LIST OF ACTIVITIES
Project Management
Initiate the project
→ Develop project charter
→ Develop team contract
Plan the project
→ Develop project management plan
→ Pre planning meeting with stakeholders
→Pre planning meeting with NGO founders
→ Create Scope statement ◊ Milestone 1 ◊
→ Create WBS
→ Conduct research and collect requirements
→ Create list of NGO founders
→ Review and approval of the plan
→ Monitor project and quality risks
→ Project communication plan
Promotions
Design digital logo, Banners
Develop digital advertisements
→ Promotions on social media
→ Model and social media influencer
COST ESTIMATES
As per Canadian Govt. rules and regulations 1560 hours are considered as full-time worker.
The following are the cost estimates produced for the project:
Cost Estimates
modules Developer
Integrate NGOs with systems 2 Software 1 282 $564.00
Developer
Perform validation testing 7 Quality 100% $300.00 $2,100.00
Assurance
Test &
Program
Manager
Provide training to transportation 7 Customer Service 100% $264.00 $924.00
people Representatives
Provide training to NGO staff 5 Customer Service 100% $264.00 $660.00
Representatives
Monitoring and controlling 4 Quality 100% $300.00 $1,200.00
Assurance
Monitoring
Week Week Week Week Week Week Week Week Week Week Week Week Week
Ending Ending Ending Ending Ending Ending Ending Ending Ending Ending Ending Ending Ending
Cost
June June July July July July Aug Aug Aug Aug Aug Sep Sep Total
Category
20th, 27th, 4th, 11th, 18th, 25th, 1st, 8th, 15th, 22nd, 29th, 5th, 12th,
2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021
Initiating
HR $1,400 $1,000 $432 $2,832
costs
Other $150 $300 $1,350 $1,800
costs
Planning
HR $753 $1,150 $500 $750 $420 $3,573
costs
Other $520 $750 $300 $200 $330 $2,100
costs
Executing
HR $4,746 $1,956 $5,004 $6,102 $1,692 $6,450 $5,904 $1,200 $384 $816 $34,254
costs
Other $1,100 $700 $1,584 $3,384
costs
Closing
In the early stage of the project (Week 1, above), costs are relatively low. This corresponds to the
Initiating Phase. Costs tend to increase during the Planning Phase and the start of the Executing
As the Executing Phase continues (Weeks 4 to 7), the costs continue to rise rapidly, peaking at about
the
three-fourths point of the project and then beginning to fall as the work nears completion.
During the Closing Phase (Week 8), the costs are relatively low.
RACI Chart
An RACI Chart provides useful information to the people working on the project. The below RACI Chart
RACI CHART
Dhru Technica Quality Strategy Customer
Payal Sajan Software Software
v Hiren l Project Assuranc & Risk Service
(PM) a Designer Developer
(PA) Manager e Manager Representatives
Project
A,R A,C I I C I I I C C
Management
Design
Systems C I I I A A,R,C A,R C A,C I
Develop
Systems C I I I A,R C A,R,C A,C A,C I
Integrate
Systems C,I,R I I I A,R C A,R,C A,C A,C I
Test &
Validations C I C C A,R C R,C A,R,C A,R I
Promotions A,R R,C R,C R,C C A C C A,R,C C
Provide
C R,I C C A,R I I A,C A,R,C A,R
Training
R–Responsible A–Accountable C–Consulted I–Informed
REFERENCES
https://www.cic.gc.ca/english/helpcentre/answer.asp?qnum=664&top=29
https://www.glassdoor.ca/Salaries/project-manager-salary-SRCH_KO0,15.htm
https://www.glassdoor.ca/Salaries/business-analyst-salary-SRCH_KO0,16.htm
https://www.glassdoor.ca/Salaries/operational-risk-manager-salary-SRCH_KO0,24.htm
https://www.glassdoor.ca/Salaries/technical-program-manager-salary-SRCH_KO0,25.htm
https://www.glassdoor.ca/Salaries/software-designer-salary-SRCH_KO0,17.htm
https://www.glassdoor.ca/Salaries/software-developer-salary-SRCH_KO0,18.htm
https://www.glassdoor.ca/Salaries/software-qa-engineer-salary-SRCH_KO0,20.htm
https://www.glassdoor.ca/Salaries/customer-service-representative-salary-SRCH_KO0,31.htm