WEEKLY PROGRESS REPORT

PREPARED BY
MASTERS DEVELOPMENT MANAGEMENT (INDIA) PVT. LTD.

REPORT PERIOD : 09 AUGUST 2020 TO 15 AUGUST 2020


Reported On : 15 August 2020
MASTERS

PROJECT : SUNSHINE ONE


DEVELOPER : SPL ESTATES PRIVATE LIMITED
A. CONSTRUCTION PROGRESS UPDATE

As per Schedule Cumulative


Progress up to Progress of the Balance
Sl No Activity UOM Scope Qty. Actual Start Actual Finish Progress Till Status Remarks
Previous Week week Scope
Start Date Finish Date this Week

A PILE FOUNDATION

SUNSHINE ONE Nos 1205 06-01-2020 13-12-2020 204 14 218 987

1 3D Tower Nos 284 15-09-2020 13-12-2020 284

2 3E Tower Nos 284 01-08-2020 28-11-2020 284

3 2A Tower Nos 212 15-09-2020 13-12-2020 06-01-2020 23 23 189

4 2B Tower Nos 212 06-01-2020 10-08-2020 20-01-2020 181 4 185 27 In Progress

5 1A Tower Nos 213 01-08-2020 28-11-2020 10-08-2020 10 10 203 In Progress

SPL Estates Private Limited 2 of 3 Masters Development Management (India) Pvt. Ltd.
MASTERS

PROJECT : SUNSHINE ONE


DEVELOPER : SPL ESTATES PRIVATE LIMITED
B. WEEKLY LABOUR REPORT

SL. Sunshine One


Date Day Wise Total
No. Tower - 2A Tower - 2B Tower - 3D Tower - 3E Tower - 1A

A Piling Work - Average 20 28 48

09 August 2020

10 August 2020 15 30 45

11 August 2020 21 27 48

12 August 2020 21 27 48

13 August 2020 22 28 50

14 August 2020 22 28 50

15 August 2020