Professional Documents
Culture Documents
Herve Baron - Engineering Training - Instrument - Control
Herve Baron - Engineering Training - Instrument - Control
BARON
PROCESS
PLANT LAYOUT
EQUIPMENT
CIVIL
PIPING
PIPELINE
ELECTRICAL
HERVE
BARON
Process design
Equipment specification
Process
data sheet Vendor
Rotating drawings Layout
Pressure vessels
Fired equipment Civil
PROCESS
PLANT LAYOUT
EQUIPMENT
CIVIL
PIPING
The discipline is commonly split in 3
PIPELINE specialties. Which ones?
PROCESS
PLANT LAYOUT
EQUIPMENT
CIVIL
PIPELINE
INSTRUMENTATION
PROCESS
PLANT LAYOUT
EQUIPMENT
CIVIL
PIPING
PIPELINE
INSTRUMENTATION
PROCESS
PLANT LAYOUT
EQUIPMENT
CIVIL
PIPELINE
INSTRUMENTATION
INSTRUMENTATION
• Field instrumentation
• Systems:
Process Control System
Unit Control System
Emergency Shutdown System
Fire & Gas System
Other systems
• Installation
93-E161
Gas outlet
INSTRUMENTATION
• Field instrumentation
• Systems:
Process Control System
Unit Control System
Emergency Shutdown System
Fire & Gas System
Other systems
• Installation
Package controlled
by Central Process
Control System
Package controlled
by Central Process
Control System
Package
controlled by
Package controlled
by Central Process
Control System
Engineering documents
Vendor documents
P&IDs
Control Narratives
Vendor documents
P&IDs
Control Narratives
INSTRUMENTATION
• Field instrumentation
• Systems:
Process Control System
Unit Control System
Emergency Shutdown System
Fire & Gas System
Other systems
• Installation
SIL: Safety Integrity Level: Level used for specifying the safety integrity
requirement of SIFs. There are 4 levels:
SIL: Safety Integrity Level: Level used for specifying the safety integrity
requirement of SIFs. There are 4 levels:
Functional Safety: Safety Instrumented Systems for the Process Industry Sector
SIL: Safety Integrity Level: Level used for specifying the safety integrity
requirement of SIFs. There are 4 levels:
Functional Safety: Safety Instrumented Systems for the Process Industry Sector
SIL: Safety Integrity Level: Level used for specifying the safety integrity
requirement of SIFs. There are 4 levels:
CONSEQUENCE CONSIDERATIONS
CATEGORY Health/Safety Public Disruption Environmental Impact Financial Impact
Abbreviation S – Safety P – Public E – Environmental F – Financial
Large Major/Extended Major Impact to
Fatalities/ Serious
I Impact on Public
Community Duration/ Full Scale Company
(10,000+) Response (>$50 million)
Significant
Small
Serious Injury to Serious/Significant Impact To
Community
II Personnel/ Limited
(1,000 to
Resource Company
Impact on Public Commitment ($2 - $50
10,000)
million)
Moderate
Medical Treatment for Moderate/Limited Impact To
Minor
III Personnel/ No Impact Response of Short Company
Summary:
INSTRUMENTATION
• Field instrumentation
• Systems:
Process Control System
Unit Control System
Emergency Shutdown System
Fire & Gas System
Other systems
• Installation
INSTRUMENTATION
• Field instrumentation
• Systems:
Process Control System
Unit Control System
Emergency Shutdown System
Fire & Gas System
Other systems
• Installation
PROCESS
PLANT LAYOUT
EQUIPMENT
CIVIL
PIPING
PIPELINE
INSTRUMENTATION
Operator
station
PT JB
Process
line
Secondary cable
Multi cable
10 9 Plug – ½” NPTF
11 8 Plug – ½” NPTM
HERVE Equipment layout drawings
BARON
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
- Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
Marshalling System
Cabinet Cabinet
Operator
station
PT JB
Process
Secondary cable
Multi cable
HERVE Main schedule Milestone for Instrumentation
BARON
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
- Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
- Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
- Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
The main schedule Milestones are the commitments to the Control System Contractor.
There are 2 commitments:
- Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
http://www.editionstechnip.com/en/catalogu
e-detail/1111/oil-gas-engineering-guide-
the.html