Professional Documents
Culture Documents
1. Introduction slip occurs between the sheeting and concrete under a service live
load.
Various types of deck slab systems have been developed and Although headed studs are the most common type of shear
used for girder bridges, though a full-depth cast-in-place (CIP) connector, they may be unsuitable for profiled sheeting because of
reinforced concrete (RC) deck remains the most common system need to weld the studs to a thin steel plate. If the studs have a large
due to its economical advantages. Stay-in-place steel forms are diameter, they may cause a welding problem during fabrication.
often used for CIP RC decks because a full-depth CIP RC deck takes On the other hand, if the studs have a small diameter, a greater
a relatively long time to erect. The use of steel forms saves a number of studs must be used. Furthermore, the studs welded onto
significant amount of time during the construction of an RC deck thin steel plate may cause a fatigue problem during the service life.
slab for girder bridges. The perfobond rib shear connector may be an alternative shear
Steel forms are generally profiled and made of light-gauge steel connector that can be used with profiled sheeting. This type of
sheets with indentations or embossments. If the composite action shear connector consists of a steel plate with a number of uni-
between the form and the concrete can be obtained, the forms can formly spaced holes. If the holes are filled with concrete, con-
partially act as a tensile reinforcement and the cross-sectional area crete dowels are formed; and the dowels provide horizontal shear
of the deck can be somewhat reduced. However, the composite resistance between the sheeting and the hardened concrete. The
action is generally neglected in the design of RC bridge deck slabs perfobond rib shear connector has several potential advantages:
because the indentations or embossments in the forms fail to they are easy to customize and fabricate; they help overcome the
provide the desired level of horizontal shear resistance between fatigue problem; and a single perfobond rib can replace a number
the form and the concrete under a live load. of headed studs.
Jeong et al. [1] proposed a steel–concrete composite deck In 2006 Kim and Jeong [2] used perfobond rib shear connectors
system with profiled steel sheeting for girder bridges. In such a for a composite deck slab with profiled sheeting and experimen-
system, the interaction between the sheeting and the concrete tally investigated the behaviour of the deck slab. The type of com-
generally governs the strength and behaviour of the deck. Headed posite deck slab that they proposed for girder bridges had a longer
studs were used as shear connectors in the study of Jeong et al., span but weighed less than a typical CIP RC deck slab.
and the studs were welded onto the profiled sheeting. However, More recently, 16 deck specimens were tested with different
the results of push-out and flexural tests indicate that a horizontal shear span lengths for the purpose of evaluating the horizontal
shear capacity of the proposed deck system. The horizontal shear
capacity of the proposed deck system was evaluated by means of
∗ Corresponding author. Tel.: +82 31 910 0582; fax: +82 31 910 0578. the empirical design method described in [3], and the test results
E-mail addresses: hykim1@kict.re.kr (H.-Y. Kim), yjjeong@kict.re.kr are briefly summarized in [4]. The estimated horizontal shear
(Y.-J. Jeong). capacity of the proposed deck was identified as being at least two
0143-974X/$ – see front matter © 2009 Elsevier Ltd. All rights reserved.
doi:10.1016/j.jcsr.2009.04.016
1752 H.-Y. Kim, Y.-J. Jeong / Journal of Constructional Steel Research 65 (2009) 1751–1762
times greater than the required horizontal shear strength. The test disadvantages. During service, the condition of the deck, especially
results [2,4] indicate that the perfobond rib shear connection can the concrete, cannot be inspected visually. In addition, the profiled
be effectively used for the proposed deck system. sheeting must be protected from steel corrosion. For practical
This study elaborates the work of [2] with a series of test applications, there is also a need for a simple but effective sheet-to-
programs. This paper presents the ultimate behaviour of a sheet connection method to be developed because the size of the
steel–concrete composite deck slab designed for a prototype of a profiled sheeting is limited due to fabrication and transportation
precast prestressed concrete (PSC) I-girder bridge. The design is requirements.
based on the deck profile proposed in [2].
The clear slab span length of the proposed deck slab was 2. Proposed deck system
assumed to be 2.5 m, whereas that of a typical CIP RC deck slab for a
PSC I-girder bridge is normally less than 2.2 m. Two full-scale deck 2.1. Deck profile
slab specimens cast onto three concrete blocks were fabricated and
tested under static loading to examine the ultimate load-carrying Fig. 1 shows a schematic of the steel–concrete composite bridge
capacity of the proposed deck slab specimens under sagging and deck system proposed in [2]. The deck consists of concrete, steel
hogging bending actions. The test results are compared with the reinforcements, perfobond rib shear connectors, and profiled steel
results of a finite element (FE) analysis of a full-length bridge. The sheeting set perpendicular to the girders. Because the profiled
ultimate behaviour of the full-scale deck slab specimens is also sheeting serves as a tensile reinforcement in the design of the deck
compared with that of the simply supported deck specimens tested slab, no reinforcing bars are required at the bottom.
Fig. 2 shows a cross section of a prototype of a precast PSC I-
in [4]. In addition, the load–deflection behaviour of the proposed
girder bridge selected for the design of the proposed composite
deck system is compared with the behaviour of the RC deck slab
deck slab system. The clear slab span length (L) was assumed to
specimens tested in this study. The test results and findings are
be 2.5 m, which is approximately 1.2 times longer than a typical
summarized in this paper.
CIP RC deck slab for a precast PSC I-girder bridge.
The use of the proposed deck system in bridge construction
The standard design truck load specified in the Korean Bridge
may be costly unless consideration is given to the savings in Design Code [5] is used as the design live load. According to
construction time and maintenance costs. The proposed deck the code, the gross weight of the design truck is 43 200 kg.
system is roughly estimated to cost at least 1.6 times more than CIP The self-weight of the deck slab together with the 50 mm-thick
RC decks but it may be competitive with CIP RC decks under certain asphalt wearing surface is used for the dead load. The ultimate
circumstances. The user cost might be reduced, for example, when strength method was used for the deck design. Note also that the
the proposed deck system is used in a deck replacement project overall design process is driven by the strength limits because
for a high-traffic bridge. If the user cost is considered, the use of the horizontal shear capacity of the deck is obtained from test
the proposed deck system in construction may be a less expensive information.
choice because the expected erection time of the proposed system Fig. 3 shows cross-sectional dimensions of the proposed
is about half that of RC deck system. composite deck profile. The dimensions of the profiled steel
As discussed in [2], the proposed deck system has several sheeting were determined on the basis of structural optimization.
advantages over conventional CIP RC decks but also a few The design procedure for the deck profile is briefly summarized
H.-Y. Kim, Y.-J. Jeong / Journal of Constructional Steel Research 65 (2009) 1751–1762 1753
Fig. 8. Test set-up for the RC deck specimens: (a) RC-1 and (b) RC-2.
times greater than the required horizontal shear strength of the Table 1
deck slab. Summary of the test results.
Specimen ID Ls Pu (kN) Pcr (kN) δu (mm) δs (mm) Failure mode
2.4. Comparison of composite and RC decks PF-3 [4] L/4.0 1,554 360 20.2 1.6 Shear
RC-1 L/4.0 696 390 14.8 1.3 Shear
For a comparison of the load–deflection behaviour of the PF-6 [4] L/2.0 863 150 21.8 1.7 Shear–flexural
proposed deck system with that of a conventional CIP RC deck slab, RC-2 L/2.0 375 50 51.6 3.7 Flexural
Fig. 10. Failure mechanisms of the RC deck specimens: (a) RC-1 and (b) RC-2.
50
700 2,500 700 2,500 700 450
7,600
b
Fig. 12. A full-scale deck slab specimen: (a) dimensions in millimeters and (b) the testing fixture.
1756 H.-Y. Kim, Y.-J. Jeong / Journal of Constructional Steel Research 65 (2009) 1751–1762
75 550 a
a
50
180
100
650
320 b
280
6@125
b
Fig. 15. Reinforcement details of a full-scale deck slab specimen.
140
Fig. 15(b), 16 mm bars (H16-2) are uniformly spaced at 250 mm as
100 a transverse reinforcement to control the cracking. The use of the
perfobond rib as a chair for the reinforcement obviates the need to
140 use conventional chairs during the erection stage.
As shown in Fig. 15(b), the 16 mm bars (H16-1) pass through
140
every second hole of the perfobond ribs to reinforce the concrete
dowels. Fig. 14(b) shows that two 22 mm bars are placed at both
1000 ends of the perfobond ribs to provide end-anchorage. The end
anchorage was used because the test results in [4] indicate that the
Fig. 13. Reinforcement details for a concrete block (units: mm): (a) front view and use of the end-anchorage can effectively increase the horizontal
(b) side view. shear resistance of the composite deck.
In the longitudinal direction of the specimen, the top reinforce-
ment over the composite section is extended to the cantilevered
a overhang. As a means of resisting the compressive stresses induced
by the sagging moment of the deck, the 19 mm bars that are uni-
formly spaced at 125 mm are also placed for the bottom reinforce-
ment in the cantilevered concrete overhang section. Because the
profiled sheeting serves as a stay-in-place form, no form work is
needed for the composite sections between the concrete blocks,
though a conventional plywood form is used for the cantilevered
overhang.
The pouring of normal density concrete with a design strength
of 30 MPa, a slump of 120 mm, and entrained air of 5.1% began
b Center bars after the placement of the reinforcements. The mean compressive
Perfobond rib strength of the air-cured concrete at the time of the test, as
evaluated in three cylinder tests, is 33.1 MPa.
Anchor bars
3.2. Test procedure
Fig. 16 shows the test set-ups for the full-scale deck slab speci-
mens, and Fig. 17 shows the two loading schemes used in the test.
The specimens have identical dimensions but are named PGF-1
and PGF-2 to distinguish the loading schemes. Both specimens are
Profiled sheeting subjected to a three-point load; however, the shear span length (Ls )
of the composite deck sections is assumed to be L/4 for specimen
Fig. 14. Fabrication of a full-scale deck slab specimen: (a) deck-to-girder PGF-1 and L/2 for specimen PGF-2. Thus, the behaviour of the deck
connection and (b) profiled sheeting with perfobond ribs. slab under a hogging and sagging bending action can be compared
with that of the simply supported deck slab specimens tested in [4].
4, respectively. An SS400-grade mild steel plate with a thickness Fig. 17(a) also shows the locations of the strain gauges and
of 6 mm was profiled through a press braking process to form the LVDTs. Three LVDTs (D1, D2, and D3 in Fig. 17(a)) are placed
profiled sheeting. The perfobond rib was fabricated by first cutting underneath the specimens to measure the vertical displacements
a 6 mm thick steel plate and then cutting holes in the plate with of the deck slab at different loading stages. As shown in Fig. 17(a),
a plasma jet machine. The perfobond rib was welded onto the a number of strain gauges are mounted on the bottom flange of the
profiled sheeting with an automatic welding machine. profiled sheeting (S1 and S2).
Fig. 15(a) shows that 19 mm bars (H19) are uniformly spaced at The load is incrementally applied to the specimens in a two-
125 mm as the primary reinforcement. At the top layer, as shown in stage of loading step. In the first stage, loads P1 and P2 are
H.-Y. Kim, Y.-J. Jeong / Journal of Constructional Steel Research 65 (2009) 1751–1762 1757
Fig. 16. Test set-up of the specimens: (a) PGF-1 and (b) PGF-2.
Fig. 17. Instrumentation and loading scheme of the specimens: (a) PGF-1 and (b) PGF-2.
simultaneously applied to the specimen until concrete cracking overturning during the test, especially at the failure stage. In
occurs, either at the top of the cantilevered overhang or the addition, vertical monotonic loadings with a displacement control
concrete deck section above the concrete block. In the second stage of 0.02 mm/s were independently applied to the specimens by
of loading, load P1 maintains the final load level of the first stage means of two servo-controlled actuators with a 3500 kN capacity.
of loading but load P2 is continually increased until the specimen
fails. 3.3. Test results and discussion
Fig. 16 shows that load P2 was applied through a rigid spreader
beam. Note also that the load was applied through a line over the Fig. 18 shows the failure mechanism of specimen PGF-1, and
full width of the deck to prevent the possibility of the specimens Fig. 19 shows the failure mechanism of specimen PF-3, which was
1758 H.-Y. Kim, Y.-J. Jeong / Journal of Constructional Steel Research 65 (2009) 1751–1762
Fig. 19. Failure mechanisms of specimen PF-3 (Ls = L/4.0) tested in [4].
tested in [4] with the same shear span length as specimen PGF-1. the concrete block (Block 3) at P1 = 290 kN. The tip displacement
Fig. 18(a) shows that the first concrete crack occurs on top of the at the cantilevered overhang is 2.62 mm at the initial cracking load.
concrete slab above the concrete block (Block 3 in Fig. 12(a)) at When load P2 reaches about 640 kN, flexural cracks occur at
P1 = 250 kN. The tip displacement at the cantilevered overhang is the bottom of the concrete underneath the loading point. When
6.12 mm at the initial cracking load. load P2 approaches the ultimate load level, diagonal shearing
When load P2 reaches about 450 kN, hairline cracks occur at the cracks develop within the shear span of the composite section
bottom of the concrete within the shear span (Fig. 18(b)). These and spread progressively towards the top of the concrete at the
cracks spread progressively towards the top of the concrete at the loading point. The cracking pattern within the composite section
loading point as load P2 is further increased. of specimen PGF-2 (Fig. 20(a)) is similar to that of the simply
The cracking pattern within the composite section of specimen supported specimen PF-6 (Fig. 21). The ultimate behaviour of the
PGF-2 (Fig. 18(a)) is quite different from that of the simply composite section in specimen PGF-2 is affected by the flexural
and shear strength of the composite deck. The tensile stresses
supported specimen PF-3 (Fig. 19) tested in [4]. Because specimen
that develop in a diagonal direction within the shear span of the
PF-3 is simply supported its ultimate behaviour is mainly affected
composite section cause diagonal shear cracking of the concrete.
by flexural and vertical shear strength of the composite deck. On
During and after the test, a concrete section at the deck-
the other hand, the failure of the composite section in specimen
to-girder connection was visually inspected and no visible
PGF-2 is characterized by the development of a number of diagonal
deformation or crack was observed. The test results of the full-scale
shearing cracks which appear in the concrete at an angle of deck slab specimens indicate that the bending and shear stresses
approximately 45 degrees. This outcome may be due to the fact that developed in the composite section are effectively transferred
that the hogging bending of the composite section in specimen to the concrete blocks through the deck-to-girder connection.
PGF-2 is restrained by the concrete sections above the concrete The load–deflection behaviour of the composite deck section
block whereas specimen PF-3 is a rotation-free condition at the under hogging and sagging bending actions was quantitatively
supports. Thus, the ultimate behaviour of the composite section in analyzed on the basis of the load versus vertical displacement
specimen PGF-1 is mainly affected by the vertical shear strength of curves of the slab specimens. The load–vertical displacement
the deck slab. curves are presented in Fig. 22 for specimens PGF-1 and PGF-2 and
Fig. 20 shows the failure mechanism of specimen PGF-2, and for the simply supported composite deck specimens with the same
Fig. 21 shows the failure mechanism of specimen PF-6, which was shear span lengths. The vertical displacements presented in Fig. 22
tested in [4] with the same shear span length as specimen PGF-2. are the displacements measured at the mid-span of the composite
The first concrete crack occurs on top of the concrete slab above section between Block 2 and Block 3.
H.-Y. Kim, Y.-J. Jeong / Journal of Constructional Steel Research 65 (2009) 1751–1762 1759
Fig. 21. Failure mechanisms of specimen PF-6 (Ls = L/2.0) tested in [4].
Table 2
Comparison of the test data and the results of the FE analysis.
Description Gauge no. PGF-1 PFG-2
Test FE Test FE
4. Conclusion and higher initial cracking load can contribute to the potential
advantages of the proposed deck system over a conventional RC
The behaviour of a steel–concrete deck slab system with deck.
profiled steel sheeting and perfobond rib shear connectors was Two full-scale deck slab specimens that were continually cast
experimentally and numerically investigated in this study. The onto three-concrete blocks were tested under sagging and hogging
conclusions from the test results are summarized below. bending actions. Under the service load level, the response of the
The load–deflection behaviour of the proposed deck system full-scale deck slab specimens is at least three times stiffer than
is compared with that of a CIP RC deck system. The test results that of the simply supported deck slab specimens, regardless of
of the simply supported deck slabs indicate that the ultimate the shear span length. The test results confirm that, if the failure
load-carrying capacity and initial concrete cracking load of the is associated with the flexural strength of the deck, the ultimate
proposed deck system is at least 220% and 230% greater than the strength of the proposed deck under sagging and bending actions
corresponding values of an RC deck slab, respectively, while the is at least 1.6 times greater than that of the simply supported
proposed deck system weighs about 23% less than the RC deck deck slab under a hogging bending action alone. However, if the
system. failure is associated with the vertical shear strength of the deck,
The consequent reduction in the dead load of the deck slab may the difference is insignificant.
lead to lighter superstructures and reduced foundation loads. If the The vertical displacements and normal stresses measured in
design of a long span deck is considered, the lighter deck weight the full-scale deck specimens are many times smaller than those
1762 H.-Y. Kim, Y.-J. Jeong / Journal of Constructional Steel Research 65 (2009) 1751–1762
obtained by a full-length bridge analysis, regardless of the loading [8] Oguejiofor EC, Hosain MU. Behaviour of perfobond rib shear connectors in
conditions. This outcome is due to the fact that the test set-up used composite beams: Full-size tests. Can J Civil Eng 1992;19:224–35.
[9] Oguejiofor EC, Hosain MU. A parametric study of perfobond rib shear
in the present study prevents any vertical deflections or rotations connectors. Can J Civil Eng 1994;21:614–25.
of the girders. [10] Klaiber FW, Wipe TJ. An alternate shear connector for composite action. In:
Proc. mid-continent transportation symposium 2000. 2000.
[11] Valente I, Cruz PJS. Experimental analysis of perfobond shear connection
References between steel and lightweight concrete. J Construct Steel Res 2004;60:465–79.
[12] Vellasco PCG, Andrade SAL, Ferreira LTS, Lima LRO. Semi-rigid composite
[1] Jeong YJ, Kim HY, Kim SH. Partial-interaction analysis with push-out tests. frames with perfobond and T-rib connectors Part 1: Full scale tests. J Construct
J Construct Steel Res 2005;61:1318–31. Steel Res 2007;63:263–79.
[2] Kim HY, Jeong YJ. Experimental investigation on behaviour of steel–concrete [13] Andrade SAL, Vellasco PCG, Ferreira LTS, Lima LRO. Semi-rigid composite
composite bridge decks with perfobond ribs. J Construct Steel Res 2006;62: frames with perfobond and T-rib connectors Part 2: Design models
463–71. assessment. J Construct Steel Res 2007;63:280–92.
[3] Eurocode 4. prEN 1994. Design of composite steel and concrete structures. [14] Vianna JC, Costa-Neves LF, Vellasco PCG, Andrade SAL. Experimental
European Committee for Standardization (CEN). 2005; 1994. assessment of perfobond and T-perfobond shear connectors. J Construct Steel
[4] Jeong YJ, Kim HY, Koo HB. Longitudinal shear resistance of steel–concrete Res 2009;65(2):408–21.
composite slabs with perfobond shear connectors. J Construct Steel Res 2009; [15] Vianna JC, Costa-Neves LF, Vellasco PCG, Andrade SAL. Structural behaviour
65:81–8. of T-perfobond shear connectors in composite girders: An experimental
[5] Ministry of Land, Transportation, and Maritime Affairs. Highway bridge design approach. Eng Struct 2008;30(9):2381–91.
code. Seoul, Korea; 2008 [in Korean]. [16] Johnson RP. Composite structures of steel and concrete. 2nd edition Oxford:
[6] Zellner W. Recent designs of composite bridges and a new type of Blackwell Scientific Publications; 1994.
shear connectors. Composite construction in steel and concrete. In: Proc. [17] Ministry of Land, Transportation, and Maritime Affairs. Highway bridge design
engineering foundation conference. 1987. p. 240–52. manual: Typical drawings. Kim HY, editor. Seoul (Korea). 2008 [in Korean].
[7] Veldanda MR, Hosain MU. Behaviour of perfobond rib shear connectors: Push- [18] Finite Element Analysis Ltd. LUSAS reference manual. Ver. 14.2–3. Surrey, (UK).
out tests. Can J Civil Eng 1992;19:1–10. 2008.