Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21 7
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins
103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21 6
103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22 7
(Selected Borrow Material)
205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22 6
(Common Material)
205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7
bridge
205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22 4
201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins
103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21
103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)
205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)
205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge
205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins
103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21
103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)
205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)
205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge
205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins
103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21
103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)
205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)
205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge
205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins
103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21
103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)
205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)
205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge
205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins
103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21
103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)
205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)
205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge
205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22
206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22 6
GRS
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21 1
Electrical Manhole
206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22 5
Integral Bridge
103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22 12
206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22 3
(include waterstop at construction joint)
205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22 2
Integral Bridge
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21 6
Earth Retaining System (GRS method), including Crushed
Stone layer (200mm)
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21 5
for, Integral Bridge, Including Crushed Stone Layer
(200mm)
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22 10
for Retaining Wall, including compacted crushed stone
layer (200mm)
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22 7
Assemblies
206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole
206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge
103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22
206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)
205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including Crushed
Stone layer (200mm)
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including Crushed Stone Layer
(200mm)
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies
206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole
206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge
103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22
206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)
205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including Crushed
Stone layer (200mm)
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including Crushed Stone Layer
(200mm)
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies
206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole
206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge
103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22
206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)
205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including Crushed
Stone layer (200mm)
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including Crushed Stone Layer
(200mm)
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies
206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole
206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge
103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22
206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)
205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including Crushed
Stone layer (200mm)
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including Crushed Stone Layer
(200mm)
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies
206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole
206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge
103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22
206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)
205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including Crushed
Stone layer (200mm)
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including Crushed Stone Layer
(200mm)
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies
Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2
Legend: Notes /
BidDocs Schedule Remarks
Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Legend:
BidDocs Schedule
Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Legend:
BidDocs Schedule
Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Legend:
BidDocs Schedule
Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Legend:
BidDocs Schedule
Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22
Legend:
BidDocs Schedule
[Before - Work Inspection Request, Key Plan, Blowup Plan; Additonal Requirements for
7 Submission of Work Inspection Request Dated on Sept. 10, 2021 - Section Plan based on
approved shopdrawing, Computation with Illustration, Pgrogress Photos(Before &
CHANGES IN WIR REQUIREMENTS After)]
8 MATERIAL APPROVAL PVC pipes "CROWN" - Waiting for the Approval
Cast Iron Cover "JAMAN" - Awaiting for Comments of POSCO & GCR
Curing Compound "SPAKTON" - Awaiting for Comments of POSCO & GCR
Rubber Water Stop "SPAKTON" - Awaiting for comments of POSCO & GCR
Forming Anchor "POWER STEEL" - Awaiting for Comments of POSCO & GCR
9 Bar Bending Schedule Approval of BBS, Formworks, & Concrete Spacer
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 -1453
201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4
103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 54 Sat, 06-Nov-21 Fri, 07-Jan-22 8
(Selected Borrow Material)
205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22 6
(Common Material)
205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7
bridge
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22 7
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22 4
206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Sat, 16-Apr-22 6
GRS
206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21 1
Electrical Manhole
206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22 5
Integral Bridge
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Tue, 21-Jun-22 12
206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22 3
(include waterstop at construction joint)
205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Thu, 14-Apr-22 2
Integral Bridge
206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21 6
Earth Retaining System (GRS method), including Crushed
Stone layer (200mm)
206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21 5
for, Integral Bridge, Including Crushed Stone Layer
(200mm)
206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22 10
for Retaining Wall, including compacted crushed stone
layer (200mm)
206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22 7
Assemblies
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2
Legend:
Notes / Remarks
BidDocs Schedule -Slack Time
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule