Professional Documents
Culture Documents
Dear reader,
This document is a summary of the Project Management book of Nicholas and Steyn. It can be
considered as an extended table of contents or reading guide. The information written down is NOT
complete and can mostly NOT be used directly on the exam. Further elaboration on topics can be
found in the book on the pages as mentioned throughout the summary. It helped me to get through
the contents of the book; what is discussed and where. Enjoy the reading and good luck with
preparing for the exam!
System approach:
(a) Orderly Way of Appraisal: Analyse the situation from all the angles.
1. The objectives and the performance criteria of the whole system
2. The environment and constraints of the system
3. The resources of the system
4. The elements of the system, their functions, attributes, and performance measures
5. The interaction among the elements
6. The management of the system.
(b) Systems models – Sensitivity Analysis
1. Physical model
2. Conceptual model
There are several stakeholders within the SDC: Further elaboration on page 72.
1. System customers (buyers, clients, owners) including customer management and users and
operators
2. System contractors (systems development organization, developer, promoter, consultant)
including contractor top management, project management, the doers
Types of contracts:
1. Fixed Price Contracts
a. Fixed Price Contract
b. Fixed Price with Redetermination
2. Cost-Plus Contracts
a. Cost Plus Fixed Fee
b. Guaranteed Maximum Price
c. Time and Materials Contract
3. Incentive Contracts
a. Cost Plus Incentive Fee
b. Fixed Price Incentive Fee
c. Other
5.6. Scheduling
A project schedule shows the timing for work tasks and when specific events and project milestones
should occur (page 170). There are several types of schedules like: project schedule (general), activity
schedule (specific, Gantt chart).
Crashed activity: when the maximum effort is applied so that the activity can be completed in the
shortest possible time. It becomes also the most costly activity.
7.3. PERT
PERT is a method to apply in project with uncertain activities duration. Further elaboration on page
241. It consists of the following parts:
1. Three Time Estimates: optimistic, pessimistic and most likely duration. They are used to
calculate the expected duration of an activity, and the variance. The riskier the activity the
higher the variance. See assignment 1.
2. Probability of Finishing by a Target Completion Date: expected duration will be exceeded
50% of the time. Can be approached by a normal distribution. Therefore, chance that a
project will be finished within a certain amount of time.
3. Near Critical Paths
4. Meeting the Target Date: three ways to speed up the process to meet the target date,
however each solution has its drawbacks:
a. Fast-track activities on the critical path
b. Add resources to critical and near-critical activities
c. Substitute time-consuming activities or delete them
5. Monte Carlo Simulation of a PERT Network
6. Why Projects are Often Late