MUNICIPAL CORPORATION,AMRITSAR

AMRUT PHASE-I & II


NAME OF ESTT. AMT. ALOTT.AMT DATE OF
SR.No NAME OF WORK RATES SCOPE OF WORK WORK COMPLETED
CONTRACTOR (Rs. in lacs.) (Rs. in lacs.) COMPLETION
Water Supply Package-
1 M/s R.S Builders 4551.81 6.97% Above 4869.07 250 Km 220 Km 30.9.2021
1 (Phase I)

Drilling of Tubewells M/s H.R


2 339.25 4.00% Below 325.68 17 Tubewells Work Completed 26.9.2020
Package-2 (Phase I) Enterprises

8 OHSR's
OHSR Package-3 M/s Rajan
3 654.59 1.19% Below 646.80 11 OHSR's Completed 2 31.12.2021
(Phase I) Builders
OHSR's In Progress

Water Supply &


4 Sewerage Package-2A M/s R.S Builders 1208.13 4.99% Above 1268.42 73 Km 20 Km 15.10.2021
(Phase II)

GRAND TOTAL 6753.78 7109.97