Spesifikasi Main Engine

PHT. SDS. 36
Data Engine Main Engine No. 1 Main Engine No.2
Manufacture Yanmar
Model No 6 LAH -STE
Serial No 6546 6545
Power@Rpm 1900 1900
Genset Matching Power
Starting
Lo Capacity
Coolant Capacity
Spesifikasi Auxiliary Engine
PHT. SDS. 36
Data Engine Auxiliary Engine No. 1 Auxiliary Engine No.2
Manufacture Yanmar
Model No 4 TNE 98T
Serial No
Power@Rpm
Genset Matching Power
Starting
Lo Capacity
Coolant Capacity
Altenator Altenator No. 1 Altenator No. 2
Manufacture
Model No
Phase/ Frequency / Volts
Automation Panel Automation Panel # 1 Automation Panel # 2
Manufacture
Model
Jam Mulai Jam Selesai Total Jam
No Tanggal Kegiatan Keterangan
Wib Wib Kerja
1. Jum’at, 11/9/2020 Main Engine No. 1 ( PS ) 09.00 17.00 8 jam Istirahat, 12.00 – 13.00
Buka Accessoris Engine :
Cylinder head Cop
Push Rod
Rock arm
pipa mapel bahan bakar
Injector
Lepas Bosh Pump
Lepas Govenor
Lepas Fuel Filter
Lepas Oil Filter
Turbo Charge
Exhaust
Dinamo Stater
Altenator Charge
Lepas Oil Pump
Carter
2. Sabtu, 12/9/2020 Main Engine No. 1 ( PS ) 08.00 14.00 8 Jam Istirahat, 12.00 – 13.00
Cylinder Block : 14.30 16.00 Istirahat, 14.00 – 14.30
Lepas Cylinder Head 1 s/d 6
Lepas Crank Pin 1 s/d 6
Lepas Piston 1 s/d 6
Lepas Main Bearing 1 s/d 6
Lepas trust bearing
Lepas Liner 1 s/d 6
Lepas Intercooler
Balik Cylinder Block
Akhir Total Jam 16 Jam
3. Senin, 14/09/2020 Auxiliary Engine No.1 ( PS ) 08.00 16.00 10 Jam Istirahat, 12.00 - 13.00
Buka Accessoris Engine :
Cylinder head Cop
Push Rod
Rock arm
Fuel Pump
Pipa mapel bahan bakar
Injector
Heag Exhanger
Turbo Charge
Exhaust
Dinamo Stater
Altenator Charge
Lepas Oil Pump
Carter
Auxiliary Engine No.1 ( PS ) 16.30 18.00 Istirahat, 16.00 –16.30
Cylinder Block :
Lepas Cylinder Head
Lepas Crank Pin 1 s/d 4
Lepas Piston 1 s/d 4
Lepas Main Bearing 1 s/d 5
Lepas trust bearing
Lepas Liner 1 s/d 4
Kopel engine dan altenator di lepas
Lepas Ball Joint Engine
Balik Cylinder Block
Lepas Fly wheel
4. Selasa, 15/09/2020 Main Engine No. 2 ( STD ) 08.00 16.00 10 Jam Istirahat, 12.00 – 13.00
Buka Accessoris Engine : 16.00 18.00 Istirahat, 16.00 – 16.30
Cylinder head Cop
Push Rod
Rock arm
pipa mapel bahan bakar
Injector
Lepas Bosh Pump
Lepas Govenor
Lepas Fuel Filter
Lepas Oil Filter
Turbo Charge
Exhaust
Dinamo Stater
Altenator Charge
Lepas Oil Pump
Carter
5. Rabu, 16/09/2020 Main Engine No. 2 ( STD ) 08.00 16.00 13 Jam Istirahat, 12.00 – 13.00
Cylinder Block : 17.00 21.00 Istirahat, 16.00 – 17.00
Lepas Cylinder Head 1 s/d 6
Lepas Crank Pin 1 s/d 6
Lepas Piston 1 s/d 6
Lepas Main Bearing 1 s/d 6
Lepas trust bearing
Lepas Liner 1 s/d 6
Lepas Intercooler
Balik Cylinder Block
Auxiliary Engine No.2 ( STD )
Buka Accessoris Engine :
Cylinder head Cop
Push Rod
Rock arm
Fuel Pump
Pipa mapel bahan bakar
Injector
Heag Exhanger
Turbo Charge
Exhaust
Dinamo Stater
Altenator Charge
Lepas Oil Pump
Carter
6. Kamis, 17/09/2020 Auxiliary Engine No. 2 ( STD ) 08.00 16.00 8 Jam Istirahat, 13.00 – 13.00
Cylinder Block :
Lepas Cylinder Head
Lepas Crank Pin 1 s/d 4
Lepas Piston 1 s/d 4
Lepas Main Bearing 1 s/d 5
Lepas trust bearing
Lepas Liner 1 s/d 4
Kopel engine dan altenator di lepas
Lepas Ball Joint Engine
Balik Cylinder Block
Lepas Fly wheel
Main Engine No. 1 & 2
Proses Pemindahan Komponen – Komponen Engine Ke
Gudang Rukindo :
Cylinder Head ( 12 Pcs )
Piston ( 12 Pcs )
Conneting Rod ( 12 Pcs )
Auxiliary Engine No. 1 & 2
Cylinder Head ( 2 Unit )
Cylinder Block ( 2 Unit )
Turbocharge ( 2 Unit )
Piston ( 8 Pcs )
Connecting Rod ( 8 Pcs )
7. Jum’at, 18/09/2020 Main Engine No. 1 & 2 08.00 16.00 8 Jam Istirahat, 12.00 – 13.00
Proses Cleaning :
Lepas Seal Valve Steam / Kuku Macan, Stainer Klep –
Intake & Exhaust ( 48 Pcs )
Lepas Spring Klep Intake ( 24 Pcs )
Lepas Spring Klep Exhaust ( 24 pcs )
Lepas Klep Intake ( 24 Pcs )
Lepas Klep Exhaust ( 24 Pcs )
Cleaning Permukaan, Ruang Udara Intake & Exhaust
Cleaning Piston
Cleaning Cylinder Block
Pekerjaan Altenator PHT. SDS. 36
15 Altenator No. 1
Pengecekan Kondisi Altenator
Pengecekan Stator Exsister
Magger Test Awal
Pengecekan Terminasi R,S,T to Panel Auxiliary Engine
Pengecekan Komponen2 Panel Auxiliary Engine
Altenator No. 2 ( STD )
Pengecekan Kondisi Altenator
Pengecekan Stator Exsister
Magger Test Awal
Pengecekan Terminasi R,S,T to Panel Auxiliary Engine
Pengecekan Komponen2 Panel Auxiliary Engine
16 Altenator No. 1 ( PS )
Lepas Koneksi R, S, T – Panel engine dan altenator.
Lepas Stator exsister.
Lepas cover belakang altenator.
Lepas plat kopel altenator – Fly wheel yang melekat
pada as rotor.
Lepas rotor dari stator, dan diletakan pada posisi kerja
yang aman.
Pengecekan Bearing belakang pada rotor.
Cleaning Stator Exsister mengunakan electrical cleanner.
17 Altenator No. 2 ( STD )
Lepas Koneksi R, S, T – Panel engine dan altenator.
Lepas Stator exsister.
Lepas cover belakang altenator.
Lepas plat kopel altenator – Fly wheel yang melekat
pada as rotor.
Lepas rotor dari stator, dan diletakan pada posisi kerja
yang aman.
Pengecekan Bearing belakang pada rotor.
Cleaning Stator Exsister mengunakan electrical cleanner.
18 Altenator No. 1 ( PS )
Cleaning Rotor, mengunakan electrical cleaner.
Cleaning Stator, mengunakan electrical cleaner.
Lepas Bearing 6203, mengunakan Tracker 7”. ( Renew )
Proses Pengeringan ( open ), mengunakan lampu sorot
250 w.
Altenator No. 2 ( STD )
Cleaning Rotor, mengunakan electrical cleaner.
Cleaning Stator, mengunakan electrical cleaner.
Lepas Bearing 6203, mengunakan Tracker 7”. ( Renew )
Proses Pengeringan ( open ), mengunakan lampu sorot
250 w.
8. Sabtu, 19/09/2020
9. Senin, 21/09/2020
10. Selasa, 22/09/2020 Main Engine No. 1 & 2 08.00 16.00 8 Jam Istirahat, 12.00 – 13.00
Proses Cleaning :
Lepas Liner Kanan/Kiri
11. Rabu, 23/09/2020 Main Engine No. 1 & 2 08.00 16.00 8 Jam Istirahat, 12.00 – 13.00
Proses Cleaning :
Cleaning Blok dengan Sikat Brush Kanan/Kiri
Lepas Cooler Cover
Lepas Cleaner Kanan No 2
Brushing Liner Kiri
12. Kamis, 24/09/2020 Main Engine No. 1 & 2 08.00 16.00 8 Jam Istirahat, 12.00 – 13.00
Buka Accessoris Engine :
LO Cooler Kanan
LO Cooler Kiri
Proses Cleaning :
Cleaning LO Cooler
Skir Klep 3 Kanan