You are on page 1of 58

WEL-COME

To all FOR Trainingg


ON
“Condition
Condition Monitoring”
Monitoring
Of
Circuit Breaker
By Vivekanand Sindkar - CEO

© SCOPE T&M Pvt Ltd


Contains of the Program
g
™ Snap Shot of Circuit Breaker
™ Different area of concern in a breaker
™ Different kind of condition monitoring on breaker
™Off Line condition monitoring
™ Snaps of different equipments used for condition
monitoringg
™ Advance conditioning Monitoring Tool: “DCRM Test”
™ ON Line condition monitoringg : “RTMon”
™ Maintenance Manager for Capturing, storing & giving
trend analysis of CB & its condition.

© SCOPE T&M Pvt Ltd


Importance of Circuit Breaker

¾To switch Transmission Lines,


Transformers, Shunt Reactors,
Capacitor Banks etc.

¾ To close/ reclose an open circuit

¾ And
A d off course the most important
to clear a fault to protect equipment,
human life!

© SCOPE T&M Pvt Ltd


Type of Circuit Breaker

Circuit
Breaker

Arc
Voltage Operating
R ti
Rating
Quenching
M h i
Mechanism
Application
Medium

Out Door In Door

© SCOPE T&M Pvt Ltd


Why Testing is required?

¾ Testing
g is NOT DONE for finding g the
damaged /faulty components only, but also for
finding the TREND / DRIFTING of
CONDITION of different components of
Circuit Breaker with respect to time.

..Condition Monitoring of Circuit Breaker

© SCOPE T&M Pvt Ltd


Different Components of CB

Circuit Breaker

I t
Interrupter
t Di i M
Driving Mechanism
h i C t lU
Control Unit
it

© SCOPE T&M Pvt Ltd


Different Testing for different Components of CB

Circuit Breaker
Testing

Testing Testing Testing


Interrupter Driving Mechanism Control Unit

Contact Resistance, Total Travel,


DCRM test, Datum Velocity, Coil current,
Timing test, Wipe of Default velocity coil voltage
Contact Dew Point
Contact, Point, Total Healthiness of Auxiliary contact timing
fault current, arc time etc damping mechanism

© SCOPE T&M Pvt Ltd


T ti & Diagnosis
Testing Di i
Of
Circuit Breaker

OFF Line Test


(CB is not charged)
Operational Conditions

ON Line Test
Physical Condition
(CB is charged)

© SCOPE T&M Pvt Ltd


Circuit Breaker Testing

¾ ON Line Test ¾ OFF Line Test


™ Trip/Close Coil Current ™ Close, Trip, C-O time….
™ Signaling / Auxiliary ™ Resistance of Main & Arching
Contact Timings contact
™ Line Current & Fault ™ Insertion/Wipe
I i /Wi off theh contact
Current ™ Velocity, Travel characteristics
™ Cumulative Fault Current ™ Coil current, Voltage drop across
™ Station Battery Voltage coil
il
™ Velocity ™ Damping Mechanism healthiness
™ Arch duration measurement
& many more

© SCOPE T&M Pvt Ltd


OFF Line Testing

™ Time Test
¾ Close, Trip & C-O of Main Contact, PIR Contact
¾ Opening Time of PIR Contact
¾ Bounce/Chattering in Main, PIR Contact

9 Importance of Time Measurement

Time measurement is the MINIMUM measurement that must be


taken on all kind of circuit breaker.

© SCOPE T&M Pvt Ltd


Definition of Time

¾ Closing Time:
Closing Time = Time for energizing the coil
+ Timee for
o latch
c movement
ove e
+ Time for mechanical movement of
shaft till first contact touch.

© SCOPE T&M Pvt Ltd


Factors Effecting Timing of Circuit Breaker

¾ Energization
g of Coil
¾ Latch / Plunger Movement
¾ Mechanical Movement of shaft for movingg the main &
PIR contact

© SCOPE T&M Pvt Ltd


Coil Test

¾ Measurement of
™TRIP & CLOSE coil current
™ VOLTAGE DROP across the coil.
™ Time taken for energisation of coil.
coil
™ Maximum current flowing through the coil

© SCOPE T&M Pvt Ltd


Travel Mechanism Test
¾ Measurement of
™ Velocity: Datum Velocity , Default Velocity
™ T l Travel
Total T l
™ Wipe of the Contact
™ Over Travel

How to measure all these parameters?

By Measuring TIMING & TRAVEL

© SCOPE T&M Pvt Ltd


Circuit Breaker Timer

© SCOPE T&M Pvt Ltd


HISAC 2406

© SCOPE T&M Pvt Ltd


ULTIMA Analyser Rack with Modules

MAIN / PIR DCRM Space for


SSR Module MODULE Module optional
modules

CPU Module

MAINS Inlet

MAINS ON/OFF
Switch

USB Communication

MASTER EARTHING

Auxiliary Module
Travel &
Coil current
Module
© SCOPE T&M Pvt Ltd
© SCOPE T&M Pvt Ltd
How the OFF Line test is conducted?
¾ Take the shut down of the breaker
¾ Open the Isolator
¾ Connect the cable to circuit breaker contact( Across) Interrupter
for measuring time, connect the coil current cable to coil to
measure coilil current, connect transducer
d to mechanism
h i for f taping
i
travel & velocity. …Connect all this to HISAC
¾ Tap the existing + DC supply from the control panel through our
Breaker control cable. The output of the +DC will be extended to
CB “+Trip” & “+Close” . Now the kit is ready to operate the
circuit breaker.
¾ Take the operation through Laptop (with HISAC ULTIMA TEST
MANAGER)

© SCOPE T&M Pvt Ltd


Have we measured all the conditions?

¾ NO

We have only checked the “Operational


Operational
Condition of breaker”…..

What is the actual “PHYSICAL CONDITION


of breaker Contacts”?

© SCOPE T&M Pvt Ltd


……. Contact Resistance Test

What is Contact resistance Test of Circuit Breaker?
Contact Resistance measurement of circuit breaker is measured
across
c oss thee breaker
b e e contact
co c by injection
jec o of
o LARGE
G Amps.
ps. of
o
Direct Current (DC), typically 100 Amps.

© SCOPE T&M Pvt Ltd


Contact Resistance Meter

© SCOPE T&M Pvt Ltd


……Test Result of Contact Resistance Test
¾ Inject 100 Amps DC current across breaker contacts

¾ Measure
e su e thee “voltage
vo ge drop”
d op develops
deve ops across
c oss thee contacts
co c s ofo current
cu e
injection.

¾ Measure the voltage drop

¾ Convert
C t “ measuredd voltage
lt drop”
d ” into
i t resistance.
it

¾ Display the current injected & Resistance of MAIN CONTACT.


CONTACT

© SCOPE T&M Pvt Ltd


Components of Interrupter

1. Main Contact
2. Main Contact mounted by number of screws
3. Arching Contact TIP
4. PTFE Nozzle of arching contact
5
5. Puffer & nuts
6. Helicoil spring of coupling bolt
7. Number of bolts for mounting & connecting various
components.
8. Driving Mechanism / Operating Link

© SCOPE T&M Pvt Ltd


Limitation of Contact Resistance Test

A It does not speak about the


Ö Erosionof Arching contact
Ö Contact Misalignment
Ö Arcing Contact Resistance
Ö Damage of different components of moving mechanism

© SCOPE T&M Pvt Ltd


Think ???????


Can I see the healthiness of interrupter without OPENING the arching
chamber?

Think!!
!

© SCOPE T&M Pvt Ltd


Over coming
g Limitations……

9 Can I measure the resistance when breaker


contact undergoes CLOSE – OPEN operation?

If we can measure the resistance of main & arcing


contacts dynamically while the breaker contacts and
mechanisms are moving, the dynamic resistance
signature
g will reveal the condition or healthiness of
interrupters.

© SCOPE T&M Pvt Ltd


Dynamic Contact Resistance Measurement

The dynamic contact resistance SIGNATURE is a NON-


INVASIVE
AS diagnosis
i i measurement which i indicates
i i the erosion
i
of arcing and main contacts, looseness, damage, Misalignment
and helps to measure length of arching tip.

© SCOPE T&M Pvt Ltd


Why DCRM…
• DCRM signature with Travel curve gives fairly
good idea about healthiness of main & arcing
contacts
t t
• The abnormal wear & tear or excessive pitting of
contacts is indicated
• Certain mechanical weaknesses, undetected by
travel measurement
measurement, are reflected in DCRM
measurement
• Gives prior indication of deterioration of
Operating mechanism linkages
• Comparison with old signatures makes condition
monitoring and corrective measures possible
© SCOPE T&M Pvt Ltd
Measuring Dynamically… The
Concept

Static Contact Resistance Dynamic Contact Resistance


• The CB is kept in closed • The CB undergoes C-O operation.
condition. • The current is injected in CB
• Current is injected in CB contacts and continuous samples
contacts and
d millivolt
ll l drop
d is of
f contact resistance are taken.
k
measured only once. • Resistance Variation of Contact
• The calculated contact System During contact insertion
resistance value reflects the & opening is plotted on time scale.
contact resistance of main
contact
© SCOPE T&M Pvt Ltd
Tools Requires for Dynamic Resistance Measurement
¾ HISAC Ultima
¾ DCRM
™ 1 Channel ….For measuring ONE break at a time.
™ 2 Channel…..For measuring two break at a time i.e. ONE Pole
™ 3 Channel…..For
Channel For measuring THREE breaks at a time…Three
time Three pole of single
break per pole system.
™ 6 Channel…..For measuring SIX breaks at a time…Three pole of two
break per pole system.

¾ HISAC Ultima – TEST MANAGER


¾ Transducer for the breaker under test.

© SCOPE T&M Pvt Ltd


Set Up for Testing….

HISAC
TEST MANAGER

© SCOPE T&M Pvt Ltd


Typical DCRM Signature…
Signature

© SCOPE T&M Pvt Ltd


Typical graph of DCRM…

© SCOPE T&M Pvt Ltd


Parameters to be monitored…

• Variations of Resistance values at the time of


Arcing and main contact close/ trip.
• Insertion of Arcing contact.
• Insertion of Main Contact.
• Contact travel.
• Resistance during closed conditions and its
comparison with static contact resistance value.
• Damping system healthiness

© SCOPE T&M Pvt Ltd


Normal DCRM signature

© SCOPE T&M Pvt Ltd


DCRM Comparison

© SCOPE T&M Pvt Ltd


Case Study
Study-11
• 400kV SF6 CB commissioned in 1997 was
controlling Bus Reactor.
• CB had given about 8 years service with 1400
operations.

© SCOPE T&M Pvt Ltd


Healthy Pole

© SCOPE T&M Pvt Ltd


Suspected Pole

© SCOPE T&M Pvt Ltd


Observations

• Moving Arcing contact was found de-shaped and had


expanded
d d
• One Counter Head Screw of Moving Main Contact
assembly was found loose
• PTFE Nozzle of moving contact assembly found cracked.
• Scratch marks were also seen on Main Moving Contact

© SCOPE T&M Pvt Ltd


RF
Communication

Control Room

Tran-Reci

OR USB

Polling Wiring from RTMon to CR


420 kV SF6 GCB
With SP/Pneumatic Mechanism

© SCOPE T&M Pvt Ltd


RTMon Field Unit Ver.2.0

© SCOPE T&M Pvt Ltd


Communication through RS 485

© SCOPE T&M Pvt Ltd


Installation of RTMon in S/S
CB1 CB2 CB3 CB4 CB5 ……. CBn

Measurement
RTMon RTMon RTMon RTMon RTMon RTMon
1 2 3 4 5 ……. n
n,<=255

Yard polling Wired / Manual / RF Link (500m)

C t lR
Control Room Trans-receiver Modem

USB Link

HQ IBM Compatible
PC+ RtMon
Software

Remote PC
Internet
© SCOPE T&M Pvt Ltd
Graph through RTMon software

© SCOPE T&M Pvt Ltd


Auxiliary Trip
Auxiliary Close
Event

AUX-A1 Delta

AUX-A2
Clearing Time

Main
Contact
Virtual Channel -
Shown only for
Interpretation
Arcing
Time

LINE
CURRENT

FAULT
CURRENT
Current
System Trigger
Interruption

COIL

Tripping Time Time


© SCOPE T&M Pvt Ltd
What RTMon can do for us?

¾ RTMon can measure circuit breaker performance during normal


operation as well as in fault condition.
¾ Check the results with the design parameters and can issue “Pass”
or “Fail”
“F il” condition.
diti
¾ Raises ALARAM to indicate deviation
¾ Build a History of performance for Predictive maintenance
resulting in, maximum system availability

© SCOPE T&M Pvt Ltd


SCHELOG
Maintenance Manager

© SCOPE T&M Pvt Ltd


SCHELOG - Maintenance Manager
¾ Purpose

• End Users and their Roles

• Assumptions - Entities and Nomenclature

• Proposed Reports

• Architecture

• Proposed
p User Interface

© SCOPE T&M Pvt Ltd


SCHELOG - Maintenance Manager
SCHELOG is a system by which maintenance of equipments
can be scheduled, conducted, monitored and analyzed.

Purpose of SCHELOG
¾ Schedule test activities for the various types of equipments.

¾ Collect test results and monitor the test activities using system
generated alarms. Especially of those that do not communicate with
SCADA

¾ Analyze test results to reduce downtime and carry out pro-active


maintenance.

¾ Enable timely action thereby minimizing the possibility of system


failure and avoiding huge documentation.

¾ Mandatory TOOL for conducting RLA & RLE of GRID EQUIPMENTS.


© SCOPE T&M Pvt Ltd
SCHELOG - Maintenance Manager

Role based Users of SCHELOG

¾ Substation Engineer (Conduct and Monitor tests)

¾ Substation In-charge (Schedule, Monitor, Forward and


Approve tests)

¾ Regional HQ User (Forward, Approve and Analyze tests)

¾ Corporate Center User (Approve and Analyze tests)

© SCOPE T&M Pvt Ltd


SCHELOG - Maintenance Manager
Equipment Tests

¾ EUT TType specific


ifi ttestt d
definitions
fi iti with
ith attached
tt h d
frequency, approval level and test parameters

¾ Define parameter limits based on component type

¾ Pre
Pre-defined
defined test formats

¾ Test Schedule Plan on yearly basis with ad-hoc


changes
h

¾ Test Instruments Calibration Schedule

© SCOPE T&M Pvt Ltd


SCHELOG - Maintenance Manager

Reports

¾ Trend Analysis of a component against test parameter

¾ P
Performance
f comparison
i a componentt off different
diff t
types / make (e.g. CB – ABB v/s CGL)

¾ Report of major maintenance of components

¾ Test Schedules (Date wise


wise, Substation wise
wise, EUT
Location wise, Status wise)

¾ Equipment Failure Reports (EFR)

© SCOPE T&M Pvt Ltd


SCHELOG - Maintenance Manager

© SCOPE T&M Pvt Ltd


Benefits of SCHELOG - Maintenance Manager
Benefits
¾ SCHELOG is designed to acquire data in order to monitor substation
equipment.
equipment
¾ This VALUE is in the form of a responsive scheduling feature, asset-
linked database and the possibilities of analysis of data to enable actions
that lead to Condition Based Maintenance of assets.
¾ Startup graphics is in the form of single line diagrams for substations.
Each equipment location is easily identified in a manner the engineers
are familiar with
GUI Features
1. Movement of cursor near an equipment symbol gives the location ID automatically.
2. A visual alarm on equipment symbol indicates that a scheduled activity is pending.

¾ Trend Analysis reports are available for trend of single parameters over
the period of time.

© SCOPE T&M Pvt Ltd


Circuit Breaker Testing

Maintain & Analyze ON Line Testing


The TREND analysis & more
th
throughh SCHELOG Maintenance
M i t
Of Circuit Breaker
Manager Software & Analysis

OFF Line
Testing of the
Circuit Breaker
& analysis

© SCOPE T&M Pvt Ltd


THANK YOU
ON Behalf
O e a o of

SCOPE T&M
SCO & PVT LTD
12 Ganesh Apartment 376 L.J.Road
Mahim, Mumbai -400016
Email:marketing@scopetnm.com
Vivekanand.sindkar@isoscelespower.com
www.scopetnm.com
t

© SCOPE T&M Pvt Ltd

You might also like