SUNSHINE ONE

WEEKLY PROGRESS REPORT

PREPARED BY
MASTERS DEVELOPMENT MANAGEMENT (INDIA) PVT. LTD.

REPORT PERIOD : 16 AUGUST 2020 TO 22 AUGUST 2020


Reported On : 22 August 2020
MASTERS

PROJECT : SUNSHINE ONE


DEVELOPER : SPL ESTATES PRIVATE LIMITED
A. CONSTRUCTION PROGRESS UPDATE

As per Schedule Cumulative


Progress up to Progress of the Balance
Sl No Activity UOM Scope Qty. Actual Start Actual Finish Progress Till Status Remarks
Previous Week week Scope
Start Date Finish Date this Week

A PILE FOUNDATION

SUNSHINE ONE Nos 1205 06-01-2020 13-12-2020 208 16 234 971

1 3D Tower Nos 284 15-09-2020 13-12-2020 284

2 3E Tower Nos 284 01-08-2020 28-11-2020 284

3 2A Tower Nos 212 15-09-2020 13-12-2020 06-01-2020 23 23 189

4 2B Tower Nos 212 06-01-2020 10-08-2020 20-01-2020 185 4 189 23 In Progress

5 1A Tower Nos 213 01-08-2020 28-11-2020 10-08-2020 10 12 22 191 In Progress

SPL Estates Private Limited 2 of 3 Masters Development Management (India) Pvt. Ltd.
MASTERS

PROJECT : SUNSHINE ONE


DEVELOPER : SPL ESTATES PRIVATE LIMITED
B. WEEKLY LABOUR REPORT

SL. Sunshine One


Date Day Wise Total
No. Tower - 2A Tower - 2B Tower - 3D Tower - 3E Tower - 1A

A Piling Work - Average 23 30 53

16 August 2020

17 August 2020 16 23 39

18 August 2020 23 30 53

19 August 2020 26 34 60

20 August 2020

21 August 2020

22 August 2020 26 34 60

SPL Estates Private Limited 3 of 3 Masters Development Management (India) Pvt. Ltd.