You are on page 1of 22

Northern Builders

Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule Offset Start January February March April


Duration
Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Tue, 07-Sep-21 Tue, 28-Sep-21 7

201(4)d Backfill 89 Fri, 05-Nov-21 Wed, 09-Mar-22 9

104(1) Subgrade Preparation (Common Material) 24 Mon, 21-Mar-22 Thu, 21-Apr-22 13

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21 7
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21 6

103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22 7
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22 6
(Common Material)

205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7
bridge

205(2) Geogrid, 37.5KN/m 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7

205(3) Geogrid, 75.0KN/m 108 Tue, 12-Oct-21 Thu, 10-Mar-22 7

205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22 4

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Fri, 29-Jul-22 15
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule April May


Bill No. Item Description Duration Start End Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 24 Mon, 21-Mar-22 Thu, 21-Apr-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21

103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge

205(2) Geogrid, 37.5KN/m 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Fri, 29-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


May June July August September
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 24 Mon, 21-Mar-22 Thu, 21-Apr-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21

103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge

205(2) Geogrid, 37.5KN/m 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Fri, 29-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


September October November December January
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 24 Mon, 21-Mar-22 Thu, 21-Apr-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21

103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge

205(2) Geogrid, 37.5KN/m 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Fri, 29-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


January February March April May
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 24 Mon, 21-Mar-22 Thu, 21-Apr-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21

103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge

205(2) Geogrid, 37.5KN/m 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Fri, 29-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


May June July
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 24 Mon, 21-Mar-22 Thu, 21-Apr-22

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 49 Tue, 07-Sep-21 Fri, 12-Nov-21
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 70 Fri, 27-Aug-21 Thu, 02-Dec-21

103(1)c Embankment for At grade section for Depot 74 Mon, 11-Oct-21 Thu, 20-Jan-22
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 118 Wed, 06-Oct-21 Fri, 18-Mar-22
(Common Material)

205(1) Cement Mixed Approach Block for internal 108 Wed, 06-Oct-21 Fri, 04-Mar-22
bridge

205(2) Geogrid, 37.5KN/m 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 20 Mon, 04-Jul-22 Fri, 29-Jul-22
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule Offset Start January February March April


Duration
Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 195 Sat, 25-Sep-21 Sat, 25-Jun-22 5
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22 6
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21 1
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22 5
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22 12

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22 3
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22 2
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21 6
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21 5
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22 10
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22 7
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule April May


Bill No. Item Description Duration Start End Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 195 Sat, 25-Sep-21 Sat, 25-Jun-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


May June July August September
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 195 Sat, 25-Sep-21 Sat, 25-Jun-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


September October November December January
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 195 Sat, 25-Sep-21 Sat, 25-Jun-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


January February March April May
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 195 Sat, 25-Sep-21 Sat, 25-Jun-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


May June July
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 195 Sat, 25-Sep-21 Sat, 25-Jun-22
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 115 Mon, 08-Nov-21 Sat, 16-Apr-22
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 10-May-21 Tue, 11-May-21
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 162 Sat, 06-Nov-21 Tue, 21-Jun-22
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 15 Wed, 01-Jun-22 Tue, 21-Jun-22

206(6)i Structural Concrete, 40 MPa for Retaining Wall 114 Mon, 29-Nov-21 Thu, 05-May-22
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 137 Wed, 06-Oct-21 Thu, 14-Apr-22
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 12 Mon, 27-Sep-21 Tue, 12-Oct-21
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 25 Tue, 01-Feb-22 Mon, 07-Mar-22
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Wed, 10-Nov-21 Wed, 10-Nov-21
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 120 Mon, 08-Nov-21 Sat, 23-Apr-22
Assemblies

Miscellaneous Structures (Part E) 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 53 Wed, 19-Jan-22 Sat, 02-Apr-22


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule Offset Start January February March April


Duration
Bill No. Item Description Duration Start End Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
Structural Earth Works Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2

RIVER BANK PROTECTION WORKS FOR -3


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend: Notes /
BidDocs Schedule Remarks

Revised Schedule Revised Schedule


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule April May


Bill No. Item Description Duration Start End Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule

Revised Schedule Revised Schedule


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


May June July August September
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule

Revised Schedule Revised Schedule


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


September October November December January
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule

Revised Schedule Revised Schedule


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


January February March April May
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
Structural Earth Works Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule

Revised Schedule Revised Schedule


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

Revised Detailed Schedule


May June July
Bill No. Item Description Duration Start End Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
Structural Earth Works Works 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR


DOLORES 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule

Revised Schedule Revised Schedule


Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Building Works (Package CP N-05)
Sub-Con: Northern Builders
Project Star May 05, 2021 (Wednesday)
Project Fini Jul 29, 2022 (Friday)
No. of Mont 14

No. Reason of Delays Remarks


[March 2, 2021 - Announced Schedule for Turnover of Area Zone 2; June 30, 2021 - EEI
1 Submits an Inspection Request for Clearing & Grubbing @ Site 1; June 9, 2021 - POSCO ,
TURNOVER OF AREA sent an email regarding on EEI handovered area]
2 Temporary Control Points Validation / Bench Marks near in Site Location (April 6, 2021).
CONTROL POINTS VALIDATION Control Points are under validation of GCR & POSCO due to some errors
3 Note: May 19, 2021 - 2:14pm, Posco Sent an Email Regarding on NSCR-PSC-NBS-N05-
REVISION OF PLANS & WORKING DRAWINGS (Rev. 29 - Rev. 31) CRKDPT-TRL-W-000010_Issuance of IFC Drawing Rev. 31 (Set 1 & 2)
4 REQUIREMENTS FOR MANPOWER
5 Covid 19 Pandemic Cases (from Month of April to May, & Month of August) : Affected
HEALTH ISSUES by Covid - from Management to Workers on Site
6 WEATHER CONDITION (Heavy Rainfall that causes Work Stoppage - Aug. 18-19, 21,23, & Sept. 1, 2021)

[Before - Work Inspection Request, Key Plan, Blowup Plan; Additonal Requirements for
7 Submission of Work Inspection Request Dated on Sept. 10, 2021 - Section Plan based on
approved shopdrawing, Computation with Illustration, Pgrogress Photos(Before &
CHANGES IN WIR REQUIREMENTS After)]
8 MATERIAL APPROVAL PVC pipes "CROWN" - Waiting for the Approval
Cast Iron Cover "JAMAN" - Awaiting for Comments of POSCO & GCR
Curing Compound "SPAKTON" - Awaiting for Comments of POSCO & GCR
Rubber Water Stop "SPAKTON" - Awaiting for comments of POSCO & GCR
Forming Anchor "POWER STEEL" - Awaiting for Comments of POSCO & GCR
9 Bar Bending Schedule Approval of BBS, Formworks, & Concrete Spacer
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start


Duration
Bill No. Item Description Duration Start End Duration Start End
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 -1453

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 -1453

201(3)a Structures Excavation for Geosynthethic Reinforced Soil 41 Mon, 01-Feb-21 Sat, 13-Mar-21 150 Tue, 07-Sep-21 Mon, 28-Feb-22 7
Structure (GRS), Integral Bridge, Retaining Wall, Electrical
Manholes and Detention Basins

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 119 Mon, 21-Jun-21 Fri, 05-Nov-21 4

103(1)c Embankment for At grade section for Depot 74 Mon, 15-Mar-21 Thu, 27-May-21 54 Sat, 06-Nov-21 Fri, 07-Jan-22 8
(Selected Borrow Material)

205(7) Embankment for GRS and Integral Bridge 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22 6
(Common Material)

205(1) Cement Mixed Approach Block for internal 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7
bridge

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22 7

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22 7

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22 4

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22 15
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start


Duration
Bill No. Item Description Duration Start End Duration Start End
Structura Works (Part D)
207(1)c Reinforcing Steel, Grade 60 for Structure in 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22 5
Depot

206(6)a Structural Cast in Situ Concrete, 40 MPa for 24 Mon, 03-May-21 Wed, 26-May-21 115 Mon, 08-Nov-21 Sat, 16-Apr-22 6
GRS

206(6)b Structural Cast in Situ Concrete, 28 MPa for 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21 1
Electrical Manhole

206(6)g Structural Cast in Situ Concrete, 40 MPa for 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22 5
Integral Bridge

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 15 Wed, 01-Jun-22 Tue, 21-Jun-22 12

206(6)i Structural Concrete, 40 MPa for Retaining Wall 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22 3
(include waterstop at construction joint)

205(6) Forming Anchor & Stopper for GSR and 156 Mon, 02-Aug-21 Tue, 04-Jan-22 137 Wed, 06-Oct-21 Thu, 14-Apr-22 2
Integral Bridge

206(10)c Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21 6
Earth Retaining System (GRS method), including  Crushed
Stone layer (200mm)

206(10)f Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21 5
for, Integral Bridge, Including  Crushed Stone Layer
(200mm)  

206(10)i Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22 10
for Retaining Wall, including compacted crushed stone
layer (200mm)

206(10)j Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21 7
Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)

209(5) Miscellaneous Steelwork - Expansion Joint 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22 7
Assemblies

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 4

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 5
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start


Duration
Bill No. Item Description Duration Start End Duration Start End
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 3

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 2

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 2

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 2

RIVER BANK PROTECTION WORKS FOR -3


DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
RIVER
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
Notes / Remarks
BidDocs Schedule -Slack Time

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule