Planned
Building Issued to Feedback from Final
No. of Retails Submission TEAM
Number Domopan Domopan Submission
Date
B01 4 23-Sep-2021 T2
B02 4 21-Sep-2021 T2
B03 3 19-Sep-2021 T2 12-Sep-2021
B07 1 9-Sep-2021 T2 12-Sep-2021
B09 2 9-Sep-2021 T1 12-Sep-2021
B13 2 31-Aug-2021 T2
B22 2 27-Sep-2021 T2
B23 4 13-Sep-2021 T1
B28 2 27-Sep-2021 T2
B29 3 15-Sep-2021 T1
B30 11 20-Sep-2021 T1
B32 3 19-Sep-2021 T2 12-Sep-2021
B33 6 23-Sep-2021 T1
B34 7 22-Sep-2021 T2 12-Sep-2021
B35 6 28-Sep-2021 T1
B36 2 30-Sep-2021 T1
B37 2 4-Oct-2021 T1
B39 2 4-Oct-2021 T1
B40 9 19-Sep-2021 T2
B41 6 7-Oct-2021 T1
B46 5 14-Sep-2021 T2 29-Aug-2021 9-Sep-2021
B47 5 8-Sep-2021 T2 12-Sep-2021
B48 4 8-Sep-2021 T2 5-Sep-2021
B49 3 8-Sep-2021 T2 12-Sep-2021
B50 3 8-Sep-2021 T2 12-Sep-2021