You are on page 1of 22

Northern Builders

Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 1 Week 2 Week 3 Week 4 Week 12 Week 23 Week 34 Week 45 Week 16 Week 27 Week 38 Week 49
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 16 Tue, 07-Sep-21 Tue, 28-Sep-21 218

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22 255

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22 398

Structures Excavation for Geosynthethic Reinforced Soil


Structure (GRS), Integral Bridge, Retaining Wall, Electrical 218
201(3)a Manholes and Detention Basins 41 Mon, 01-Feb-21 Sat, 13-Mar-21 49 Tue, 07-Sep-21 Fri, 12-Nov-21

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21 186

Embankment for At grade section for Depot


(Selected Borrow Material) 210
103(1)c 74 Mon, 15-Mar-21 Thu, 27-May-21 74 Mon, 11-Oct-21 Thu, 20-Jan-22

Embankment for GRS and Integral Bridge


(Common Material) 177
205(7) 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22

Cement Mixed Approach Block for internal bridge


205
205(1) 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22 219

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22 211

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22 115

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22 441

Structura Works (Part D)


Reinforcing Steel, Grade 60 for Structure in Depot
166
207(1)c 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22

Structural Cast in Situ Concrete, 40 MPa for GRS


189
206(6)a 24 Mon, 03-May-21 Wed, 26-May-21 -147 Mon, 08-Nov-21 Fri, 16-Apr-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule April May


Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 110 Week 211 Week 312 Week 413 Week 114 Week 215 Week 316
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22

Structures Excavation for Geosynthethic Reinforced Soil


Structure (GRS), Integral Bridge, Retaining Wall, Electrical
201(3)a Manholes and Detention Basins 41 Mon, 01-Feb-21 Sat, 13-Mar-21 49 Tue, 07-Sep-21 Fri, 12-Nov-21

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21

Embankment for At grade section for Depot


(Selected Borrow Material)
103(1)c 74 Mon, 15-Mar-21 Thu, 27-May-21 74 Mon, 11-Oct-21 Thu, 20-Jan-22

Embankment for GRS and Integral Bridge


(Common Material)
205(7) 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22

Cement Mixed Approach Block for internal bridge


205(1) 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Structura Works (Part D)


Reinforcing Steel, Grade 60 for Structure in Depot
207(1)c 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22

Structural Cast in Situ Concrete, 40 MPa for GRS


206(6)a 24 Mon, 03-May-21 Wed, 26-May-21 -147 Mon, 08-Nov-21 Fri, 16-Apr-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July August
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 417 Week 118 Week 219 Week 320 Week 421 Week 122 Week 223 Week 324 Week 425 Week 126 Week 227 Week 328
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22

Structures Excavation for Geosynthethic Reinforced Soil


Structure (GRS), Integral Bridge, Retaining Wall, Electrical
201(3)a Manholes and Detention Basins 41 Mon, 01-Feb-21 Sat, 13-Mar-21 49 Tue, 07-Sep-21 Fri, 12-Nov-21

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21

Embankment for At grade section for Depot


(Selected Borrow Material)
103(1)c 74 Mon, 15-Mar-21 Thu, 27-May-21 74 Mon, 11-Oct-21 Thu, 20-Jan-22

Embankment for GRS and Integral Bridge


(Common Material)
205(7) 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22

Cement Mixed Approach Block for internal bridge


205(1) 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Structura Works (Part D)


Reinforcing Steel, Grade 60 for Structure in Depot
207(1)c 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22

Structural Cast in Situ Concrete, 40 MPa for GRS


206(6)a 24 Mon, 03-May-21 Wed, 26-May-21 -147 Mon, 08-Nov-21 Fri, 16-Apr-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


August September October November
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 429 Week 130 Week 231 Week 332 Week 433 Week 134 Week 235 Week 336 Week 437 Week 138 Week 239 Week 340
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22

Structures Excavation for Geosynthethic Reinforced Soil


Structure (GRS), Integral Bridge, Retaining Wall, Electrical
201(3)a Manholes and Detention Basins 41 Mon, 01-Feb-21 Sat, 13-Mar-21 49 Tue, 07-Sep-21 Fri, 12-Nov-21

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21

Embankment for At grade section for Depot


(Selected Borrow Material)
103(1)c 74 Mon, 15-Mar-21 Thu, 27-May-21 74 Mon, 11-Oct-21 Thu, 20-Jan-22

Embankment for GRS and Integral Bridge


(Common Material)
205(7) 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22

Cement Mixed Approach Block for internal bridge


205(1) 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Structura Works (Part D)


Reinforcing Steel, Grade 60 for Structure in Depot
207(1)c 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22

Structural Cast in Situ Concrete, 40 MPa for GRS


206(6)a 24 Mon, 03-May-21 Wed, 26-May-21 -147 Mon, 08-Nov-21 Fri, 16-Apr-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


November December January February
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 441 Week 142 Week 243 Week 344 Week 445 Week 146 Week 247 Week 348 Week 449 Week 150 Week 251 Week 352
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22

Structures Excavation for Geosynthethic Reinforced Soil


Structure (GRS), Integral Bridge, Retaining Wall, Electrical
201(3)a Manholes and Detention Basins 41 Mon, 01-Feb-21 Sat, 13-Mar-21 49 Tue, 07-Sep-21 Fri, 12-Nov-21

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21

Embankment for At grade section for Depot


(Selected Borrow Material)
103(1)c 74 Mon, 15-Mar-21 Thu, 27-May-21 74 Mon, 11-Oct-21 Thu, 20-Jan-22

Embankment for GRS and Integral Bridge


(Common Material)
205(7) 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22

Cement Mixed Approach Block for internal bridge


205(1) 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Structura Works (Part D)


Reinforcing Steel, Grade 60 for Structure in Depot
207(1)c 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22

Structural Cast in Situ Concrete, 40 MPa for GRS


206(6)a 24 Mon, 03-May-21 Wed, 26-May-21 -147 Mon, 08-Nov-21 Fri, 16-Apr-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


February March April May
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 453 Week 154 Week 255 Week 356 Week 457 Week 158 Week 259 Week 360 Week 461 Week 162 Week 263 Week 364
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22

Structures Excavation for Geosynthethic Reinforced Soil


Structure (GRS), Integral Bridge, Retaining Wall, Electrical
201(3)a Manholes and Detention Basins 41 Mon, 01-Feb-21 Sat, 13-Mar-21 49 Tue, 07-Sep-21 Fri, 12-Nov-21

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21

Embankment for At grade section for Depot


(Selected Borrow Material)
103(1)c 74 Mon, 15-Mar-21 Thu, 27-May-21 74 Mon, 11-Oct-21 Thu, 20-Jan-22

Embankment for GRS and Integral Bridge


(Common Material)
205(7) 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22

Cement Mixed Approach Block for internal bridge


205(1) 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Structura Works (Part D)


Reinforcing Steel, Grade 60 for Structure in Depot
207(1)c 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22

Structural Cast in Situ Concrete, 40 MPa for GRS


206(6)a 24 Mon, 03-May-21 Wed, 26-May-21 -147 Mon, 08-Nov-21 Fri, 16-Apr-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 465 Week 166 Week 267 Week 368 Week 469 Week 170 Week 271 Week 372 Week 473
Mobilization / Demobilization

Bill No. 2 Earth Works (PartA)


102(1) Unsuitable Excavation for dry condition 16 Mon, 01-Feb-21 Tue, 16-Feb-21 16 Tue, 07-Sep-21 Tue, 28-Sep-21

201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22

104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22

Structures Excavation for Geosynthethic Reinforced Soil


Structure (GRS), Integral Bridge, Retaining Wall, Electrical
201(3)a Manholes and Detention Basins 41 Mon, 01-Feb-21 Sat, 13-Mar-21 49 Tue, 07-Sep-21 Fri, 12-Nov-21

103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21

Embankment for At grade section for Depot


(Selected Borrow Material)
103(1)c 74 Mon, 15-Mar-21 Thu, 27-May-21 74 Mon, 11-Oct-21 Thu, 20-Jan-22

Embankment for GRS and Integral Bridge


(Common Material)
205(7) 50 Mon, 12-Apr-21 Mon, 31-May-21 118 Wed, 06-Oct-21 Fri, 18-Mar-22

Cement Mixed Approach Block for internal bridge


205(1) 57 Mon, 15-Mar-21 Mon, 10-May-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22

205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22

205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22

Surface Cource (Part C)


107(1) Sub-ballast 23 Mon, 19-Apr-21 Tue, 11-May-21 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Structura Works (Part D)


Reinforcing Steel, Grade 60 for Structure in Depot
207(1)c 283 Mon, 12-Apr-21 Wed, 19-Jan-22 195 Sat, 25-Sep-21 Sat, 25-Jun-22

Structural Cast in Situ Concrete, 40 MPa for GRS


206(6)a 24 Mon, 03-May-21 Wed, 26-May-21 -147 Mon, 08-Nov-21 Fri, 16-Apr-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 1 Week 2 Week 3 Week 4 Week 12 Week 23 Week 34 Week 45 Week 16 Week 27 Week 38 Week 49
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole 28
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21

Structural Cast in Situ Concrete, 40 MPa for


Integral Bridge 158
206(6)g 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21 395

Structural Concrete, 40 MPa for Retaining Wall


(include waterstop at construction joint) 112
206(6)i 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22

Forming Anchor & Stopper for GSR and Integral


Bridge 74
205(6) 156 Mon, 02-Aug-21 Tue, 04-Jan-22 130 Fri, 15-Oct-21 Thu, 14-Apr-22

Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for Earth


Retaining System (GRS method), including  Crushed Stone layer 196
(200mm)
206(10)c 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule April May


Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 110 Week 211 Week 312 Week 413 Week 114 Week 215 Week 316
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21

Structural Cast in Situ Concrete, 40 MPa for


Integral Bridge
206(6)g 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21

Structural Concrete, 40 MPa for Retaining Wall


(include waterstop at construction joint)
206(6)i 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22

Forming Anchor & Stopper for GSR and Integral


Bridge
205(6) 156 Mon, 02-Aug-21 Tue, 04-Jan-22 130 Fri, 15-Oct-21 Thu, 14-Apr-22

Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for Earth


Retaining System (GRS method), including  Crushed Stone layer
(200mm)
206(10)c 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July August
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 417 Week 118 Week 219 Week 320 Week 421 Week 122 Week 223 Week 324 Week 425 Week 126 Week 227 Week 328
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21

Structural Cast in Situ Concrete, 40 MPa for


Integral Bridge
206(6)g 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21

Structural Concrete, 40 MPa for Retaining Wall


(include waterstop at construction joint)
206(6)i 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22

Forming Anchor & Stopper for GSR and Integral


Bridge
205(6) 156 Mon, 02-Aug-21 Tue, 04-Jan-22 130 Fri, 15-Oct-21 Thu, 14-Apr-22

Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for Earth


Retaining System (GRS method), including  Crushed Stone layer
(200mm)
206(10)c 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


August September October November
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 429 Week 130 Week 231 Week 332 Week 433 Week 134 Week 235 Week 336 Week 437 Week 138 Week 239 Week 340
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21

Structural Cast in Situ Concrete, 40 MPa for


Integral Bridge
206(6)g 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21

Structural Concrete, 40 MPa for Retaining Wall


(include waterstop at construction joint)
206(6)i 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22

Forming Anchor & Stopper for GSR and Integral


Bridge
205(6) 156 Mon, 02-Aug-21 Tue, 04-Jan-22 130 Fri, 15-Oct-21 Thu, 14-Apr-22

Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for Earth


Retaining System (GRS method), including  Crushed Stone layer
(200mm)
206(10)c 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


November December January February
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 441 Week 142 Week 243 Week 344 Week 445 Week 146 Week 247 Week 348 Week 449 Week 150 Week 251 Week 352
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21

Structural Cast in Situ Concrete, 40 MPa for


Integral Bridge
206(6)g 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21

Structural Concrete, 40 MPa for Retaining Wall


(include waterstop at construction joint)
206(6)i 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22

Forming Anchor & Stopper for GSR and Integral


Bridge
205(6) 156 Mon, 02-Aug-21 Tue, 04-Jan-22 130 Fri, 15-Oct-21 Thu, 14-Apr-22

Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for Earth


Retaining System (GRS method), including  Crushed Stone layer
(200mm)
206(10)c 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


February March April May
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 453 Week 154 Week 255 Week 356 Week 457 Week 158 Week 259 Week 360 Week 461 Week 162 Week 263 Week 364
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21

Structural Cast in Situ Concrete, 40 MPa for


Integral Bridge
206(6)g 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21

Structural Concrete, 40 MPa for Retaining Wall


(include waterstop at construction joint)
206(6)i 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22

Forming Anchor & Stopper for GSR and Integral


Bridge
205(6) 156 Mon, 02-Aug-21 Tue, 04-Jan-22 130 Fri, 15-Oct-21 Thu, 14-Apr-22

Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for Earth


Retaining System (GRS method), including  Crushed Stone layer
(200mm)
206(10)c 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 465 Week 166 Week 267 Week 368 Week 469 Week 170 Week 271 Week 372 Week 473
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21

Structural Cast in Situ Concrete, 40 MPa for


Integral Bridge
206(6)g 88 Tue, 01-Jun-21 Fri, 27-Aug-21 162 Sat, 06-Nov-21 Tue, 21-Jun-22

103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21

Structural Concrete, 40 MPa for Retaining Wall


(include waterstop at construction joint)
206(6)i 163 Mon, 09-Aug-21 Tue, 18-Jan-22 114 Mon, 29-Nov-21 Thu, 05-May-22

Forming Anchor & Stopper for GSR and Integral


Bridge
205(6) 156 Mon, 02-Aug-21 Tue, 04-Jan-22 130 Fri, 15-Oct-21 Thu, 14-Apr-22

Blind Layer Concrete/Lean Concrete (t=100mm),15 MPa for Earth


Retaining System (GRS method), including  Crushed Stone layer
(200mm)
206(10)c 1 Mon, 05-Apr-21 Mon, 05-Apr-21 43 Mon, 18-Oct-21 Wed, 15-Dec-21
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 1 Week 2 Week 3 Week 4 Week 12 Week 23 Week 34 Week 45 Week 16 Week 27 Week 38 Week 49
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including  Crushed Stone Layer (200mm)   174
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21

Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa for


Retaining Wall, including compacted crash stone layer (200mm) 300
206(10)i 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22

Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for


Miscellaneous Manholes in Main Line and Depot, including 209
compacted sand layer(150mm)
206(10)j 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21

Miscellaneous Steelwork - Expansion Joint


Assemblies 206
209(5) 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 146

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 141

Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 77

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 38

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 44

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 41

RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22 -89

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule -Slack Time Notes / Remarks

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule April May


Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 110 Week 211 Week 312 Week 413 Week 114 Week 215 Week 316
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including  Crushed Stone Layer (200mm)  
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21

Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa for


Retaining Wall, including compacted crash stone layer (200mm)
206(10)i 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22

Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for


Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
206(10)j 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21

Miscellaneous Steelwork - Expansion Joint


Assemblies
209(5) 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule -Slack Time Notes / Remarks

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July August
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 417 Week 118 Week 219 Week 320 Week 421 Week 122 Week 223 Week 324 Week 425 Week 126 Week 227 Week 328
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including  Crushed Stone Layer (200mm)  
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21

Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa for


Retaining Wall, including compacted crash stone layer (200mm)
206(10)i 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22

Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for


Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
206(10)j 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21

Miscellaneous Steelwork - Expansion Joint


Assemblies
209(5) 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule -Slack Time Notes / Remarks

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


August September October November
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 429 Week 130 Week 231 Week 332 Week 433 Week 134 Week 235 Week 336 Week 437 Week 138 Week 239 Week 340
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including  Crushed Stone Layer (200mm)  
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21

Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa for


Retaining Wall, including compacted crash stone layer (200mm)
206(10)i 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22

Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for


Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
206(10)j 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21

Miscellaneous Steelwork - Expansion Joint


Assemblies
209(5) 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule -Slack Time Notes / Remarks

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


November December January February
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 441 Week 142 Week 243 Week 344 Week 445 Week 146 Week 247 Week 348 Week 449 Week 150 Week 251 Week 352
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including  Crushed Stone Layer (200mm)  
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21

Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa for


Retaining Wall, including compacted crash stone layer (200mm)
206(10)i 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22

Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for


Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
206(10)j 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21

Miscellaneous Steelwork - Expansion Joint


Assemblies
209(5) 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule -Slack Time Notes / Remarks

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


February March April May
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 453 Week 154 Week 255 Week 356 Week 457 Week 158 Week 259 Week 360 Week 461 Week 162 Week 263 Week 364
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including  Crushed Stone Layer (200mm)  
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21

Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa for


Retaining Wall, including compacted crash stone layer (200mm)
206(10)i 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22

Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for


Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
206(10)j 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21

Miscellaneous Steelwork - Expansion Joint


Assemblies
209(5) 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule -Slack Time Notes / Remarks

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14

BidDocs Detailed Schedule Revised Detailed Schedule


May June July
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 465 Week 166 Week 267 Week 368 Week 469 Week 170 Week 271 Week 372 Week 473
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including  Crushed Stone Layer (200mm)  
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21

Blinding Layer Concrete/Lean Concrete (t=50mm), 15 MPa for


Retaining Wall, including compacted crash stone layer (200mm)
206(10)i 8 Wed, 07-Apr-21 Wed, 14-Apr-21 25 Tue, 01-Feb-22 Mon, 07-Mar-22

Blind Layer Concrete/ Lean Concrete (50mm) 15 Mpa for


Miscellaneous Manholes in Main Line and Depot, including
compacted sand layer(150mm)
206(10)j 1 Thu, 15-Apr-21 Thu, 15-Apr-21 1 Wed, 10-Nov-21 Wed, 10-Nov-21

Miscellaneous Steelwork - Expansion Joint


Assemblies
209(5) 1 Fri, 16-Apr-21 Fri, 16-Apr-21 120 Mon, 08-Nov-21 Sat, 23-Apr-22

Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22

Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22

Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21

Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22

STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22

Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22

RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22

N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21

SUBBASE AND BASE COURSE 20 Mon, 04-Jul-22 Fri, 29-Jul-22

Legend:
BidDocs Schedule -Slack Time Notes / Remarks

BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Building Works (Package CP N-05)
Sub-Con: Northern Builders
Project Star May 05, 2021 (Wednesday)
Project Fini Jul 29, 2022 (Friday)
No. of Mont 14

No. Reason of Delays Remarks


[March 2, 2021 - Announced Schedule for Turnover of Area Zone 2; June 30, 2021 - EEI
1 Submits an Inspection Request for Clearing & Grubbing @ Site 1; June 9, 2021 - POSCO ,
TURNOVER OF AREA sent an email regarding on EEI handovered area]
2 Temporary Control Points Validation / Bench Marks near in Site Location (April 6, 2021).
CONTROL POINTS VALIDATION Control Points are under validation of GCR & POSCO due to some errors
3 Note: May 19, 2021 - 2:14pm, Posco Sent an Email Regarding on NSCR-PSC-NBS-N05-
REVISION OF PLANS & WORKING DRAWINGS (Rev. 29 - Rev. 31) CRKDPT-TRL-W-000010_Issuance of IFC Drawing Rev. 31 (Set 1 & 2)
4 REQUIREMENTS FOR MANPOWER
5 Covid 19 Pandemic Cases (from Month of April to May, & Month of August) : Affected
HEALTH ISSUES by Covid - from Management to Workers on Site
6 WEATHER CONDITION (Heavy Rainfall that causes Work Stoppage - Aug. 18-19, 21,23, & Sept. 1, 2021)

[Before - Work Inspection Request, Key Plan, Blowup Plan; Additonal Requirements for
7 Submission of Work Inspection Request Dated on Sept. 10, 2021 - Section Plan based on
approved shopdrawing, Computation with Illustration, Pgrogress Photos(Before &
CHANGES IN WIR REQUIREMENTS After)]
8 MATERIAL APPROVAL PVC pipes "CROWN" - Waiting for the Approval
Cast Iron Cover "JAMAN" - Awaiting for Comments of POSCO & GCR
Curing Compound "SPAKTON" - Awaiting for Comments of POSCO & GCR
Rubber Water Stop "SPAKTON" - Awaiting for comments of POSCO & GCR
Forming Anchor "POWER STEEL" - Awaiting for Comments of POSCO & GCR
9 Bar Bending Schedule Approval of BBS, Formworks, & Concrete Spacer

You might also like