You are on page 1of 3

Comm/ JB No 0993/C3

Rev 00 01/ 28.06.13


Isgec Heavy Engineering Ltd

SECTION 3 – HYDRAULIC TEST


3.1 Purpose These isolated instruments or equipments
must be vented to atmosphere to prevent
Hydraulic test in a boiler is carried out to any built up of pressure.
check leakages of pressure parts and Calibrated pressure gauges are required to
prove the strength of the boiler at a be connected on the boiler steam drum.
pressure greater than the working Dial pressure gauge used in testing shall
pressure of the boiler, and is carried out preferably have dials graduated over their
at following stages:- entire range of about double the intended
On completion of erection. maximum test pressure, but in no case
the range shall be less than 1.5 times of
On completion of repair of boiler test pressure. The Calibrated pressure
pressure parts. gauges size must be greater than 150 mm.
On completion of annual overhaul. Ensure the availability of the sufficient
At the request of statutory authority quantity of DM water as per the
to fulfill the statutory requirement. requirement for hydro test (approximately
3 times of boiler water holding capacity).

3.2 Preparation for Test Check boiler filling pump/boiler feed


pump is ready in all respect for boiler
Check that all tools, equipment and water filling.
loose items have been removed from
drums and manifolds. Check all hanger tie rods, pipe supports
and locking arrangement are placed as per
Check that all NDT activities and Post drawing.
weld heat treatment wherever
applicable after Boiler pressure parts Check that constant load hangers, spring
welding have been completed. loaded hangers are locked in position with
locking pin. Check that all temporary
Check that all drums manholes and supports are removed.
manifolds inspection caps are tightly
sealed. Hydraulic test is to be carried out up to
the root valves of mountings.
Close all stop valves, drain valves and
blow down valves. Wherever double Check that Proper lighting, approach
isolation valves are provided close the platforms and communication systems are
second valve. ready.

Remove all safety valves and fit blank Pressure Parts must not be covered with
flanges for flanged type Safety valves. insulation for first hydro test.
For Welded safety valves, hydro test Temporary water filling connection with
plugs are to be installed ensuring that proper supports must be complete.
correct plug is fitted as per
identification. For test taken at Two sets of drum and other important
working pressure hydraulic plugs gaskets must be kept ready as spare.
need not be provided. Check all buck stays and seismic supports
Open all air release valves. are installed as per drawing.

Isolate all the instruments except the Ensure that all attachment welding with
test pressure gauge. pressure parts is complete including fin to
tube and anchors to pressure parts.

1 X 80 TPH CFBC Boiler Section 3, Page 1


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C3
Rev 00 01/ 28.06.13
Isgec Heavy Engineering Ltd

Close air vents of economizer, water wall


top header, drum, super heater in
sequence, when water starts coming out
Hydraulic test should be carried freely without air.
out on boiler in cold condition.
Sudden changes in temperature When boiler is full of water and all air
caused by filling a hot boiler with vents have been closed, inspect boiler at
relatively cool water will cause full water level condition for any leak. If
thermal stresses, leading to leak observed- stop the test, repair it. If no
serious damage. The leak found proceed for pressure rising to
temperature of the water used as 50 % of working pressure. Observe the
a medium of pressure testing rate of pressure drop by stopping the
shall not be less than 20 0C and pump; pressure drop rate should not be
not greater than 50 0C, 40 0C is appreciable. In case pressure drop is high
an ideal. check and correct. Raise pressure slowly
to desired hydro test pressure. Rate of
pressure increase must not exceed 50 psig
(3.5 kg /cm2g) per minute. Test pressure
should never exceed by more than 6 % of
required test pressure.
NOTE:
Hot condition : Furnace temperature
more than 200deg C
Warm condition: Furnace temperature
60 deg to 200 deg C. When filling the boiler with the
feed pump ensure that the
Cold condition: Furnace temperature discharge pressure does not fall
less than 60 deg C. below its normal operating
pressure. This is required to
avoid overloading of pump. This
can be done by throttling the
3.3 Procedure of Hydro-test flow at the discharge stop valve.

Start filling boiler by means of boiler Maintain boiler feed water pH


filling pump from lowest point between 9.5 to 10.5 (10.5 to 11
possible i.e. through economizer if boiler is to be preserved),
bottom header drain or water wall water quality as per contract &
drain. Maintain boiler feed water pH Oxygen scavenger to 200 ppm
between 9.5 to 10.5 and oxygen
scavenger to 200 ppm. If the boiler is Do not weld any pressure parts
required to be idle after the hydrotest or attachments to pressure parts
(There is a long gap between hydrotest with water inside the tubes.
and boiler firing), it is suggested to
preserve the boiler. In that case the
pH of the DM water to be maintained
For a newly erected boiler, the test
between 10.5 to 11.0 and Oxygen
pressure shall be maintained for
scavenger to 200 ppm.
maximum 30 minutes at 1.5 times
As boiler fills, operate all blow down maximum allowable working pressure of
and drain valves to prove them clear. drum / design pressure of drum (201
Kg/Cm2(g) for this boiler) and then
pressure shall be reduced to maximum

1 X 80 TPH CFBC Boiler Section 3, Page 2


M/s. PT Tereos FKS, Indonesia
Comm/ JB No 0993/C3
Rev 00 01/ 28.06.13
Isgec Heavy Engineering Ltd

allowable working pressure and If Hydro test is found satisfactory and


maintained at sufficient time to permit Boiler is required to be preserved, then
close visual inspection for leakage of slowly depressurize the boiler by opening
pressure parts. Carry out a thorough a suitable vent till the pressure reduces to
examination on all boiler parts under about 10 kg/cm2. Close all drains and
pressure, mark locations of leaks / vents and maintain the pressure of 3 to 10
sweats. The pressure should be kg/cm2 during the idle period.
monitored at the boiler drum
elevation.
3.4 Action after the Test
NOTE: In case of welded safety valves, remove
Boiler must be hydro tested to 1.5
hydro test plug and reinstall the normal
Times maximum allowable working
Safety valve seat after depressurizing and
pressure (design pressure of the
draining the boiler. In case of flanged
drum) only for first time after
safety valves, refit the valves.
completion of erection (As per
Relevant Code requirement). All Reinstate instruments that have been
subsequent hydro tests must be sealed off for the test.
done at normal working pressure at
The drained water should never be reused.
Superheater outlet to avoid any
undue stresses on boiler unless If Boiler is under preservation, check the
there is any specific requirement level of oxygen scavenger and water pH
given by statutory/ inspection weekly. Oxygen scavenger level should not
authority. fall below 100 ppm and pH should not fall
below 10.5. When pressure falls to about 3
Cyclic Hydraulic test is adopted to kg/cm2, again raise the boiler pressure to
detect weak joints which do not get 10 Kg/Cm2 and maintain this throughout
exposed in normal hydraulic test. the idle period. If pH or oxygen scavenger
After the pressure is raised to hydro level falls below the desired level, boosting
test pressure, reduce the pressure of chemical may be done and checked. If it
below working pressure to about 75% is not possible to boost the levels to
of working pressure. Again the desired value, boiler must be fully drained
pressure is raised to the test pressure. and the process shall be repeated using
This is repeated for three times. A fresh water having the desired chemical
thorough inspection is done after levels.
three cycles to detect any leaks.
Reduce the pressure gradually by
crack opening the drain valves/ vent
valves till the boiler reaches 5 Kg/Cm2
and then open all the vent valves. Do Boiler should always be filled
with treated water as specified
not keep any drain open below 5
Kg/Cm2 pressure till all vents are in Contract. Filling the boiler
opened. Further drain the boiler to with untreated water will cause
sufficiently low level to allow leaks / internal damage, corrosion to
sweats to be rectified. the pressure parts.

Refill and pressurize the boiler as per


the procedure out lined above. Re-
check for leaks and repeat as often as
is necessary until all leaks are
stopped.

1 X 80 TPH CFBC Boiler Section 3, Page 3


M/s. PT Tereos FKS, Indonesia

You might also like