You are on page 1of 23

Comm/ JB No 0993/C10

Rev 00 01/ 01.07.13


Isgec Heavy Engineering Ltd.

SECTION 10 – INSPECTION DURING MAINTENANCE


SAFETY FIRST

10.1 Safety Precautions Before canceling the PTW the recipient


should sign the PTW with a statement
Before carrying out inspection/ repairs on of work carried out.
any part of the boiler or its auxiliary
equipment and controls a work permit
authorizing such inspections/repairs
must be obtained from the relevant
NOTE:
authority. Supervisor should ensure that Full proof mechanism must be
the system is de energized / Isolated adopted in PTW system.
before starting the job. On completion of
inspection/ repair the work permit must
be returned for cancellation. System is to
be normalized on cancellation of work The issuing authority must ensure that
permits. issue or cancellation of any permit in no
way affects safety of personnel or
10.1 Permit to work (PTW) system equipment covered by a permit issued for
another section of plant.
A permit to work is a printed form and
issued to employees before they may work During periodic overhaul it is a general
on specified items of plant. The objective practice to isolate all electrical systems
of this practice is to make it safe for and mechanism. While power testing of
employee to work and the permit is the any equipment, safety of personnel
guarantee of safety. Only authorized working in adjacent areas is of prime
persons of the owner are allowed to issue consideration. Warning must be given
the PTW after ensuring isolation/ safety and areas of doubt must be evacuated for
at the work place. Person incharge for safety reasons.
carrying out the work should be present
at job location with the PTW.
However the following must be made clear NOTE:
time and again to the persons obtaining
permits.
Please refer O & M manuals of
For own safety they must ensure that OEMs for specific procedures and
they do not work on equipment for operating and maintenance
which a permit is necessary until it
recommendations for the various
has been issued.
auxiliaries.
If they are drawing permit themselves,
they should read carefully to make
sure that they know which part is General
declared safe. If they have any doubt,
they must ask the engineer issuing When a boiler is shut down for
the permit. inspection/ repairs, it is either blow down
or filled completely with water depending
All copies of a PTW must be signed, on the reason for the shut down. The
PTW should be signed in the presence opportunity should be taken to inspect
of the engineer issuing or canceling it.

1 X 80 TPH CFBC Boiler Section 10, Page 1


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

the boiler, both internally and externally, A complete and adequate supply of
as conditions permit. lubricants must be available at all
times. The grades recommended by
In case boiler is to be emptied following
the various makers of the auxiliary
procedure shall be adopted:
equipment in their literature must be
adhered to.
When pressure in the boiler has fallen
to approximately 15 % of the working All threads must be treated with a
pressure the blow downs may be suitable lubricant on assembly to
opened and the pressure reduced to facilitate disassembly and prevent
30 psig (2.1 kg /Cm2.g) corrosion.
At this pressure the air release valve / All screw threads/ valve spindles are
vents should opened. This will properly treated initially, and during
prevent a vacuum forming within the subsequent maintenance it is advised
boiler as it cools further. that they are re-treated as a matter of
normal routine. For normal
With all drain and vents open the
applications Molybdenum Disulphide
boiler is drained as far as possible.
grease can be utilized.
If the boiler is to be kept out of service for
longer than 48 hours it must either be
10.2 Boiler (Internals & Externals)
absolutely dried out or completely filled
with water by adding chemicals. 10.2.1 Boiler Drums
Please refer Section 8 for Protection of
Idle Boiler Certain baffle plates inside the drum
may also require, removal to give
access to the tube ends.
On completion of maintenance /
overhaul of boiler and its auxiliaries, Cover the tube openings with
an inspection must be carried out to tarpaulin while cleaning the drums
confirm that job is complete and Remove all debris and foreign matter
correctly executed. from drum.
All surplus materials, tools etc. must Before entering a boiler drum
be removed from inside the furnace, personnel must empty all loose items
boiler drums, ducts, hoppers and i.e. mobile phones, Spectacles, coins,
from the surroundings of boiler & cigarette lighters, penknives etc. from
auxiliary plant. their pockets. This will avoid the risk
Galleries and Ladders must be clear. of tubes becoming blocked by such
items falling into them causing
All drive couplings must be uneven water distribution,
disconnected to facilitate checking of overheating and subsequent tube
drive unit alignment and direction of failure.
rotation.
All tools and equipment taken into a
Low voltage (24 volts DC supply) drum must be carefully catalogued to
electrical supply only should be used ensure their removal before sealing
for temporary inspection lamps and the drum. Anything that is
extension leads. inadvertently dropped into a tube
must be reported immediately and it
Suitable protective Clothing, Gloves,
should be removed. If a tube becomes
Face Masks, must be worn by
blocked permission must be obtained
personnel entering boiler drums, duct
from the inspecting authority for the
work, gas spaces etc.

1 X 80 TPH CFBC Boiler Section 10, Page 2


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

tube to be cut, the object removed and sludge. Use water only of the specified
the tube re-welded. feed water quality.
Remove any oil or grease traces using Check that all blind cap nuts are
a dry cloth. tight.
Water Level indication:-
a. The water line is normally a well-
defined line, which indicates a
steady water level. An indistinct WARNING :
broad bank will indicate an erratic
water level, the cause of which Volatile solvents such as carbon
must be sought in the boiler water tetrachloride must not be used in
analysis. confined spaces, as their fumes are
b. Check the T.D.S. and alkalinity as
highly dangerous.
these may be such as to cause
priming or foaming. Collect a sample of loose scale or
sludge for analysis.
c. Leakage from the feed pipe or too
vigorous a discharge from the riser Correct water treatment of both feed
tubes may also cause this and drum water will ensure the
symptom. internal cleanliness of both drums
and heating tubes between overhaul
Check tightness of joints on all periods.
internal pipes, and security of the
pipe clamps.
All joints of drum internals are fitted
with proper gaskets and there should
NOTE:
not be any gap between matching.
Do not use oil or grease on nuts &
studs.

Before entering a boiler drum


personnel must empty all
loose items. Cap nuts only are to be used
in drums to avoid thread
All items taken into a drum deterioration.
must be carefully catalogued
and removed before sealing
the drum. Anything that is Examine the landing faces of drum
inadvertently dropped into a manholes/ man lids for blemishes
tube must be reported before shutting tight the man lids.
immediately and removed. Manhole gaskets to be cleaned to good
Surface finish. Replace gasket if found
damaged.
Open blow down valves and wash
Use only the specified gaskets. Before
through drum with a high pressure
installing the gaskets on drum
water jet. Care to be taken to prevent
manhole, ensure the condition of the
blockage of blow down lines with
gasket to withstand the pressure.

1 X 80 TPH CFBC Boiler Section 10, Page 3


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Ensure complete seal welding of hood relevant drawing must be consulted to


plate with steam drum ascertain the correct weld preparation
and welding technique, material etc.
Gap is not allowed between baffle
to be used. Ensure that a minimum
plates two joints, cyclone separator
length of spool piece should not be
matching flanges, demister pads after
less than 200 mm and welded by
installation. Repair as required.
qualified welder.
Ensure that the fixing of demister
pad, cyclone separator and other
Method of Expanding Tubes
internals are as per drawing.
Clean the new tube inside and out to
Ensure saddle support of drums are remove any protective coating, scale
free from base saddle & bolts are in or rust.
hand tight condition in slotted holes
for free expansion & movement Remove any roll or die marks from the
tube ends. These must be smooth and
washed with a highly volatile grease
10.2.2 Inspection Manifolds / solvent to ensure that they are clean
Header Stubs/ Tubes and dry.
Clean the tube seats in the drum or
Examine internal surfaces for rust, manifold in similar manner.
loose deposits, grease. Any trace of
these must be manually removed. Select a tube expander to suit the
High pressure water jet can be used diameter and thickness of the tube
for this purpose. and the width of tube seat. The
length of the rollers should be
Examine the landing on hand holes sufficient to expand the tube to a
and removable inspection caps for diameter ½ or greater than the tube
blemishes that could affect the seal. diameter dependant on the gauge of
Replace and secure all inspection the tube.
caps. Insert the tube in the seat and set the
Tube Repairs inside projection to that specified on
the relevant drawing.
Faulty expanded tubes are cut off
local to each end, the stubs remaining Insert the expander sufficiently far
are then trimmed and driven into the into the tube to allow the small end of
drum or manifold from where they are the belling roller to enter. Then
retrieved. withdraw the expander sufficiently to
ensure that a reasonable amount of
A new tube is prepared and expanded expansion takes place before belling
in position in the manner described in commences.
below.
Turn the mandrill, the expander will
progress into the tube until the collar
abuts on the tube end. Expand the
tube slowly to avoid overheating. It is
preferable to under-roll rather than to
AVOID DAMAGE TO TUBE over-roll a tube since if a subsequent
HOLES. hydraulic test shows up a leak it is to
be tightened by an additional roll. An
over-rolled tube however would have
Welded Tubes to be removed and replaced by a new
Faulty tube sections are simply cut tube.
out and new sections welded in. The

1 X 80 TPH CFBC Boiler Section 10, Page 4


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Over rolling will be evidenced by temporary supports to avoid jamming


flaking of the tube metal under the of fuel during operation.
rollers.
Ensure the tightness of foundation
Where straight rolling expanders are bolts of gear box.
used, the belling is done with a hand
Ensure the lubrication of the drives as
belling tool.
specified in the lubrication schedule,
Avoid excessive lubrication of if required fill up fresh lubricants up
expander. Do not use mineral oils. to the normal level
Recommended lubricant is undiluted
Check alignment of all rotary
SHELL FRI 6 Soluble oil or equivalent
equipments, foundation bolt tightness
which is easily removed by the boiling
& installation of proper safety guards.
out process.
Check alignment with drives (Fuel
feeding system drives) and ensure the
10.2.3 Furnace and Fuel feeding free rotation of the shaft. Megger value
& Earthing is to be ensured before
When a markedly different draught starting the motor. Take No load trial
loss is observed compared with of motor & record its running
previously recorded figures for similar parameters.
boiler conditions, this will indicate
that fouling has advanced to a stage Ensure direction of rotation of the
where external cleaning by wire drives as per drawing before coupling.
brushing is necessary. Ensure sealing of side water wall
Inspect the tube surfaces, air nozzles panel with roof tubes
opening, fuel spreaders opening and Ensure the attachment link of buck
refractory application work. stay is completely welded with water
Observe any build up of deposits on wall & pins are tack welded at bottom
refractory surfaces, which are likely to side & free for movement during
break loose as the boiler cools down. expansion.
Any debris should be removed before Ensure sealing of pressure parts in
re-starting the boiler, checking at the general.
same time for damage to refractory or
heating surfaces, which may have Ensure supports in the integral piping
been incurred. are as per drawing.

Check the condition of fuel opening in Ensure proper sealing of scallop plate
furnace and side sealing repair, if with tubes and seal boxes.
necessary. Ensure proper sealing of air nozzles
There should be no accumulation of with the fins.
ash within the boiler. Ensure saddle support of all headers
Ensure seal around doors and are free from base saddle & bolts
openings are as per drawing. looseness is adjusted as per drawing
for free expansion & movement.
Ensure sealing rope or ceramic rope is
provided between all connecting
flanges in the fuel feeding system & 10.2.3.1 Refractory Inspection
blots are full tightened.
Every opportunity should be taken to
Ensure internal surfaces of all
inspect the brick work/ refractory
connecting duct, silo & chutes are free
inside the boiler for general condition,
from any debris, misalignment and
erosion and formation of cracks.

1 X 80 TPH CFBC Boiler Section 10, Page 5


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

The refractory must be stored in a Ensure the alignment & pitch of


clean, dry place where it is not likely economizer coils are as per drawing.
to be disturbed and contaminated by
Ensure economizer coils sealing with
water/ oils or grease which will
casing are as per drawing.
destroy their bonding properties.
Ensure the gap between Soot blower’s
Any damage incurred or discovered
Lance pipe to coils and outer casing is
must be repaired by dismantling the
as per drawing.
panel to the root and recasting.
Adhere strictly to the maker’s Ensure expansion joints are as per
instruction for mixing and applying drawings and expansion clearances
the refractory material. are adequate.
Drying out after repair must be done
according to the refractory dryout 10.2.6 Deaerator
procedure.
Ensure sliding support between the
10.2.4 Super heater base and one end saddle support of
deaerator are as per drawing.
Ensure the gap between super heater Use wire brush to clean deaerator
coil bend to adjacent pressure part surface and remove any dirt, rust or
panel is as per drawing mill scale, also clean the surface of
the deaerator manhole area.
Ensure the gap between super heater
coil to side water wall panel is as per Inspect the deaerator storage tank,
drawing. scrubber system and deaerator head
before filling the deaerator.
Ensure that guide plates are fitted in
the lugs provided on super heater Ensure cleanliness of holes in inner
coils are as per drawing. Ensure that jacket of scrubber system inside the
there is a sufficient gap between the storage tank.
guide plate and side panels so that
Ensure integrity of welding of spray
they do not rub after expansion.
nozzle box, SS Tray & other internals
Ensure the alignment & pitch of super in deaerator head & spray head.
heater coils are as per drawing. Check for proper gaskets in branch
pipes.
Ensure super heater coils sealing with
panel tubes & welding of seal boxes Examine the landing faces of
are as per drawing deaerator manholes/ man lids for
dent / marking before shutting tight
the man lids.
10.2.5 Economizer Check the pipe line supports as per
drawing and pre set at cold load
Ensure the gap between economizer condition.
coil to side casing is as per drawing Check that all the Nuts of U clamps
Ensure that Soot blower support are tight and tack welded so that they
plates orientation & elevation are as do not fall down during operation due
per drawing. to vibrations.

Ensure that inner casing plates are


erected and welded as per drawing.
10.2.7 Ducting, Bunker, Hopper &

1 X 80 TPH CFBC Boiler Section 10, Page 6


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Expansion joints A. Gas tightness test.


Ensure sealing rope or ceramic rope is
Start the ID fan and PA fan. Slowly
provided between all connecting
regulate the VFD in the circuit to raise
flange, manhole & bolts are fully
the pressure of the furnace to about
tightened.
100 mmwc.
Ensure engagement or alignment of
Take a burning swab/ soap solution
support hangers and supporting rods
and put it around
are as per drawing and supports are
pre set for the cold load condition. i. Manhole & Peephole doors
ii. Duct Joints
Ensure sealing of air / gas through
iii. Fan flanges
damper’s spindle bearings and
iv. Hopper Joints
tightness of shutoff dampers.
v. Expansion bellow Joints
Clean expansion joints to allow proper vi. All flanged Joints
flexibility and sealing of flue gas / air.
Flame will deflect wherever leakage
Ensure baffle plates welding, its will be there. Soap solution shall show
supports and their distance between bubbles.
baffle plates are as per drawing.
Mark the leaking point and carry out
Ensure that quadrants or indicators rectification.
are showing correct reading for SHUT
and OPEN damper positions and Repeat the test until all leakages are
marked on the duct for clear arrested.
indication.
B. Air Tightness Test
10.2.7.1 Gas and Air Tightness Test
Start the ID fan and PA fan. Slowly
It is generally noticed that at times regulate the VFD in the circuit to raise
during operation of boilers the the pressure of the fans to maximum
leakages in the air and gas side of the operating pressure of the fans.
boiler are high which causes loading All dampers in the air circuit near the
of fans. Such undesired loading acts furnace entry shall be closed.
as a restraint for loading the boiler or
in fixing the correct regime of Take a burning Swab/ Soap solution
combustion. and put it around joints in the
ducting. Flame will deflect wherever
The best way of eliminating this is to leakage will be there. Soap solution
carry out Air and Gas tightness test shall show bubbles.
on the vulnerable points in boilers.
Mark the leaking point and carry out
Leakage test of individual ducting / rectification.
hoppers to be carried out by running
respective fans. Repeat the test until all leakages are
arrested.
Vital areas that require specific attention
during checking :

i) Tubular Air heaters


ii) Duct joints
10.2.7.2 Procedure iii) Welding joints
iv) Damper and expansion joints

1 X 80 TPH CFBC Boiler Section 10, Page 7


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Care must always be exercised not to


over tighten valves when shutting.
Other Alternate procedures for
checking:
Smoke Test: This test is similar to air 10.2.9 Fans
and gas leak test with an addition of
smoke generation in the boiler before Clean fan casing, impeller and
pressurizing. Any leakages shall be connecting ducting and remove all
identified visually by smoke coming out obstruction.
from leaking areas. Smoke can be Ensure tightness of all mountings and
generated by smoke bombs, smoke foundation bolts.
generating machines or by firing wood/
jute/ cotton waste etc. Ensure bearing is free from dust &
other foreign material & recommended
Kerosene Test: This test is conducted for lubricant is filled.
detecting the leakages thru the weld
joints normally in ducts. A paste of lime/ Check the end gaps on both sides of
chalk is applied on one side of the joint floating bearing and ensure that it is
and after drying, Kerosene is sprayed on as per drawing. Ensure that lock rings
the other side of the joints. The leakage are installed in the fixed bearing.
areas shall be seen as wet areas on the Ensure locking arrangement of
side where lime/ chalk is applied. bearing sleeve with lock nut and
locking arrangement of hub with shaft
is as per drawing.
Ensure fan bearings (DE & NDE)
WARNING : make a full contact at bottom surface
& all around with bearing housing.
Smoke generating machines using
petroleum fuels must not be used Ensure the fixing of fan shaft seals at
as there is a fire/ explosion hazard. fan casing are as per drawing.
Machines using organic chemicals Check the clearance between rollers /
like Glycerin & Rose water can be balls and the inside diameter of the
safely used. bearing outer ring (cage).

Care must be taken while handling Check the distance between the shaft
Kerosene for the fire hazards ends (DBSE) and gap between both
halves of the coupling is as per
drawing.
Check alignment with drive and
10.2.8 Boiler house piping & valves ensure the free rotation of the
impeller.
Lubricate the valve spindles and After erection, Megger value &
adjust gland packing as necessary for Earthing is to be ensured before
free movement. starting the motor. Take No load trial
Each valve must be checked for full of motor & record its running
and free movement of the spindle parameters.
between SHUT and OPEN limits. Ensure direction of rotation of the
Position indicators must be checked drive is as per drawing before
for correct indication both at local and coupling.
remote.
Check coupling is properly fitted &
alignment is perfectly done.

1 X 80 TPH CFBC Boiler Section 10, Page 8


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Check the operation of dampers and halves of the coupling is as per


ensure that all the flaps are in drawing.
operating condition. Ensure that
Megger value & Earthing is to be
OPEN & CLOSE direction is clearly
ensured before starting the motor.
marked.
Take No load trial of motor & record
Start the fan with minimum speed. its running parameters.
Open the dampers.
Ensure direction of rotation of the
Check vibration, temperature, motor drive is as per drawing before
current, abnormal sound etc. coupling.
Increase speed of the fan up to full Ensure cooling water fittings for
speed, keeping a continuous watch glands & instrument fittings in the
on bearing / casing temperatures, pump are leak free and orientation is
vibration, motor current etc. Shut as per drawing.
down immediately if any abnormality
If bearings are water-cooled check
is observed. Warning of approaching
water supply and its pressure. If
seizure will be given by an increase of
glands are water-cooled and water
load (Amps) on electric motors.
sealed, ensure that water being used
Record all temperature, vibration and conforms to OEM recommendation.
current readings of this initial run-up
Check bearings are lubricated as per
period at 10 minutes interval.
lubrication schedule.
Open suction valves & check for
10.2.10 Pumps sufficient suction pressure & suction
differential pressure across strainer.
Check cleanliness of suction strainer
before installation. Ensure that minimum recirculation,
balancing leak off line valves & cooling
Rotate the shaft by 180 degree of a water supply for pump are locked
multistage pump every week to avoid open.
rusting, sagging & corrosion during
non working condition (Idle). Shaft Ensure all instrument, interlock &
should be hand free. protection are in line & working
satisfactory.
Ensure the flushing of cooling water
supply line to the pump and check its Start pump and keep a constant
pressure. watch on suction pressure, suction
DP, balancing leak pressure discharge
Check the alignment reading of the pressure, bearing temperature,
coupling of pump by three dial gauge vibration, motor current, abnormal
is within 0.04 mm/m in axial & sound etc. Shut down immediately if
transverse directions. The alignment any abnormality is found.
is to be checked both with and
without connection of piping. Record the temperature, vibration,
current, suction pressure, balancing
Check that there is no leakage from leak off pressure etc readings of this
the mechanical seal. In case gland initial run-up period at 10 minutes
seal is fitted, drop by drop leakage interval.
shall be ensured to allow cooling of
gland.
Check the distance between the shaft
ends (DBSE) and gap between both

1 X 80 TPH CFBC Boiler Section 10, Page 9


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

When shutting a cold valve,


For Centrifugal Pumps allowance must be made for
spindle expansion in warm up
These Pumps must only be condition, by easing back a
started with suction valve little from tight shut position.
open and discharge valve in Failure to take this
SHUT condition. As pump precaution shall result in
picks up speed discharge spindle distortion and valve
valve is to be opened failure.
immediately.

For Positive Displacement


Pumps:
Valves and seats must be lapped
These pumps must only be independently using suitable lapping
started with both the suction plates. These should be kept perfectly
and discharge valve OPEN to flat and should be renewed upon if
avoid overloading and damage any signs of wear becoming apparent.
of pump. Lapping abrasives should be used; the
natural porosity of the lapping plates
will retain all that is necessary to
produce a finished surface.
10.2.11 Boiler Valves and Fittings
Lapping Equipment
Lubricate the spindles and adjust
gland packing for free movement. Two large grinding plates are provided
Each valve must be checked for full for lapping the various discs for valves
and free movement of the spindle of all sizes. These plates are used also
between SHUT and OPEN limits. for reconditioning the plates used for
Position indicators must be checked lapping the valves seats. When
for correct indication at local and reconditioning the lapping plates it is
remote. necessary to remove the pilot piece in
order that the plate can be laid flat on
Care must always be exercised not to the grinding plate. The pilot piece is
over tighten valves when shutting. replaced after reconditioning.
Normally the valves are of such design Safety valve heads cannot be lapped
as to allow repeated reconditioning of on the flat grinding plate; a set of
seats by facing or lapping depending special plates for this purpose is
on the seat condition. Do not attempt required.
to lap out deep blemishes. Time can
be saved by refacing, followed by a A complete set of lapping plates to
final lap. suit all sizes of valve seats is to be
maintained by the maintenance team.

1 X 80 TPH CFBC Boiler Section 10, Page 10


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

10.2.12 Water Level Gauges


WARNING :
The water level gauge must be
properly cleaned for easy visibility and
proper illumination to be provided. Boiler and auxiliaries interlocks
must never be bypassed. Any bypass
Wherever a remote reading gauge is for simulation if required shall be
provided, this must be crosschecked done only when the boiler is in
with local gauge for accuracy at stopped condition. Any such event
regular intervals. must be properly recorded with
reasons of doing so and must be
normalized without fail before
10.2.13 Instruments and Control restart.
Equipment

Correct installation and functioning of By simulating the various failure


instrumentation is essential for the conditions and observing the
operation of the boiler. Therefore sequence of action induced, interlocks
availability of all instruments and can be checked for correct setting and
controls must be ensured before functioning.
lighting up.
Ensure that all protection & interlocks
Ensure that calibration of all draught, are checked for proper functioning.
pressure gauges and transmitters
(pressure / temperature / level / flow 10.2.14 Air Pre heater (APH)
/ Position) is completed
Ensure sealing of air heater bottom
Check all control equipment ensuring tube sheet with the supporting
that actuators respond in correct structure to avoid any leakage during
sense. Lubricate according to makers operation.
recommendations.
Ensure complete sealing of air heater
Check limits switches of all actuators tube sheets with expansion bellow/
for proper functioning. casing to avoid any leakage during
Ensure all VFD & Control panels are operation.
tested and calibrated Ensure baffle plates welding and its
Ensure power cylinders are operating supports and distance between baffle
satisfactorily. plates are as per drawing.

Ensure that control system, UPS is Ensure sealing rope or ceramic rope is
working satisfactorily. provided between all connecting
flanges, manholes and bolts are fully
Ensure all control logics are checked tightened.
for proper functioning.
Interlocks 10.2.15 Soot Blowers
Interlocks are provided to safeguard
the boiler and its associated
Ensure the inclination of lance in cold
equipment from possible damage due
condition is as per drawing so that,
to component failure or some
during operation soot blower will be
abnormal occurrence in boiler
perpendicular to the wall in the
operation.
horizontal plane.

1 X 80 TPH CFBC Boiler Section 10, Page 11


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Ensure that the nozzle orientation of Check bolt tightness and tack welding
lance is parallel to the coils to be of tumbling hammers so that they do
cleaned in home position. In rotary not get dislodged during operation.
and short retractable blowers, the
Check alignment with drive and
nozzles position must be aligned with
ensure the free rotation of the rapping
centre line between the two adjacent
shaft.
coils.
Ensure bearings and gear boxes are
Ensure the gap between lance edge
lubricated as per lubrication schedule
and the adjacent water wall tube /
casing is as per drawing. Ensure earth resistance is below one
ohm (1 ohm). Check that independent
Check the condition of sleeves and
earthing has been provided for
rectify as required.
individual TR sets, ESP MCC panels
Ensure that rotary soot blower lance and Rapping panels.
is not under tension due to
Check that mechanical door interlock
intermediate supports.
(Castle Keys) are installed and
Ensure that gland packing of specified sequence is checked before charging
quality is filled in the stuffing box of the ESP.
feed tube and valve stem (poppet
valve)
Ensure proper lubrication of moving 10.3 Long Term Maintenance
parts of the soot blower. Schedule
Ensure proper operation of poppet
valve w.r.t. the limit switches.
Ensure direction of rotation of the
drive is as per drawing before WARNING :
coupling.
Ensure that the poppet valve is set as Do not attempt repair
per the operating pressure. beyond your capabilities.

10.2.16 ESP
1. Steam Drum
Ensure alignment of discharge
electrodes with respect to collecting Operational Checks:
plates to maintain corona gap i.e. T-
gauge passing Check for steam and water leaks from
connections and fittings to the drum.
Ensure that all opening in hopper are
sealed and hopper welding is Prior to Shutdown:
completed in all respect to make it air
Check drums pressure gauges, safety
tight.
valves water level gauges for accuracy &
Ensure that any cutouts made in reliability.
hopper/ ESP for installing the
instruments are properly sealed. Annually:
Special care is to be taken in double
casing areas (for hopper heaters) Inspect the drum internally for evidence
where sealing is to be done in both of the following:-
inside and outside plate. Surface cracks or grooving

1 X 80 TPH CFBC Boiler Section 10, Page 12


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Carryover Mark all adjusted internals for future


removal and reinstallation.
Any sign of oil or other substances
that may have entered the boiler. Inspect and replace manhole gaskets
if damaged or deteriorated.
Signs of pitting
Remove all drum internals and
Sludge or scale accumulation
inspect for wear, corrosion & erosion.
Corrosion
Clean out any debris that has
accumulated inside the drum. Remove
any scale and sediment.
Inspect for a noticeable and smooth
water level. 2 Headers (Manifolds / Header
Inspect for welding condition of hood Inspection Stubs)
plate to drum
Annually:-
Inspect the drum shell between tube
openings (ligaments) for pitting or
Examine internal surfaces for rust,
cracking.
loose deposits, grease. Any trace of
Check for and clean any scale or sludge these must be manually removed.
in the following areas:- High pressure water jet can be used
for this purpose. Water used must be
Primary scrubber elements. of same quality as that of feed water.
Feed water line. Examine the landing on hand holes
and removable inspection caps for
Continuous blow-down line. blemishes that could affect the seal.
Chemical feed line. Inspect header caps / flange joints for
Openings to safety valves must be free signs of leaks or cracking by DP test.
of obstructions, such as mud or scale
Repair the following if any trace of leaks Every Five Years:-
or obstruction has been found during
operation:- Check headers for the Corrosion.
Connections to blow-down Inspect for cracking of welds in the
Connections to water columns and areas listed below using non-
level gauges. destructive testing method:-

Connections to pressure gauges a. Tube to header welds.

Connections to transmitters b. Header shell between tubes


(ligaments).
Inspect the drum internals to ensure that
joints in the following areas are tight:- c. Nozzle to header welds.

Steam cyclone separators. d. Lug and hanger connections.

All baffles. e. Thermo-wells & hand-hole fittings.

Steam scrubbers. f. Longitudinal and circumferential


welds.
Chemical, feed and blow-down lines.
g. Drain connections.
h. Cracking in safety valve opening.

1 X 80 TPH CFBC Boiler Section 10, Page 13


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Take random ultrasonic tube thickness


measurements in critical locations, such
3 Furnace as:-
At furnace headers & tubes.
Operational Checks:-
Around fuel inlet opening.
If possible, inspect the slagging
condition of furnace walls through 4 Super heater
ports. Use extreme caution when
doing so. Always wear tinted goggles Annually:-
or shield to protect eyes from harmful
light rays, slag or ash particles. Do
Externally inspect tubes for signs of:-
not stand directly in front of open
ports. - Overheating (swelling or blistering)
Walk around the exterior and observe - Warping
for any hot spots or gas leaks.
- Misalignment
Prior to Shutdown: - Corrosion
Check for gas leaks at observation ports, - Fouling
as well as manhole and access doors.
Note or mark any areas in which leakage - Erosion
is occurring (for ease of location during If internal deposits are suspected,
shutdown). tube section should be removed for
Annually:- inspection, the determined and
corrected prior to returning to service.
Inspect the tube surfaces for signs of
leaking, corrosion, overheating Inspect supports.
(blistering and bulging), warping, Check attachment to tube welds for
misalignment, pitting, or cracking. cracking or wear.
Inspect furnace side wall at junction Check supports, spacers and seal
of furnace and convection pass for plates for proper location and
cracking due to differential expansion. condition, attachment to tube welds.
Inspect furnace sealing for any Inspect the condition of super heater
leakages. seals where the tubes penetrate the
Check the condition of all refractory. wall panels.

Clean and reset manholes. Inspect Inspect the condition of sleeves


condition of gasket. wherever provided.

Inspect the condition of seal around


doors and openings. 5 Economizer
Inspect the inner surfaces of furnace
wall tubes for deposits and scale. Operational Checks:-
Inspect the condition of fuel feeding
system Listen for any unusual noise around
the economizer section, which may be
indicative of an economizer leak (i.e.
Every 5 years:- hissing)

1 X 80 TPH CFBC Boiler Section 10, Page 14


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Inspect ash hoppers to make sure Inspect the condition of sleeves


they are emptied properly. wherever provided.

Prior to Annual Shutdown:- 6 Hopper

Annually:- Operational Checks:-

Visually inspect economizer to locate Inspect for air leaks or gas leak around
any deposits that may interfere with the hopper.
heat transfer or block gas paths.
Inspect for signs of overheating
After visual inspection, determine if
Review the pressure drop between the
cleaning is necessary. Perform a water
hopper and furnace regularly.
wash directly after shutdown using a
warm alkaline solution with a pH level Changes in this pressure for a given
between 10.5 and 11.0 if required. load condition may indicate for
Care must be taken to dry the restriction problems.
surfaces out be operating the fans.
Annually:-
Externally inspect tubes for signs of:
- Overheating (swelling or blistering) Inspect hopper for accumulation of
ash & other foreign materials.
- Warping
Inspect all internal baffles, tie-bars
- Misalignment and trusses to ensure they are in good
- Corrosion & Erosion condition.

- Fouling Check to ensure that the dampers are


clean and free to move. Lubricate all
If pitting has been found in the steam moving parts with a high temperature
drum take economizer tube sample anti-seize compound.
and inspect them internally for
pitting. Inspect hopper corners and expansion
joints for signs of cracking or tears.
If internal deposits are suspected,
tube sections should be removed for
inspection, the cause determined and 7 Ducts and Dampers
corrected prior to returning to service.
Check & Inspect attachment to tube Operational Checks:-
welds for cracking or wear.
Check around all ducts and flues for
Inspect economizer hopper trusses
and gusset plates for erosion and signs of leakage.
corrosion damage. Check position of fan dampers.
Check supports, spacers and seal Inspect ducts and expansion joints for
plates for proper location and signs of cracking or tears.
condition, attachment to tube welds.
Inspect expansion joints for signs of Annually:-
cracking or tears.
Inspect the condition of seals where Checks for Flue Gas Path
the tubes penetrate the casing.
Gas tightness.

1 X 80 TPH CFBC Boiler Section 10, Page 15


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Disengagement or misalignment of
support hangers and supporting rods. Prior to Annual Shutdown:-
Tightness of the mounting hardware.
Inspect external areas of boiler for
Corrosion and erosion on inner damaged support equipment. By taking a
surfaces. walk around piping systems, and
Excessive deposits of dust and ash. indication of support and supported
equipment, condition can be obtained.
Inspect all refractory surfaces exposed This will aid in the formation of a
to flue gases. shutdown maintenance schedule.
Annually:-
Checks for Duct
Inspect boiler for alignment, noting
Air tightness. any abnormal movement
Disengagement or misalignment of Check condition of header guides and
support hanger and supporting rods. supports to ensure alignment yet
Tears and cracks at corners. permit expansion of tubes without
excessive strain.
Check that main steam piping and
Checks for Air/ Flue gas Dampers connected equipment are properly
aligned and have proper clearance for
Leakage through damper spindle expansion.
bearings and shaft packing glands.
Inspect for sings of support failure
Sticking operation of control dampers such as changes in scale readings on
over the control range. flexible type supports.
Warp age & Overheating. On spring type hangers, check for
Tightness of shutoff dampers & broken spring. Measure and record
Ensure vanes are free to operate. spring lengths.
Lubricate all drives & bearings. Check piping supports and hangers
for disengagement or misalignment.
Examine damper assemblies for wear Verify each hanger is carrying load.
of blades and blade spindles.
Inspect hanger rods for tightness.

8 Expansion Joints Check for corrosion of hanger


components, including tube spacers
and support saddles. If corrosion is
Inspect the internal and external
found, apply a rust inhibitor.
condition of all expansion joints
(especially non-metallic types). Look for broken or cracked hanger
Determine if any unusual wear or rods, pins, lugs, ties or saddles.
pluggage has occurred. Tighten any loose nuts.
Inspect for warp age or cracks. For constant support hangers, inspect
levers and remove any dust deposits
Clean expansion joints and remove
found. Re-pack with greases.
excessive dust collection to allow
proper flexibility and sealing of flue Inspect drum and down-comer
gas. hydraulic shock arrestors for damage.
Check the fluid lever and look for fluid
leakage.
9 Supports

1 X 80 TPH CFBC Boiler Section 10, Page 16


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Check for leakage at valves by audio-


visual inspection, at normal operating
pressure.
Every 2 Years:- Check the clearance of the lifting lever
on the leaking valve. Note and log the
Inspect buck-stays for straightness and severity of any leaky safety valve.
their attachment to furnace walls.
Check drain lines and drip pans are
not plugged.
Every 5 Years:-
When safety valves do operate, note
the opening and resetting pressures
Perform visual and magnetic particle
as accurately as possible. After
inspection of support ties, saddles and
normal operating pressure has
attachment weld.
resumed, check for leakage at valve.
Incorrect setting will require
10 Refractory and Insulation adjustment.
Assess leakage rate from weekly
Operational Checks:- checklist if a noticeable increase has
occurred. Plan for an early shutdown
Inspect around all air and gas to repair. Early shutdowns can reduce
passages for possible air or gas leaks. damage to valves.
Inspect around the boiler casing for
gas leaks or hot spots. Annually:-
Annually:-
Clean internal parts, there should be no
Inspect the condition of the refractory accumulation of rust, scale or other
around fuel feeder opening / throats foreign substances, which will interfere
and surrounding wall area. Repair or with their free operation. Recondition
replace as necessary. valve seats (laps) (if required).

Inspect the condition of refractory.


Repair wherever necessary. Refer Manufacturer O & M Manual for
Detail Overhaul
Inspect the condition of the refractory
around access doors and observation
ports.
12 Boiler Valves
Inspect the refractory seal in all seal
boxes. Operational Checks:-
Inspect the condition or refractory
surface exposed to flue gases like as Make note of any leaky valves and
Furnace zone, Chimney, ash hoppers, prepare a report for type & class of valve,
scrubbing system etc. location, quantity and stock in hand.
Annually:-
11 Safety Valves
Check seating surfaces of body and
disc for flaws or cracks. Re-lap if
Operation Checks:-
repairable.

1 X 80 TPH CFBC Boiler Section 10, Page 17


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Examine the back seat for erosion and service and replace, install new glass
corrosion. Replace if erosion is too if it is discolored, chipped. If for any
deep. reason the glass and cushion gaskets
are removed, replace them.
Inspect the gasket between body and
bonnet for dents, friction flaws,
erosion and corrosion. Repair gasket Every 6 months:-
seat by sand paper or lapping. If a
flaw still exists in the redial direction, Replace mica gasket and glass
discard and replace. assembly.
Check the stem for cracks, bend, Perform a total rebuild as a
flaws deflection, deformation and preventative measure, since ports
erosion of packing contact section. If tend to fail in succession. Follow
cracked, replace. Minor defects can be proper torque tightening procedure.
repaired by sand papering.
Check the stuffing box for erosion and
Annually:-
corrosion. Repair by lapping if flaw is
not too deep.
Check that all connecting piping to
Check, guide sections of body and the column and glass is clear and
disc for erosion and corrosion. unobstructed.
Check bonnet bolts, hinge bolts and Repair any leaks of steam or water
nuts for erosion, corrosion and coming from piping or valves observed
elongation of screw pitch. Replace if during operation.
deformed.
Refer Manufacturer O & M Manual for
Replace gasket and gland packing. Detail Overhaul

13 Water Level Indicators


14 Long Retractable Soot Blowers:
Operational Checks:-
Operational Checks:-
Check to see if the gauge or indicator
is showing the proper water level. On While doing a routine inspection of the
water gauges this can be done by boiler, inspect for steam traps and
opening the drain slightly, then condensate, steam or oil leaks from the
quickly closing the drain to avoid soot blowers.
damage to the mica gaskets. Watch
for the water level to return to its
normal position. Weekly:-
Replace any burnt out indicator During routine soot blowing, check and
lights. verify blowing pressures at individual soot
blowers
Check for water or steam leaks from
ports or from the connections to the
drum. Leakage at the water column or Monthly:-
drain connection will cause a false
water level in the gauge glass. Perform a visual inspection of soot
Inspect glass for discoloration or blower at rest and during normal
fouling. If glass appears dirty (fouled), operation to check for proper
blow down to clean it, remove it from extension and retraction.

1 X 80 TPH CFBC Boiler Section 10, Page 18


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Check for proper direction of rotation. and inspect internals for corrosion or
damage.
Check the extended or blowing
position of the nozzle or element to Ensure the valve spring, spring
ensure that it will give good cleaning retainer, yoke and trigger are intact,
results without damaging the walls & and that the lance tube is not riding
lance, which it is, designed to clean. on the wall box seal.
Check the start and finish-blowing Check for Lubrication of rotating
arcs on corner mounted blowers and parts.
those, which are mounted adjacent to
Test forward and reverse limit switch
division walls etc., to ensure that the
actuator for proper spring action and
blowing medium is being directed in
check for broken or distorted parts.
the proper area for best cleaning
results and to avoid damaging tubes. Check auxiliary lance and feed tube
support for the brackets, roller, fork
Check the wall-box sleeve alignment
lever etc.
to boiler wall to ensure it is
perpendicular (plumb) with the Refer Manufacturer O & M Manual for
vertical place of the wall in all Detail Overhaul
directions.
Check for condensate or slag in wall- 15 Rotary Soot Blowers:
boxes. Condensate in a wall-box can
indicate a leaky puppet valve, while Operational Checks:-
slag can reveal the need for seal air.
While doing a routine inspection of the
Ensure that the wall-box seal plate is boiler, inspect for steam traps and
free to float. condensate, steam or oil leaks from the
Inspect wall-box and sleeve for soot blowers.
damage. A damaged wall-box and
sleeve can result in deteriorated wall- Weekly:-
box and damaged boiler wall
refractory or insulation. This in turn During routine soot blowing, check and
can result in support problems and verify blowing pressures at individual soot
casing leaks. blowers.
Ensure the proper operation of all
Monthly:-
moving and mechanical part.
Check the condition of the expand Perform a visual inspection of blowers
cable. at rest and during normal operation,
to ensure proper rotation and re-set.
Inspect tubes and tube sleeves in the
vicinity of soot blower paths for Check for proper direction of rotation.
possible metal loss due to erosion,
Check the extended or blowing
steam cutting, rubbing of soot-blowers
position of the nozzle or element to
or corrosion.
ensure that it will give good cleaning
Check condition of the feed tube and results without damaging the walls &
valve stem packing. Replace if hard lance, which it is, designed to clean.
and dry. Add more packing rings to
Check the start and finish blowing
the feed tube gland as necessary. Do
arcs of blowers to ensure that blowing
not over tighten.
medium is being directed in the
Check puppet valve condition. If the proper area for best cleaning results
valve shows signs of leakage, re-lap it and to avoid damaging tubes.

1 X 80 TPH CFBC Boiler Section 10, Page 19


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Check the wall-box sleeve alignment Inspect bearing lubrication and check
to boiler wall to ensure it is for proper oil level / grease. Lubricate
perpendicular (plumb) with the drive assembly linkages
vertical plane of the wall in all
If ring-oiled, check for free revolution
directions. Ensure that the wall-box
and adequately distributed oil.
seal plate is free to float.
Check for loose material, which may
Check for condensate or slag in wall-
get sucked into the fan.
boxes. Condensate in a wall-box can
indicate a leaky puppet valve, while Check bearing temperatures. If hot,
slag can reveal the need for seal air. determine cause and remedy the
situation.
Ensure that the wall-box seal plate is
free to float. Ensure a flow of water is getting to the
bearings and water outlet temperature
Inspect wall-box and sleeve for
is not excessively warm (if water
damage. A damaged wall-box sleeve
cooling is provided)
can result in deteriorated wall boxes
and damaged boiler wall refractory or Ensure that fan shaft seals and
insulation. This in turn can result in bearing seal are intact and functional.
support problems and casing leaks.
Feel the unusual motor or fan noises,
Ensure the proper operation of all check vibration and take vibration
moving and mechanical parts. readings.
Inspect for main bearing condition
Maintain control room records / log
and drive pins if worn-out replaced
book for bearing temperature,
the same.
vibration, oil usage, damper operation
Inspect tubes and tube sleeves in the and indication etc. on Daily / shift
vicinity of soot blower paths for basis.
possible metal loss due to erosion,
steam cutting, rubbing of soot blowers
or corrosion. Annually:-
Check puppet valve condition. If the Check motor & fan bearing condition
valve shows signs of leakage, re-lap it and change bearing oil / grease.
and inspect internals for corrosion or Analyze a sample from each bearing.
damage.
Flush cooling water jackets it
Ensure the valve spring, spring provided.
retainer, yoke and trigger are intact,
and that the portion or the trigger the Check motor-fan alignment and its
makes contact with the valve stem coupling
does not show excessive wear. Inspect Fan shaft seals, Fan casing,
Check for Lubrication of rotating cone and ducts, Impeller for wear and
parts. corrosion.
Refer Manufacturer O & M Manual for Check foundation for cracking,
Detail Overhaul sagging or any other deterioration to
concrete or steel works.

16 Fans Lubricate the linkage connections of


dampers.
Operational Checks:- Check the static and dynamic
balancing of the fan.

1 X 80 TPH CFBC Boiler Section 10, Page 20


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

Check the fan shaft for any cracks by Inspect rollers / balls for flat spots,
D.P. Test, Ultrasonic testing etc. pitting and irregular surface & Check
bearing hold-down bolts for tightness.

Fan Housing Apply new sealant, reassemble and re-


torque bolts.
Check for signs of wear or corrosion, Inspect bearing sleeve and lock nut
damage. with washer for wear, tear and
Check tightness of foundation bolts. looseness.

Visually inspect for cracks Inspect oil seals, if found damaged


then replace.
Check all instrumentation operations.
Impeller
Check for abrasive wears on blades, Lube Oil Sets
casing, and cone. Take oil samples from all units.
Check that the impeller is completely Clean unit, replace oil and filters.
clean, and that the blades and the
shroud are free of any build up. Check pressure and flow settings.

Check that the impeller is tight on the Checks all hoses and pipes for leaks.
shaft. Check instrumentation and standby
Check that the shaft is straight and pump operation.
crack free.
Coupling
Check for mechanical damage
indicating an object has entered the Clean and inspect for internal wear.
impeller during operation. Renew all worn sealing devices.
Visually inspect for weld cracks, if in Renew all lubricants.
doubt, perform a liquid dye penetrate
test. Re-torque all bolts.
Check for proper gap setting.
Inlet Cone Check alignment and realign if
Check for signs of wear or corrosion, required.
damage.
Check clearance and fit up, ensure it 17 Drag chain feeders
is correct.
During every shut down of the boiler,
Bearings / Plummer Block drag chain feeders chain to be checked for
looseness and to be tightened. Worn out
Clean all bearings and Plummer plates, chain links to be replaced.
blocks. Check clearance between Alignment of the motor with the gear
rollers / balls and the inside diameter boxes to be checked. Drive side chain to
of the bearing outer ring. Check be cleaned and lubricated with fresh
bearing gaps in housing. grease. Non drive end side sprocket self
Inspect the bearing seals. Take drain cleaning plate bolts to be tightened.
oil, grease sample. Inspection of inner side liner to be done. If
any abnormality found, it is to be
rectified. All the bearings to be cleaned

1 X 80 TPH CFBC Boiler Section 10, Page 21


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

thoroughly, grease should be completely seal blower line valves should not be
removed and filled with fresh grease. disturbed.
Return leg wind box drain should be
18 CFBC Systems opened and checked for any
accumulation of ash inside. If any
material is present, it is to be cleaned and
Wall seal Blowers the drain to be closed again.
Wall seal blowers belt tightness should be Stripper Cooler
checked during regular operation of the
unit as well as during shut down time. If During every shutdown, stripper cooler
any of the belts found worn out, all the inside material must be cleaned.
belts should be replaced simultaneously. Solid transfer line should be cleaned
Alignment of belt should be checked and completely and the air slide plates in the
proper tightness of the belt to be solid transfer line to be inspected, if any
maintained. deflection found, it is to be adjusted.
Suction filter cleaning to be carried out If any bed ash is present inside, it is to be
periodically and during each shutdown. cleaned completely.
Tightening of the foundation bolts and Passages between section to section
bolts of motor and blower should be should to be completely cleaned.
checked. Discharge NRV should be
periodically checked for proper Wind box of stripper cooler to be checked
functioning. Safety valve setting should for any accumulation of bed ash inside.
be checked periodically
Air line in stripper cooler to be cleaned
Boiler Bed and Loop Seal from the nipple provided at the bottom.

During every long shutdown of the boiler, Rotary air lock passage to be checked for
the boiler bed should be completely any foreign material and it is to be
cleaned; all the bed nozzles are to be cleaned.
cleaned with compressed air. DP study to Solid transfer line to be inspected for
be carried out to compare the values with intactness of refractory inside. If
the initial values obtained during refractory inside is loose or if it has got
commissioning of boiler. If required removed, the same should be applied.
further cleaning to be carried out to
obtain the DP reading nearer to the Physically check the flow of air through
original values. air slides of solid transfer line by opening
the mobilizing air. In case any obstruction
The bed ash in lift and down legs is to be is observed, same is to be cleaned.
cleaned completely, after completion of
cleaning the nozzles are to be inspected. Wind box of solid transfer line to be
Wall seal blower to be operated for about checked for any accumulation of bed ash,
an hour and nozzles to be checked for if any accumulation is found, it is to be
proper air flow through the holes. If any cleared using the plug provided at the
of the nozzles are found chocked, the bottom.
same should be cleaned. After completion
Bed Pressure Transmitters
of this checking, the wall seal blower to be
stopped and bed ash to be filled up to the Bed pressure transmitters are to be
spillover portion level in lift and down leg. checked for zero indication when there is
After filling bed ash the wall seal blower no bed material in the bed and fans are in
to be run again to check fluidization of stop condition. If there is any change
material inside. The settings of the wall from zero indication the pocket mouth
should be checked for any possibility of

1 X 80 TPH CFBC Boiler Section 10, Page 22


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C10
Rev 00 01/ 01.07.13
Isgec Heavy Engineering Ltd.

chocking and if any chocking is there, it


is to be cleaned.
Bed pressure transmitters have to read
pressure of bed material in fluidizing
furnace. In case a conventional impulse
line is used it will get choked with bed
material within no time. To avoid this, a
purging air is provided in the impulse line
with a constant air flow to prevent the
back flow of bed material in the impulse
line. The air flow thru this purge line is
set when the boiler is not in operation
and there is no bed material inside and
no fans are running. The air must be
sufficient that it prevents back flow. This
will be adjusted by the commissioning
engineer. After adjustment, the flow
control valve/ rotameter must be locked
and no further changes are allowed. Now
the transmitter will start showing some
reading, depending on length of line and
flow thru it. This value is to be made
ZERO with the help of HART
communicator. The indicated values
before zero setting should be recorded for
future reference. Now the bed
transmitters are ready for putting into
service

1 X 80 TPH CFBC Boiler Section 10, Page 23


M/s. PT Tereos FKS, Indonesia

You might also like