AL QOOZ CONTRACTING LLC

HAZARD IDENTIFICATION AND RISK ASSESMENT DATE


page 2
PAGE

TASK/JOB/OPERATION: BACK FILLING


PROJECT : PROPOSED FACTORY AND FACILITIES ON PLOT NO:KHIA5-14A_B
CREW/SUBCONTRACTORS:

DATE: Date next Review :


Recommended PPE: Hard hat,Safety shoes,Safety Harness overalls,Dust mask,Goggles,Gloves
EQUIPMENT REQUIRED: Excavator,shovel,skid steer loader(bobcat)

Legal compliance
harm/consequ
Risks Who

Control E/I/R
/Activities
Job steps

might be
/potential
identified

Hazards

Remarks
Risk Rating/Risk
Hazard

ences
Sl no

Mitigation action to be taken/Hazard/risk Residual Risk


level Control METHOD

L S R L S R

Tool box talks to be given before commencing the


activity,proper access shall be provide for vehicle and
Inhalation of dust and pedestrian and area barricaded,damaged tools and
possible harmful fumes equipment not to use in the site,people not to work
Personal injury
and gases may lead to excavation when heavy equipment is in operation,all
2 Dust property damage,loss No 3 5 High R 3 3 Med
long term personnel to HSE induction training from safety
of life,deadth department before entering the site,to ensure proper
illness/cough/long
disease use of PPE during entire work,sprinkle the water if
required to reduce dust,ensure proper compaction of
soil

1-Improbable 1-Negligible Likelihood X


Review by Main -Contractor Approved by Consultant
Severity

2-Remote 2-Minor Severity E -Eliminate


Control
Likely

Risk

3-Occassional 3-Reportable High 15-25 I- Isolate


COENGR Engineering
4-Probable 4-serious Medium 7-12 R-Reduce Al Qooz Contracting LLC
Consultancy
5-Frequent 5-Catastrophic Low 1-6