SCOPE OF WORK

1. Setting of Tiles Ground and 2nd Floor


2. Fabrication and Installation of Ceiling with Design
3. Fabrication of Wooden Cabinet Kitchen
4. Fabrication of Dry Wall Partition 3 Room
5. Fabrication of Kitchen Counter
6. Fabrication of Bar Counter
7. Fabrication of Wooden Cabinet Bar Counter
8. Re Installation of Door CR
9. Electrical
10.Plumbing
11. Paints
12. Installation of Door And Jamb 3 Room
13. Paints Stair Handrills

NOTHING FOLOWS

Labor and Materials


Cost PHP 310,000.00

MR. EDDIE A. BANIOLA MR./MRS JUDERICK FABABIER


Foreman / Contractor Home Owner
No. 0921701887

*Note – Materials is not Included

1. Sink 7. Nob
2. Door 8. Window
3. Light 9. Granite
4. Tiles 10. Faucet
5. Adhesive 11. Grout
6. Fullout Basket