templates 12 mm. to 19 mm. thick or metal sheet template shall be made to correspond
to each connecting gussets plate and rivet holes shall be accurately marked on them and drilled. The
templates shall be laid on the steel members and holes of the steel members shall also be marked for
curing. The base of steel column and the .position of Anchor bolts shall be carefully set out
2.2.3. Ail stiffeners shall be formed by pressure and where practicable the metal shall not to be cut and
welded in making these. In major work, or whore so specified, shop drawings giving complete details
and information for the fabrication of the component parts of the structure including location, type,
size, (origin and details or rivets, bolts or weld shall be prepared in advance of the actual fabrication
and as distinctly marked or stenciled with paint with the identification mark as given in the stop
drawings. The bars shall be thickened at the ends, so as to provide for screwed threads and gradually
Page | 127
Part 3 : Conditions of Contract & Contract Forms
tapered off to meet their normal section. Great accuracy shall be observed in fabrication of various
member, so that these can be assembled without being unduly packed, stained, or forced into position
and when build up shall be true and tree from twists, brinks, buckles, or open joints. Before making
holes in individual members for fabrication the steel work intended to be riveted or belted together
shall be as ambled or clamped properly and tightly so as to ensure close abutting or lapping or the
surfaces of the different members. All softeners shall bear tightly both at top and bottom without
being drawn or caulked. The abutting joints shall be cut or crossed true and straight and fitted close
together. Web splice plates and tillers under stiffened shall be cut to fit within 3 mm. or flange Angles
Web plates of Girders shall have no cover. Plates shall have their ends flush with the top of angles
forming the flanges unless otherwise required. The web plates when spiced shall have clearance of not
more than 6 mm. The erection, clearance for created ends of members connecting steel shall preferably
be not greater than 5 mm. The erection clearance at the ends of beams without web cleats shall not be
more than 3 mm. at each end but where for a practical reason greater clearance is necessary, suitably
designed seating shall be provided. Pains and rollers shall be accurately tuned to gauge. These straight
and smooth and free from flows. The roller bearing shall be provided with adequate arraignments fur
holding the girders or truss resting on it. In columns caps and bases, the ends of shifts together with
the attached gussets Angles, channels etc after riveting together shah be accurately mechanized so
that the parts connected Butt against each other over the entire surfaces of contact connecting angles
or channels shall he fabricated and placed in position with greater accuracy so that they are nut unduly
reduced in thickness by machining. The ends of bearing stiffeners shall be mechanized or ground to tit
tightly both at the top and bottom, Alt holes shall generally be drilled to the required size and at
required, position. Sub punching shall be permitted provided it is done 3 mm. or less in diameter and
reamer thereafter to the require size. The holes for rivets and bolts shall be larger by 0 4. to 6 mm. than
the nominal diameter of rivets or black holts depending upon me diameter of rivets.
Holes shall have their axis perpendicular to the surface bored through. The drilling or remarrying shall
be free from burrs, and the holes should be clean and accurate holes for counter sunk bolts shall be
made in such a mariner that their heads fit flush with the surface after fixing.
(i) Rivets and turned and fitted bolts shall be used where the connections is such that slip under
load has to be avoided.
(ii) Black bolts may be used very sparingly where a force is carried through a connection without
impact, vibration or reversal or stresses.
Page | 128
2.2.4. Riveting:
The parts assembled for riveting shall be in close contact with each other and the bearing
stiffeners shall bear tightly both at top and bottom without being drawn or caulked. Members to be
riveted shall be properly pinned or bolted and rigidly held to gather while riveting. Drifting of holes shall
not be permitted except to draw the parts together and the drifting tools so used shall have maximum
diameter not exceeding, the nominal diameter of rivets or bolls. Drifting done during assembling shall
not distort the metal 01 enlarge the holes. The shanks of rivets shall project beyond the plate-surface
sufficiently so as to fill hole thoroughly and form the required head after riveting. The riveting shall be
done by hydraulic or pneumatic process. However where such facilities air not available, hand riveting
may be permitted. The rivet shall be heated red hot, care being taken to control the temperature of
heating so as not to burn the steel. Rivers of diameter less than 10 mm. may be fitted cold. Rivets shall
be of heat finish with heads full and of equal size. All loose, burnt or badly formed reverts with
concentric or deficient heads shall be cut out and replaced. The heads of rivets shall be central to
shanks and shall grip the assembled member firmly. In cutting out rivets, care shall be taken so as not
be injure assembled members, caulking or reequipping shall not be permitted.
For testing rivets, a hammer weighing approximately 0 25 kg shall be used. Both heads of
the rivets shall be tapped slack rivets will give a hollow sound and a jar. All rivet heads shall be painted
with red lead paint within a week of their fixing.
2.2.5. All bolt heads and nuts shall be hexagonal arid of equal size unless specified otherwise. The
screwed heads shall conform to I.S. 1363-1960 and the threaded surface shall not be tapered. The bolts
shall be of such length so as to project two clear threads beyond the nuts when fixed in position and
these shall lit in the holes without any shakes. The nut shall be fit in the threaded ends of bolts properly.
Where turned and fitted bolts are required to be used in place of rivets shall be provided with washers
not less than 6 mm. thick so that the nut when tightened shall not bear on the unthreaded body of the
bolt Tapered washers shall be provided for all heads and nuts bearing on leveled surfaces. The threaded
portion of the bolt shall not be within the thickness of the parts bolted together, the faces of the bolt
heads and nuts abutting against steel members shall be machine finished. Where there is a risk of the
nut being removed or becoming loose due to vibrations or reversal of stresses, these shall be secured
from slackening by me use of locknuts, spring washers, cross-cutting or hammering down of threads as
directed.
Bolts, nuts, and washers shall be thoroughly cleaned and dipped in double boiled linseed
oil before use. The whole steel work shall be painted with a coat of priming coat of red lead, as per
relevant specification of painting.
Page | 129
Part 3 : Conditions of Contract & Contract Forms
(a) All work shall be measured on the basis of finished dimensions as fixed at site and measured
net unless specified otherwise.
(b) The weight of steel sections, steel rods, and steel strips in finished work shall be calculated
Hum standard weight on the same basis on which steel is supplied to Contractor by department or
those given in relevant I.S. if steel is arranged by the contractor.
(c) The weight of steel plates and strips shall be taken from relevant I.S. based on 7.35 kg./ sq.
meter for every millimeter sheet thickness if steel is supplied to the contractor by department.
(d) Unless otherwise specified, weight of cleats, brackets, packing pieces, bolts, nuts, washer,
distance pieces, separators, diaphragm gusset (taking overall square dimensions) fish plates etc. shall
be added to the weight of respective items.
(e) In riveted work allowance is to be made for weight of rivet hands. No deductions shall be
made for rivet or bolts holes excluding holes for anchor or holding down bolts.
(f) For forged steel and steel castings, weight shall be calculated on the basis of 7850 kg./cum.
(g) Unless otherwise specified, no allowance shall be made for the weld metal in case of welded
steel structure.
(h) Dimensions other than cross sections and thickness of plates shall be measured to nearest
0.001m
3.2. The rate includes cost of all material, labour, erection, hoisting scaffolding, protective measure,
required for proper completion of the item of work. This shall also include conveyance and delivery
handling, loading, unloading and storing etc. required for completing the item described above
including necessary wastage involved.
Item99: Providing corrugated G.I. sheets roofing fixed with glavanished iron J or L Hooks, Bolts and
nuts 8mm diameter with bitumen and G.I. limpet washer. filled with white lead complete-excluding the
cost of purlins, Rafters and Trusses (1) 0.80 mm thick sheet.
Page | 130
The specification for G.I. sheet shall be as per material specification number M-23. It shall be fixed with
glavanished iron J or L Hooks, Bolts and nuts 8mm diameter with bitumen and G.I. limpet washer. filled
with white lead complete-excluding the cost of purlins, Rafters and Trusses (1) 0.80 mm thick sheet.
The measurement and payment shall be made on the basis of sq.mt. of complete finished work.
Item100: Providing and Laying Controlled cement concrete M-200 and finishing smooth with curing etc.
complete including the cost of formwork but excluding the cost of reinforsement for R.C.C work in
Coping & Lintel bend.
The work shall be executed as per specification of Item No.3 except the work is for providing and
Laying Controlled cement concrete M-200 and finishing smooth with curing etc. complete including the
cost of formwork but excluding the cost of reinforsement for R.C.C work in Coping & Lintel bend.
General
This work shall consist of painting the walls with weather proof emulsion exterior paint on exterior wall
surfaces of the dimensions shown on the drawings and conforming to these specifications or as
approved by the Engineer in charge.
Page | 131
Part 3 : Conditions of Contract & Contract Forms
MATERIALS
Exterior emulsion paint shall be of specified colour as approved by Engineer in charge the ready
mixed exterior emulsion paint shall not be allowed, If however ready mix emulsion paint of specified
shade or tint is not available white ready mixed paint with approved Steiner will be allowed in such case
the contractor shall ensure that the shade of the paint so allowed shall be uniform exterior emulsion
paint shall meet with the following general requirements
1. Exterior emulsion paint shall not show excessive setting in freshly opened full cam and shall
easily be redepresed with a paddle to a smooth homogeneous state. The exterior emulsion paint shall
show no curding, livering cracking or colour separation and shall be free form lumps and skins.
2. The exterior emulsion paint as received shall brush easily possess good leveling properties and
show no running or sagging tendencies.
3. The exterior emulsion paint shall not skin within 48 hours in a three quarters filled closed
container
4. The exterior emulsion paint shall dry to a smooth uniform finish free from roughness grit
unevenness and other imperfections
5. Ready mix exterior emulsion paint if allowed for specified shade, shall be used exactly as
received from the manufacturers and generally according to their instruction and without any
admixtures whatsoever.
2.1 Scaffolding :
Where scaffolding is required, it shall be erected in such a way that as far as possible no part of
scaffolding shall rest against the surface to be distempered. A properly secured strong and well tied
suspended platform (joola) may be used for distempering. Where ladders are used, pieces of old gunny
bags.
The exterior emulsion paint on exterior wall surfaces shall be diluted with water or any other
prescribed thinner in a manner recommended by the manufacturer only. Sufficient quantity of
distemper required for a day’s work shall be prepared.
Page | 132
3.1 For undecorated surfaces, after the primer coat is dried for at least 48 hours, the surface shall be
lightly sand papered to make it smooth for receiving the exterior emulsion paint, taking care not to rub
out the priming coat. All loose particles shall be dusted off after rubbing. Minimum two coats of the
exterior emulsion paint shall be applied with brushes in horizontal strokes followed immediately by
vertical strokes which together shall constitute one coat. The subsequent coats shall be applied after a
time interval of at least 24 hours between consecutive coats to permit proper drying of the preceding
coat. The finished surface shall be even and uniform without patches, brush marks, distemper drops
etc.
3.2 Sufficient quantity of the exterior emulsion paint shall be mixed to finish one room at a time.
3.1. The unit rate wall painting with exterior emulsion paint and including a primary coat with alkali
resistance primer of approved brand shall include the cost of all materials, tools and plant required for
mixing, cleaning brushing sand papering & painting with all required specials and Lapi compound,
finishing as per direction of the Engineer-in-charge, and all other incidental expenses for producing pipe
line work of specified diameter to complete the structure or its components as shown on the drawings
and according to these specifications. They shall also include the cost of making, fixing and removing of
all scaffolding and forms required for the work.
3.2 The rate of wall painting with exterior emulsion paint shall include the cost of all labour,
materials tools and plant scaffolding and all incidental expenses as described herein above.
3.3. The wall painting with exterior emulsion paint shall be measured for its length and height
limiting dimensions to those specified on plan or as directed. The rate shall be for a unit of one square
meter.
3.4. The payment will be made on square meter basis of the finished work.
Providing yellow or goradu soil for garden development both side of roads and surrounding area as per
instructions of Engineer-in charge.
Page | 133
Part 3 : Conditions of Contract & Contract Forms
2. The yellow or Goradu soil filling at requred depth, clean, free from dust and deleterious
matters obtained from a source as approved by the Engineer-in-charge.
3. After yellow or Goradu soil shall be filled in suitable layers not exceeding 30 cm. at a time
and each layer well compacted by rodding to maximum density or as directed by the Engineer-in-
charge.
4. Mode of measurement shall be the total cubical content (in cum.) of the area covered by brick
bat.
5. Unit rate includes the cost of materials, labour and tools and plant to complete the work.
Work of Supplying and planting dibbing semi carpet lawn at distance of about 15cm x 15cm after
proper anti termite treatment and rolling the same by hand roller and watering shall be
carriedout as under:
Narrow down seed types by climate: It shall be decided on the basis of which type is best for
surrounding climate, or based on the current time of year and temperature or decided by Engineer-in-
Charge in planting lawns.
Choose a specific seed type: It should provide better resilience to disease and environmental factors.
Browse blends and mixtures to find one suited to lawn's sunlight levels, preferred grass texture,
drought resistance, and durability to foot traffic. Avoid supplying low-quality seed blends using the
following tips:
Look for germination percentages above 75%, and an expiration date no more than ten months in the
past, for best sprouting results.
Look for grass seed containing less than 0.5% weed seeds.
Page | 134
Avoid annual ryegrass, which dies permanently in winter. Avoid rough "agricultural" perennial ryegrass,
or mixtures that include more than 20% of any type of ryegrass, or it can take over your lawn with its
rough texture and appearance.[20]
Work on the lawn in sections: After proper anti termite treatment, divide large lawns into sections
measuring approximately 6m x 6m. Work on each section separately, following the steps below for that
section before moving on to the next one. This lets you divide your work into multiple work sessions if
necessary, while ensuring that every section receives all the care it needs.
Sow the grass: Spread grass seed at distance of about 15cm x 15cm after proper anti termite
treatment using a seed distributor or lawn spreader if possible, to ensure even coverage. Drop the
seeds by hand if no other options are available, but always refer to the recommended sowing density
on the grass seed package. For even distribution, sow half the recommended seeds while walking in
parallel rows back and forth lengthwise across the lawn, then sow the remaining half while walking in
rows widthwise. If there is no recommended seed density on the packaging, use the following
guidelines:
Utility grass (designed for moderate to heavy use) can be sown at 15–20 grams per square meter.
Most "ornamental" grass designed for light use can be sown at 20–25g per sq m.
Lightly rake the soil: Use a rake to cover the majority of the seeds with a light layer of soil, no deeper
than 3 mm. This protects the seeds from birds and wind, but still makes it easy for the young grass
sprouts to push through the soil.
For grass seeds sown in the summer, a thin layer 6mm of mulch can help retain moisture. Straw or hay
mulch is not recommended, as it may contain weed seeds.
Stay off the lawn while it grows:Put up signs or temporary barriers if necessary to keep people off the
lawn. Do not step on the soil at all until the grass has germinated, which usually takes 10–14 days. Walk
across it as infrequently and lightly as possible for about six months after planting.
Page | 135
Part 3 : Conditions of Contract & Contract Forms
Water the seeds: Letting the seed dry out completely will prevent germination. To prevent this, water
the seeds immediately after planting with a light sprinkler, just to the point of "puddling." Repeat
frequently throughout each day until sprouts appear. After this occurs, water less often, but more
heavily, now that the established plants won't be washed away. The exact frequency of watering
depends on the temperature, humidity, and grass variety. Increase the watering frequency if the grass
turns brown, unless it is the dormant season (winter for warm-season grass, or summer for cold-season
grass).
If using a blend with Kentucky bluegrass, keep watering with the gentle, more frequent schedule after
the first sprouts appear. Look closely for the next few days for a new layer of small seedlings to sprout,
as "KBG" can take longer to germinate than other species.After this second wave of sprouts appears,
you can switch to a less frequent watering schedule.
Roll the lawn once the grass is 5–7½cm tall:Once the grass reaches this height, press it down with a
light garden roller – either an empty metal one, or a plastic one filled with about 4 liters of water.[29] If
you do not have a garden roller, it may attempt to lightly press the grass into the soil with the wheels of
a rotary mower, or by treading across it carefully, but try not to press it so hard that the soil becomes
hard and compacted.
Page | 136
The varieties of palms must be true to the type, healthy, straight and well established in earthen pots.
The plants must have about 2-3 rings formation on the lower portion of stem and also having 5-6 leave.
Repotted plants shall be rejected straightway.
(A) Bottom Palm Dia. 20-25 cm & Ht. 20-25 cm 120 to 150
(B) Triangle Palm Dia. 20-25 cm & Ht. 20-25 cm 120 to 150
(F) Green Mahindi Dia. 20-25 cm & Ht. 20-25 cm 120 to 150
(G) Varigated Ficus Dia. 20-25 cm & Ht. 20-25 cm 120 to 150
(H) New black Ficus Dia. 20-25 cm & Ht. 20-25 cm 120 to 150
(I) Pendula asopalav Dia. 20-25 cm & Ht. 20-25 cm 120 to 150
The Planting of the Palms shall be carried out after excavating pits 0.60 mt x 0.60 mt x 60 mt
size and removing and refilling the pits with extra fertile field soil (Yellow earth) at the rate 70% and
manure at the rate of 30% of the excavated soil. These refilled materials should be treated with anti
termite treatment as and when directed. The Plantation should be maintained for 3 months.
It shall be made on number basis of flowering plants including bowing and developing flowering
plants grown in nursery having approximate height 4 to 5 ft or height as per land scape plan with
natural growth and natural colour planted in a lump of soil packed in polithin bag or earthan pot
including organic & chemica fertilizer pestisides,fungicides, hormones & maintaining the plants up to
Page | 137
Part 3 : Conditions of Contract & Contract Forms
three month as deserted including labour charges for planting in pits and placing properly and
filling the pit with required prepared mix soil and watering and disporting
Item105: Providing laying and jointing in true line and level, Consil 25mm dia. U.P.V.C. Pipe (SCH- 40) for
cold water including fittings make PRINCE / SUPREME / ASTRAL / FINOLEX or equivalent as approved by
Engineer In Charge. Pipe shall be fixed on the wall with the help of clamp at every two metre C/C or
shall be concelled as directed including necessary 25mm tube MT fittings, such as such ruducing
coupler, union, band plug, endcap, pipe clip, Tee, hex nipple, elbow, cuopler,..etc complete As directed
By Engineer in Charge & using bonding materials.fittings etc. including testing of pipe and joints and
fixing the same with adhesive solvent, including cost of all materials, Labours. Etc.
1.0 Materials
1.1. The specified dia. U.P.V.C. pipes of ISI mark of approved quality shall be used.
2. Workmanship
U.P.V.C. pipes and fittings shall be of the diameter, size and type specified in the item. The pipe shall be
full lengths of 2 meter as far as possible. All the pipes shall be fixed on wall face at locations indicated
on drawings or as ordered by the Engineer-in-charge. Pipe shall be secured to face of wall below all
joints by M.S. clamps with wooden gut ties.The spigot of the upper pipe shall be properly fitted into the
socket of the lower pipe such that there is uniform annular space for fitting with the jointing materials.
One third depth of annular space between the item. The pipe shall be full lengths of 2 meter as far as
possible. All the pipes shall be fixed on wall face at locations indicated on drawings or as ordered by the
Engineer-in-charge. Pipe shall be secured to face of wall below all joints by M.S. clamps with wooden
gut ties.The spigot of the upper pipe shall be properly fitted into the socket of the lower pipe such that
there is uniform annular space for fitting with the jointing materials. One third depth of annular space
between the socket and the spigot shall be filled with spun-yarn soaked in bitumatic jointing compound
and shall be pressed home by means of caulking tool. The remaining 2/3 depth of the joints shall be
filled in with stiff cement mortar 1:2 and shall be pressed with caulking tool and finished smooth at top
at an angle of 45 sloping up. The joints shall be filled with cement mortar 1:2 (1 cement : 2 sand) span
spun yarn. The joints shall be filled with cement mortar 1.2 (1 cement : 2 sand) and spurn yarn. The pipes
Page | 138
without care shall be fixed to wall with M.S. clamps The pipes will earns shall be secured with 100 mm
before steel or iron barrel distance pieces or boils and stout galvanised iron nails 10 cms long into hand
wool plug fixed in walls. Access doors to fittings shall be provided with 3 mm. rubber insertion packing
and secured without screws to made air and water tight.All soil pipes shall be earned up above the roof
and shall have a wire ball on guarded or a cowl.The ventilating pipe or shaft shall be carried out to a
height of at least one meter above the outer covering of the roof of the building or in the case of
windows in a gable wall or a dormer windows, it shall carried up to a ridge of the roof or at least tow
meters above the top of the windows. In case of flat roof to which access for use is provided, it shall be
carried out up to a height of at least on meter above the parapet or two meters measured vertically
from the top of any windows or opening which any exist up to a horizontal distance of five meters from
the vent pipe into such building and in no case shall be carried out to a height less then three
meters.Where ventilating pipes are carried in pipe shafts, the shaft shall be of a minimum size of one
meter. If !he shells are also used to give fight and air to rooms, the ventilating pipes must be carried out
to a horizontal distance at root level not loss than five meter from the site of the shaft. The sand cast
iron pipes above parapet shall be fixed with M.S. clamps and stays. The clamps shall be made from 1.5
mm. thick MS flat or 3 mm. width band to the required shape and size to fit tightly one the sockets
when tightened with screw bolts. It shall be formed of two semi circular pieces with flanged ends on
both sides, with holes to fit in the screw bolts and nuts 100 mm. dia. M.S. Bars, One end of the stay shall
be bent to form a hook to be fixed with clamps by means of bolts and the other end shall be bent for
embedding in wall in cement concrete block of size 200 mm. x 100 mm. x 100 mm. in 1:2:4 mix. The
concrete shall be finished to match the surrounding surfaces.
The connection between the main pipe and branch pipes shall be made by using branches and bends
with access doors for cleaningThe waste from lavatories, kitchens basins, sinks, baths and other floor
traps shall be separately connected to respective stacks of upper floor. The waste stack of lavatories
shall be connected directly to main hole while the waste stack of other shall be separately discharged
over gulley trap.
3.0. Measurements
The length of pipe shall be measured including all fittings along its length in running meters correct to a
centimeter. No allowance shall be made for the portion of pipe length entered in the sockets of the
adjacent pipe of fittings.
The rate includes all labour, and materials, tools and plant etc. required for satisfactory completion of
this item.
Page | 139
Part 3 : Conditions of Contract & Contract Forms
Item106: Plantation of tree in soil including digging 45x45x45 cm size pits preparing soil & providing and
mixing organic fertiliser watering,planting and filling the pits
as per direction of engineer incharge.
Excavating the pits of 45x45x45 cm. size and Removing the excavated soil and refilling the same with
70% of extra fertile soil and 30% of well rotted farm yard manure including fertilizer, insectside etc.
complete as per detailed specification.
1.0 Before starting the work the site shall be cleared from any vegetation, thrown articles or waste
and any undulation. The ground shall be made in one plane. If required, it shall be stripped and make it
cleaned. Fresh soil shall be used for making the ground in level. After ascertaining the ground in one
plane and in good condition, the area to be developed shall be marked and a final layout shall be
decided to decide the region for plantation, grass Lawn, walk way, benches, play centre etc. in
consultation with the Engineer in charge. The payment for walk way, benches, play centre shall be
made separately in different items.
2.0 Grass Lawn shall be planted uniformly so that it can cover the whole region and no decided
space shall be left uncovered. After planting the grass Lawn, it shall be watered very well. The plants of
different sizes and species shall be planted at the places as decided by the Engineer in charge. The size
of the various pits shall be sufficient enough to provide space for different sizes of plants. After
planting the plants it shall be watered well and required qty of organic manure shall be utilized for
healthy growth of the plants.
Item107: Providing Tree Plants having minimum 1.mtr height and healthy growth of various kinds as like
plat form Gulmahore,Kanaj,Ambla,Ranitree,Saptarani,Cherry, Cryjeliya,Spethodia,Paras, Pipala,
Galmalo, Nem, Borsalli,Kadam,Buch,Chompo,Asopalav and as suggested etc.complete.
The work shall be executed as per specification of Item No.104 except the work is for providing Tree
Plants having minimum 1.mtr height and healthy growth of various kinds as like plat form
Gulmahore,Kanaj,Ambla,Ranitree,Saptarani,Cherry, Cryjeliya,Spethodia,Paras Pipala, Galmalo, Nem,
Borsalli,Kadam,Buch,Chompo,Asopalav and as suggested etc.complete.
Page | 140
Page | 141
Part 3 : Conditions of Contract & Contract Forms
DRAWING SECTION
Page | 142
Page | 143
Part 3 : Conditions of Contract & Contract Forms
Page | 144
Page | 145
Part 3 : Conditions of Contract & Contract Forms
Page | 146
Section IX – Particular Conditions of Contract
Page | 147
Section IX – Particular Conditions of Contract
Contract Forms
Page | 148
Section IX – Particular Conditions of Contract
These General Conditions of Contract (GCC), read in conjunction with the Particular
Conditions of Contract (PCC) and other documents listed therein, should be a complete
document expressing fairly the rights and obligations of both parties.
Page | 149
Section IX – Particular Conditions of Contract
A. General
Page | 150
Section IX – Particular Conditions of Contract
on a time basis for the Contractor’s employees and
Equipment, in addition to payments for associated
Materials and Plant.
(n) A Defect is any part of the Works not completed in
accordance with the Contract.
(o) The Defects Liability Certificate is the certificate
issued by Project Manager upon correction of defects
by the Contractor.
(p) The Defects Liability Period is the period named in
the PCC pursuant to GCC Sub-Clause 38.1 and
calculated from the Completion Date.
(q) Drawings means the drawings of the Works, as
included in the Contract, and any additional and
modified drawings issued by (or on behalf of) the
Employer in accordance with the Contract, include
calculations and other information provided or
approved by the Project Manager for the execution of
the Contract.
(r) The Employer is the party who employs the
Contractor to carry out the Works, as specified in the
PCC.
(s) Equipment is the Contractor’s machinery and vehicles
brought temporarily to the Site to construct the
Works.
(t) “In writing” or “written” means hand-written, type-
written, printed or electronically made, and resulting
in a permanent record;
(u) The Initial Contract Price is the Contract Price listed in
the Employer’s Letter of Acceptance.
(v) The Intended Completion Date is the date on which it
is intended that the Contractor shall complete the
Works. The Intended Completion Date is specified in
the PCC. The Intended Completion Date may be
revised only by the Project Manager by issuing an
extension of time or an acceleration order.
(w) Materials are all supplies, including consumables,
used by the Contractor for incorporation in the
Works.
(x) Plant is any integral part of the Works that shall have
a mechanical, electrical, chemical, or biological
function.
(y) The Project Manager is the person named in the PCC
(or any other competent person appointed by the
Employer and notified to the Contractor, to act in
Page | 151
Section IX – Particular Conditions of Contract
replacement of the Project Manager) who is
responsible for supervising the execution of the
Works and administering the Contract.
(z) PCC means Particular Conditions of Contract.
(aa) The Site is the area defined as such in the PCC.
(bb) Site Investigation Reports are those that were
included in the bidding document and are factual and
interpretative reports about the surface and
subsurface conditions at the Site.
(cc) Specification means the Specification of the Works
included in the Contract and any modification or
addition made or approved by the Project Manager.
(dd) The Start Date is given in the PCC. It is the latest date
when the Contractor shall commence execution of
the Works. It does not necessarily coincide with any
of the Site Possession Dates.
(ee) A Subcontractor is a person or corporate body who
has a Contract with the Contractor to carry out a part
of the work in the Contract, which includes work on
the Site.
(ff) Temporary Works are works designed, constructed,
installed, and removed by the Contractor that are
needed for construction or installation of the Works.
(gg) A Variation is an instruction given by the Project
Manager which varies the Works.
(hh) The Works are what the Contract requires the
Contractor to construct, install, and turn over to the
Employer, as defined in the PCC.
(ii) “Contractor’s Personnel” refers to all personnel
whom the Contractor utilizes on the Site or other
places where the Works are carried out, including the
staff, labor and other employees of each
Subcontractor.
(jj) “Key Personnel” means the positions (if any) of the
Contractor’s personnel that are stated in the
Specification.
(kk) “ES” means Environmental and Social (including
Sexual Exploitation and Abuse (SEA), and Sexual
Harassment (SH)).
(ll) “Sexual Exploitation and Abuse” “(SEA)” means the
following:
Sexual Exploitation is defined as any actual or
attempted abuse of position of vulnerability,
Page | 152
Section IX – Particular Conditions of Contract
differential power or trust, for sexual purposes,
including, but not limited to, profiting monetarily,
socially or politically from the sexual exploitation of
another;
Sexual Abuse is defined as the actual or threatened
physical intrusion of a sexual nature, whether by force
or under unequal or coercive conditions.
(mm) “Sexual Harassment” “(SH)” is defined as
unwelcome sexual advances, requests for sexual
favors, and other verbal or physical conduct of a
sexual nature by the Contractor’s Personnel with
other Contractor’s or Employer’s Personnel; and
(nn) “Employer’s Personnel” refers to the Project
Manager and all other staff, labor and other
employees (if any) of the Project Manager and of the
Employer engaged in fulfilling the Employer’s
obligations under the Contract; and any other
personnel identified as Employer’s Personnel, by a
notice from the Employer or the Project Manager to
the Contractor.
3. Language and 3.1 The language of the Contract and the law governing the
Law Contract are stated in the PCC.
3.2 Throughout the execution of the Contract, the Contractor
shall comply with the import of goods and services
prohibitions in the Employer’s country when
(a) as a matter of law or official regulations, the Borrower’s
country prohibits commercial relations with that country; or
(b) by an act of compliance with a decision of the United
Nations Security Council taken under Chapter VII of the
Charter of the United Nations, the Borrower’s Country
prohibits any import of goods from that country or any
payments to any country, person, or entity in that country.
5. Delegation 5.1 Unless otherwise specified in the PCC, the Project Manager
may delegate any of his duties and responsibilities to other
people, except to the Adjudicator, after notifying the
Contractor, and may revoke any delegation after notifying
the Contractor.
7. Subcontracting 7.1 The Contractor may subcontract with the approval of the
Project Manager, but may not assign the Contract without
the approval of the Employer in writing. Subcontracting
shall not alter the Contractor’s obligations. The Contractor
shall require that its Subcontractors execute the Works in
accordance with the Contract, including complying with the
relevant ES requirements and the obligations set out in Sub-
Clause 28.1.
8. Other 8.1 The Contractor shall cooperate and share the Site with
Contractors other contractors, public authorities, utilities, and the
Employer between the dates given in the Schedule of Other
Contractors, as referred to in the PCC. The Contractor shall
also provide facilities and services for them as described in
20
In lump-sum contracts, delete “Bill of Quantities” and replace with “Activity Schedule.”
Page | 154
Section IX – Particular Conditions of Contract
the Schedule. The Employer may modify the Schedule of
Other Contractors, and shall notify the Contractor of any
such modification.
8.2 The Contractor shall also, as stated in the Specifications or
as instructed by the Project Manager, cooperate with and
allow appropriate opportunities for the Employer’s or any
other personnel, notified to the Contractor by the Employer
or Project Manager, to conduct any environmental and
social assessment.
Page | 155
Section IX – Particular Conditions of Contract
9. Personnel and 9.1 The Contractor shall employ the Key Personnel and use the
Equipment Equipment identified in its Bid, to carry out the Works or
other personnel and Equipment approved by the Project
Manager. The Project Manager shall approve any proposed
replacement of Key Personnel and Equipment only if their
relevant qualifications or characteristics are substantially
equal to or better than those proposed in the Bid.
9.2 The Project Manager may require the Contractor to remove
(or cause to be removed) any person employed on the Site
or Works, including the Key Personnel (if any), who:
(a) persists in any misconduct or lack of care;
(b) carries out duties incompetently or negligently;
(c) fails to comply with any provision of the Contract;
(d) persists in any conduct which is prejudicial to safety,
health, or the protection of the environment;
(e) based on reasonable evidence, is determined to have
engaged in Fraud and Corruption during the execution
of the Works;
(f) has been recruited from the Employer’s Personnel;
(g) undertakes behavior which breaches the Code of
Conduct for Contractor’s Personnel (ES).
If appropriate, the Contractor shall then promptly appoint
(or cause to be appointed) a suitable replacement with
equivalent skills and experience.
Notwithstanding any requirement from the Project
Manager to remove or cause to remove any person, the
Contractor shall take immediate action as appropriate in
response to any violation of (a) through (g) above. Such
immediate action shall include removing (or causing to be
removed) from the Site or other places where the Works are
being carried out, any Contractor’s Personnel who engages
in (a), (b), (c), (d), (e) or (g) above or has been recruited as
stated in (f) above.”
9.3 The Contractor shall take all necessary safety measures to
avoid the occurrence of incidents and injuries to any third
party associated with the use of, if any, Equipment on public
roads or other public infrastructure. The Contractor shall
monitor road safety incidents and accidents to identify
negative safety issues, and establish and implement
necessary measures to resolve them.
9.4 Labor
9.4.1 Engagement of Staff and Labor. The Contractor shall
provide and employ on the Site for the execution of Page
the | 156
Works such skilled, semi-skilled and unskilled labor as is
necessary for the proper and timely execution of the
Contract. The Contractor is encouraged, to the extent
practicable and reasonable, to employ staff and labor with
appropriate qualifications and experience from sources
within the Country.
Unless otherwise provided in the Contract, the Contractor
shall be responsible for the recruitment, transportation,
Section IX – Particular Conditions of Contract
10. Employer’s and 10.1 The Employer carries the risks which this Contract states are
Contractor’s Employer’s risks, and the Contractor carries the risks which
Risks this Contract states are Contractor’s risks.
11. Employer’s 11.1 From the Start Date until the Defects Liability Certificate has
Risks been issued, the following are Employer’s risks:
(a) The risk of personal injury, death, or loss of or damage
to property (excluding the Works, Plant, Materials, and
Equipment), which are due to
(i) use or occupation of the Site by the Works or for
the purpose of the Works, which is the
unavoidable result of the Works or
(ii) negligence, breach of statutory duty, or
interference with any legal right by the Employer
or by any person employed by or contracted to
him except the Contractor.
(b) The risk of damage to the Works, Plant, Materials, and
Equipment to the extent that it is due to a fault of the
Employer or in the Employer’s design, or due to war or
radioactive contamination directly affecting the
country where the Works are to be executed.
11.2 From the Completion Date until the Defects Liability
Certificate has been issued, the risk of loss of or damage to
the Works, Plant, and Materials is an Employer’s risk except
loss or damage due to
(a) a Defect which existed on the Completion Date,
(b) an event occurring before the Completion Date, which
was not itself an Employer’s risk, or
(c) the activities of the Contractor on the Site after the
Completion Date.
12. Contractor’s 12.1 From the Starting Date until the Defects Liability Certificate
Risks has been issued, the risks of personal injury, death, and loss
of or damage to property (including, without limitation, the
Works, Plant, Materials, and Equipment) which are not
Employer’s risks are Contractor’s risks.
13. Insurance 13.1 The Contractor shall provide, in the joint names of the
Employer and the Contractor, insurance cover from the
Start Date to the end of the Defects Liability Period, in the
amounts and deductibles stated in the PCC for the following
events which are due to the Contractor’s risks:
(a) loss of or damage to the Works, Plant, and Materials;
(b) loss of or damage to Equipment;
Page | 157
Section IX – Particular Conditions of Contract
(c) loss of or damage to property (except the Works,
Plant, Materials, and Equipment) in connection with
the Contract; and
(d) personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by
the Contractor to the Project Manager for the Project
Manager’s approval before the Start Date. All such
insurance shall provide for compensation to be payable in
the types and proportions of currencies required to rectify
the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and
certificates required, the Employer may effect the insurance
which the Contractor should have provided and recover the
premiums the Employer has paid from payments otherwise
due to the Contractor or, if no payment is due, the payment
of the premiums shall be a debt due.
13.4 Alterations to the terms of an insurance shall not be made
without the approval of the Project Manager.
13.5 Both parties shall comply with any conditions of the
insurance policies.
14. Site Data 14.1 The Contractor shall be deemed to have examined any Site
Data referred to in the PCC, supplemented by any
information available to the Contractor.
15. Contractor to 15.1 The Contractor shall construct and install the Works in
Construct the accordance with the Specifications and Drawings.
Works 15.2 If the Contract specifies that the Contractor shall design any
part of the permanent Works, the Contractor shall take into
account the Employer’s requirements which may include, if
stated in the Specifications:
(a) designing structural elements of the Works taking
into account climate change considerations;
(b) applying the concept of universal access (the
concept of universal access means unimpeded
access for people of all ages and abilities in
different situations and under various
circumstances; and
(c) considering the incremental risks of the public’s
potential exposure to operational accidents or
natural hazards, including extreme weather events.
16. The Works to 16.1 The Contractor may commence execution of the Works on
Be Completed the Start Date and shall carry out the Works in accordance
by the Intended with the Program submitted by the Contractor, as updated
Completion with the approval of the Project Manager, and complete
Page | 158
Section IX – Particular Conditions of Contract
Date them by the Intended Completion Date.
16.2 The Contractor shall not carry out mobilization to the Site
unless the Project Manager gives approval, an approval that
shall not be unreasonably delayed, to the measures the
Contractor proposes to address environmental and social
risks and impacts, which at a minimum shall include applying
the Management Strategies and Implementation Plans
(MSIPs) and Code of Conduct for Contractor’s Personnel
submitted as part of the Bid and agreed as part of the
Contract.
The Contractor shall submit, to the Project Manager for its
approval any additional MSIPs as are necessary to manage
the ES risks and impacts of ongoing Works. These MSIPs
collectively comprise the Contractor’s Environmental and
Social Management Plan (C-ESMP). The Contractor shall
review the C-ESMP, periodically (but not less than every six
(6) months), and update it as required to ensure that it
contains measures appropriate to the Works. The updated
C-ESMP shall be submitted to the Project Manager for its
approval.
17. Approval by the 17.1 The Contractor shall submit Specifications and Drawings
Project showing the proposed Temporary Works to the Project
Manager Manager, for his approval.
17.2 The Contractor shall be responsible for design of Temporary
Works.
17.3 The Project Manager’s approval shall not alter the
Contractor’s responsibility for design of the Temporary
Works.
17.4 The Contractor shall obtain approval of third parties to the
design of the Temporary Works, where required.
17.5 All Drawings prepared by the Contractor for the execution
of the temporary or permanent Works, are subject to prior
approval by the Project Manager before this use.
18. Health, Safety 18.1 The Contractor shall be responsible for the safety of all
and Protection activities on the Site.
of the 18.2 The Contractor shall:
Environment
(a) comply with all applicable health and safety
regulations and Laws;
(b) comply with all applicable health and safety
obligations specified in the Contract;
(c) take care for the health and safety of all persons
entitled to be on the Site and other places, if any,
Page | 159
Section IX – Particular Conditions of Contract
where the Works are being executed;
(d) keep the Site and Works clear of unnecessary
obstruction so as to avoid danger to these persons;
(e) provide fencing, lighting, safe access, guarding and
watching of the Works until the issue of the Contract
Completion Certificate;
(f) provide any Temporary Works (including roadways,
footways, guards and fences) which may be necessary,
because of the execution of the Works, for the use and
protection of the public and of owners and occupiers
of adjacent land;
(g) provide health and safety training of Contractor’s
Personnel as appropriate and maintain training
records;
(h) actively engage the Contractor’s Personnel in
promoting understanding, and methods for,
implementation of health and safety requirements, as
well as in providing information to Contractor’s
Personnel, training on occupational safety and health,
and provision of personal protective equipment
without expense to the Contractor’s Personnel;
(i) put in place workplace processes for Contractor’s
Personnel to report work situations that they believe
are not safe or healthy, and to remove themselves
from a work situation which they have reasonable
justification to believe presents an imminent and
serious danger to their life or health.
(j) Contractor’s Personnel who remove themselves from
such work situations shall not be required to return to
work until necessary remedial action to correct the
situation has been taken. Contractor’s Personnel shall
not be retaliated against or otherwise subject to
reprisal or negative action for such reporting or
removal;
(k) where the Employer’s Personnel, any other
contractors employed by the Employer, and/or
personnel of any legally constituted public authorities
and private utility companies are employed in carrying
out, on or near the site, of any work not included in
the Contract, collaborate in applying the health and
safety requirements, without prejudice to the
responsibility of the relevant entities for the health
and safety of their own personnel; and
(l) establish and implement a system for regular (not less
than six-monthly) review of health and safety
Page | 160
Section IX – Particular Conditions of Contract
performance and the working environment.
Subject to GCC Sub-Clause 16.2, the Contractor shall submit
to the Project Manager for its approval a health and safety
manual which has been specifically prepared for the Works,
the Site and other places (if any) where the Contractor
intends to execute the Works.
The health and safety manual shall be in addition to any
other similar document required under applicable health and
safety regulations and laws.
The health and safety manual shall set out all the health and
safety requirements under the Contract,
(a) which shall include at a minimum:
(i) the procedures to establish and maintain a safe
working environment without risk to health at all
workplaces, machinery, equipment and processes
under the control of the Contractor, including
control measures for chemical, physical and
biological substances and agents;
(ii) details of the training to be provided, records to
be kept;
(iii) the procedures for prevention, preparedness and
response activities to be implemented in the case
of an emergency event (i.e. an unanticipated
incident, arising from both natural and man-made
hazards, typically in the form of fire, explosions,
leaks or spills, which may occur for a variety of
different reasons including failure to implement
operating procedures that are designed to
prevent their occurrence, extreme weather or
lack of early warning);
(iv) remedies for adverse impacts such as
occupational injuries, deaths, disability and
disease;
(v) the measures to be taken to avoid or minimize the
potential for community exposure to water-
borne, water-based, water-related, and vector-
borne diseases,
(vi) the measures to be implemented to avoid or
minimize the spread of communicable diseases
(including transfer of Sexually Transmitted
Diseases or Infections (STDs), such as HIV virus)
and non-communicable diseases associated with
the execution of the Works, taking into
Page | 161
Section IX – Particular Conditions of Contract
consideration differentiated exposure to and
higher sensitivity of vulnerable groups. This
includes taking measures to avoid or minimize the
transmission of communicable diseases that may
be associated with the influx of temporary or
permanent Contract-related labor;
(vii) the policies and procedures on the management
and quality of accommodation and welfare
facilities if such accommodation and welfare
facilities are provided by the Contractor in
accordance with GCC Sub-Clause 9.4.6; and
(b) any other requirements stated in the Specification
18.3 Protection of the environment
The Contractor shall take all necessary measures to:
18.3.1 protect the environment (both on and off the Site); and
18.3.2 limit damage and nuisance to people and property resulting
from pollution, noise and other results of the Contractor’s
operations and/ or activities.
The Contractor shall ensure that emissions, surface
discharges, effluent and any other pollutants from the
Contractor’s activities shall exceed neither the values
indicated in the Specifications, nor those prescribed by
applicable laws.
In the event of damage to the environment, property
and/or nuisance to people, on or off Site as a result of the
Contractor’s operations, the Contractor shall agree with
the Project Manager the appropriate actions and time
scale to remedy, as practicable, the damaged environment
to its former condition. The Contractor shall implement
such remedies at its cost to the satisfaction of the Project
Manager.
19. Archaeological 19.1 All fossils, coins, articles of value or antiquity, structures,
and Geological groups of structures, and other remains or items of
Findings geological, archaeological, paleontological, historical,
architectural or religious interest found on the Site shall be
placed under the care and custody of the Employer. The
Contractor shall:
(a) take all reasonable precautions, including fencing-off
the area or site of the finding, to avoid further
disturbance and prevent Contractor’s Personnel or
other persons from removing or damaging any of
Page | 162
Section IX – Particular Conditions of Contract
these findings;
(b) train relevant Contractor’s Personnel on appropriate
actions to be taken in the event of such findings; and
(c) implement any other action consistent with the
requirements of the Specifications and relevant laws.
The Contractor shall, as soon as practicable after discovery
of any such finding, notify the Project Manager of such
discoveries and carry out the Project Manager’s instructions
for dealing with them.
20. Possession of 20.1 The Employer shall give possession of all parts of the Site to
the Site the Contractor. If possession of a part is not given by the
date stated in the PCC, the Employer shall be deemed to
have delayed the start of the relevant activities, and this
shall be a Compensation Event.
21. Access to the 21.1 The Contractor shall allow the Project Manager and any
Site person authorized by the Project Manager (including the
Bank staff or consultants acting on the Bank’s behalf,
stakeholders and third parties, such as independent
experts, local communities, or non-governmental
organizations), including to carry out environmental and
social audit, as appropriate,access to the Site and to any
place where work in connection with the Contract is being
carried out or is intended to be carried out.
22. Instructions, 22.1 The Contractor shall carry out all instructions of the Project
Inspections and Manager which comply with the applicable laws where the
Audits Site is located.
22.2 The Contractor shall keep, and shall make all reasonable
efforts to cause its Subcontractors and subconsultants to
keep, accurate and systematic accounts and records in
respect of the Works in such form and details as will clearly
identify relevant time changes and costs.
Page | 163
Section IX – Particular Conditions of Contract
appointed by the Bank. The Contractor’s and its
Subcontractors’ and subconsultants’ attention is drawn to
GCC Sub-Clause 25.1 (Fraud and Corruption) which provides,
inter alia, that acts intended to materially impede the
exercise of the Bank’s inspection and audit rights constitute
a prohibited practice subject to contract termination (as
well as to a determination of ineligibility pursuant to the
Bank’s prevailing sanctions procedures).
23. Appointment of 23.1 The Adjudicator shall be appointed jointly by the Employer
the Adjudicator and the Contractor, at the time of the Employer’s issuance
of the Letter of Acceptance. If, in the Letter of Acceptance,
the Employer does not agree on the appointment of the
Adjudicator, the Employer will request the Appointing
Authority designated in the PCC, to appoint the Adjudicator
within 14 days of receipt of such request.
23.2 Should the Adjudicator resign or die, or should the Employer
and the Contractor agree that the Adjudicator is not
functioning in accordance with the provisions of the
Contract, a new Adjudicator shall be jointly appointed by the
Employer and the Contractor. In case of disagreement
between the Employer and the Contractor, within 30 days,
the Adjudicator shall be designated by the Appointing
Authority designated in the PCC at the request of either
party, within 14 days of receipt of such request.
24. Procedure for 24.1 If the Contractor believes that a decision taken by the
Disputes Project Manager was either outside the authority given to
the Project Manager by the Contract or that the decision
was wrongly taken, the decision shall be referred to the
Adjudicator within 14 days of the notification of the Project
Manager’s decision.
24.2 The Adjudicator shall give a decision in writing within 28
days of receipt of a notification of a dispute.
24.3 The Adjudicator shall be paid by the hour at the rate
specified in thePCC, together with reimbursable expenses
of the types specified in the PCC, and the cost shall be
divided equally between the Employer and the Contractor,
whatever decision is reached by the Adjudicator. Either
party may refer a decision of the Adjudicator to an
Arbitrator within 28 days of the Adjudicator’s written
decision. If neither party refers the dispute to arbitration
within the above 28 days, the Adjudicator’s decision shall be
final and binding.
24.4 The arbitration shall be conducted in accordance with the
arbitration procedures published by the institution named
Page | 164
Section IX – Particular Conditions of Contract
and in the placespecifiedin the PCC.
25. Fraud and 25.1 The Bank requires compliance with the Bank’s Anti-
Corruption Corruption Guidelines and its prevailing sanctions policies
and procedures as set forth in the WBG’s Sanctions
Framework, as set forth in Appendix A to the GCC.
25.2 The Employer requires the Contractor to disclose any
commissions or fees that may have been paid or are to be
paid to agents or any other party with respect to the
bidding process or execution of the Contract. The
information disclosed must include at least the name and
address of the agent or other party, the amount and
currency, and the purpose of the commission, gratuity or
fee.
26. Stakeholder 26.1 The Contractor shall provide relevant contract- related
Engagement information, as the Employer and/or Project Manager may
reasonably request to conduct Stakeholder engagements.
“Stakeholder” refers to individuals or groups who:
(i) are affected or likely to be affected by the Contract;
and
(ii) may have an interest in the Contract.
The Contractor may also directly participate in Stakeholder
engagements, as the Employer and/or Project Manager may
reasonably request
27. Suppliers (other 27.1 Forced Labor: The Contractor shall take measures to require
than its suppliers (other than Subcontractors) not to employ or
Subcontractors) engage forced labor including trafficked persons as
described in GCC Sub-Clause 9.4.14. If forced
labor/trafficking cases are identified, the Contractor shall
take measures to require the suppliers to take appropriate
steps to remedy them. Where the supplier does not remedy
the situation, the Contractor shall within a reasonable
period substitute the supplier with a supplier that is able to
manage such risks.
27.2 Child Labor: The Contractor shall take measures to require
its suppliers (other than Subcontractors) not to employ or
engage child labor as described in GCC Sub-Clause 9.4.15. If
child labor cases are identified, the Contractor shall take
measures to require the suppliers to take appropriate steps
to remedy them. Where the supplier does not remedy the
situation, the Contractor shall within a reasonable period
substitute the supplier with a supplier that is able to
manage such risks.
27.3 Serious Safety Issues: The Contractor, including its
Page | 165
Section IX – Particular Conditions of Contract
Subcontractors, shall comply with all applicable safety
obligations, including as stated in GCC Sub-Clause 18.2. The
Contractor shall also take measures to require its suppliers
(other than Subcontractors) to adopt procedures and
mitigation measures adequate to address safety issues
related to their personnel. If serious safety issues are
identified, the Contractor shall take measures to require the
suppliers to take appropriate steps to remedy them. Where
the supplier does not remedy the situation, the Contractor
shall within a reasonable period substitute the supplier with
a supplier that is able to manage such risks.
27.4 Obtaining natural resource materials in relation to supplier:
The Contractor shall obtain natural resource materials from
suppliers that can demonstrate, through compliance with
the applicable verification and/ or certification
requirements, that obtaining such materials is not
contributing to the risk of significant conversion or
significant degradation of natural or critical habitats such as
unsustainably harvested wood products, gravel or sand
extraction from river beds or beaches.
If a supplier cannot continue to demonstrate that obtaining
such materials is not contributing to the risk of significant
conversion or significant degradation of natural or critical
habitats, the Contractor shall within a reasonable period
substitute the supplier with a supplier that is able to
demonstrate that they are not significantly adversely
impacting the habitats.
28. Code of 28.1 The Contractor shall have a Code of Conduct for the
Conduct Contractor’s Personnel.
The Contractor shall take all necessary measures to ensure
that each Contractor’s Personnel is made aware of the Code
of Conduct including specific behaviors that are prohibited,
and understands the consequences of engaging in such
prohibited behaviors.
These measures include providing instructions and
documentation that can be understood by the Contractor’s
Personnel and seeking to obtain that person’s signature
acknowledging receipt of such instructions and/or
documentation, as appropriate.
The Contractor shall also ensure that the Code of Conduct is
visibly displayed in multiple locations on the Site and any
other place where the Works will be carried out, as well as in
areas outside the Site accessible to the local community and
Page | 166
Section IX – Particular Conditions of Contract
project affected people. The posted Code of Conduct shall
be provided in languages comprehensible to Contractor’s
Personnel, Employer’s Personnel and the local community.
The Contractor’s Management Strategy and Implementation
Plans shall include appropriate processes for the Contractor
to verify compliance with these obligations.
29. Security of the 29.1 The Contractor shall be responsible for the security of the
Site Site, and:
(a) for keeping unauthorized persons off the Site;
(b) authorized persons shall be limited to the Contractor’s
Personnel, the Employer’s Personnel, and to any other
personnel identified as authorized personnel
(including the Employer’s other contractors on the
Site), by a notice from the Employer or the Project
Manager to the Contractor.
Subject to GCC Sub-Clause 16.2, the Contractor shall submit
for the Project Manager’s No-objection a security
management plan that sets out the security arrangements
for the Site
The Contractor shall (i) conduct appropriate background
checks on any personnel retained to provide security; (ii)
train the security personnel adequately (or determine that
they are properly trained) in the use of force (and where
applicable, firearms), and appropriate conduct towards
Contractor’s Personnel, Employer’s Personnel and affected
communities; and (iii) require the security personnel to act
within the applicable Laws and any requirements set out in
the Specifications.
The Contractor shall not permit any use of force by security
personnel in providing security except when used for
preventive and defensive purposes in proportion to the
nature and extent of the threat.
In making security arrangements, the Contractor shall also
comply with any additional requirements stated in the
Specification.”
B. Time Control
30. Program and 30.1 Within the time stated in the PCC, after the date of the
Progress Letter of Acceptance, the Contractor shall submit to the
Reports Project Manager for approval a Program showing the
general methods, arrangements, order, and timing for all
the activities in the Works. In the case of a lump-sum
contract, the activities in the Program shall be consistent
Page | 167
Section IX – Particular Conditions of Contract
with those in the Activity Schedule. The Project Manager’s
approval of the Program shall not alter the Contractor’s
obligations. The Contractor may revise the Program and
submit it to the Project Manager again at any time. A
revised Program shall show the effect of Variations and
Compensation Events.
30.2 An update of the Program shall be a program showing the
actual progress achieved on each activity and the effect of
the progress achieved on the timing of the remaining work,
including any changes to the sequence of the activities.
30.3 The Contractor shall monitor progress of the Works and
submit to the Project manager progress report and any
updated Program showing the actual progress achieved and
the effect of the progress achieved on the timing of the
remaining Works, including any changes to the sequence of
the activities, at intervals no longer than the period stated in
the PCC. If the Contractor does not submit an updated
Program within this period, the Project Manager may
withhold the amount stated in the PCC from the next
payment certificate and continue to withhold this amount
until the next payment after the date on which the overdue
Program has been submitted. In the case of lump-sum
Contract, the Contractor shall provide an updated Activity
Schedule within 14 days of being instructed to by the Project
Manager.
30.4 Unless otherwise stated in the Specifications, each progress
report shall include the Environmental and Social (ES) metrics
set out in Appendix B.
30.5 In addition to the progress reports, the Contractor shall
inform the Project Manager immediately of any allegation,
incident or accident in the Site, which has or is likely to have a
significant adverse effect on the environment, the affected
communities, the public, Employer’s Personnel, Project
Manager’s personnel or Contractor’s Personnel. This
includes, but is not limited to, any incident or accident
causing fatality or serious injury; significant adverse effects
or damage to private property; or any allegation of SEA
and/or SH. In case of SEA and/or SH, while maintaining
confidentiality as appropriate, the type of allegation (sexual
exploitation, sexual abuse or sexual harassment), gender and
age of the person who experienced the alleged incident
should be included in the information.
The Contractor, upon becoming aware of the allegation,
incident or accident, shall also immediately inform the
Project Manager of any such incident or accident on the
Subcontractors’ or suppliers’ premises relating to the Works
Page | 168
Section IX – Particular Conditions of Contract
which has or is likely to have a significant adverse effect on
the environment, the affected communities, the public,
Employer’s Personnel, or Contractor’s, its Subcontractors’
and suppliers’ personnel. The notification shall provide
sufficient detail regarding such incidents or accidents. The
Contractor shall provide full details of such incidents or
accidents to the Project Manager within the timeframe
agreed with the Project Manager.
The Contractor shall require its Subcontractors and suppliers
(other than Subcontractors) to immediately notify the
Contractor of any incidents or accidents referred to in this
Subclause.
31. Extension of 31.1 The Project Manager shall extend the Intended Completion
the Intended Date if a Compensation Event occurs or a Variation is issued
Completion which makes it impossible for Completion to be achieved by
Date the Intended Completion Date without the Contractor
taking steps to accelerate the remaining work, which would
cause the Contractor to incur additional cost.
31.2 The Project Manager shall decide whether and by how much
to extend the Intended Completion Date within 21 days of
the Contractor asking the Project Manager for a decision
upon the effect of a Compensation Event or Variation and
submitting full supporting information. If the Contractor has
failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay by this failure
shall not be considered in assessing the new Intended
Completion Date.
32. Acceleration 32.1 When the Employer wants the Contractor to finish before
the Intended Completion Date, the Project Manager shall
obtain priced proposals for achieving the necessary
acceleration from the Contractor. If the Employer accepts
these proposals, the Intended Completion Date shall be
adjusted accordingly and confirmed by both the Employer
and the Contractor.
32.2 If the Contractor’s priced proposals for an acceleration are
accepted by the Employer, they are incorporated in the
Contract Price and treated as a Variation.
33. Delays Ordered 33.1 The Project Manager may instruct the Contractor to delay
by the Project the start or progress of any activity within the Works.
Manager
34. Management 34.1 Either the Project Manager or the Contractor may require
Meetings the other to attend a management meeting. The business of
a management meeting shall be to review the plans for
Page | 169
Section IX – Particular Conditions of Contract
remaining work and to deal with matters raised in
accordance with the early warning procedure.
34.2 The Project Manager shall record the business of
management meetings and provide copies of the record to
those attending the meeting and to the Employer. The
responsibility of the parties for actions to be taken shall be
decided by the Project Manager either at the management
meeting or after the management meeting and stated in
writing to all who attended the meeting.
35. Early Warning 35.1 The Contractor shall warn the Project Manager at the
earliest opportunity of specific likely future events or
circumstances that may adversely affect the quality of the
work, increase the Contract Price, or delay the execution of
the Works. The Project Manager may require the
Contractor to provide an estimate of the expected effect of
the future event or circumstance on the Contract Price and
Completion Date. The estimate shall be provided by the
Contractor as soon as reasonably possible.
35.2 The Contractor shall cooperate with the Project Manager in
making and considering proposals for how the effect of
such an event or circumstance can be avoided or reduced by
anyone involved in the work and in carrying out any
resulting instruction of the Project Manager.
C. Quality Control
36. Identifying 36.1 The Project Manager shall check the Contractor’s work and
Defects notify the Contractor of any Defects that are found. Such
checking shall not affect the Contractor’s responsibilities.
The Project Manager may instruct the Contractor to search
for a Defect and to uncover and test any work that the
Project Manager considers may have a Defect.
37. Tests 37.1 If the Project Manager instructs the Contractor to carry out
a test not specified in the Specifications to check whether
any work has a Defect and the test shows that it does, the
Contractor shall pay for the test and any samples. If there is
no Defect, the test shall be a Compensation Event.
38. Correction of 38.1 The Project Manager shall give notice to the Contractor of
Defects any Defects before the end of the Defects Liability Period,
which begins at Completion, and is defined in the PCC. The
Defects Liability Period shall be extended for as long as
Defects remain to be corrected.
38.2 Every time notice of a Defect is given, the Contractor shall
correct the notified Defect within the length of time
specified by the Project Manager’s notice.
Page | 170
Section IX – Particular Conditions of Contract
39. Uncorrected 39.1 If the Contractor has not corrected a Defect within the time
Defects specified in the Project Manager’s notice, the Project
Manager shall assess the cost of having the Defect
corrected, and the Contractor shall pay this amount.
D. Cost Control
40. Contract Price21 40.1 The Bill of Quantities shall contain priced items for the
Works to be performed by the Contractor. The Bill of
Quantities is used to calculate the Contract Price. The
Contractor will be paid for the quantity of the work
accomplished at the rate in the Bill of Quantities for each
item.
41. Changes in the 41.1 If the final quantity of the work done differs from the
Contract Price22 quantity in the Bill of Quantities for the particular item by
more than 25 percent, provided the change exceeds 1
percent of the Initial Contract Price, the Project Manager
shall adjust the rate to allow for the change. The Project
Manager shall not adjust rates from changes in quantities if
thereby the Initial Contract Price is exceeded by more than
15 percent, except with the prior approval of the Employer.
41.2 If requested by the Project Manager, the Contractor shall
provide the Project Manager with a detailed cost
breakdown of any rate in the Bill of Quantities.
21
In lump-sum contracts, replace GCC Sub-Clauses 40.1 as follows:
40.1 The Contractor shall provide updated Activity Schedules within 14 days of being instructed
to by the Project Manager. The Activity Schedule shall contain the priced activities for the
Works to be performed by the Contractor. The Activity Schedule is used to monitor and
control the performance of activities on which basis the Contractor will be paid. If payment
for materials on site shall be made separately, the Contractor shall show delivery of
Materials to the Site separately on the Activity Schedule.
22
In lump-sum contracts, replace entire GCC Clause 41 with new GCC Sub-Clause 41.1, as follows:
41.1 The Activity Schedule shall be amended by the Contractor to accommodate changes of
Program or method of working made at the Contractor’s own discretion. Prices in the
Activity Schedule shall not be altered when the Contractor makes such changes to the
Activity Schedule.
23
In lump-sum contracts, add “and Activity Schedules” after “Programs.”
Page | 171
Section IX – Particular Conditions of Contract
42.3 If the Contractor’s quotation is unreasonable, the Project
Manager may order the Variation and make a change to the
Contract Price, which shall be based on the Project
Manager’s own forecast of the effects of the Variation on
the Contractor’s costs.
42.4 If the Project Manager decides that the urgency of varying
the work would prevent a quotation being given and
considered without delaying the work, no quotation shall be
given and the Variation shall be treated as a Compensation
Event.
42.5 The Contractor shall not be entitled to additional payment
for costs that could have been avoided by giving early
warning.
42.6 If the work in the Variation corresponds to an item
description in the Bill of Quantities and if, in the opinion of
the Project Manager, the quantity of work above the limit
stated in GCC Sub-Clause 41.1 or the timing of its execution
do not cause the cost per unit of quantity to change, the
rate in the Bill of Quantities shall be used to calculate the
value of the Variation. If the cost per unit of quantity
changes, or if the nature or timing of the work in the
Variation does not correspond with items in the Bill of
Quantities, the quotation by the Contractor shall be in the
form of new rates for the relevant items of work. 24
42.7 Value Engineering: The Contractor may prepare, at its own
cost, a value engineering proposal at any time during the
performance of the contract. The value engineering
proposal shall, at a minimum, include the following;
(a) the proposed change(s), and a description of the
difference to the existing contract requirements;
(b) a full cost/benefit analysis of the proposed change(s)
including a description and estimate of costs
(including life cycle cost) the Employer may incur in
implementing the value engineering proposal;
(c) a description of any effect(s) of the change on
performance/functionality; and
(d) a description of the proposed work to be performed, a
program for its execution and sufficient ES
information to enable an evaluation of ES risks and
impacts.
The Employer may accept the value engineering proposal if
the proposal demonstrates benefits that:
24
In lump-sum contracts, delete this paragraph.
Page | 172
Section IX – Particular Conditions of Contract
(a) accelerates the contract completion period; or
(b) reduces the Contract Price or the life cycle costs to the
Employer; or
(c) improves the quality, efficiency, safety or sustainability
of the Facilities; or
(d) yields any other benefits to the Employer,
without compromising the functionality of the Works.
If the value engineering proposal is approved by the
Employer and results in:
(a) a reduction of the Contract Price; the amount to be
paid to the Contractor shall be the percentage
specified in the PCC of the reduction in the Contract
Price; or
(b) an increase in the Contract Price; but results in a
reduction in life cycle costs due to any benefit
described in (a) to (d) above, the amount to be paid to
the Contractor shall be the full increase in the Contract
Price.
43. Cash Flow 43.1 When the Program,25 is updated, the Contractor shall
Forecasts provide the Project Manager with an updated cash flow
forecast. The cash flow forecast shall include different
currencies, as defined in the Contract, converted as
necessary using the Contract exchange rates.
44. Payment 44.1 The Contractor shall submit to the Project Manager monthly
Certificates statements of the estimated value of the work executed
less the cumulative amount certified previously.
44.2 The Project Manager shall check the Contractor’s monthly
statement and certify the amount to be paid to the
Contractor.
44.3 The value of work executed shall be determined by the
Project Manager.
44.4 The value of work executed shall comprise the value of the
quantities of work in the Bill of Quantities that have been
completed.26
44.5 The value of work executed shall include the valuation of
Variations and Compensation Events.
44.6 The Project Manager may exclude any item certified in a
previous certificate or reduce the proportion of any item
25
In lump-sum contracts, add “or Activity Schedule” after “Program.”
26
In lump-sum contracts, replace this paragraph with the following: “The value of work executed shall
comprise the value of completed activities in the Activity Schedule.”
Page | 173
Section IX – Particular Conditions of Contract
previously certified in any certificate in the light of later
information.
44.7 If the Contractor was, or is, failing to perform any ES
obligations or work under the Contract, the value of this
work or obligation, as determined by the Project Manager,
may be withheld until the work or obligation has been
performed, and/or the cost of rectification or replacement,
as determined by the Project Manager, may be withheld
until rectification or replacement has been completed.
Failure to perform includes, but is not limited to the
following:
(a) failure to comply with any ES obligations or work
described in the Works’ Requirements which may
include: working outside site boundaries, excessive
dust, failure to keep public roads in a safe usable
condition, damage to offsite vegetation, pollution of
water courses from oils or sedimentation,
contamination of land e.g. from oils, human waste,
damage to archeology or cultural heritage features, air
pollution as a result of unauthorized and/or inefficient
combustion;
(b) failure to regularly review C-ESMP and/or update it in a
timely manner to address emerging ES issues, or
anticipated risks or impacts;
(c) failure to implement the C-ESMP e.g. failure to provide
required training or sensitization;
(d) failing to have appropriate consents/permits prior to
undertaking Works or related activities;
(e) failure to submit ES report/s (as described in Appendix
B), or failure to submit such reports in a timely
manner;
(f) failure to implement remediation as instructed by the
Project Manager within the specified timeframe (e.g.
remediation addressing non-compliance/s).
45. Payments 45.1 Payments shall be adjusted for deductions for advance
payments and retention. The Employer shall pay the
Contractor the amounts certified by the Project Manager
within 28 days of the date of each certificate. If the
Employer makes a late payment, the Contractor shall be
paid interest on the late payment in the next payment.
Interest shall be calculated from the date by which the
payment should have been made up to the date when the
late payment is made at the prevailing rate of interest for
commercial borrowing for each of the currencies in which
payments are made.
Page | 174
Section IX – Particular Conditions of Contract
45.2 If an amount certified is increased in a later certificate or as
a result of an award by the Adjudicator or an Arbitrator, the
Contractor shall be paid interest upon the delayed payment
as set out in this clause. Interest shall be calculated from the
date upon which the increased amount would have been
certified in the absence of dispute.
45.3 Unless otherwise stated, all payments and deductions shall
be paid or charged in the proportions of currencies
comprising the Contract Price.
45.4 Items of the Works for which no rate or price has been
entered in shall not be paid for by the Employer and shall be
deemed covered by other rates and prices in the Contract.
47. Tax 47.1 The Project Manager shall adjust the Contract Price if taxes,
duties, and other levies are changed between the date 28
days before the submission of bids for the Contract and the
date of the last Completion certificate. The adjustment shall
be the change in the amount of tax payable by the
Contractor, provided such changes are not already reflected
in the Contract Price or are a result of GCC Clause 49.
48. Currencies 48.1 Where payments are made in currencies other than the
currency of the Employer’s country specified in the PCC, the
exchange rates used for calculating the amounts to be paid
shall be the exchange rates stated in the Contractor’s Bid.
49. Price 49.1 Prices shall be adjusted for fluctuations in the cost of inputs
Adjustment only if provided for in the PCC. If so provided, the amounts
certified in each payment certificate, before deducting for
Advance Payment, shall be adjusted by applying the
respective price adjustment factor to the payment amounts
due in each currency. A separate formula of the type
specified below applies to each Contract currency:
Pc = Ac + BcImc/Ioc
Page | 176
Section IX – Particular Conditions of Contract
where:
Pc is the adjustment factor for the portion of the
Contract Price payable in a specific currency “c.”
Ac and Bc are coefficients27specified in the PCC,
representing the nonadjustable and adjustable
portions, respectively, of the Contract Price payable in
that specific currency “c;” and
Imc is the index prevailing at the end of the month being
invoiced and Ioc is the index prevailing 28 days before
Bid opening for inputs payable; both in the specific
currency “c.”
49.2 If the value of the index is changed after it has been used in
a calculation, the calculation shall be corrected and an
adjustment made in the next payment certificate. The index
value shall be deemed to take account of all changes in cost
due to fluctuations in costs.
50. Retention 50.1 The Employer shall retain from each payment due to the
Contractor the proportion stated in the PCC until
Completion of the whole of the Works.
50.2 Upon the issue of a Certificate of Completion of the Works
by the Project Manager, in accordance with GCC Sub-Clause
57.1, half the total amount retained shall be repaid to the
Contractor and half when the Defects Liability Period has
passed and the Project Manager has certified that all
Defects notified by the Project Manager to the Contractor
before the end of this period have been corrected. The
Contractor may substitute retention money with an “on
demand” Bank guarantee.
51. Liquidated 51.1 The Contractor shall pay liquidated damages to the
Damages Employer at the rate per day stated in the PCC for each day
that the Completion Date is later than the Intended
Completion Date. The total amount of liquidated damages
shall not exceed the amount defined in the PCC. The
Employer may deduct liquidated damages from payments
due to the Contractor. Payment of liquidated damages shall
not affect the Contractor’s liabilities.
51.2 If the Intended Completion Date is extended after
liquidated damages have been paid, the Project Manager
shall correct any overpayment of liquidated damages by the
27
The sum of the two coefficients A c and Bc should be 1 (one) in the formula for each currency. Normally, both coefficients shall be
the same in the formulae for all currencies, since coefficient A, for the nonadjustable portion of the payments, is a very approximate
figure (usually 0.15) to take account offixed cost elements or other nonadjustable components. The sum of the adjustments
for each currency are added to the Contract Price.
Page | 177
Section IX – Particular Conditions of Contract
Contractor by adjusting the next payment certificate. The
Contractor shall be paid interest on the overpayment,
calculated from the date of payment to the date of
repayment, at the rates specified in GCC Sub-Clause 45.1.
52. Bonus 52.1 The Contractor shall be paid a Bonus calculated at the rate
per calendar day stated in the PCC for each day (less any
days for which the Contractor is paid for acceleration) that
the Completion is earlier than the Intended Completion
Date. The Project Manager shall certify that the Works are
complete, although they may not be due to be complete.
53. Advance 53.1 The Employer shall make advance payment to the
Payment Contractor of the amounts stated in the PCC by the date
stated in the PCC, against provision by the Contractor of an
Unconditional Bank Guarantee in a form and by a bank
acceptable to the Employer in amounts and currencies
equal to the advance payment. The Guarantee shall remain
effective until the advance payment has been repaid, but
the amount of the Guarantee shall be progressively reduced
by the amounts repaid by the Contractor. Interest shall not
be charged on the advance payment.
53.2 The Contractor is to use the advance payment only to pay
for Equipment, Plant, Materials, and mobilization expenses
required specifically for execution of the Contract. The
Contractor shall demonstrate that advance payment has
been used in this way by supplying copies of invoices or
other documents to the Project Manager.
53.3 The advance payment shall be repaid by deducting
proportionate amounts from payments otherwise due to
the Contractor, following the schedule of completed
percentages of the Works on a payment basis. No account
shall be taken of the advance payment or its repayment in
assessing valuations of work done, Variations, price
adjustments, Compensation Events, Bonuses, or Liquidated
Damages.
54. Securities 54.1 The Performance Security shall be provided to the Employer
no later than the date specified in the Letter of Acceptance
and shall be issued in an amount specified in the PCC, by a
bank or surety acceptable to the Employer, and
denominated in the types and proportions of the currencies
in which the Contract Price is payable. The Performance
Security shall be valid until a date 28 days from the date of
issue of the Certificate of Completion in the case of a Bank
Guarantee, and until one year from the date of issue of the
Certificate of Completion in the case of a Performance
Bond.
Page | 178
Section IX – Particular Conditions of Contract
55. Dayworks 55.1 If applicable, the Dayworks rates in the Contractor’s Bid
shall be used only when the Project Manager has given
written instructions in advance for additional work to be
paid for in that way.
55.2 All work to be paid for as Dayworks shall be recorded by the
Contractor on forms approved by the Project Manager.
Each completed form shall be verified and signed by the
Project Manager within two days of the work being done.
55.3 The Contractor shall be paid for Dayworks subject to
obtaining signed Dayworks forms.
57. Completion 57.1 The Contractor shall request the Project Manager to issue
a Certificate of Completion of the Works, and the Project
Manager shall do so upon deciding that the whole of the
Works is completed.
58. Taking Over 58.1 The Employer shall take over the Site and the Works within
seven days of the Project Manager’s issuing a certificate of
Completion.
59. Final Account 59.1 The Contractor shall supply the Project Manager with a
detailed account of the total amount that the Contractor
considers payable under the Contract before the end of
the Defects Liability Period. The Project Manager shall
issue a Defects Liability Certificate and certify any final
payment that is due to the Contractor within 56 days of
receiving the Contractor’s account if it is correct and
complete. If it is not, the Project Manager shall issue
within 56 days a schedule that states the scope of the
corrections or additions that are necessary. If the Final
Account is still unsatisfactory after it has been
resubmitted, the Project Manager shall decide on the
amount payable to the Contractor and issue a payment
certificate.
60. Operating and 60.1 If “as built” Drawings and/or operating and maintenance
Maintenance manuals are required, the Contractor shall supply them by
Manuals the dates stated in the PCC.
60.2 If the Contractor does not supply the Drawings and/or
manuals by the dates stated in the PCC pursuant to GCC
Page | 179
Section IX – Particular Conditions of Contract
Sub-Clause 60.1, or they do not receive the Project
Manager’s approval, the Project Manager shall withhold
the amount stated in the PCC from payments due to the
Contractor.
61. Termination 61.1 The Employer or the Contractor may terminate the
Contract if the other party causes a fundamental breach of
the Contract.
61.2 Fundamental breaches of Contract shall include, but shall
not be limited to, the following:
Page | 180
Section IX – Particular Conditions of Contract
63. Property 63.1 All Materials on the Site, Plant, Equipment, Temporary
Works, and Works shall be deemed to be the property of
the Employer if the Contract is terminated because of the
Contractor’s default.
64. Release from 64.1 If the Contract is frustrated by the outbreak of war or by
Performance any other event entirely outside the control of either the
Employer or the Contractor, the Project Manager shall
certify that the Contract has been frustrated. The
Contractor shall make the Site safe and stop work as
quickly as possible after receiving this certificate and shall
be paid for all work carried out before receiving it and for
any work carried out afterwards to which a commitment
was made.
Page | 181
Section IX – Particular Conditions of Contract
65. Suspension of 65.1 In the event that the Bank suspends the Loan or Credit to
Bank Loan or the Employer, from which part of the payments to the
Credit Contractor are being made:
(a) The Employer is obligated to notify the Contractor of
such suspension within 7 days of having received the
Bank’s suspension notice.
(b) If the Contractor has not received sums due to it
within the 28 days for payment provided for in GCC
Sub-Clause 45.1, the Contractor may immediately
issue a 14-day termination notice.
Page | 182
Section IX – Particular Conditions of Contract
Page | 183
Section IX – Particular Conditions of Contract
Notwithstanding any other provision of this Clause, Force
Majeure shall not apply to obligations of either Party to make
payments to the other Party under the Contract.
Page | 184
Section IX – Particular Conditions of Contract
(a) the amounts payable for any work carried out for which a
price is stated in the Contract;
(b) the Cost of Plant and Materials ordered for the Works
which have been delivered to the Contractor, or of which
the Contractor is liable to accept delivery: this Plant and
Materials shall become the property of (and be at the risk
of) the Employer when paid for by the Employer, and the
Contractor shall place the same at the Employer's disposal;
(c) any other Cost or liability which in the circumstances was
reasonably incurred by the Contractor in the expectation of
completing the Works;
(d) the Cost of removal of Temporary Works and Contractor's
Equipment from the Site and the return of these items to
the Contractor's works in his country (or to any other
destination at no greater cost); and
(e) the Cost of repatriation of the Contractor's staff and labour
employed wholly in connection with the Works at the date
of termination.
65.8 Release from Performance under the Law
Notwithstanding any other provision of this Clause, if any
event or circumstance outside the control of the Parties
(including, but not limited to, Force Majeure) arises which
makes it impossible or unlawful for either or both Parties to
fulfil its or their contractual obligations or which, under the
law governing the Contract, entitles the Parties to be
released from further performance of the Contract, then
upon notice by either Party to the other Party of such event
or circumstance:
(a) the Parties shall be discharged from further performance,
without prejudice to the rights of either Party in respect of
any previous breach of the Contract, and Page | 185
(b) the sum payable by the Employer to the Contractor shall be
the same as would have been payable under Sub-Clause 66.6
[Optional Termination, Payment and Release] if the Contract
had been terminated under Sub-Clause 66.6.
Section IX – Particular Conditions of Contract
APPENDIX A
TO GENERAL CONDITIONS
1. Purpose
1.1 The Bank’s Anti-Corruption Guidelines and this annex apply with respect to
procurement under Bank Investment Project Financing operations.
2. Requirements
2.1 The Bank requires that Borrowers (including beneficiaries of Bank financing);
bidders (applicants/proposers),consultants, contractors and suppliers; any sub-
contractors, sub-consultants, service providers or suppliers; any agents (whether
declared or not); and any of their personnel, observe the highest standard of ethics
during the procurement process, selection and contract execution of Bank-financed
contracts, and refrain from Fraud and Corruption.
2.2 To this end, the Bank:
a. Defines, for the purposes of this provision, the terms set forth below as
follows:
i. “corrupt practice” is the offering, giving, receiving, or soliciting,
directly or indirectly, of anything of value to influence improperly
the actions of another party;
ii. “fraudulent practice” is any act or omission, including
misrepresentation, that knowingly or recklessly misleads, or
attempts to mislead, a party to obtain financial or other benefit or
to avoid an obligation;
iii. “collusive practice” is an arrangement between two or more
parties designed to achieve an improper purpose, including to
influence improperly the actions of another party;
iv. “coercive practice” is impairing or harming, or threatening to
impair or harm, directly or indirectly, any party or the property of
the party to influence improperly the actions of a party;
v. “obstructive practice” is:
(a) deliberately destroying, falsifying, altering, or concealing
of evidence material to the investigation or making false
statements to investigators in order to materially impede a
Bank investigation into allegations of a corrupt,
fraudulent, coercive, or collusive practice; and/or
threatening, harassing, or intimidating any party to
Page | 186
Section IX – Particular Conditions of Contract
prevent it from disclosing its knowledge of matters
relevant to the investigation or from pursuing the
investigation; or
(b) acts intended to materially impede the exercise of the
Bank’s inspection and audit rights provided for under
paragraph 2.2 e. below.
b. Rejects a proposal for award if the Bank determines that the firm or individual
recommended for award, any of its personnel, or its agents, or its sub-
consultants, sub-contractors, service providers, suppliers and/ or their
employees, has, directly or indirectly, engaged in corrupt, fraudulent, collusive,
coercive, or obstructive practices in competing for the contract in question;
c. In addition to the legal remedies set out in the relevant Legal Agreement, may
take other appropriate actions, including declaring misprocurement, if the
Bank determines at any time that representatives of the Borrower or of a
recipient of any part of the proceeds of the loan engaged in corrupt,
fraudulent, collusive, coercive, or obstructive practices during the procurement
process, selection and/or execution of the contract in question, without the
Borrower having taken timely and appropriate action satisfactory to the Bank
to address such practices when they occur, including by failing to inform the
Bank in a timely manner at the time they knew of the practices;
d. Pursuant to the Bank’s Anti- Corruption Guidelines and in accordance with the
Bank’s prevailing sanctions policies and procedures, may sanction a firm or
individual, either indefinitely or for a stated period of time, including by publicly
declaring such firm or individual ineligible (i) to be awarded or otherwise
benefit from a Bank-financed contract, financially or in any other manner;28 (ii)
to be a nominated29 sub-contractor, consultant, manufacturer or supplier, or
service provider of an otherwise eligible firm being awarded a Bank-financed
contract; and (iii) to receive the proceeds of any loan made by the Bank or
otherwise to participate further in the preparation or implementation of any
Bank-financed project;
e. Requires that a clause be included in bidding/request for proposals documents
and in contracts financed by a Bank loan, requiring (i)
bidders(applicants/proposers), consultants, contractors, and suppliers, and
their sub-contractors, sub-consultants, service providers, suppliers, agents
personnel, permit the Bank to inspect30 all accounts, records and other
28
For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i)
applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-
contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such
contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract.
29 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider
(different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in
its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to
meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower.
30 Inspections in this context usually are investigative (i.e., forensic) in nature. They involve fact-finding activities undertaken by
the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the
veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is
not limited to: accessing and examining a firm's or individual's financial records and information, and making copies thereof as
relevant; accessing and examining any other documents, data and information (whether in hard copy or electronic format)
deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant
individuals; performing physical inspections and site visits; and obtaining third party verification of information.
Page | 187
Section IX – Particular Conditions of Contract
documents relating to the procurement process, selection and/or contract
execution, and to have them audited by auditors appointed by the Bank.
Page | 188
Section IX – Particular Conditions of Contract
APPENDIX B
[Note to Employer: the following metrics may be amended to reflect the specifics of the
Contract. The Employer shall ensure that the metrics provided are appropriate for the
Works and impacts/key issues identified in the environmental and social assessment]
Page | 189
Section IX – Particular Conditions of Contract
ii. number of workers, work hours, metric of PPE use (percentage of workers
with full personal protection equipment (PPE), partial, etc.), worker
violations observed (by type of violation, PPE or otherwise), warnings given,
repeat warnings given, follow-up actions taken (if any);
f. worker accommodations:
i. number of expats housed in accommodations, number of locals;
ii. date of last inspection, and highlights of inspection including status of
accommodations’ compliance with national and local law and good
practice, including sanitation, space, etc.;
iii. actions taken to recommend/require improved conditions, or to improve
conditions.
g. Health services: provider of health services, information and/or training, location of
clinic, number of non-safety disease or illness treatments and diagnoses (no names
to be provided);
h. gender (for expats and locals separately): number of female workers, percentage of
workforce, gender issues raised and dealt with (cross-reference grievances or other
sections as needed);
i. training:
i. number of new workers, number receiving induction training, dates of
induction training;
ii. number and dates of toolbox talks, number of workers receiving
Occupational Health and Safety (OHS), environmental and social training;
iii. number and dates of communicable diseases (including STDs) sensitization
and/or training, no. workers receiving training (in the reporting period and
in the past); same questions for gender sensitization, flag person training.
iv. number and date of SEA and SH prevention sensitization and/or training
events, including number of workers receiving training on Code of Conduct
for Contractor’s Personnel (in the reporting period and in the past), etc.
j. environmental and social supervision:
i. environmentalist: days worked, areas inspected and numbers of
inspections of each (road section, work camp, accommodations, quarries,
borrow areas, spoil areas, swamps, forest crossings, etc.), highlights of
activities/findings (including violations of environmental and/or social best
practices, actions taken), reports to environmental and/or social
specialist/construction/site management;
ii. sociologist: days worked, number of partial and full site inspections (by
area: road section, work camp, accommodations, quarries, borrow areas,
spoil areas, clinic, HIV/AIDS center, community centers, etc.), highlights of
Page | 190
Section IX – Particular Conditions of Contract
activities (including violations of environmental and/or social requirements
observed, actions taken), reports to environmental and/or social
specialist/construction/site management; and
iii. community liaison person(s): days worked (hours community center
open), number of people met, highlights of activities (issues raised, etc.),
reports to environmental and/or social specialist /construction/site
management.
k. Grievances: list new grievances (e.g. number of allegations of SEA and SH)
received in the reporting period and number of unresolved past grievances by
date received, complainant’s age and sex, how received, to whom referred to for
action, resolution and date (if completed), data resolution reported to
complainant, any required follow-up (Cross-reference other sections as needed):
i. Worker grievances;
ii. Community grievances
l. Traffic, road safety and vehicles/equipment:
i. traffic and road safety incidents and accidents involving project vehicles &
equipment: provide date, location, damage, cause, follow-up;
ii. traffic and road safety incidents and accidents involving non-project
vehicles or property (also reported under immediate metrics): provide
date, location, damage, cause, follow-up;
iii. overall condition of vehicles/equipment (subjective judgment by
environmentalist); non-routine repairs and maintenance needed to
improve safety and/or environmental performance (to control smoke,
etc.).
m. Environmental mitigations and issues (what has been done):
i. dust: number of working bowsers, number of waterings/day, number of
complaints, warnings given by environmentalist, actions taken to resolve;
highlights of quarry dust control (covers, sprays, operational status); % of
rock/ spoil lorries with covers, actions taken for uncovered vehicles;
ii. erosion control: controls implemented by location, status of water
crossings, environmentalist inspections and results, actions taken to
resolve issues, emergency repairs needed to control
erosion/sedimentation;
iii. quarries, borrow areas, spoil areas, asphalt plants, batch plants: identify
major activities undertaken in the reporting period at each, and highlights
of environmental and social protection: land clearing, boundary marking,
topsoil salvage, traffic management, decommissioning planning,
decommissioning implementation;
Page | 191
Section IX – Particular Conditions of Contract
iv. blasting: number of blasts (and locations), status of implementation of
blasting plan (including notices, evacuations, etc.), incidents of off-site
damage or complaints (cross-reference other sections as needed);
v. spill clean-ups, if any: material spilled, location, amount, actions taken,
material disposal (report all spills that result in water or soil contamination;
vi. waste management: types and quantities generated and managed,
including amount taken offsite (and by whom) or
reused/recycled/disposed on-site;
vii. details of tree plantings and other mitigations required undertaken in the
reporting period;
viii. details of water and swamp protection mitigations required undertaken in
the reporting period.
n. compliance:
i. compliance status for conditions of all relevant consents/permits, for the
Work, including quarries, etc.): statement of compliance or listing of issues
and actions taken (or to be taken) to reach compliance;
ii. compliance status of C-ESMP/ESIP requirements: statement of compliance
or listing of issues and actions taken (or to be taken) to reach compliance
iii. compliance status of SEA and SH prevention and response action plan:
statement of compliance or listing of issues and actions taken (or to be
taken) to reach compliance
Page | 192
Section IX – Particular Conditions of Contract
Section IX -Particular Conditions of Contract
A.General
GCC1.1(d) The financing institution is:TheWorldBank
GCC1.1(r) The THE EXECUTIVE ENGINEER, KADANA DIVISION NO.1 , DIWADA COLONY,
KADANA GUJARAT
GCC1.1(v) The Intended Completion Date forthewholeoftheWorks shall be 18
months (including rainy season) after commencement date
GCC1.1(y) The Project Manager THE EXECUTIVE ENGINEER, KADANA DIVISION NO.1,
DIWADA COLONY, KADANA GUJARAT
GCC1.1(aa) The Site is located at THE EXECUTIVE ENGINEER, KADANA DIVISION NO.1,
DIWADA COLONY, KADANA, TA. KADANA Dist. PANCHMAHAL, GUJARAT.
GCC1.1(dd) The Start Date shallbe10 days after the date of issue of notice to proceed
with works to the contractor.
GCC1.1(hh) Resurfacing of Panam Patiya to Panam Dam Road km. 0/00 To 14/000 Ta.
Shahera, Dist. Panchamahal,Gujarat underDRIP-II.……………..2020/21
GCC1.1(jj) GCC 1.1 (jj) is replaced with the following:
“Key Personnel are the Contractor’s personnel named in GCC 9.1 of the
Particular Conditions of Contract.”
Page | 193
Section IX – Particular Conditions of Contract
GCC2.3(i) Thefollowingdocuments also form part of
theContract:
S. No. Document Description of the document
“Salient features of major labour and other laws that are applicable to
construction industry in India are given as Appendix 1 to these General
Conditions of Contract.”
“The Contractor may subcontract with the approval of the Project Manager
up to a ceiling specified in PCC, but may not assign the Contract without the
approval of the Employer in writing.”
7.4 The Contractor shall not be required to obtain any consent from the
Employer for:
(Note: 1. All bidders are expected to indicate clearly in the bid, if they
proposed sub-contracting elements of the works amounting to more
than 10 percent of the Bid Price. For each such proposal the
qualification and the experience of the identified sub-contractor in the
relevant field should be furnished along with the bid to enable the
employer to satisfy himself about their qualifications before agreeing
for such sub-contracting and include it in the contract. In view of the
above, normally no additional sub-contracting should arise during
execution of the contract.
Page | 195
Section IX – Particular Conditions of Contract
companies etc.)”
GCC 7.1 The ceiling for sub-contractor is 25% [This is in addition to what was stated
in bid and incorporated in contract agreement.].Hiding information about
any sub-contracting not authorized by the Employer shall be treated as
violation of Appendix A to General Conditions (Fraud and Corruption).
GCC 8.1 Schedule of other contractors: Not applicable
GCC 9 The following is inserted as a sub-clause at the end of GCC 9.2:
“In all the above cases, the contractor shall ensure that the person leaves
the site within seven days and has no further connection with the work in
the contract. The Contractor shall appoint a suitable replacement within 28
days or earlier as may be agreed to between the Project Manager and the
Contractor.”
“9.5 The Contractor shall not employ any retired Gazetted officer who has
either not completed two years after the date of retirement or has not
obtained permission from the Government authorities for
employment with the Contractor31.
9.6 During continuance of the Contract, the Contractor and his Sub-
Contractors shall abide at all times by all existing labour enactments
and rules made there under, regulations, notifications and bye laws of
the State or Central Government or local authority and any other labour
laws (including rules), regulations, bye laws that may be passed or
notification that may be issued under any labour law prevailing on the
Base Date either by the State or the Central Government or the local
authority. The Contractor shall keep the Employer indemnified in case
any action is taken against the Employer by the competent authority on
account of contraventions including amendments. If the Employer is
caused to pay or reimburse, such amounts as may be necessary to
cause or observe, or for non-observance of the provisions stipulated in
the notifications/bye laws/Acts/Rules/regulations including
amendments, if any, on the part of the Contractor, the Project
Manager/ Employer shall have the right to deduct any money due to
31
Based on Government Directives.
Page | 196
Section IX – Particular Conditions of Contract
the Contractor including his amount of performance security and if
applicable, the Environmental and Social (ES) Performance Security.
The Employer/ Project Manager shall also have right to recover from
the Contractor any sum required or estimated to be required for
making good the loss or damage suffered by the Employer.
9.7 The employees of the Contractor and the Sub-Contractor in no case shall
be treated as the employees of the Employer at any point of time.
9.8 The Contractor shall duly comply with the provisions of the
Apprentices Act 1961 (III of 1961) and the rules made there under, and
comply, failure or neglect to shall be subject to all liabilities and penalties
provided in the said Act and Rules.”
GCC 9.1 [insert the name/s of each Key Personnel agreed by the Employer prior to
Contract signature, Schedule of Key Personnel and equipment as indicated in
accepted bid & construction methodology].
Page | 197
Section IX – Particular Conditions of Contract
GCC 15.1 GCC 15.1 is replaced with the following:
“The Contractor shall construct and install the Works in accordance with
the Specifications and Drawings and as per instructions of Project
Manager.”
GCC15.2 Thefollowingis added as sub-clause15.2:
―If so instructed byProject Manager, the Contractorshallsubmittothe
Project Managerforreview, ahealthand safetymanual,
specificallypreparedfortheWorks, theSiteandotherplaces(if any)wherethe
Contractor intends
to execute theWorks. Themanual shall beinaddition to anyothersimilar
document required underapplicable health and
safetyregulationsandLaws. Thehealthand safetymanual and its updates
shallbereviewedalongwith the Contractor‘s Environmental and Social
Management Plan (C-ESMP) described in sub-clause16.2.ǁ
GCC 18 (add The following is inserted as a new sub-clause 18.3.3:
new 18.3.3)
“18.3.3 During continuance of the contract, the contractor and his sub-
contractors shall abide at all times by all existing enactments on
environmental protection and rules made thereunder, regulations,
notifications and by-laws of the State or Central Government, or local
authorities and other law, bye-law, regulations that may be passed or
notification that may be issued in this respect in future by the State or
Central Government or the local authority. Salient features of the major
laws are given in Appendix 1 to the General Conditions of Contract.”
GCC20.1 The Site Possession Date(s) shall be: Within 10 days from issuance of
letter of acceptance.
GCC 23 The following is inserted as a new sub-clause 23.1.1:
“31.1 The Project Manager shall extend the Intended Completion Date
including milestones if a Compensation Event occurs or a Variation is
issued which makes it impossible for Completion to be achieved by
the Intended Completion Date as per the agreed milestones without
the Contractor taking steps to accelerate the remaining work, which
would cause the Contractor to incur additional cost.”
In GCC 31.2, replace the words “Intended Completion Date” at the first
occurrence by the words “Intended Completion Date/ Milestones”; and at
the second occurrence by the words “Intended Completion Date/
Milestone”.
Page | 199
Section IX – Particular Conditions of Contract
GCC 34 GCC 34.1 is replaced with the following:
“Either the Project Manager or the Contractor may require the other to
attend a management meeting (which will be held at the place indicated
in PCC. The periodicity shall be fixed by Project Manager/ Contractor
jointly). The business of a management meeting shall be to review the
progress of construction with reference to the construction program
given in accordance with GCC 30.1, the plans for remaining work and to
deal with matters raised in accordance with the early warning procedure.”
GCC 34.1 Venue of management meeting will be: officeofChief Engineer and
Additional Secretary (South Gujarat), Block No. 09, 2nd Floor, New
Sachivalay, Gandhinagar, Gujarat
The management meetings shall be held at intervals of ……..(State the
periodicity).
C.QualityControl
“GCC 37.1 The Contractor shall institute Quality Assurance (QA) and Quality
Control (QC) systems in accordance with Quality Assurance
Plan to demonstrate compliance with the requirements of the
Contract as approved by the Project Manager. Compliance
with the QA/QC systems shall not relieve the Contractor of any
of his duties obligations or responsibilities under the Contract.
2. Where the failure to correct a particular defect within the specified time
is considered as a fundamental breach of contract a notice should be given
to the contractor as stated in GCC 61.2(e).”
D. Cost Control
Page | 200
Section IX – Particular Conditions of Contract
GCC 41& GCC 41 & 42 are replaced as under:
42
1. The Engineer-in-charge shall have power to make any alterations in or
addition to the original specifications, drawings, designs and instructions
that may appear to him to be necessary or advisable during the progress
of the work and the contractor shall be bound to carry out the work in
accordance with any instructions in this connection which may be given
to him in writing signed by the Engineer-in-charge and such alternation
shall not invalidate the contract and any additional work which the
contractor may be directed to do in the manner above specified as part
of the work shall be carried out by the contractor on the same
conditions in all respects on which he agreed to do the main work and at
the same rate as are specified in the tender for the main work.
2. Except that when the quantity of any item exceeds the quantity as in the
tender by more than 10% the contractor will be paid for the quantity in
excess of 10% at the rate entered in the S. 0. R. of the year during which
the excess in quantity is first executed or tender rate whichever is less.
3. If the additional or altered work includes any class of work for which no
rate is specified in this contract, then such class of work shall be carried
out.
(i) At the rate derived from the item within the contract which is
comparable to the one involving additional or altered class of
work; where there are more than one comparable items, the
item of the contract which is nearest in comparison with
regard to class or classes of the work involved shall be
selected and the decision of the Superintending Engineer as
to the nearest comparable item shall be final and binding on
the contractor.
(ii) if the rate cannot be derived in accordance with (i) above,
such class of works shall be carried out at the rate entered in
the Schedule of Rates of the Division for the year in which the
tender was received, increased or decreased by the
percentage by which the tender amount is more or less as
compared to the amount arrived at the rates in the "Schedule
of Rates" of the Division in the year in which the tender was
received. If the Schedule of rates of the Division does not
contain all the items, the percentage increase or decrease of
the tender shall be calculated considering such items which
were included in the "Schedule of Rates" of the Division for
the year and for materials consumed on such item the rate to
be charged would be the basic rate taken into account for
fixing the rate in S. O. R. referred to above, instead of the rate
stipulated for FREE ISSUE MATERIALS.
Page | 201
Section IX – Particular Conditions of Contract
4. If the additional or altered work, for which no rate is entered in the
"Schedule of Rates" of the Division is ordered to be carried out before
the rate is agreed upon, then the contractor shall within seven days of
the date of receipt by him of the order to carry out the work, inform the
Engineer-in-charge of the rate, which it is his intention to charge for such
class of work and arrange to carry it out in such manner as he may
consider it advisable, provided always that if the contractor shall
commence work or incur any expenditure in regard thereof before the
rates shall have been determined as lastly herein before mentioned,
then in such cases he shall only be entitled to be paid ;In respect of the
work carried out or expenditure incurred by him prior to the date of the
determination of the rate as aforesaid according to such rate or rates as
shall be fixed by the Engineer-in -charge. In the event of the dispute, the
decision of the Superintending Engineer of the Circle shall be final.
The time limit for the completion of the work shall be extended in the
proportion that the increase in the cost occasioned by alternations bears
to the cost of the original contract work and the certificate of the
Engineer-in-charge as to such proportion shall be final and conclusive.
GCC 42.7 Provisions related to Value Engineering do not apply.
GCC 43.1 The second sentence in GCC 43.1 is replaced with the following:
At the end of GCC 44.2 after the words ‘the Contractor’, the following words
are added:
“after taking into account any credit or debit for the month in question in
respect of materials for the works in the relevant amount and under
conditions set forth in GCC Sub-Clause 53.1 (Secured Advance)”
Page | 202
Section IX – Particular Conditions of Contract
GCC 45 GCC 45.1 is replaced with the following:
“45.5 The Contractor shall open an Escrow Account with his bank for the
purpose of receiving all the payments as well as incurring expenditure under
this Contract. The Account shall be open to verification and audit at any time
by the Employer or designee of the Employer. This account will be controlled
solely by the Contractor’s Project Officers (Project Manager and/or Finance
Manager or equivalent designate). No other Contractor employees or
associates will have access to the Project Account or the funds therein. The
Contractor shall report monthly on the status of this account including actual
bank account statements. The Contractor shall provide all Account statements
as requested by the Employer.”
GCC 45.1 Interest rate forDelayedpayment is 5 %perannum
GCC 45.3 All payments (and deductions) shall be paid or charged in Indian Rupees.
GCC 47 The following sub-clause is inserted before GCC 47.1, and GCC 47.1 is re-
numbered as GCC 47.2:
In first line of the re-numbered GCC 47.2, replace the words ‘the date 28 days
before’ with the words ‘the deadline for’.
GCC 48 All payments shall be made in Indian Rupees.
Page | 203
Section IX – Particular Conditions of Contract
GCC 49 GCC 49 is replaced with the following:
Price variation clause: Price variation: For (A) Labour (B) Materials and (C) P.O.L
The amounts payable to the contractor for the work done shall be adjusted for
increase or decrease in the rates of labour/ materials excepting those materials
supplied by Government as per Schedule-A and P.O.L. as under.
(B) Materials other than cement, Steel and Asphalt: The increase or
decrease in cost of materials other than cement and steel shall be
calculated quarterly in accordance with the following formula:
Vm = 0.75 x {Pm/100 x R x i-io/io}
Page | 204
Section IX – Particular Conditions of Contract
quarter under consideration due to change in the rates
of material
(C) P.O.L: The increase or decrease in cost of petrol, diesel, oil and
lubricants shall be calculated quarterly in accordance with the
following formula:
Vd = 0.75 x {pd/100 x R x D-Do/Do}
Page | 205
Section IX – Particular Conditions of Contract
be carried out for the quarter in which the tenders
were opened.
(2) The sum total price adjustment for B will be excluding the cost of
Materials supplied from the Departmental store to the Contractor at
fixed rate as specified in DEPARTMENTALLY ISSED MATERIALS and
cement, steel and asphalt valued at input rates mentioned as under on
which the sanctioned estimate is based.
(4) The value of extra items will be excluded for working out the value of 'R'
in the above formula in all these cases.
(6) Price adjustment shall be applicable only for the work that is carried out
within the stipulated time or extensions thereof as per not attributable
to the contractor. No claims for price adjustment other than those
Page | 206
Section IX – Particular Conditions of Contract
provided herein shall be entertained.
(7) This clause will be applicable in respect of works which of the estimated
cost put to tender is above Rs.25.00lacs and the time limit involved is
more than 18moths.
Price Variation for Cement, Steel and Asphalt brought by Contractor: The
amounts payable to the contractors for the work done involving use of cement,
steel and asphalt when these materials are not supplied by the Government as
for DEPARTMENTALLY ISSED MATERIALS shall be adjusted for increase or
decrease in the rates of these materials as under.
(4) Price variation for cement, steel and asphalt brought by the contractor.
The star rates for cement, mild steel and for steel & asphalt to be brought by
the Contractor shall be considered Ex-Supply Depot/Godown as under: -
[The above star rates are linked with Reserve Bank of India price index for
steel and cement & asphalt for the month in which the DTPs are approved.
The month in which DTPs are approved will be specified in the tender
document.
Star rates should be mentioned in the tender copy as under:
II(a) For steel & H.Y.S.D. bars, rate of SAIL should be obtained for the month
in which the DTPs. are approved and mentioned as star rate before issue
of tender copy.
II(b) For asphalt the Star Rate is based on the Koyali Refinery prevailing in the
month of which D.T.P is approved and should be mentioned before issue
of tender copy.
III. For basic index specific month in which the DTPs are approved should be
mentioned before issue of tender copy.]
The fluctuations in rates of cement and steel shall be adjusted in the bills
Page | 207
Section IX – Particular Conditions of Contract
payable to the contractors as under:
A=B x {C1/C0 – 1} x D
C1- The (quarterly) average corresponding index for steel, cement, asphalt for
the quarter under consideration (as published in monthly bulletin or Reserve
Bank of India)
Co. – Price index of cement/steel asphalt for the month in which the DTPs are
approved published in monthly bulletin of Reserve Bank of India.)
D-- Qty. of cement/steel actually brought by the contractor on site of work and
consumed in the work during the quarter duly supported with bill as recorded
in cement consumption register or MB (for steel).
1. No ceiling escalation for difference in the cost of steel and cement will
be applicable.
2. This clause shall be operative from the date of issue of work order and
up to the expiry of original and extended time limit, if the delay for the
reasons attributable to the contractor, Star rate is not payable, however
recovery will be effected.
3. This formula shall be used individually for Cement/mild steel and Tor
steel for calculation adjustment.
4. The cement and steel brought by the contractor on site of work shall be
used only after the same in tested by the Department.
5. If such materials are not found as per the requirement of L.S
specification, the same shall be removed by the contractor for which no
claim shall be entertained
6. This Cause will be applied to the work inspective of the cost of the work.
Conditions for variation in rates of asphalt only: -
Page | 208
Section IX – Particular Conditions of Contract
the work. This difference shall be Payable /recoverable for the asphalt
consumed in the work executed during original & extended time limit, if
time limit is extended for reasons of delay attributable to the
department. This difference shall not payable for the work executed in
extended time limit, when extension is given for the reason of delay
attributable to the contractor, however in case if price of asphalt is
decreased during the extended time limit than difference between the
actual rate of purchase and the quoted star rate shall be recovered from
the contractor.
7. (A) The difference will be payable/recoverable for the asphalt procured
on and after the date of issue of work order and this price variation will
not be subject to any ceiling. In case the contractor has procured the
asphalt, before issue of work order either of original purchase rate or
the prevailing rate of asphalt at the time of actual consumption in the
work, whichever is less, will be considered for calculating the difference
payable / recovered.
(B). variation in rates of asphalt shall be payable only after cross
verification of refinery gate passes of asphalt with the issuing refinery or
in case of imported asphalt invoices shall be cross verified with the
statutory documents of the authorized dealer and authorized importer.
8. No advance payment or secured Advance will be payable against
asphalt.
9. This part of clause for price variation of asphalt will be applicable for
works estimated to cost above Rs. 5 Lacs and involving use of asphalt.
10. It is permissible to use asphalt product by Private Companies like ESSAR
and imported asphalt also. If the contractor opt to use asphalt produced
by Private Companies or imported asphalt.
a. The Contractor can procure asphalt produced by Private
company of India or imported asphalt and use in the work.
b. The Contractor will have to produce in original, the purchase
invoice of asphalt.
c. All the conditions for variation in rates of asphalt shall be
applicable for the imported asphalt.
d. For calculation of variation in the rate of asphalt, the rate
prevalent at Indian port at the time of purchase in case of
imported asphalt or the rate as per purchase invoice in case of
asphalt purchased from private Indian company or Ex. Refinery
rate of Indian Public Sector undertaking refinery (IOC, HPCL,
BPCL) in the date of purchase, whichever is less, shall be
considered for working out the difference and for comparison of
the Star rate shown above in this clause. This difference shall be
payable / recoverable for the asphalt consumed in the work
executed during original & extended time limit if time limit is
extended for reasons of delay attributable to the department.
This difference shall not be payable for the work executed in
extended time limit, when extension is given for the reason of
delay attributable to the contractor, however in case if price of
asphalt is decreased than difference between the actual rate of
Page | 209
Section IX – Particular Conditions of Contract
purchase and the quoted star rate shall be recovered from the
contractor.
11. If the contractor use imported Asphalt, it will be verified that the
imported Asphalt to be used is of specified viscosity Grade before
permitting to use imported Asphalt. Grade Certificate of Refinery from
which Asphalt is imported only must be obtained. Grade Certificate of
any other Laboratory / institution should not be accepted. For testing of
imported asphalt, six conditions stipulated in R&B Circular No.
STR/102006/1577/8/H Dated 22-11-2017 should also be compiled with.
“On completion of the whole works the Contractor may substitute the balance
retention money with an “on demand” Bank guarantee.”
GCC 51 In the first sentence of GCC 51.1, the following words are inserted after the
words ‘Intended Completion Date’:
“(for the whole of the works or the milestones as stated in the PCC)”
In the first sentence in GCC 51.2 the following words are inserted after the words
‘Intended Completion Date’:
“including milestones”
GCC 51.1 Theliquidated damagesforthe whole ofthe Works are[0.05%of the final
Contract Price] per day.Themaximum amount ofliquidated damages for the
whole oftheWorks is[10 percentage]of thefinalContract Price.
Page | 210
Section IX – Particular Conditions of Contract
GCC 52.1 Provisions related to Bonus do not apply.
(iii) The recovery of the advance shall be affected from the second
month from the month in which advance is given and full recovery
will be completed by the time seventy-five percent of scheduled
time is completed.
(v) The advance will be granted for the plant and machinery actually
brought to the site of work.
Page | 211
Section IX – Particular Conditions of Contract
(viii) In the case of used or second hand equipment brought by
the contractor advance will be allowed at 50 percent of the value
of the equipment arrived at in the following manner.
The advance shall be repaid with percentage deductions from the interim
payments certified by the Project Manager under the Contract. Deductions
shall commence in the next Interim Payment Certificate following that in which
the total of all such payments to the contractor has reached not less than 15
percent of the Contract Price or 9 months from the date of payment of first
installment of advance, whichever period concludes earlier, and shall be made
at the rate of 15% of the amounts of all Interim Payment Certificates until such
time as the advance has been repaid, always provided that the advance shall be
Page | 212
Section IX – Particular Conditions of Contract
completely repaid prior to the expiry of the original time for completion.
If the terms of the Performance Security and additional security , specify its
expiry date, and the Contractor has not become entitled to receive the
Completion Certificate by the date 28 days prior to the expiry date, the
Contractor shall extend the validity of the Performance Security and additional
security, until the end of extended Completion Period.”
GCC 54.1 The Performance Security amount is 5 percent of Contract Amount plus
additional security for unbalanced bids [in terms of ITB Clause 41.2], and
Environmental and Social (ES) Performance Security amount is 1 percent of
Contract Amount .
[Notes: The Bank Guarantees shall be unconditional (on demand) (see Section X,
Contract Forms).
Throughout this bidding document the term ’performance security’, unless the
context clearly indicates otherwise, means and includes both ‘the performance
security and the ES performance security’ to be submitted by the successful
bidder in the amounts specified above.
E.FinishingtheContract
GCC 59.1 The following is added after the words ‘issue a payment certificate’ at the
end of GCC 59.1:
GCC 61.2(g) The maximum number of days is: 200 days after commencement of
works
GCC 61.2(l) Hiding any information regarding changes in roles and responsibilities of
JV members, which is not authorized by the Employer, shall also be
treated as violation of Appendix A to General Conditions (Fraud and
Corruption).
GCC 62 The following is added after the words ‘issue of the certificate’ in the first
sentence of GCC 62.1;
The following is added after the words ‘date of the certificate’ at the end of
GCC 62.2:
Page | 214
Section IX – Particular Conditions of Contract
APPENDICES
Page | 215
Appendix 1
(a) Employees Compensation Act 1923: The Act provides for compensation in
case of injury, disease or death arising out of and during the course of
employment.
(b) Payment of Gratuity Act 1972: gratuity is payable to an employee under the
Act on satisfaction of certain conditions on separation if an employee has
completed 5 years’ service or more or on death at the rate of 15 days wages
for every completed year of service. The Act is applicable to all
establishments employing 10 or more employees.
(c) Employees P.F. and Miscellaneous Provision Act 1952 (since amended): The
Act provides for monthly contribution by the employer plus workers @ 10% or
8.33%. The benefits payable under the Act are:
(i) Pension or family pension on retirement or death, as the case may be.
(d) Maternity Benefit Act 1961: The Act provides for leave and some other
benefits to women employees in case of confinement or miscarriage etc.
(e) Sexual Harassment of Women at the Workplace (Prevention, Prohibition and
Redressal) Act, 2013: This Act defines sexual harassment in the workplace,
provides for an enquiry procedure in case of complaints and mandates the
setting up of an Internal Complaints Committee or a Local Complaints
Committee
(f) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for
certain welfare measures to be provided by the Contractor to contract labour
and in case the Contractor fails to provide, the same are required to be
provided, by the Principal Employer by law. The Principal Employer is
required to take Certificate of Registration and the Contractor is required to
take license from the designated Officer. The Act is applicable to the
establishments or Contractor of Principal Employer if they employ 20 or more
contract labour.
(g) Minimum Wages Act 1948: The Employer is supposed to pay not less than the
Minimum Wages fixed by appropriate Government as per provisions of the
Act if the employment is a scheduled employment. Construction of Buildings,
32
This list is only illustrative and not exhaustive. Bidders and Contractors are responsible for checking the correctness and
completeness of the list. The law as current on the date of bid opening will apply.
Page | 216
Section X – Contract Forms
Roads, Runways are scheduled employments.
(h) Payment of Wages Act 1936: It lays down the mode, manner and by what
date the wages are to be paid, what deductions can be made from the wages
of the workers.
(i) Equal Remuneration Act 1976: The Act provides for payment of equal wages
for work of equal nature to male and female workers and for not making
discrimination against Female employees in the matters of transfers, training
and promotions etc.
(j) Payment of Bonus Act 1965: The Act is applicable to all establishments
employing 20 or more employees. Some of the State Governments have
reduced this requirement from 20 to 10. The Act provides for payments of
annual bonus subject to a minimum of 8.33% of the wages drawn in the
relevant year. It applies to skilled or unskilled manual, supervisory,
managerial, administrative, technical or clerical work for hire or reward to
employees who draw a salary of Rs. 10,000/- per month or less. To be eligible
for bonus, the employee should have worked in the establishment for not less
than 30 working days in the relevant year. The Act does not apply to certain
establishments.
(k) Industrial Disputes Act 1947: the Act lays down the machinery and procedure
for resolution of Industrial disputes, in what situations, a strike or lock-out
becomes illegal and what are the requirements for laying off or retrenching
the employees or closing down the establishment.
(l) Trade Unions Act 1926: The Act lays down the procedure for registration of
trade unions of workmen and employers. The Trade Unions registered under
the Act have been given certain immunities from civil and criminal liabilities.
(m) Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits
employment of children below 14 years of age in certain occupations and
processes and provides for regulation of employment of children in all other
occupations and processes. Employment of Child Labour is prohibited in the
Building and Construction Industry.
(n) Inter-State Migrant workmen’s (Regulation of Employment & Conditions of
Service) Act 1979: The Act is applicable to an establishment which employs 5
or more inter-state migrant workmen through an intermediary (who has
recruited workmen in one state for employment in the establishment situated
in another state). The Inter-State migrant workmen, in an establishment to
which this Act becomes applicable, are required to be provided certain
facilities such as housing, medical aid, traveling expenses from home upto the
establishment and back,etc.
(o) The Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Act 1996 and the Building and Other Construction
Workers Welfare Cess Act, 1996 (BOCWW Cess Act): All the establishments
who carry on any building or other construction work and employ 10 or more
workers are covered under these Acts. All such establishments are required
to pay cess at the rate not exceeding 2% of the cost of construction as may be
notified by the Government. The Employer of the establishment is required
to provide safety measures at the building or construction work and other
welfare measures, such as Canteens, First –Aid facilities, Ambulance, Housing
accommodations for workers near the work place etc. The Employer to
whom the Act applies has to obtain a registration certificate from the
Page | 217
Registering Officer appointed by the Government.
(p) Factories Act 1948: the Act lays down the procedure for approval of plans
before setting up a factory engaged in manufacturing processes, health and
safety provisions, welfare provisions, working hours, annual earned leave and
rendering information regarding accidents or dangerous occurrences to
designated authorities. It is applicable to premises employing 10 persons or
more with aid of power or 20 or more persons without the aid of power.
(q) Weekly Holidays Act -1942
(r) Bonded Labour System (Abolition) Act, 1976: The Act provides for the
abolition of bonded labour system with a view to preventing the economic
and physical exploitation of weaker sections of society. Bonded labour covers
all forms of forced labour, including that arising out of a loan, debt or
advance.
(s) Employer’s Liability Act, 1938: This Act protects workmen who bring suits for
damages against employers in case of injuries endured in the course of
employment. Such injuries could be on account of negligence on the part of
the employer or persons employed by them in maintenance of all machinery,
equipment etc. in healthy and sound condition.
(t) Employees State Insurance Act 1948: The Act provides for certain benefits to
insured employees and their families in case of sickness, maternity and
disablement arising out of an employment injury. The Act applies to all
employees in factories (as defined) or establishments which may be so
notified by the appropriate Government. The Act provides for the setting up
of an Employees’ State Insurance Fund, which is to be administered by the
Employees State Insurance Corporation. Contributions to the Fund are paid
by the employer and the employee at rates as prescribed by the Central
Government. The Act also provides for benefits to dependents of insured
persons in case of death as a result of an employment injury.
(u) The Personal Injuries (Compensation Insurance) Act, 1963: This Act provides
for the employer’s liability and responsibility to pay compensation to
employees where workmen sustain personal injuries in the course of
employment.
(v) Industrial Employment (Standing Order) Act 1946: It is applicable to all
establishments employing 100 or more workmen (employment size reduced
by some of the States and Central Government to 50). The Act provides for
laying down rules governing the conditions of employment by the Employer
on matters provided in the Act and get the same certified by the designated
Authority.
Page | 218
Section X – Contract Forms
SALIENT FEATURES OF SOME OF THE MAJOR LAWS THAT ARE APPLICABLE FOR
PROTECTION OF ENVIRONMENT.
1. The Environment (Protection) Act, 1986 and as amended: This provides for the
protection and improvement of environment and for matters connected therewith,
and the prevention of hazards to human beings, other living creatures, plants and
property. ‘Environment’ includes water, air and land and the inter-relationship
which exists among and between water, air and land, and human beings, other
living creatures, plants, micro-organism and property.
2. The Forest Conservation Act, 1980, as amended, and Forest (Conservation) Rules,
1981 as amended: These provides for protection of forests by restricting conversion
of forested areas into non- forested areas and prevention of deforestation, and
stipulates the procedures for cutting any trees that might be required by the
applicable rules. Permissions under the Act also stipulates the norms and
compliance requirements of the employer and any contractor on behalf of the
employer.
3. State Tree Preservation Acts as may be in force: These provide for protection of
trees of important species. Contractors will be required to obtain prior permission
for full or partial cutting, uprooting, or pruning of any such trees.
4. The Wildlife (Protection) Act, 1972, and as amended: This provides for protection of
wildlife through notifying National Parks and Sanctuaries and buffer areas around
these zones; and to protect individuals of nationally important species listed in the
Annex of the Act.
5. The Biological Diversity Act, 2002: This provides for conservation of biological
diversity, sustainable use of components of biological diversity, and fair and
equitable sharing of the benefits arising out of the use of biological resources,
knowledge and for matters connected therewith or incidental thereto.
6. The Public Liability Insurance Act, 1991 as amended and The Public Liability
Insurance Rules, 1991 as amended: These provide for public liability insurance for
the purpose of providing immediate relief to the persons affected by accident
occurring while handling hazardous substances and for mattes connected herewith
or incidental thereto. Hazardous substance means any substance or preparation
which is defined as hazardous substance under the Environment (Protection) Act
1986, and exceeding such quantity as may be specified by notification by the
Central Government.
7. The Ancient Monuments and Archaeological Sites and Remains Act, 1958 and the
Ancient Monuments and Archaeological Sites and Remains (Amendment and
Validation) Act, 2010, the Ancient Monuments and Archaeological Sites and
Remains Rules, 1959 amended 2011, the National Monuments Authority Rules, 2011
and the similar State Acts: These provide for conservation of cultural and historical
remains found in India. Accordingly, area within the radii of 100m and 300m from
the “protected property” are designated as “protected area” and “controlled
area” respectively. No development activity (including building, mining, excavating,
blasting) is permitted in the “protected area” and development activities likely to
damage the protected property is not permitted in the “controlled area” without
Page | 219
prior permission of the Archaeological Survey of India (ASI) or the State
Departments of Art and Culture or Archaeology as applicable.
8. The Environmental Impact Assessment Notification, 2006 and as amended: This
provides for prior environmental clearance for new, modernization and expansion
projects listed in Schedule 1 of the Notification. Contractors will be required to
ensure that no work starts until applicable clearances under the Notification is not
available. Contractors will be responsible for implementation of any environmental
management plan stipulated as per the permission under this Notification; and will
be required to prepare and submit to the employer and compliance report
stipulated in the permission under the Notification.
9. The Water (Prevention and Control of Pollution) Act, 1974 as amended, and the
Water (Prevention and Control of Pollution) Rules, 1975 as amended: These provide
for the prevention and control of water pollution and the maintaining and restoring
of wholesomeness of water. ‘Pollution’ means such contamination of water or
such alteration of the physical, chemical or biological properties of water or such
discharge of any sewage or trade effluent or of any other liquid, gaseous or solid
substance into water(whether directly or indirectly) as may, or is likely to, create a
nuisance or render such water harmful or injurious to public health or safety, or to
domestic, commercial, industrial, agricultural or other legitimate uses, or to the life
and health of animals or plants or of aquatic organisms. Contractors will need to
obtain consent for establishment and consent for operation of any item of work or
installation of equipment that generates waste water, and observe the required
standards of establishment and operation of these items of work or installations; as
well as install and operate all required waste water treatment facilities.
10. The Water (Prevention and Control of Pollution) Cess Act, 1977 and The Water
(Prevention and Control of Pollution) Cess Rules, 1978: These provide for the levy
and collection of a cess on water consumed by persons carrying on certain
industries and by local authorities, with a view to augment the resources of the
Central Board and the State Boards for the prevention and control of water
pollution under the Water (Prevention and Control of Pollution) Act, 1974.
11. The Air (Prevention and Control of Pollution) Act, 1981 as amended, and the Air
(Prevention and Control of Pollution) Rules, 1982: These provides for prevention,
control and abatement of air pollution. ‘Air Pollution’ means the presence in the
atmosphere of any ‘air pollutant’, which means any solid, liquid or gaseous
substance (including noise) present in the atmosphere in such concentration as
may be or tend to be injurious to human beings or other living creatures or plants
or property or environment. Contractors will need to obtain consent for
establishment and consent for operation of any item of work or installation of
equipment that generates air pollution such as batching plants, hot mix plants,
power generators, backup power generation, material handling processes, and
observe the required standards of establishment and operation of these items of
work or installations.
12. Noise Pollution (Control and Regulation) Rules, 2000, and as amended: This
provides for standards for noise for day and night for various land uses and
specifies special standards in and around sensitive receptors of noise such as
Page | 220
Section X – Contract Forms
schools and hospitals. Contractors will need to ensure compliance to the applicable
standards, and install and operate all required noise control devices as may be
required for all plants and work processes.
13. Chemical Accidents (Emergency Planning, Preparedness and Response) Rules,
1996: This provides for Requirement of preparation of on-site and off-site Disaster
Management Plans for accident-prone areas.
14. The Explosives Act 1884 and the Explosives Rules, 2008: These provide for safe
manufacture, possession, sale, use, transportation and import of explosive
materials such as diesel, Oil and lubricants etc.; and also for regulating the use of
any explosives used in blasting and/or demolition. All applicable provisions will need
compliance by the contractors.
15. The Petroleum Rules, 2002: This provides for safe use and storage of petroleum
products, and will need to be complied by the contractors.
16. The Gas Cylinder Rules 2004 and amendments: This provides for regulations related
to storage of gas, and possession of gas cylinder more than the exempted quantity.
Contractors should comply with all the requirements of this Rule.
17. Manufacture, Storage and Import of Hazardous Chemical Rules of 1989 and as
amended: These provide for use and storage of hazardous material such as highly
inflammable liquids like HSD/LPG. Contractors will need to ensure compliance to
the Rules; and in the event where the storage quantity exceeds the regulated
threshold limit, the contractors will be responsible for regular safety audits and
other reporting requirements as prescribed in the Rules.
18. Hazardous & Other Wastes (Management and Transboundary Movement) Rules,
2016: These provide for protection of general public from improper handling
storage and disposal of hazardous waste. The rules prescribe the management
requirement of hazardous wastes from its generation to final disposal. Contractors
will need to obtain permission from the State Pollution Control Boards and other
designated authorities for storage and handling of any hazardous material; and will
to ensure full compliance to these rules and any conditions imposed in the permit.
19. The Bio Medical Waste Management Rules, 2016: This provides for control, storage,
transportation and disposal of bio-medical wastes. As and where the contractor has
any first aid facility and dispensaries, established in either temporary or permanent
manner, compliance to these Rules are mandatory.
20. Construction and Demolition Waste Management Rules, 2016: This provides for
management of construction and demolition waste (such as building materials
possible to be reused, rubble and debris or the like); and applies to all those waste
resulting from construction, re-modelling, repair or demolition of any civil structure.
Contractor will need to prepare a waste disposal plan and obtain required approval
from local authorities, if waste generation is more than 20 tons in any day or 300
tons in any month during the contract period; and ensure full compliance to these
rules and any conditions imposed in the regulatory approval.
Page | 221
21. The E-Waste (Management) Rules, 2016: This provides for management of E-
wastes (but not covering lead acid batteries and radio-active wastes) aiming to
enable the recovery and/or reuse of useful material from e-waste, thereby reducing
the hazardous wastes destined for disposal and to ensure the environmentally
sound management of all types of waste of electrical and electronic equipment.
This Rule applies to every manufacturer, producer, consumer, bulk consumer,
collection centers, dealers, e-retailer, refurbisher, dismantler and recycler involved
in manufacture, sale, transfer, purchase, collection, storage and processing of e-
waste or electrical and electronic equipment listed in Schedule I, including their
components, consumables, parts and spares which make the product operational.
22. Plastic waste Management Rules, 2016: This provides for control and management
of the plastic waste generated from any activity. Contractors will ensure
compliance to this Rule.
23. The Batteries (Management and Handling) Rules 2001: This provides for ensuring
safe disposal and recycling of discarded lead acid batteries likely to be used in any
equipment during construction and operation stage. Rules require proper control
and record keeping on the sale or import of lead acid batteries and recollection of
the used batteries by registered recyclers to ensure environmentally sound
recycling of used batteries. Contractors will ensure compliance to this Rule.
24. The Ozone Depleting Substances (Regulation and Control) Rules, 2000 and as
amended: This provides for regulation of production and consumption of ozone
depleting substances in the country, and specifically prohibits export to or import
from countries not specified in the Rules, and prohibits unless specifically
permitted, any use of ozone depleting substance.
25. The Coastal Regulation Zone Notifications, 1991 and as amended: This provides for
regulation of development activities within the 500m of high tide line in coastal
zone and 100m of stretches of rivers and estuaries influenced by tides. Contractors
will be required to ensure that no work starts until applicable clearances under the
Notification is not available. Contractors will be responsible for implementation of
any plan stipulated as per the permission under this Notification; and will be
required to prepare and submit to the employer and compliance report stipulated
in the permission under the Notification.
26. The Motor Vehicle Act 1988 as amended (and State Motor Vehicle Acts as may be in
force) and the Motor Vehicle Rules, 1989, and as amended (and State Motor Vehicle
Rules as may be in force): To minimize the road accidents, penalizing the guilty,
provision of compensation to victim and family and check vehicular air and noise
pollution. Contractors will be required to ensure full compliance to these rules.
27. Easement Act, 1882: This provides for the rights of landowners on groundwater.
Contractors will need to ensure that other landowners’ rights under the Act is not
affected by any groundwater abstraction by the contractors.
28. State Groundwater Acts and Rules as may be in force and the Guidelines for
Groundwater Abstraction for drinking and domestic purposes in Notified Areas and
Page | 222
Section X – Contract Forms
Industry/Infrastructure project proposals in Non-Notified areas, 2012: These provide
for regulating extraction of ground water for construction/industrial and drinking
and domestic purposes. Contractors will need to obtain permission from
Central/State Groundwater Boards prior to groundwater abstraction through
digging any bore well or through any other means; and will to ensure full
compliance to these rules and any conditions imposed in the permit.
29. The Mines Act, 1952 as amended; the Minor Mineral and concession Rules as
amended; and the State Mineral (Rights and Taxation) Acts as may be in force:
These provide for for safe and sound mining activity. The contractors will procure
aggregates and other building materials from quarries and borrow areas approved
under such Acts. In the event the contractors open any new quarry and/or borrow
areas, appropriate prior permission from the State Departments of Minerals and
Geology will need to be obtained. Contractors will also need to ensure full
compliance to these rules and any conditions imposed in the permit.
30. The Insecticides Act, 1968 and Insecticides Rules, 1971 and as amended: These
provide for regulates the manufacture, sale, transport, distribution, export, import
and use of pesticides to prevent risk to human beings or animals, and for matters
connected therewith. No one should import or manufacture; sell, stock or exhibit
foe sale; distribute, transport, use: (i) any misbranded insecticides, (ii) any
insecticide the sale, distribution or use of which is for the time being prohibited
under the Act; and (iii) any insecticide except in accordance with the condition on
which it was registered under the Act.
31. National Building Codes of India, 2005 and as amended: This provides guidelines for
regulating the building construction activities in India. The code mainly contains
administrative regulations, development control rules and general building
requirements; stipulations regarding materials, structural design and construction;
and building and plumbing services. Contractors will be required to comply with all
Bureau of Indian Standards Codes dealing with: (i) use and disposal of asbestos
containing materials in construction; (ii) paints containing lead; (iii) permanent and
temporary ventilations in workplace; (iv) safety, and hygiene at the workplace; (v)
prevention of fire; (vi) prevention of accidents from faulty electrical gadgets,
equipment and accessories; and all other such codes incidental to the Contract.
Page | 223
BOQ SCHEDULES
[The following Schedules are for example only. The schedules may be modified and
specified as appropriate for each work]
Schedule 7:
Page | 224
Section X – Contract Forms
Appendix - 333
Appointment of Adjudicator
Sub:____________________________________________________(Name of the
Contract)
To
We hereby confirm your appointment as Adjudicator for the above contract to carry
out the assignment specified in this Letter of Appointment.
The Adjudicator shall visit the worksite once in 3 (three)months till the completion of
the work indicated above or as specifically requested by Employer/ Contractor for the
period up to the end of defects liability period with prior intimation to the Employer
and the contractor. The duration of each visit shall ordinarily be for one day only.
These durations are approximate and (Name of the employer and Name of the
Contractor) may find it necessary to postpone or cancel the assignment and/or shorten
or extend the duration.
The appointment will become effective upon confirmation of letter by you. The
appointment of Adjudicator shall be liable for termination under a 30 (thirty) days
written notice from the date of issue of the notice, if both Employer and the Contractor
33
If ITB 51makes provision of an Adjudicator from list provided by an institution, kindly modify Appendix 3 to state that the fee and
reimbursable payable to the adjudicator shall be as per the rules of the Institution.
Page | 225
so desire. Also the appointment shall automatically stand terminated 14 days after the
defect notice / correction period as stated in Clauses 23 and 24 of the Conditions of
Contract is over.
The Adjudicator will be paid a fee of Rs.______ (Rupees ____________only) per each
day of visit at the worksite. The actual expenses for boarding and traveling in
connection with the assignment will be reimbursed to the Adjudicator. The Adjudicator
will submit a pre-receipted bill in triplicate to the employer indicating the date of the
visit, fees for the visit and a proof in support of the actual expenditure [only for items
valued above Rs. 500 each] incurred by him against boarding, lodging and traveling
expenses after performing the visit on each occasion. The Employer will make the
admissible payment (both the Employer’s and the Contractor’s share) to the
Adjudicator within 30 days of the receipt of the bill. The Contractor’s share on this
account (half the paid amount) will be recovered by the Employer from the
Contractor’s bills against the work.
In accepting this assignment, the Adjudicator should understand and agree that he is
responsible for any liabilities and costs arising out of risks associated with travel to and
from the place of emergency repatriation, loss or damage to personal/professional
effects and property. The Adjudicator is advised to effect personal insurance cover in
respect of such risks if he does not already have such cover in place. In this regard, the
Adjudicator shall maintain appropriate medical, travel, accident and third-party liability
insurance. The obligation under this paragraph will survive till termination of this
appointment.
The Adjudicator will carry out the assignment in accordance with the highest standard
of professional and ethical competence and integrity, having due regard to the nature
and purpose of the assignment, and will conduct himself in a manner consistent
herewith. After visiting the worksite, the Adjudicator will discuss the matter with the
Employer and if necessary with the Contractor before arriving at any decision.
The Adjudicator will agree that all knowledge and information not within the public
domain, which may be acquired while carrying out this service shall be all time and for
all purpose, regarded as strictly confidential and held in confidence, and shall not be
directly or indirectly disclosed to any party whatsoever, except with the permission of
the employer and the contractor. The Adjudicator’s decision should be communicated
in the form of a speaking order specifying the reasons.
The Adjudicator will agree that any manufacturing or construction firm with which
he might be associated with, will not be eligible to participate in bidding for any
Page | 226
Section X – Contract Forms
goods or works resulting from or associated with the project of which this
consulting assignment forms a part
Signature
Place:
Date:
Name of Employer
Attachment: Copy of contract document between the employer and contractor and
format for recommendation.
Page | 227
SUMMARY OF AJUDICATIOR’S RESPONSIBILITIES
Page | 228
Section X – Contract Forms
Sample Format of Adjudicator’s Recommendation
[Project Name]
Recommendation of Adjudicator
Hearing Date:____________
Dispute
Contractor’s Position
Employer’s Position
Recommendation
Explanation
(This section could also be called Considerations, Rationale, Findings, Discussion, and so
on.)
Page | 229
The Adjudicator’s description of how each recommendation was reached.
Respectfully submitted,
Page | 230
Section X – Contract Forms
Section X - Contract Forms
This Section contains forms which, once completed, will form part of the Contract.
The forms for Performance Security, ES performance security if applicable, and
Advance Payment Security, when required, shall only be completed by the successful
Bidder after contract award.
Page | 231
NOTIFICATION OF AWARD
Letter of Acceptance
[on letterhead paper of the Employer]
[The Letter of Acceptance shall be the basis for formation of the Contract as described
in ITB Clause 47. This Standard Form of Letter of Acceptance shall be filled in and sent
to the successful Bidder only after evaluation of bids has been completed, subject to
any review by the World Bank required under the Loan Agreement.]
. . . . . . . [date]. . . . . . .
This is to notify you that your Bid dated . . . .[insert date] . . . . for execution of the . . .
. . . . . . .[insert name of the contract and identification number, as given in the PCC]. . .
. . . . . . . for the Accepted Contract Amount of . . . . . . . . .[insertamount in numbers
and words], as corrected and modified34 in accordance with the Instructions to
Bidders is hereby accepted by our Agency.
You are requested to furnish the Performance Security, plus additional security for
unbalanced bids in terms of ITB Clause 41, and ES Performance Security[Delete ES
Performance Security if it is not required under the contract]in the form detailed in
ITB Clause 50 for amounts35 of Rs. …….., and Rs. ……. specified therein, within 21
days of the receipt of this letter of acceptance, and visit this office to sign the
contract, failing which action as stated in ITB Clause 50.2 will be taken in accordance
with the Conditions of Contract. The securities shall be valid upto 28 days from the
date of completion i.e.upto …………. and shall be as per the Performance Security
Form and the ES Performance Security Form[Delete reference to the ES Performance
Security Form if it is not required under the contract],included in Section X -Contract
Forms, of the bidding document.
[or]
36
To be used only if the Contractor disagrees in the Bid with the Adjudicator proposed by the Employer in the Instructions to Bidders,
and has accordingly offered another candidate.
Page | 232
Section X – Contract Forms
name of the Appointing Authority], the Appointing Authority, we are hereby
requesting such Authority to appoint the Adjudicator in accordance with ITB 51.1 and
GCC 23.137.
We note that as per your bid, you do not intend to subcontract any component of
work.
[OR]
We note that as per your bid, you propose to employ M/s. ………………… as sub-
contractor for executing ……………………..
We have reviewed the construction methodology submitted by you alongwith the bid
in response to ITB Clause 16 and our comments are given in the attachment. You are
requested to submit a revised Program including ES requirements as per Clause 26 of
General Conditions of Contract within 14 days of receipt of this letter of acceptance.
37
To be used only if the Contractor disagrees in the Bid with the Adjudicator proposed by the Employer in the ITB, has accordingly
offered another candidate, and the Employer does not accept the counterproposal.
Page | 233
Issue of Notice to proceed with the work
_________ (date)
To
______________________________
______________________________
Dear Sirs:
Yours faithfully,
Page | 234
Section X – Contract Forms
Contract Agreement
WHEREAS the Employer desires that the Works known as . . . . . [name of the
Contract]. . . . .should be executed by the Contractor, and has accepted a Bid by the
Contractor for the execution and completion of these Works and the remedying of
any defects therein,
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Contract documents referred to.
2. The following documents shall be deemed to form and be read and construed as
part of this Agreement. This Agreement shall prevail over all other Contract
documents.
(iii) the Contractor’s Bid including completed schedules and priced bill of quantities,
(xi) any other document listed in the PCC as forming part of the Contract.
Page | 235
4. The Employer hereby covenants to pay the Contractor in consideration of the
execution and completion of the Works and the remedying of defects therein, the
Contract Price or such other sum as may become payable under the provisions of the
Contract at the times and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed
in accordance with the laws of Indiaon the day, month and year specified above.
for and on behalf of the Employer for and on behalf the Contractor
in the in the
presence of: presence
of:
Page | 236
Section X – Contract Forms
Performance Security- Bank Guarantee
[including Additional Performance Security for unbalanced bids]
AND WHEREAS it has been stipulated by you in the said Contract that the
Applicant shall furnish you with a Bank Guarantee by a recognized bank for the sum
specified therein as security for compliance with his obligations in accordance with
the Contract;
AND WHEREAS we have agreed to give the Applicant such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible
to you, on behalf of the Applicant, up to a total of ____________________ [amount
of guarantee39] ___________________________ [in words], such sum being payable
in the types and proportions of currencies in which the Contract Price is payable, and
we undertake to pay you, upon your first written demand and without cavil or
argument, any sum or sums within the limits of ____________________ [amount of
guarantee] as aforesaid without your needing to prove or to show grounds or
reasons for your demand for the sum specified therein.
This guarantee shall be valid until ……… 40, and any demand for payment under
it must be received by us at this office on or before that date.
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
40Insert
the date twenty-eight days after the expected completion dateas described in GC Clause 53.1. The Employer should note that in
the event of an extension of this date for completion of the Contract, the Employer would need to request an extension of this
guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration date established in the
guarantee. In preparing this guarantee, the Employer might consider adding the following text to the form, at the end of the
penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a period not to exceed [six
months][one year], in response to the Employer’s written request for such extension, such request to be presented to the
Guarantor before the expiry of the guarantee
Page | 238
Section X – Contract Forms
Environmental and Social Performance Security
ES – Bank Guarantee
AND WHEREAS it has been stipulated by you in the said Contract that the
Applicant shall furnish you with a Bank Guarantee by a recognized bank for the sum
specified therein as security for compliance with his Environmental and Social (ES)
obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Applicant such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible
to you, on behalf of the Applicant, up to a total of ____________________ [amount
of guarantee42] ___________________________ [in words], such sum being payable
in the types and proportions of currencies in which the Contract Price is payable, and
we undertake to pay you, upon your first written demand and without cavil or
argument, any sum or sums within the limits of ____________________ [amount of
guarantee] as aforesaid without your needing to prove or to show grounds or
reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the
Applicant before presenting us with the demand.
41In
the case of a JV, insert the name of the Joint Venture
42
An amount shall be inserted by the Guarantor, representing the percentage of the Contract Price specified in the Contract less
provisional sums, if any, and denominated in Indian Rupees.
Page | 239
We further agree that no change or addition to or other modification of the
terms of the Contract or of the Works to be performed thereunder or of any of the
Contract documents which may be made between you and the Applicant shall in any
way release us from any liability under this guarantee, and we hereby waive notice of
any such change, addition or modification.
This guarantee shall be valid until ……… 43, and any demand for payment under
it must be received by us at this office on or before that date.
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
43 Insert
the date twenty-eight days after the expected completion dateas described in GC Clause 53.1. The Employer should note that in
the event of an extension of this date for completion of the Contract, the Employer would need to request an extension of this
guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration date established in the
guarantee. In preparing this guarantee, the Employer might consider adding the following text to the form, at the end of the
penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a period not to exceed [six
months][one year], in response to the Employer’s written request for such extension, such request to be presented to the
Guarantor before the expiry of the guarantee
Page | 240
Section X – Contract Forms
Advance Payment Security
Demand Guarantee
Gentlemen:
44
In the case of a JV, insert the name of the Joint Venture
45
An amount shall be inserted by the bank representing the amount of the Advance Payment, and denominated
in Indian Rupees.
Page | 241
We further agree that no change or addition to or other modification of the
terms of the Contract or of Works to be performed thereunder or of any of the
Contract documents which may be made between _____________________ [name
of Employer] and the Applicant, shall in any way release us from any liability under
this guarantee, and we hereby waive notice of any such change, addition or
modification.
This guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract until _________________________ [name of Employer]
receives full repayment of the same amount from the Applicant. Consequently any
demand for payment under this guarantee must be received by us at this office on or
before that date.
Yours truly,
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
Page | 242
Section X – Contract Forms
Retention Money Security
Demand Guarantee
Date: ____________________________
46
In the case of a JV, insert the name of the Joint Venture
47 The Guarantor shall insert an amount representing the amount of the second half of the Retention Moneyor if the amount guaranteed
under the Performance Guarantee when the Taking-Over Certificate is issued is less than half of the Retention Money, the
difference between half of the Retention Money and the amount guaranteed under the Performance Security.
Page | 243
It is a condition for any claim and payment under this guarantee to be made that the
payment of the second half of the Retention Money referred to above must have
been received by the Applicant on its account number _________ at ___________
[name and address of Bank].
This guarantee shall expire, at the latest, 21 days after the date when the Employer
has received a copy of the Defects Liability Certificate issued by the Project Manager.
Consequently, any demand for payment under this guarantee must be received by us
at this office on or before that date.
_____________________
[Signature(s) and seal of the guarantor]
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
Page | 244