Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 1 Week 2 Week 3 Week 4 Week 12 Week 23 Week 34 Week 45 Week 16 Week 27 Week 38 Week 49
Mobilization / Demobilization
201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22 255
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22 398
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21 186
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22 219
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22 211
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22 115
201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22
201(4)d Backfill 19 Tue, 23-Feb-21 Sat, 13-Mar-21 89 Fri, 05-Nov-21 Wed, 09-Mar-22
104(1) Subgrade Preparation (Common Material) 8 Tue, 16-Feb-21 Tue, 23-Feb-21 24 Mon, 21-Mar-22 Thu, 21-Apr-22
103(1)b Embankment (Using Common Excavation Soil) 71 Mon, 22-Feb-21 Mon, 03-May-21 70 Fri, 27-Aug-21 Thu, 02-Dec-21
205(2) Geogrid, 37.5KN/m 52 Mon, 01-Mar-21 Wed, 21-Apr-21 108 Wed, 06-Oct-21 Fri, 04-Mar-22
205(3) Geogrid, 75.0KN/m 65 Mon, 15-Mar-21 Tue, 18-May-21 108 Tue, 12-Oct-21 Thu, 10-Mar-22
205(5) Gravel Bag filled with Crushed Stone 2 Fri, 28-May-21 Sat, 29-May-21 88 Mon, 20-Sep-21 Wed, 19-Jan-22
BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 1 Week 2 Week 3 Week 4 Week 12 Week 23 Week 34 Week 45 Week 16 Week 27 Week 38 Week 49
Structural Cast in Situ Concrete, 28 MPa for
Electrical Manhole 28
206(6)b 2 Mon, 12-Apr-21 Tue, 13-Apr-21 2 Mon, 10-May-21 Tue, 11-May-21
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21 395
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21
103(5) Grade Stabilized Crushed Stone (M-40) 5 Tue, 01-Jun-21 Sat, 05-Jun-21 -270 Fri, 01-Jul-22 Mon, 21-Jun-21
BidDocs Detailed Schedule Revised Detailed Schedule Offset Start January February March
Duration
Bill No. Item Description Duration Start End Duration4 Start5 End6 Week 1 Week 2 Week 3 Week 4 Week 12 Week 23 Week 34 Week 45 Week 16 Week 27 Week 38 Week 49
Blinding Layer Concrete/Lean Concrete (t=100mm), 15 MPa for,
Integral Bridge, Including Crushed Stone Layer (200mm) 174
206(10)f 1 Tue, 06-Apr-21 Tue, 06-Apr-21 12 Mon, 27-Sep-21 Tue, 12-Oct-21
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22 146
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22 141
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21 77
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22 38
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22 44
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22 41
RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22 -89
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21 0
Legend:
BidDocs Schedule -Slack Time Notes / Remarks
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21
Legend:
BidDocs Schedule -Slack Time Notes / Remarks
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21
Legend:
BidDocs Schedule -Slack Time Notes / Remarks
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21
Legend:
BidDocs Schedule -Slack Time Notes / Remarks
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21
Legend:
BidDocs Schedule -Slack Time Notes / Remarks
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21
Legend:
BidDocs Schedule -Slack Time Notes / Remarks
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Buuilding Works (Package CP N-05)
Sub-Con: Northern Builders
Project Start: May 05, 2021 (Wednesday)
Project Finish: Jul 29, 2022 (Friday)
No. of Months: 14
Miscellaneous Structures (Part E) 78 Tue, 01-Jun-21 Mon, 30-Aug-21 62 Mon, 25-Oct-21 Tue, 18-Jan-22
Plumbing & Sanitary Works (Part F) 64 Tue, 31-Aug-21 Fri, 12-Nov-21 53 Wed, 19-Jan-22 Sat, 02-Apr-22
Structural Earth Works Works 105 Thu, 27-May-21 Sat, 25-Sep-21 87 Thu, 12-Aug-21 Sat, 11-Dec-21
Drainage System & River Bank Protection 53 Mon, 29-Nov-21 Fri, 28-Jan-22 46 Thu, 06-Jan-22 Thu, 10-Mar-22
STRUCTURAL WORKS 63 Mon, 18-Oct-21 Wed, 29-Dec-21 53 Wed, 01-Dec-21 Fri, 11-Feb-22
Drainage Work 54 Thu, 25-Nov-21 Wed, 26-Jan-22 45 Wed, 05-Jan-22 Tue, 08-Mar-22
RIVER BANK PROTECTION WORKS FOR DOLORES 152 Mon, 02-Aug-21 Tue, 25-Jan-22 190 Wed, 05-May-21 Tue, 25-Jan-22
N.DEPOT SUB STATION 20 Fri, 05-Nov-21 Sat, 27-Nov-21 20 Fri, 05-Nov-21 Sat, 27-Nov-21
Legend:
BidDocs Schedule -Slack Time Notes / Remarks
BidDocs Schedule
Revised Schedule Dist. Bet. BDS to RS Start Date Revised Schedule
Northern Builders
Project Schedule
Project: Malolos-Clark Railway Project - Civil & Building Works (Package CP N-05)
Sub-Con: Northern Builders
Project Star May 05, 2021 (Wednesday)
Project Fini Jul 29, 2022 (Friday)
No. of Mont 14
[Before - Work Inspection Request, Key Plan, Blowup Plan; Additonal Requirements for
7 Submission of Work Inspection Request Dated on Sept. 10, 2021 - Section Plan based on
approved shopdrawing, Computation with Illustration, Pgrogress Photos(Before &
CHANGES IN WIR REQUIREMENTS After)]
8 MATERIAL APPROVAL PVC pipes "CROWN" - Waiting for the Approval
Cast Iron Cover "JAMAN" - Awaiting for Comments of POSCO & GCR
Curing Compound "SPAKTON" - Awaiting for Comments of POSCO & GCR
Rubber Water Stop "SPAKTON" - Awaiting for comments of POSCO & GCR
Forming Anchor "POWER STEEL" - Awaiting for Comments of POSCO & GCR
9 Bar Bending Schedule Approval of BBS, Formworks, & Concrete Spacer