Professional Documents
Culture Documents
STC-GS-3
ACCA AC Coach Attendant ACCI AC Coach Mechanic
Ah Ampere hour Alt Alternator
Amp Ampere CD1 Condenser Motor1
CD2 Condenser Motor2 CP1 Compressor motor1
CP2 Compressor motor2 DP Double pole
Emergency Feeding Earth Leakage
EFT ELD
Terminal Detector
Keep doors closed during run & open at station when train
is stopped.
Phase II- Module no. STC-GS-3 CAMTECH, Gwalior
DUTIES OF AC COACH MECHANIC
Check all the grills inside the coach. These should be in open
condition.
5. O.H.P. – 1 & 2
For over heat protection of heater 1 and 2.
Vane relay for check air loss in the air supply to both
side blower.
8. Transformer
415V/ 110V, step down transformer for control circuit.
1. Visually inspect, both upper and under frame and ensure all
fittings are intact at their places.
IV. Feel the temperature suction side cold, delivery side hot
and liquid line should be warm.
Phase II- Module no. STC-GS-3 CAMTECH, Gwalior
OPERATING PROCEDURE FOR AC COACHES
After closing of CP1 & CP2 contacts check the load current
in the inverter output side ammeters (21-23 Amps).
Connect Female socket end to the coach and male socket end
to the pre-cooling socket.
o The earth fault shall be checked with the help of test lamp. If
earth fault is there then feed extension should not be done.
o Remove (+ve) fuse from battery box and (-ve) fuse from
main junction box to disconnect the power supply of battery.
o L-II & fan circuits of the dark coach shall be switched off
before connecting supply from healthy coach.
TC TC
Railways:
A. Coach Particulars
12. Communicate line failures & Non-AC etc to base depot immediately
DE spanner set 8 pcs of sizes 6/7. 8/9, 10/11, 12/13, 14/15, 16/17,
10. 1 set
18/19, 20/22
17. Hammer ½ kg 1
Date ------ Originating/Destination station ----- Train No. ----- From ----- To ----
Note : Depot mechanic shall ensure the implementation of all the SMIs and modifications issued by
RDSO during primary maintenance. No coach should be given in service until all SMIs &
modification sheets are complied for the coach.
DERAILMENT/ COLLISION
(INCLUDING LEVEL
CROSSING ACCIDENTS)
FIRE IN TRAIN
CYCLONE/ STORM/
FLOOD
REPORTED BOMB IN
TRAIN
EXPLOSION OF BOMB IN
A TRAIN
OPERATION OF FIRE
EXTINGUISHERS
Hold the nozzle and aim towards near to the base of the fire.
Hit the operating knob and ensure that the powder is sprayed
properly.
After extinguishing fire, isolate the fired equipment from the circuit.
ELECTRIC SHOCK
Let his head be slightly lower than the rest of the body,
and raise his legs.
10. All the major depots should carry out failure analysis of
major equipments & the information should be sent to
RDSO periodically.
C : Alternator Pulley
D : Alternator Shaft
E : Terminal Board
Axle pulley & Axle pulley pad
V-Belt
Battery box
Under Frame
Fans
Light Fitting
EFT/BCT
Wiring
Others
Existence of eight bolts with flat washers, full tightness
of bolts.
Back
Full complement of RR Box fixing bolts and its
tightness.
All stud assembly (stud, nut, lock nut, split pin, plain
washer )should be replaced during IOH &POH.
Axle pulley Stud size 20Øx2.5x175mm.
Back
• Suspension hanger pin, split cotter for 4.5 KW
alternator: As per RDSO drg. No.3939 Alt.2.
• Material specification of
Back
• The suspension hanger pin shall be hard Chromium
plated as per IS:1337(Rev-2)
• IS-1875 Cl 4.
Carbon - 0.40-0.50.
Silicon - 0.15-0.35.
Manganese - 0.60-0.90.
Sulphur - 0.04 max.
Phosphorus - 0.04 max. Back
Mechanical:
Elongation-min - 15%
RDSO/PE/AC/0006-99(Rev-o).
From To
48 3150 3152
49 3152 3154
50 3154 3156
51 3156 3158
RDSO/PE/SK/AC/0047-2004 (Rev-2).
Back
Shaft material –EN-24 as per BS 970.
Carbon - 0.35-0.45.
Silicon - 0.15-0.35.
Manganese - 0.45-0.70.
Sulpher - 0.05 max.
Phosphorus - 0.05 max.
Chromium - 0.90 to1.40.
Nickel - 1.30 to1.80.
Back
Molybdenum - 0.20 to0.35.
Alternator Shaft shall be tested by ultrasonic
100%.
Back
Fits &limits on bearings of alternators, ac/dc motors fitted
on coaches:
As per IS:2709-1964. 1 Micron=0.001mm.
Nominal Shaft Inner race Housing dia Outer race
shaft tolerance bore tolerance bore
Dia in mm K5 micron tolerance hB micron J6 Micron tolerance
hB micron
10 to18 +9 -8 - -
+1 0 - -
18 to 30 +11 -10 -5 0
+2 0 +8 -9
30 to 50 +13 -12 -6 0
+2 0 +10 -11
50 to 80 +15 -15 -6 0
+2 0 +13 -13
Keep Danger board on the rake and lock the scotch block.
Cut off supply and earth the point on which you want to
work. If you have to work with power 'ON' keep your self
insulated and see that you are on firm support.
Do not handle electric switches of appliances with wet
hands. Be more careful in handling electric gear inside
bathrooms and during monsoon weather.
Do not lean against electrical poles or stay wire.
Do not play with electricity.
Use 5- pin plugs and check up earth connections carefully.
Each plug socket to be protected and controlled by a
proper fuse/MCB and a switch on the live side.
25 KW alternator
V-belts
Phase wires Field wires
If the coach was in ideal condition for a long time, to gain the
residual magnetism, check the field winding of alternator with
110V DC in series with test lamp of 25W/ 40W.
3. At RRU/ ERRU
Check the condition of HRC field fuses (6 Amps) & main fuse
(160 Amps) in the RRU/ ERRU. Replace them, if blown out.
Check the continuity of field & phase windings for open circuit
with multimeter.
4A Glass Fuse
Check the condition of Earth
Leakage Detector (ELD).
I/P MCB-8
for T/F
O/P MCB -
RSW1 9 for T/F
Control T/F
MCB-1
a. If it is in tripped condition,
check the over load setting (2.1
to 3.1A) and reset it.
C3 Contactor
C2 Contactor
MCB-3
AC Control Panel MCB-2
C5Contactor
C4 Contactor
MCB-5
MCB-4
AC Control Panel
vi. Check the incoming terminals of contactor (C4)
(331, 332, 333) of CP-1, contactor (C5) (334,
335, 336) of CP-2 and out going terminals of
contactor (C4) (310,311,312) of CP-1, contactor
(C5) (313, 314, 315) of CP2 respectively. If
found defective, bypass the contactors.
(b) HP1 or HP2 red LED glowing
iv. Check and ensure that all the grills are in open
condition.
At Battery
1. AC WRA/ Monoblock Motor
RSW for WRA
Selection
WRA Overload
contactor cum MCB
ON button
Power Panel
6. Belts smoke
Cause Action to be Taken
• Alternator pulley jam • Cut the belts and connect
TC from Adjacent coach.
जो कार्य तम
ु आज
कर सकते हो,
उसे कल पर कदापप
मत छोड़ो।
Phase II – Module No. STC-GS-3
Fires in coaches could be broadly classified under
two heads viz:
Overvoltage
Failure of the insulation due to deterioration/
mechanical damage
Local heating due to loose / defective joints and loose
connections
Overheat of fuel pipe line near turbo changer
Loose connection
Smoke from mobile charging point
Ciggerate/bidi butts and gutakha wrapper in
fuse distribution board/ roof openings
35 A –ve
Emergency feed to adjacent
6 A +ve Fuse
Fuse coaches.
Rotary Junction Panel
Each circuit is protected by a 16 Amps fuse, which is
second level protection.
CFL
FANS
EFT
6 A FUSE
MAIN
POSITIVE
WIRES
L1 L2 F SPM NEG
FDB
COACH FLOOR
Sabotage / Discrepancy.
Strengthening
not provided
for cover
PVC grommets and bushes to be provided at
cable entry point.
Provide proper connectors for feeding supply
to fans, berth lights, step lights, FT fittings.
Never allow
coaches with
earth leakage.